Calc no WHP-TLJOC-S-C-0101
Project title Thang Long Wellhead Platform Proj no 493-J1-0041
Client Thang Long JOC Phase/CTR
Calculation title Padeye Check for Topside Page of
Calculation objective
Establish the required proportions of the Thang Long topside padeyes.
Calculation method
Spreadsheet based calculations based on results of the COG shift study and Thang Long MTO..
Assumptions
The location of the COG of the topside will fall within a 1m x 1m envelope of that predicted by the Thang Long MTO.
References
API - RP2A Recommended Practice for Planning Designing and Constructing Fixed Offshore Platforms - WSD.
Manual of Steel Construction (ninth edition)- AISC
Conclusions
The padeye proportions and the connection to the primary framing of the topside are acceptable for the range of
loads anticipated.
ems/project_execution/pefm10b.xls
386423383.xls
Rev 19a
Calculation Checklist
Calc no WHP-TLJOC-S-C-0101
Project title Thang Long Wellhead Platform Proj no 0
Client Thang Long JOC Phase/CTR
Calculation title Padeye Check for Topside Page of
Please check boxes for all applicable items checked or delete if not appropriate:
Calculations:
Calculation number assigned and registered (usual format is Proj No-CAL-Discipline
code-Seq No eg XXXX-CAL-E-001, but format may be varied by Project Manager).
✘ Project title shown.
✘ Calculation title shown.
✘ Revision history box complete and signed.
Index.
Appropriate stamp for preliminary issues.
✘ Calculation objectives (aims) stated.
✘ Calculation method defined or described (including formulae if relevant).
✘ Reference made to text, standard or code. Check version/edition with
that required for project.
✘ Source of input data stated (with revision number and date if relevant).
✘ Assumptions stated.
✘ Summary of results or conclusions if appropriate.
For software based calculations, reference to software verification if available.
✘ Method clear and easy to follow.
✘ Input data correct.
✘ Calculation arithmetically correct OR software previously verified and reference
to verification checked.
✘ Calculation result within expected limits.
✘ Calculation tolerances stated if significant.
Units used as required by client.
✘ Abbreviations correct.
✘ Appropriate cross-references.
✘ Sketches included and clearly labelled, where required.
✘ Attachments included and referenced, as required.
Checking records:
Checked and annotated copy of calculation filed (use "Check Print" stamp).
Corrections made as required and calculation dated and signed on cover sheet by checker.
Revisions:
Changes clouded.
Revision history block updated.
Calculation re-checked if required.
ems/project_execution/pefm10b.xls
386423383.xls
Rev 19a
PROJ No 350/04662
PHASE/CTR
ACTIVITY PRIMARY DECK COG CALCULATION
PROJECT Thang Long Topsides FILE WHP-TLJOC-S-C-0101
SUBJECT COG shift assessment SHEET OF
25/08/09 DK
COG CALCULATION
1 2
18.00 m
A
8527 527 CoG 535 8535
Position of CoG Forces on Deck Legs Gridline : Position of Lifting Point on Deck Legs Gridline :
Joint x (m) y (m) z (m) Joint x (m) y (m) z (m)
527 -9.000 -10.500 22.200 8527 -9.000 -10.500 27.500
