Sie sind auf Seite 1von 8

International Journal of Engineering & Technology IJET-IJENS Vol:15 No:04 35

Cost Overrun in Construction Projects in Saudi


Arabia: Contractors‘ Perspective
Abdulaziz Alghonamy
Engineering Faculty, University of Hail, Hail, Saudi Arabia
Abstract-- Cost performance of a project is usually a construction projects in Saudi Arabia were completed within
particularly important consideration for the construction parties. the specified cost and schedule. Therefore, it is very necessary
Often, Cost overrun is one of the most recurring problems in the to identify the main contributors to cost overrun in
construction industry and it has an adverse impact on project construction projects in Saudi Arabia in order to overcome
success in terms of time, cost, quality and safety. This study is this critical problem. This paper presents the findings of a
conducted to investigate the cost overrun in construction projects
survey aims at identifying the risk matrix for cost overrun
in Saudi Arabia in order to identify the causes of cost overrun
and their importance according to contractors through a causes in construction projects in Saudi Arabia from the
questionnaire survey. A questionnaire survey was undertaken of contractors‘ perspective. It is hoped that these findings will
43 contractors working on construction projects in the Northern guide efforts to enhance the performance of the construction
Province of Saudi Arabia. 34 cost overrun causes were identified industry in Saudi Arabia and other developing countries.
through literature review. The study concluded that the top cost
overrun causes in construction projects in Saudi Arabia from Previous studies
contractors’ perspective are: bid award for lowest price, frequent Many studies were conducted to examine the cost overrun
changes in design, improper planning, long period between causes in construction projects. Flyvbjerg et al. (2003)
design and time of implementation, and payments delay. conducted a study of 258 transportation infrastructure projects.
Index Term-- cost overrun, construction, contractors, The distribution of the 258 projects on the three types of
contributors, risk matrix. project was as follows: rail: 58, fixed link (bridges and
tunnels): 33, and road: 167 projects. The projects were located
I NTRODUCTION in 20 nations on 5 continents, including both developed and
The construction industry is at or near the top in the annual developing nations. The geographical distribution of projects
rate of business failures and resulting liabilities compared to was: Europe: 181, North America: 61, and other: 16 projects.
other industries. This is because it is a risky business with too The main findings from the study are: (1) 9 out of 10 transport
many uncertainties that management has to deal with infrastructure projects fall victim to cost escalation, (2) For all
(Enshassi et al., 2007). The construction process is subjected project types average cost escalation is 28%, (3) Cost
to the influence of highly changing variables and escalation exists across 20 nations and 5 continents; it appears
unpredictable causes, such as: resources availability, to be a global phenomenon, (4) Cost escalation appears to be
environmental conditions, financial problems, political more pronounced in developing nations than in North America
conditions, poor productivity, and contractual relations. Cost, and Europe, (5) Cost escalation has not decreased over the
time and quality have their proven importance as the prime past 70 years. Al-Zarooni et al. (2000) conducted a survey to
factors for project success. A project may not be regarded as a investigate variations in UAE public projects' estimates. They
successful endeavor until it satisfies the cost, time, and quality found that the variations (positive or negative) between
limitations applied to it. However, it is not uncommon to see a feasibility and contract cost, ranging between -28.5% and
construction project failing to achieve its goal within the +36%. They stated that these variations could be explained
specified cost, time, and quality (Nega, 2008). However, the knowing that feasibility estimates in the government agencies
construction industry is full of projects that were completed are usually budgeted using a Single Unit Estimating (cost per
with significant cost overrun (Amhel et al., 2010). This square foot) basis, regardless of the nature of projects and
problem is not unique to developed countries but is also their associated risks or the construction complexity of each
experienced in most of the developing economies too (Kaliba building type. Odeck (2004) investigated the statistical
et al., 2009). relationship between actual and estimated costs of road
construction using data from Norwegian road construction
Saudi Arabia has experienced a construction boom during the over the years 1992-1995. The findings reveal a discrepancy
past three decades, attracting construction professionals from between estimated and actual costs, with a mean cost overrun
all over the world. According to the Saudi Ministry of of 7.9% ranging from -59% to +183%. In absolute terms, cost
Planning, the construction industry contributed between 30% overruns amounted to a formidable 519 million Norwegian
to 40% of the non-oil productive sectors at the end of each kroner. He concluded that one particular new finding that has
National Development Plan from 1980 to 2000 (Cordsman, not been shown before in previous studies is that cost overruns
2000). However, cost and time performance is considered to appear to be more predominant among smaller projects as
be one of the most serious and frequent problems in the Saudi compared to larger ones. He also concluded that the size of
Arabian construction industry (Faridi and Al-Sayegh, 2006). cost overruns can be influenced by completion time of the
Assaf and Al-Hejji (2006) found that only 30% of projects and the regions where projects are situated.

