Beruflich Dokumente
Kultur Dokumente
Contents
Introduction 6
Introduction to Power Transformers 8
Function of a Power Transformer 8
Advantages of Transformers 8
Transformer Voltage Ratio 9
Transformer Windings 9
Single and Three-Phase Transformers 10
Contents and Fittings of a Power Transformer 10
The Iron Core 11
The Windings 13
Construction 13
Connections 14
The Conservator and Breather 19
The Explosion Vent 21
The Buchholz Relay 22
Terminal Bushings 25
Tap Changers 26
Temperature Indicators 29
Instrument Transformers 29
Potential Transformers 30
Current Transformers 31
Inspection and Operation of Transformers 33
Returning a Transformer to Service after Maintenance 36
Commissioning 39
Acceptance Inspections and Testing 39
Internal Inspections 40
Pre-Start Tests 42
Maintenance and Testing 46
Heat And Contamination 46
Contamination 46
DC Tests 47
Insulation Resistance Testing 49
Tap Changer Testing 51
Test Connections 54
Polarisation Index 56
Winding Resistance 57
DC High Potential Testing (Hi-Pot) 58
AC Tests 60
Power Factor Test 60
Turns Ratio Test 61
Transformer Auxiliary Equipment 63
Bushings 63
Pressure Relief Devices 64
Sudden Pressure Relays 65
Temperature Gauges 66
Lightning Arrestors 68
Typical Power Transformer Faults 69
Review Exercise 73
References 77
Introduction
In this book you will gain the necessary skills and knowledge to understand
the requirements to complete operation, inspections, commissioning and
testing of power transformers within the power plant environment. It is
generally intended for trades or journeyman qualified personnel. However,
those wishing for relevant experience will gain required knowledge that will
assist with the field of study.
During the course of the self-paced learning, the following topics will be
covered:
1. Description of Power Transformers,
2. Components of the Transformer,
3. Instrument Transformers,
4. Inspection and Operation of Transformers.
5. Commission and Maintain Transformers.
6. Transformer Diagnostics.
Also by Wayne Smith
Condition Monitoring for Power Plants
Switchgear Operation and Maintenance for Power Plants
Test and Commission Electrical Equipment for Power Plants
Excitation Maintenance for Power Plants
Root Cause Analysis for Power Plants
Toolbox Talks for the Busy Supervisor
More Toolbox Talks for the Busy Supervisor
Star and delta connected three phase windings are shown in Figure 2.
Figure 2 - Three-Phase Winding Connections
Star and delta connections may be used on either or both the primary and
secondary windings depending on their application, and thus there are four
possible combinations. These are star-star, star-delta, delta-delta, and delta-
star; the first term indicating the primary connection and the second term
the secondary.
Since no neutral point is available with the delta connection, a star
connected secondary is necessary if the transformer is to supply single
phase loads which are connected between one line and neutral.
Insulating oil should not be permitted to come into contact with the open
atmosphere since the absorption of even a minute amount of moisture
causes a great deterioration in its insulating properties. Consequently, to
prevent moisture in the air contaminating the oil, the conservator is allowed
to breathe through an air dryer known as a Breather. Its location is shown in
Figure 3. This consists of a small vessel containing silica-gel which acts as a
drying agent. The silica-gel which should be blue in colour may be inspected
through a glass window. When the colour has changed from blue to a
whitish-pink by the absorption of moisture, the charge must be re-activated
by heating it in a warm oven.
Figure 4 - Typical Transformer Conservator
The fitting consists of a vertical pipe attached to the top of the main tank
and extending above the oil level in the conservator. The upper end is sealed
by a thin diaphragm made of a material such as bakelite which will rupture
in the event of a high internal pressure. The top of the vent is bent over so
that any oil ejected with the gas is directed away from the transformer.
The Buchholz Relay
This is a mechanically operated protective device which is fitted in the
connecting pipe between the main tank and the conservator as shown in
Figure 3. Should an internal fault develop in the windings or core, the
localised heating will vaporise and decompose some of the oil. The resultant
gas will rise through the pipe into the conservator and will be detected by
the Buchholz Relay.
If there is a major fault, the large surge of gas and oil will actuate a small flap
in the relay which trips the circuit breaker supplying the transformer and
initiates the "Buchholz Trip" alarm in the control room. With a minor fault,
or if the transformer has been overheated, the flow of bubbles will be
insufficient to actuate the flap, but the gas will collect in the body of the
relay. This lowers the oil level in the relay and allows a small float to fall
which initiates the "Buchholz Gas" alarm in the control room. This alarm will
also be initiated if the transformer oil level has been allowed to fall
sufficiently for the float to operate. Neither the flap nor the float offers any
restriction to the normal breathing action of the transformer.