535 9.000 -10.500 22.200 8535 9.000 -10.500 27.500
587 -9.000 10.500 22.200 8587 -9.000 10.500 27.500
599 9.000 10.500 22.200 8599 9.000 10.500 27.500
25/08/09 DK
P(527) -1076.569
P(535) 0.000
=
P(587) 0.000
P(599) 1076.569
CoG Shift 535' Moment Eccentricity
x y Mx My
2.245 -5.603 22607.949 19378.242
P(527) 0.000
P(535) -1076.569
=
P(587) 1076.569
P(599) 0.000
PROJ No 350/04662
PHASE/CTR
ACTIVITY PRIMARY DECK COG CALCULATION
PROJECT Thang Long Topsides FILE WHP-TLJOC-S-C-0101
SUBJECT COG shift assessment SHEET OF
25/08/09 DK
0.000
=
1076.569
P(527) 0.000
P(535) 1076.569
=
P(587) -1076.569
P(599) 0.000
P(527) 1076.569
P(535) 0.000
=
P(587) 0.000
P(599) -1076.569
PROJ No 350/04662
PHASE/CTR
ACTIVITY PRIMARY DECK COG CALCULATION
PROJECT Thang Long Topsides FILE WHP-TLJOC-S-C-0101
SUBJECT COG shift assessment SHEET OF
25/08/09 DK
Joint 8587
Maximum Sling Force from the hook point to joint (incl. COG shift)
Maximum Sling Force from the hook point to joint (No COG shift)
Joint 8599
Maximum Sling Force from the hook point to joint (incl. COG shift)
Maximum Sling Force from the hook point to joint (No COG shift)
25/08/09 DK
Joint 8527
Maximum Sling Force from the hook point to joint (incl. COG shift)
Maximum Sling Force from the hook point to joint (No COG shift)
Joint 8535
Maximum Sling Force from the hook point to joint (incl. COG shift)
Maximum Sling Force from the hook point to joint (No COG shift)
Padeye Forces
= 1.0
% of P = 15.0 %
Ps = 326.0 kN 73.29 kips
q = 85.0 deg 1.48 rad
P = 326.0 kN 73.29 kips
Px = 28.4 kN 6.39 kips
Py = 48.9 kN 10.99 kips
Pz = 324.8 kN 73.01 kips
Shackle clearance
Cw (min) = 10.3 mm 0.41 in
Cw (max) = 20.6 mm 0.81 in
C(w) = 27 mm 1.05 in
C(L) = 19 mm 0.75 in
Weld clearance
C(weld) = 0 mm 0.00 in NG
C(insp) = 338 mm 13.29 in (Cheek Plate Truncated OK)
Design for Bearing
Tension Check
Ft = 112.5 MPa 16.32 ksi
Pz = 324.76 kN 73.01 kips
At = 5000 mm 2
7.75 in2
ft = 65.0 MPa 9.42 ksi
UF = 0.58
Section properties
L = 275 mm 10.83 in
A2 = 6875 mm 2
10.66 in2
Iyy = 3.6E+05 mm4 0.86 in4
Ixx = 4.3E+07 mm4 104.09 in4
Zyy = 2.9E+04 mm 3
1.75 in3
Zxx = 3.2E+05 mm3 19.23 in3
Summary of Utilisations
UF CATEGORY
1.66 Standard bearing
#DIV/0! Cheek plate shear
#DIV/0! Cheek plate weld shear
0.65 Pin "Pull-out" shear
0.58 Tension - Section 1
0.06 Shear - Section 1
3.57 Combined bending & axial - Section 2
WORST CASE
#DIV/0!
PROJ No #REF!
PHSE/CTR #REF!
ACTIVITY #REF!
PROJECT #REF! FILE #REF!
SUBJECT Padeye Design SHEET OF
#REF! #REF!
P slin g
Z'
R
S E C T IO N 1
X '
dh r
T p
d
t
f
S E C T IO N 2
R = M a i n p l a te r a d i u s q = S lin g A n g le
T p = M a i n p la te th i c k n e s s X ' = L o cal p ad ey e X -ax is
r = C h e e k p la te ra d iu s Y ' = L o c a l p a d e y e Y - a x is ( d i re c tl y o u t o f p a g e )
t = C h e e k p l a te th i c k n e s s Z ' = L o c al p ad ey e Z -ax is
d h = H o l e d i a m e te r S e c tio n 1 = T h r o u g h p a d e y e h o l e
d = L e v e r a r m f r o m S e c ti o n 1 to S e c t i o n 2 S e c tio n 2 = A t b a s e o f p a d e y e
f = S l o p e o f p a d e y e s i d e s to th e h o r iz o n ta l
#REF! #REF!
