The investment program can be used to augment planning and budgeting at the level of the
individual measure by offering planning, budgeting and monitoring of a comprehensive budget.
Investment programs are helpful to enterprises that create an investment plan and a budget
annually, and wish to monitor the budget as a whole, rather than just at the level of individual
measures.
Using investment programs, you can obtain an overview of planning and budgeting processes in
complex enterprise structures for all investments and large projects of the group, while at the
same time maintaining strict budgetary control.
The top program position is the highest level in Investment Management which is company code
specific, and it is the highest level that can have a budget.
· Determine the SAP Profit Center prior to creating the investment program.
· Determine the SAP Cost Center relevant for overall project management.
This change in structure is required to create the individual program positions. These program
positions are the equivalent of the line items in the legacy system.
· Determine the SAP Profit Center responsible for the program position prior to changing the
program structure.
· Determine the SAP Cost Center relevant for the program position (this can be different from
the Cost Center used in the top program position).
This transaction will establish the budget in SAP for a given investment program and the
relevant program positions. The Top Program Position is the highest level where a budget can
be entered – the budgeted amounts are pushed down to the lower levels of management, i.e.
the Investment Program Positions and the Internal Orders. This type of budgeting is referred to
as "Top-Down" budgeting.
· Know the budgeted amounts for the program prior to executing the transaction.
The instruction will walk the user through steps required to create a budget Supplement
· Original Budget
· Increased budget is required but original budget needs to remain unchanged
· Determine the program type and order type prior to creating the internal order
· An internal order already existing can be referenced to minimize data input
Create Overall Budget planning for IO: Transaction Code: KO12 / KO13
· Determine the program type and order type prior to creating the internal order
· An internal order already existing can be referenced to minimize data input
Prerequisites
· An investment program with budget values
Steps required to run Investment Management Reports. This report is a drill-down report. By
double-clicking on any line item it takes the user one level lower.