Over the page shows the construction of a Buchholz Relay.
Figure 6 - Buchholz Relay
A test cock connected to the body of the relay is installed near ground level,
which enables any gas collected to be bled off and tested. The gas formed by
an electrical fault contains a large percentage of acetylene, a flammable gas,
so that if the gas is flammable, the transformer must be electrically tested. If
the gas will not burn, it can be assumed that it is air, which has been
released from the oil, particularly if the transformer has been recently
"topped up".
Terminal Bushings
Low voltage windings are usually brought out to a cable end box “mounted”
on the main tank for connection to a cable. The high voltage windings
however, are brought out of the tank through hollow insulators known as
Bushings. These are generally made of porcelain and are specially designed
in order to reduce the electrical stress to which the insulators are subjected.
High tension transformer bushings are normally oil filled and some have a
cock located at the top to allow the release of trapped air and a breather to
prevent the ingress of moisture. Sometimes a bushing may incorporate a
current transformer in its construction.
On outdoor transformers and on some indoor transformers, the high-
tension bushings are provided with skirts. These reduce the risk of a
flashover by presenting a long path for any leakage current, which may flow
due to moisture and dust on the surface.
Tap Changers
The majority of power transformers are provided with tap changing facilities
in order to control the voltage of the secondary circuit. This is achieved by
varying the number of active turns in the winding and thus the voltage
transformation ratio.
When the load and consequently the voltage remains reasonably constant,
as on the majority of power station auxiliary transformers, the tap changer is
designed for off-load operation only. This is provided by a system of bolted
links or switches and as tap changing is only permitted when the
transformer is out of service; the operating mechanism is padlocked to
prevent unauthorised operation.
Unit transformers and distribution transformers are generally provided with
on-load changers which allow variations of 5% to 15% above and below the
nominal voltage while the transformer is in service. To effect tap changing
without interruption to the load, it is evident that there will be a period
when two adjacent tappings must be temporarily bridged.
Although most testing should be performed only while the coils are
submerged in oil, if the inspection is being conducted because of problems
noted during the external or internal inspections, the following tests should
be conducted;
· Power factor tests for all winding to ground and windings to winding
values.
· Turns ratio tests for all windings and tap positions.
· Ratio and polarity tests for all current, transformers.
· Winding resistance checks for all primary and secondary windings.
· Discount the grounding connections between the core assembly and
the tank, and perform insulation resistance tests with a Megger.
Figure 11 - Typical power transformer
Pre-Start Tests
Prior to energising a transformer for the first time there are a number of
pre-start up tests that need to be completed. For oil filled transformers that
have been filled to operational values prior to the initial tests, The
transformer should then be allowed to stand without load for at least 12
hours before any tests are performed. After the 12 hour standing period, the
following tests should be performed to establish baseline data for the
transformer.
Transformer turns ratio. This test ensures that no material or tools are
shorting the windings.
Insulation resistance-dielectric absorption. This test is used to determine
whether any grounds have been left on the windings, and whether the
insulation quality is strong enough for energization.
Winding continuity resistance test. This test should be compared to the
factory supplied readings; a reading that is greater than 10 percent higher
could indicate loose internal connections.
Power factor test. This test will indicate the quality of the combined
insulating fluid and winding insulation. It will also provide important baseline
data for future testing. Values in excess of 1 percent could indicate
dampness in the transformer. Consult the manufacturer’s operations
manual for drying procedures.
Insulating fluid testing. This test will help to provide additional information if
any discrepancies are noted in the prior testing. Samples should be drawn
for the complete series of lab tests, including dissolved gas, and dielectric
strength field testing. The dielectric strength for new oil should be at least
35 kV.
After the testing is completed, the transformer should be energized for at
least 12 hours before applying the load. Because very high currents can be
developed when the transformer is first energized, any upstream fuses or
fused devices should be checked immediately after the power is applied.
If a fuse should blow, and if the transformer is allowed to operate with out
one or two fuses, it could be damaged, even if no load is applied. After 12
hours, the load should be applied slowly, and the transformer should be
carefully monitored the load is being applied. Even though satisfactory test
results have been obtained, personnel should stay away from the
transformer during the first 24 hours of energization. It is during this time
that any entrapped air will come to the surface, and the possibility of a fault
or short occurring increases.