Nomenclature
Ap Cross sectional area (main plate only)
A2 Cross sectional area for section 2
Ab Bearing area
At Cross sectional area at section 1
Avcp Shear area of cheek plate
Av Shear area of padeye
Aw Shear area of weld
C(insp) Weld inspection clearance
C(L) Shackle inner length clearance
C(w) Shackle inner width clearance
C(weld) Minimum cheek plate weld clearance
Comb. UF Utilisation for combined bending and axial
Cw (max) Maximum recommended inner width clearance
Cw (min) Minimum recommended inner width clearance
d Refer to diagram
db Bow diameter
dh Hole diameter
dp Pin diameter
E Young's Modulus
f Refer to diagram
fa Tensile stress at section 2
Fa Allowable AISC tensile stress (0.6Fy)
fb Actual bearing stress
Fb Allowable bearing stress (AISC)
fbx Stress for in-plane bending
Fbx Allowable AISC stress for in-plane bending (0.66Fy)
fby Stress for out of plane bending
Fby Allowable AISC stress for out of plane bending (0.75Fy)
Fe Allowable Von Mises
feq Equivalent Von Mises
fhz Actual Hertz stress
Fhz Allowable Hertz stress (2Fy)
fs Shear stress at section 1
ft Tensile stress at section 1
Ft Allowable tensile stress (AISC)
fv Shear stress
Fv Allowable shear stress (AISC)
fv(ave) Average shear stress
fw Shear stress
Fw Weld allowable shear stress
Fwt Weld tension stress
Fy Yield Stress
Ixx Moment of inertia about strong axis
Iyy Moment of inertia about weak axis
Lsh Inside Length of shackle
L Plate length
n Poisson's Ratio
P Dynamic Sling Force (i.e Ps*DAF)
Pcheek Force in single cheek plate
Ps Static Sling Force in (kN)
Px Component of Dynamic force in horizontal direction
Py Out of Plane Component of Force (= 25% of Total Dynamic Force)
Pz Vertical Component of Total Dynamic Force
q Sling angle in degrees to horizontal
r Cheek plate radius
R Main plate radius
SC Shackle Capacity
t Cheek plate thickness
Tp Main plate thickness
tw Cheek plate weld size
V Pullout shear force (double failure plane) = P sling/2
w Inside width of shackle
PROJ No #REF!
PHSE/CTR #REF!
ACTIVITY #REF!
PROJECT #REF! FILE #REF!
SUBJECT Padeye Design SHEET OF
#REF! #REF!
Zxx Section modulus about strong axis
Zyy Section modulus about weak axis
386423383.xls 05/08/2018
Packaged Equipment
0.914 OD x 2.54
3 V2-LA Closed Drains Sump LA-02-DX-009 1.73 m3 100% 350 @ 80 N/A 1,250 2,980
T/T
CS + 3mm CA Weight estimate from GA drawing, AEL to confirm 1 1250 -4.6 0 20
4 P2-LA Closed Drain Pump LA-02-DX-009 0.18 m3/hr 100% 20,500 @ 80 N/A 10 10 0.2 D x 0.3 H 316L SS Weight from Sprague catalogue - model no. S-216-J-60 1 10 -4.6 -1 18
0.324 OD x 1.825
6 V1-LA Instrument Gas Knockout Pot LA-02-DX-010 0.13 m3 100% 4,500 / FV @ 80 N/A 500 630
T/T
CS + 3mm CA Weight estimate from GA drawing, AEL to confirm 1 500 -5 -2.5 23.8