152904-6868-IJET-IJENS © August 2015 IJENS


IJENS
International Journal of Engineering & Technology IJET-IJENS Vol:15 No:04 36
evaluate the content of the questionnaire. Modifications and
Al-Momani (1996) conducted a study of construction cost changes have been done. The questionnaire is divided into two
prediction for public school buildings in Jordan. The study main parts. Part I is related to general information for the
conduct a data of 125 school projects carried out in Jordan for company. The surveyed contractors were requested to answer
the period 1984 - 1994. The results indicate that the actual cost questions pertaining to their experience in construction
(i.e. at the time of project completion) exceeds the original industry. Part II includes the list of the identified cost overrun
contract price by 30% while change orders result in an 8.3% causes in construction projects.
cost overrun. Enshassi et al. (2005) identified the essential
factors and their relative importance that affect accuracy of Data collection and analysis
cost estimation of building contracts in the Gaza strip. The 43 contractors working on construction projects were
results of analyzing 51 factors considered in a questionnaire successfully questioned. The questionnaire gave each
survey concluded that the main factors are: location of the respondent an opportunity to identify variables that they
project, segmentation of the Gaza strip and limitation of perceived as likely to contribute to cost overruns by
movements between areas, political situation, and financial responding on a scale from 5 (very important) to 1 (very low
status of the owner. Shehu et al. (2014) conducted a study in important). Participants then rated the frequency of occurrence
Malaysia to explore the construction cost performance of for each variable on project that they have experiences on an
projects in terms of public and private sectors based on ordinal scale: very high (5), high (4), medium (3), low (2), or
procurement methods, tendering methods, nature of project very low (1). For each variable, the mean value of the
and project size. A questionnaire survey of Malaysian respondents‘ importance rating was named the severity index.
quantity-surveying consultants was performed. They found Secondly, the mean value from respondents‘ frequency rating
that 55% of Malaysian construction projects experienced cost was named the frequency index. Accordingly the severity and
overruns and that public sector projects performed better than frequency levels are identified using Table 1. Finally, the zone
private sector projects. Based on procurement and tendering of each variable in the risk matrix was identified using Figure
methods, they found that design and build delivery method 1.
was associated with reduced cost overrun, followed by
traditional then project management. Table I
Level of cause‘s severity and frequency
Koleola et al. (2008) concluded six important factors affecting Index value (Scale) Severity Frequency
the accuracy of a pre-tender cost estimate in Nigerian
≤ 20% very low (VL) very low (VL)
construction projects. These six factors are: expertise of
consultants, quality of information and flow requirements, the 20% - 40% low (L) low (L)
project team's experience of the construction type, the tender
period and market condition, extent of completion of pre- 40% - 60% moderate (M) moderate (M)
contract design, and the complexity of design and 60% - 80% high (H) high (H)
construction. Frimpong et al. (2003) concluded that the main
causes of cost overrun and cost overruns in construction of 80% - 100% very high (VH) very high (VH)
groundwater projects in Ghana are: monthly payment
difficulties from agencies; poor contractor management;
material procurement; poor technical performances; and
escalation of material prices. Iyer et al. (2005) presented the
findings of a questionnaire survey conducted on the factors
affecting cost performance of Indian construction projects. 55
factors were identified. They concluded that the most factors
adversely affecting the cost performances of construction
projects in India are: conflict among project participants,
ignorance and lack of knowledge, presence of poor project
specific attributes and non existence of cooperation, hostile
socio economic and climatic conditions, reluctance in timely
decision, aggressive competition at tender stage; and short bid
preparation time.