Maintenance and Testing
Heat And Contamination
Heat and contamination are the two greatest enemies to the transformer’s
operation. Heat will break down the solid insulation and accelerate the
chemical reactions that take place when the oil is contaminated. All
transformers require a cooling method and it is important to ensure that the
transformer has proper cooling. Proper cooling involves cleaning the cooling
surfaces, maximizing ventilation, and monitoring loads to ensure the
transformer is not producing excess heat.
Contamination
Contamination is detrimental to the transformer, both inside and out. The
importance of basic cleanliness and general housekeeping becomes evident
when long-term service life is considered. Dirt build up and grease deposits
severely limit the cooling abilities of radiators and tank surfaces. Terminal
and insulation surfaces are especially susceptible to dirt and grease build up.
The oil in the transformer also suffers from the effects of contamination and
should be kept as pure as possible. Dirt and moisture start chemical
reactions in the oil that lower both its electrical strength and its cooling
capability. Determining the degree of contamination is accomplished by
sampling and analysing the oil on a regular basis.
DC Tests
Transformer tests can be divided into two categories, alternating current
(AC) and direct current (DC). Direct current testing is widely accepted
because of the portability of the equipment and because of the non-
destructive nature of the tests. Because the test potential can be applied
without the reactive component (capacitive and inductive charging and
recharging), DC tests can be performed at higher levels without stressing the
insulation to the same degree as an AC test.
It is important to note that, even though a winding failure may result, it
probably resulted from an incipient condition that the test was designed to
detect. If the deficiency had gone undetected, the failure may have occurred
at an unplanned time and resulted in additional equipment damage. When a
DC potential is applied across an insulation, there are three components to
the resulting current.
Capacitance charging current. When the insulation resistance is being
measured between two conductors, the conductors act like the plates in a
capacitor. These “plates” absorb a certain amount of electrical energy (the
charging current) before the applied voltage is actually developed across
them. This current results in stored energy that should be discharged after
the test by shorting across the insulation.
Dielectric absorption current. As noted above, the two conductors between
which the potential is being applied act like a capacitor. The winding
insulation and the insulating fluid then act as dielectric materials and absorb
electrical energy as their molecules become polarized, or charged. The
absorption current decreases as the materials become charged, resulting in
an apparent increase in the insulation resistance.
The absorption current results in stored energy that takes longer to dissipate
than it did to build. The insulation should be shorted for a time period equal
to or longer than the time the test was applied, preferably longer.
Leakage current. This is the current that actually flows throughout the
insulation or across its surface. Its magnitude is usually very small in relation
to the rated current of the device, and it is expressed in microamperes (one
millionth of an amp). It indicates the insulation’s actual conductivity, and
should be constant for a steady applied voltage. Leakage current that
increases with time for a constant applied voltage indicates a potential
problem.
Insulation Resistance Testing
Megger test potentials are usually applied at 500, 1,000, 2,500, and 5,000
volts DC. These potentials are obtained by using a motor driven or hand-
crank operated magneto. The hand crank units are both lightweight and
portable, and because they require no batteries or external source, they are
also extremely dependable. Motor-driven units, on the other hand, are
capable of achieving higher and more constant test voltages, but are
practically useless without batteries or a external source. Both units are
available in models capable of producing accurate readings for resistance
levels as high as 100,000 megohms. The following conditions should be
observed when performing an insulation resistance test;
Make sure that both the tank and core iron are solidly grounded.
disconnect any systems that may be connected to the transformer winding,
including high and low voltage and neutral connections, lightning arrestors,
fan systems, meters, and potential transformers.
Potential transformers are often located on the line sides of breakers or
disconnects; when the disconnect is opened, there will still be a path
available to ground. Short circuit all high and low voltage windings together
at the bushings connections; jumpers should be installed to ground, and no
winding should be left floating.
The ground connection on grounded windings must be removed. If the
ground cannot be conveniently removed, the test cannot be performed on
that winding. Such a winding must be treated as part of the grounded
circuit.
Figure 12 - Transformer Ohmmeter - Winding resistance & tap changer
tester
Tap Changer Testing
Tap-changers are mechanical devices and the most vulnerable part of a
transformer. Tap-changers result in more failures and outages than any
other component and so require frequent testing and attention to ensure
proper, reliable operation. The Transformer Ohmmeter can be used to check
the make-before-break operation of on-load tap-changers and also to
measure the contact resistance of each tap position.
FAULT EXAMPLE
Partial discharges Discharges in gas-filled cavities
in insulation, resulting from
incomplete impregnation, high
moisture in paper, gas in oil
super-saturation or cavitations
(gas bubbles in oil) leading to X
wax formation on paper.