0.35 D x 3.5 L Weight estimate based on Sch 160 pipe, 1500# flanges and
8 L1-LA Pig Launcher LA-02-DX-007 N/A N/A 23,000 @ 100 N/A 3,000 3,250
(HOLD)
CS + 3mm CA
GD Engineering QOC (included in Piping MTO)
1 3000 0 0 25
ATM + Full Liq @ Weight estimate from GA drawing, AEL to confirm. Test weight
9 T2-LA / T3-LA Chemical Injection Storage Tanks LA-01-DJ-007 2 x 1.5 m3 2 x 50%
60
N/A 1,800 3,300 1.2 x 1.6 x 1.75 316L SS
is for one compartment only
1 1800 4.5 2.25 24.3
P1-CI1LA /
11 Chemical Injection Pumps LA-01-DJ-007 75 L/day 2 x 100% 30,000 @ HOLD N/A Included in CI1-LA Included in CI1-LA Included in CI1-LA 316L SS 1
P2-CI1LA
ATM + Full Liq @ 316L SS Weight estimated on preliminary size. AEL to confirm size and
12 Diesel Fuel Storage Tank 120 L 100%
60
N/A 100 230 0.6 x 0.3 x 0.7
(HOLD) weight
1 100 7 -0.8 24.8
Vendor
13 Fixed Boom 4.1T Crane 4.1T @ 15 m 100% N/A N/A 4,900 4,900 15.2 m boom
Standard
Weight from preliminary Vendor data. AEL to confirm 1 4900 7.6 0 27.9
Included in crane Vendor Control panel is included in crane size, but has 1.7 m swing
14 Crane Control Panel N/A 100% N/A N/A 350 350
size Standard radius
1 350 7.6 3.25 27.9
Vendor Vendor
15 Crane Hydraulic Power Pack
Standard
100% N/A N/A 1,400 3,100 1.4 x 2.1 x 2.6
Standard
Weight from preliminary Vendor data. AEL to confirm 1 1400 6.6 1.3 25.3
LA-02-DJ-004 / Weight and size from Victoria WHP data. AEL to confirm
16 WP1-LA Wellhead Control Panel
009
N/A 100% N/A HOLD 1,250 1,250 1.3 x 1.0 x 1.9 316L SS
weight and size
1 1250 -4.8 2 25
18 Life Buoy (with thow line) N/A N/A AEL to provide size and weight 1 0
19 Life Raft (8 person) N/A N/A AEL to provide size and weight 1 0
20 Controlled Decent Device N/A N/A AEL to provide size and weight 1 0
21 9 kg Dry Powder Fire Extinguisher N/A N/A All safety equipment AEL to provide size and weight 1 0
may be shipped
22 Portable Eye Wash Unit N/A N/A loose and has a total AEL to provide size and weight 1 0
weight of
23 First Aid Box N/A N/A approximately 500kg AEL to provide size and weight 1 0
(based on Victoria
24 Personal Protection Equipment Box N/A N/A WHP) AEL to provide size and weight 1 0
25 Life Jacket Box N/A N/A AEL to provide size and weight 1 0
27 Appropriate Helideck Fire & Safety Equipment N/A N/A AEL to provide size and weight 1 0
Electrical 1 0
Vendor Weight and size from Victoria WHP data. AEL to confirm
28 Navigation Light N/A N/A N/A N/A 10 10 0.4 D x 0.8 H
Standard weight and size
1 10 11.6 3.4 22
Vendor Weight and size from Victoria WHP data. AEL to confirm
29 Primary Power - Solar Array SOL1-LA TBA HOLD 1 x 100% N/A N/A 250 250 9.0 x 2.5
Standard weight and size
1 250 0 7 22
Vendor Weight and size from Northern Lights catalogue - model no.