Research Method
34 cost overrun causes in construction projects were defined
through a detailed literature review. The causes were tabulated
into a questionnaire form. Then the draft questionnaire was
discussed with three experts in construction industry to

152904-6868-IJET-IJENS © August 2015 IJENS


IJENS
International Journal of Engineering & Technology IJET-IJENS Vol:15 No:04 37

VH

Frequency M

VL

VL L M H VH

Severity
Fig. 1. The risk matrix

The risk matrix includes three zones: red, yellow, and green; RESULTS AND DISCUSSION
such that: Participants
The target populations in this study are the total number of
construction contractors in the Northern Province of Saudi
1) Green zone: risks in this zone are low level, and can Arabia. Simple random sampling was used to select the
be ignored. participants from the available list.

2) Yellow zone: risks in this zone are of moderate The questionnaire was sent out to a total of 60 contractors
importance, and should be controlled. asking their perception in ranking the identified 34 causes in
terms of severity and frequency using an ordinal scale. A total
3) Red zone: risks in this zone are of critical of 43 contractors filled the questionnaire. The response rate by
importance. These are the top priorities, and close contractors is 72%. On average, the respondents have
attention should be paid to them. experience of more than 7 years.

Causes’ risk matrix


Statistical analysis Table II shows the results of risk matrix for contributors to
The statistical analyses for cost overrun causes as assessed by cost overrun in construction projects in Saudi Arabia from
contractors are performed. The tests include the computation contractors‘ perspective. It shows that 5 causes are located in
of the weighted mean, standard deviation, and coefficient of the red zone (critical causes), 28 causes are located in the
variation. These tests are used to check the compactness and yellow zone (moderate importance), and one cause is located
consistency of the responses. in the green zone (low level).

152904-6868-IJET-IJENS © August 2015 IJENS


IJENS
International Journal of Engineering & Technology IJET-IJENS Vol:15 No:04 38

Table II
Risk matrix for cost overrun causes from contractors perspective

Cause
Cause S.I Level F.I Level
zone

additional work 43.65 M 50.62 M yellow

bid award for lowest price 63.00 H 52.35 M red


changes in material types and specifications during
construction 55.32 M 51.23 M yellow

contract management 53.26 M 45.6 M yellow

contractual procedure 41.98 M 40.18 L yellow

disputes on site 47.82 M 45.4 M yellow

duration of contract period 57.82 M 52.68 M yellow

economic instability 40.32 M 58.44 M yellow

effects of weather 42.82 M 41.92 M yellow

fluctuation of prices of materials 56.13 M 52.79 M yellow

frequent changes in design 64.74 H 59.31 M red

high interest rates by bankers 39.48 M 41.05 M yellow

improper planning 71.36 H 64.53 H red

inadequate production of raw materials by the country 55.32 M 49.75 M yellow

inflationary pressure 59.56 M 57.57 M yellow

lack of adequate manpower 52.3 M 58.44 M yellow

lack of contractor experience 52.82 M 50.62 M yellow

lack of coordination between design and contractors 54.48 M 56.7 M yellow

late design work 58.65 M 48.01 M yellow

level of competitors 48.65 M 54.09 M yellow

long period between design and time of implementation 63.87 H 60.18 H red

manipulation of suppliers 50.32 M 48.01 M yellow

mistakes in design 52.82 M 59.31 M yellow

number of competitors 46.98 M 50.62 M yellow

152904-6868-IJET-IJENS © August 2015 IJENS


IJENS
International Journal of Engineering & Technology IJET-IJENS Vol:15 No:04 39
number of projects going at the same time 49.48 M 51.48 M yellow

