Purpose: Standard Operating Procedure for CW PUMP

Scope: This procedure explains the Normalization/Starting of first CW Pump and Stopping
/Isolation of CW Pump.

Responsibility: CW Pump operator, Desk Engineer, Shift In charge.

Guide line:-
 All work permit should be cancelled.
 Ensure Power supply should be normal.
 Clearance should be available from Other department.
 Before taking in Operation Ensure equipment healthiness should be
available.

Procedure:
LINE UP PROCEDURE FOR NORMALIZATION OF CW PUMPS:

1) Take clearance from all concerned service departments, i.e. no permit are pending.
2) Ensure the following:-
a) Water channel level is normal (6 meters).
b) At least 5 riser valves of cooling tower are open.
c) Inlet & Outlet valve of one pass of condenser is open.
d) Cooling water line is initially charged.
e) CW Pump discharge butterfly valve is fully closed.
f) Pump bearing oil level is normal (70%)
g) Pump motor power is healthy.
h) Pump discharge valve power is healthy.
i) Pump vent & discharge line vent should be opened.
3) Check all start permissive of Pump from DCS are healthy:
a) Pump selection in Remote mode.
b) Breaker in service.
c) Breaker healthy.
d) D.C. supply healthy.
e) Spring charged.
f) No trip alarm persists.
g) Off feedback.
h) Emergency push button released.

Issued By Reviewed Approved By


Name Mr. Shailendra Pandey Mr. Binay Prakash Kullu Mr. Rakesh Srivastava
Role Section Head DCT Department Head
Date 07-04-2015 24-04-2015 04-05-2016
1/4
LINE UP PROCEDURE FOR STARTING OF FIRST CW PUMP:

Reset all the protections if any persist.

1) Start CW Pump ,Observe the following:-


a) Discharge valve is fully open from local & DCS.
b) Normal current is reached (…. amps).
c) Pump discharge pressure (1.9 to 2.2 kg/cm2)
d) Close the Pump & discharge line vent.
e) Pump vibration (0-2mm/sec.).
f) Motor vibrations (0-4 mm/sec.).
g) Bearing & Winding Temperature.
h) Ensure there is no overflow from condenser outlet line vent near turbine floor.

LINE UP PROCEDURE FOR STARTING OF SECOND CW PUMP:

1) Take clearance from all concerned service departments, i.e. no permit are pending.
2) Ensure the following:-
a) Water channel level is normal (6 meters).
b) At least 05 riser valves of cooling tower are open.
c) Inlet & Outlet valve of both pass of condenser is open.
d) CW Pump discharge butterfly valve is fully closed.
e) Pump bearing oil level is normal (70%)
f) Pump motor power is healthy.
g) Pump discharge valve power is healthy.
h) Pump vent & discharge line vent should be opened.
3) Check all start permissive of Pump from DCS are healthy:
a) Pump selection in Remote mode.
b) Breaker in service.
c) Breaker healthy.
d) D.C. supply healthy.
e) Spring charged.
f) No trip alarm persists.
g) Off feedback.
h) Emergency push button released.

Reset all the protections if any persist

4) Start CW Pump, Observe the following:-


a) Discharge valve is fully open from local & DCS.
b) Adjust the cooling tower riser valve to maintain pump discharge pressure
between 1.3 to 1.4 ksc.
c) Close the Pump & discharge line vent.
d) Normal current is reached (…. amps).
e) Pump discharge pressure (1.3 to 1.4 kg/cm2)
f) Pump vibration (0-2mm/sec.).
g) Motor vibrations (0-4 mm/sec.).
Issued By Reviewed Approved By
Name Mr. Shailendra Pandey Mr. Binay Prakash Kullu Mr. Rakesh Srivastava
Role Section Head DCT Department Head
Date 07-04-2015 24-04-2015 04-05-2016
2/4
h) Bearing & Winding Temperature.
i) Ensure there is no overflow from condenser outlet line vent near turbine floor.
j) Open other cooling tower riser valve as per requirement.

LINE UP PROCEDURE FOR STARTING OF STAND BY CW PUMP:

1) Take clearance from all concerned service departments, i.e. no permit are pending.
2) Ensure the following:-
a) Channel level is normal (6 meters).
b) Open other closed cooling tower riser valves to reduce the pump discharge
header pressure from 1.4 ksc. (Not < 1.2 ksc).
c) Inlet & Outlet valve of both pass of condenser is open.
d) CW Pump discharge butterfly valve is fully closed.
e) Pump bearing oil level is normal (70%)
f) Pump motor power is healthy.
g) Pump discharge valve power is healthy.
h) Pump vent & discharge line vent should be opened.
3) Check all start permissive of Pump from DCS are healthy:
a) Pump selection in Remote mode.
b) Breaker in service.
c) Breaker healthy.
d) D.C. supply healthy.
e) Spring charged.
f) No trip alarm persists.
g) Off feedback.
h) Emergency push button released.

Reset all the protections if any persist.

4) Start CW Pump, Observe the following:


a) Discharge valve is fully open from local & DCS.
b) Close the Pump & discharge line vent.
c) Normal current is reached (…. amps).
d) Pump discharge pressure (1.3 to 1.4 kg/cm2)
e) Pump vibration (0-2mm/sec.).
f) Motor vibrations (0-4 mm/sec.).
g) Bearing & Winding Temperature.
h) Ensure there is no overflow from condenser outlet line vent near turbine floor.
5) Stop the CW Pump which has to spared & Ensure for following :
a) Discharge valve is fully close.
b) No reverse rotation of pump.
Adjust the cooling tower riser valve to maintain pump discharge header pressure between 1.3 to
1.4 ksc

STOPPING/ISOLATION OF CW PUMP
Issued By Reviewed Approved By
Name Mr. Shailendra Pandey Mr. Binay Prakash Kullu Mr. Rakesh Srivastava
Role Section Head DCT Department Head
Date 07-04-2015 24-04-2015 04-05-2016
3/4
STOPPING PROCEDURE:

1) Stop the CW Pump.


2) Ensure discharge valve is closed.
3) Close the cooling tower riser valve to maintain running pump discharge pressure
1.2 to 1.4 ksc.

ISOLATION PROCEDURE:

1) Ensure the following :


a) CW Pump is in OFF condition.
b) Emergency push button is pressed.
c) CW Pump motor breaker is rack out.
d) Discharge valve is fully close.
e) Discharge valve power supply is off.

Environment & safety Requirements: All PPE’s should be available (Helmet,


safety shoes, earplugs, gloves, goggles)

Position implementing function: This procedure is used as work instruction for CW


Pump operator, Desk Engineer, Shift In charge.

Reference documents: Nil

RECORDS: Nil

Issued By Reviewed Approved By


Name Mr. Shailendra Pandey Mr. Binay Prakash Kullu Mr. Rakesh Srivastava
Role Section Head DCT Department Head
Date 07-04-2015 24-04-2015 04-05-2016
4/4