30 Secondary Power - Diesel Generator TBA 8 kW (HOLD) N/A N/A N/A 300 300 1.0 x 0.5 x 0.9
Standard NL378K. AEL to confirm weight and size
1 300 6.8 -1.3 24.3
Vendor Weight and size from Victoria WHP data for one unit only. AEL
31 Battery Boxes HOLD 2 x 100% N/A N/A 350 350 1.3 x 0.4 x 1.0
Standard to confirm weight and size
1 350 6 -1.6 24
Miscellaneous 1 0
32 Workbench N/A N/A N/A N/A 60 60 0.6 x 0.6 x 1.2 CS Weight from Worley estimate. AEL to confirm 1 60 0 0 22
Lift Weight
X Y Z
file:///conversion/tmp/scratch/386423383.xls 15 of 16
386423383.xls
Thang Long Wellhead Platform Topside MTO CLIENT Thang Long JOC
PROJECT THANG LONG TOPSIDE. BILL OF MATERIALS
JOB NO. 49.-J1-0041
BY D. KIEN
REVISION A
DATE 9/15/2009
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 19.3 2895 1.948 -3.25 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 6 1.5 1350 0 0 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 2 9.4 2822 6.9 0 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 9.8 1472 3.18 3.25 20.65
MAIN DECK PLATE GIRDER PG1 - - 227 AS3678-350 1 9.1 2066 0.913 3.25 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 6.5 975 -7.702 0 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 6.5 975 -3.637 0 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 6.5 975 -2.137 0 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 6.5 975 0.693 0 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 6.5 975 2.193 0 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 6.5 975 7.598 0 20.65
MAIN DECK WELDED BEAM 700WB150 - - 150 AS3679.2-300 1 6.5 975 11.598 0 20.65
MAIN DECK BEAM 410UB60 - - 60 AS3679.1-300 1 6.50 390 3.598 0 20.8
MAIN DECK BEAM 200UB25 - - 25 AS3679.1-300 6 4.07 620 -5.67 0 20.9
MAIN DECK BEAM 200UB25 - - 25 AS3679.1-300 1 14.32 364 -0.722 0 20.9
MAIN DECK BEAM 200UB25 - - 25 AS3679.1-300 1 1.50 38 1.44 0 20.9
MAIN DECK BEAM 200UB25 - - 25 AS3679.1-300 6 6.50 991 7.598 0 20.9
MAIN DECK BEAM 150PFC - - 18 AS3679.1-300 4 1.50 106 -2.887 0 20.9
MAIN DECK BEAM 150PFC - - 18 AS3679.1-300 1 8.52 151 -0.49 0 20.9
MAIN DECK BEAM 150PFC - - 18 AS3679.1-300 4 1.41 99 2.9 0 20.9
MEZZANINE DECK WELDED BEAM PG2 - - 181 AS3678-350 1 4.0 724 5.598 3.25 23.59
MEZZANINE DECK WELDED BEAM PG2 - - 181 AS3678-350 1 3.8 688 7.598 1.35 23.59
MEZZANINE DECK BEAM 410UB60 - - 60 AS3679.1-300 1 4.00 240 5.598 -3.25 23.6
MEZZANINE DECK BEAM 410UB60 - - 60 AS3679.1-300 1 2.70 162 7.598 -1.9 23.6
MEZZANINE DECK BEAM 200UB25 - - 25 AS3679.1-300 1 6.50 165 -7.702 0 23.715
MEZZANINE DECK BEAM 310UB40 - - 40 AS3679.1-300 1 6.50 263 -3.637 0 23.663
MEZZANINE DECK BEAM 150PFC - - 18 AS3679.1-300 2 4.07 144 -5.67 -1.86 23.74
MEZZANINE DECK BEAM 150PFC - - 18 AS3679.1-300 1 6.50 115 -7 0 23.74
MEZZANINE DECK BEAM 150PFC - - 18 AS3679.1-300 4 3.63 257 -5.32 0.93 23.74
MEZZANINE DECK BEAM 150PFC - - 18 AS3679.1-300 2 4.07 144 -5.67 0 23.74