Discharges of low Sparking or arcing between bad
energy connections of different floating
potential, from shielding rings,
toroids, adjacent discs or
conductors of different
windings, broken brazing, closed
loops in the core.
Additional core grounds.
Discharges between clamping
parts, bushing and tank, high
voltage and ground, within
windings.
Tracking in wood blocks, glue of
insulating beam, winding
spacers.
Dielectric breakdown of oil, load
tap changer breaking contact.
Discharges of high Flashover, tracking or arcing of
energy high local energy or with power
follow-through.
Short circuits between low
voltage and ground, connectors,
windings, bushings, and tank,
windings and core, copper bus
and tank, in oil duct.
Closed loops between two
adjacent conductors around the
main magnetic flux, insulated
bolts of core, metal rings holding
core legs.
Overheating less Overloading the transformer in
than 300 °C emergency situations.
Blocked or restricted oil flow in
windings.
Other cooling problem, pumps
valves, etc.
Stray flux in damping beams of
yoke.
Overheating 300 to Defective contacts at bolted
700 °C connections (especially busbar),
contacts within tap changer,
connections between cable and
draw-rod of bushings.
Circulating currents between
yoke clamps and bolts, clamps
and laminations, in ground
wiring, bad welds or clamps in
magnetic shields.
Abraded insulation between
adjacent parallel conductors in
windings.
Overheating over Large circulating currents in tank
700 °C and core.
Minor currents in tank walls
created by high uncompensated
magnetic field.
Shorted core laminations.
Review Exercise
1. Give one reason by a one-to-one ratio transformer might
be used.
2. What is a possible cause of a pronounced hum coming
from a power transformer? Is there any possibility of damage to the
transformer?
3. What is the purpose of laminating the core of a power
transformer?
4. What direction would you expect the oil to flow in a power
transformer with forced circulation through external oil cooler and
how could you confirm that the flow was satisfactory?
5. What is meant by the expression "breathing of a
transformer" and what method is adopted to prevent the
transformer oil from absorbing moisture?
6. What are the main differences between the operation of
potential transformers and current transformers?
7. What special precaution is necessary in relation to current
transformers?
8. What action should be taken if a "Buchholz Gas" alarm was
received on a generator transformer?
9. What precautions are necessary to ensure the safe transfer
of an electrical load from one transformer to another?
10. List the tests to perform on an oil filled transformer if an
internal inspection has revealed a possible fault? Are there any
environmental considerations?
11. Pre-commissioning activities include filling the
transformer with oil. How long should the transformer be allowed to
settle before testing?
Circle the correct answer.
12 hours.
24 hours or as recommended by the manufacturer.
12 hours or as recommended by the manufacturer.
36 hours.
12. One important factor behind commissioning is to
establish base-line data for future testing?
True / False
13. Describe five pre-start up transformer tests?
14. Describe the recommended practices following
transformer pre-start tests?
15. Briefly discuss the effect of heat and contaminants on
transformers?
16. Describe the two categories of testing methods?
17. When a DC potential is applied across insulation, three
component resultants are present. What are they?
18. What conditions should be observed when conducting
insulation resistance tests on transformers?
19. More failures are attributed to tap changers than any
other transformer component?
True / False
20. Describe the two tap changer categories and their
operation?
21. Describe the polarisation index?
22. Describe two AC transformer tests? Why use AC?
23. Describe the action of the sudden pressure relay?
24. Describe the action of temp probes and gauges?
References
1. Electricity Commission of New South Wales Assistant Power Plant Operators
General Training Manual.
2. Pacific Power, Power Plant Operator Training Manual.
3. Fundamentals of Electrical Control (B.K. Sixsmith & J.E. Gorrie)
4. Lihir Management Company Power Station Operator Training Course (W.B. Smith)
5. Indo Kodeco Utilities Division Operations Manuals - chemical, electrical,
generator, fire, aux power (W.B. Smith)
6. New and Alternative Technologies for Electricity Generation (Pacific Power –
numerous contributors)
7. G.E. Power Systems Technical Papers - various (R.W. Smith, P. Polukort, C.E.
Maslak, C.M. Jones, B.D. Gardiner, David L. Chase)
8. Power transformer maintenance and testing (Department of the US Army)
9. Electrical Power Equipment Maintenance and Testing 2nd edition (Paul Gill)
10. Transformer maintenance (Hydroelectric research and technical services group)
11. Megger instrument company (On-line accessed March 2011)
Page 6