MEZZANINE DECK BEAM 150PFC - - 18 AS3679.1-300 2 7.00 248 4.25 0 23.74
MEZZANINE DECK BEAM 150PFC - - 18 AS3679.1-300 4 4.00 283 5.598 1.2 23.74
MEZZANINE DECK BEAM 150PFC - - 18 AS3679.1-300 1 15.00 266 4.1 0 23.74
HELIDECK WING PANEL NTH BEAM 360UB45 - - 45 AS3679.1-300 1 10.70 478 -2.052 3.55 27.667
HELIDECK WING PANEL NTH BEAM 360UB45 - - 45 AS3679.1-300 2 2.94 263 -2.052 3.55 26.87
HELIDECK WING PANEL NTH BEAM 360UB45 - - 45 AS3679.1-300 1 6.60 295 -2.052 3.55 25.87
HELIDECK WING PANEL NTH BEAM 360UB45 - - 45 AS3679.1-300 1 1.05 47 -6.202 3.55 27.37
HELIDECK WING PANEL NTH BEAM 360UB45 - - 45 AS3679.1-300 1 2.10 94 0.728 3.55 26.87
HELIDECK WING PANEL NTH BEAM 310UB40 - - 40 AS3679.1-300 1 2.10 85 -2.187 3.55 26.87
HELIDECK WING PANEL NTH BEAM 200PFC - - 23 AS3679.1-300 5 2.10 240 -2.187 3.55 26.87
HELIDECK WING PANEL NTH BEAM 200PFC - - 23 AS3679.1-300 1 1.40 32 1.58 3.55 27.17
HELIDECK WING PANEL NTH BEAM 200PFC - - 23 AS3679.1-300 1 0.70 16 2.44 3.55 27.52
HELIDECK WING PANEL NTH FLOOR PLATE PL 8 mm 20.00 - 62.80 AS3678-250 - 1256 -2.052 3.55 26.87
HELIDECK NETTING HANDRAIL INCL. KICK PLATE (ALLOWANCE) - - - 25 - 14 - 350 -2.052 3.55 25.87
HELIDECK WING PANEL STH BEAM 360UB45 - - 45 AS3679.1-300 1 10.70 478 -2.052 -3.55 27.667
HELIDECK WING PANEL STH BEAM 360UB45 - - 45 AS3679.1-300 2 2.94 263 -2.052 -3.55 26.87
HELIDECK WING PANEL STH BEAM 360UB45 - - 45 AS3679.1-300 1 6.60 295 -2.052 -3.55 25.87
HELIDECK WING PANEL STH BEAM 360UB45 - - 45 AS3679.1-300 1 1.05 47 -6.202 -3.55 27.37
HELIDECK WING PANEL STH BEAM 360UB45 - - 45 AS3679.1-300 1 2.10 94 0.728 -3.55 26.87
HELIDECK WING PANEL STH BEAM 310UB40 - - 40 AS3679.1-300 1 2.10 85 -2.187 -3.55 26.87
HELIDECK WING PANEL STH BEAM 200PFC - - 23 AS3679.1-300 5 2.10 240 -2.187 -3.55 26.87
HELIDECK WING PANEL STH BEAM 200PFC - - 23 AS3679.1-300 1 1.40 32 1.58 -3.55 27.17
HELIDECK WING PANEL STH BEAM 200PFC - - 23 AS3679.1-300 1 0.70 16 2.44 -3.55 27.52
HELIDECK WING PANEL NTH FLOOR PLATE PL 8 mm 20.00 - 62.80 AS3678-250 - 1256 -2.052 -3.55 26.87
HELIDECK NETTING HANDRAIL INCL. KICK PLATE (ALLOWANCE) - - - 25 - 14 - 350 -2.052 -3.55 25.87
MAIN DECK FLANGE INSERTS ETC ALLOWANCE 30mm RING STIFFENER 4.00 30 235.50 AS3678-350 - 942 0 0 20.65
MEZZANINE DECK FLANGE INSERTS ETC ALLOWANCE 30mm RING STIFFENER 1.50 30 235.50 AS3678-350 - 353 0 0 23.6
HELIDECK FLANGE INSERTS ETC ALLOWANCE 30mm RING STIFFENER 3.00 30 235.50 AS3678-350 - 707 0 0 27.67
CONTROL ROOM MEZZ FRAMING AND FIT OUT ONLY (2.5 kPa) INCLUDES WALLS ETC 10.00 - 250.00 - - 2500 6.29 -1.63 22.7
MAIN DECK STIFFENER PLATE (ALLOWANCE) PL 10mm 10.00 - 78.50 AS3678-250 - 785 0 0 20.5
MEZZANINE DECK STIFFENER PLATE (ALLOWANCE) PL 10mm 2.50 - 78.50 AS3678-250 - 196 0 0 23.6
HELIDECK STIFFENER PLATE (ALLOWANCE) PL 10mm 5.00 - 78.50 AS3678-250 - 393 -2.052 0 27.7
76213 SUM