payments delay 74.22 H 61.92 H red

poor financial control on site 54.48 M 53.22 M yellow

poor labor productivity 55.17 M 49.16 M yellow

poor relationship between managers and labors 53.65 M 57.57 M yellow

poor resource management 45.32 M 48.88 M yellow

project location 38.65 M 51.48 M yellow

rework 56.17 M 56.7 M yellow

social and cultural impacts 32.82 L 31.48 L green

unreasonable project time frame 56.98 M 51.48 M yellow

Top cost overrun causes planning will get resources together to achieve the
project objectives within the limited time, cost and
Table 3 shows the top contributors to cost overruns in quality.
construction projects in Saudi Arabia from contractors‘
perspective, they are: 4. Long period between design and time of
implementation: The owner should try to shorten the
1. Frequent changes in design: this could happen due to period between the design and time of
the less involvement of the owners in the early implementation, since during this period many
phases of the projects or due to the design mistakes influencing changes could be arise that might lead to
and scope changes. This situation interrupts the cost overrun.
planned schedule, especially if the changes lead to
additional works or rework. Consequently, the 5. Payments delay: Construction works involve high
project cost will increase. daily expenses and most of the contractors cannot
fulfill these expenses when the payments are delayed.
2. Bid award for lowest price: in general, the clients Due to the dely of payments by the owner, work
award bids to the lowest bidder to execute their progress can be delayed because of inadequate cash
projects. However, the lowest bidders might be low flow to support the construction expenses by
qualified contractors. Consequently, poor cost contractor, and thus project cost will increase.
performance might occur.

3. Improper planning: planning has a vital role in the


success of the construction projects, as proper

Table III
Top cost overrun causes from contractors' perspective
Risk
Cause S.I Scale F.I Scale
zone
bid award for lowest price 63 H 52.35 M red
frequent changes in design 64.74 H 59.31 M red
improper planning 71.36 H 64.53 H red
long period between design and time of
red
implementation 63.87 H 60.18 H
payments delay 74.22 H 61.92 H red

152904-6868-IJET-IJENS © August 2015 IJENS


IJENS
International Journal of Engineering & Technology IJET-IJENS Vol:15 No:04 40
Statistical analyses Figure 3 show a good data consistency and agreement
between the respondents on the severity and the frequency of
Table IV presents the statistical analyses for cost overrun the identified causes.
causes as assessed by the surveyed contractors. The table
contains the computation of the weighted mean, standard
deviation, and coefficient of variation. Table 4, Figure 2, and
Table IV
Statistical analyses for cost overrun causes as assessed by contractors
Severity Frequency
Cause
X' Sn C.V (%) X' Sn C.V (%)

additional work 2.18 1.02 41.19 2.53 0.98 46.11

bid award for lowest price 3.15 1.02 39.58 2.62 0.87 27.7

changes in material types and specifications during


construction 2.77 0.97 30.88 2.56 0.51 19.2

contract management 2.66 1.03 30.89 2.28 0.53 14.28

contractual procedure 2.10 0.61 31.95 2.01 0.56 28.47

disputes on site 2.39 0.94 42.9 2.27 1.14 48.46

duration of contract period 2.89 1.14 36.05 2.63 0.91 31.86

economic instability 2.02 1.15 39.59 2.92 0.9 46.08

effects of weather 2.14 0.88 43.64 2.10 0.93 44.83

fluctuation of prices of materials 2.81 1.1 34.84 2.64 0.72 18.51

frequent changes in design 3.24 0.94 31.6 2.97 0.89 27.54

high interest rates by bankers 1.97 0.85 43.55 2.05 0.79 41.73

improper planning 3.57 0.93 28.31 3.23 0.47 11.09

inadequate production of raw materials by the country 2.77 0.98 40.23 2.49 0.8 29.44

inflationary pressure 2.98 1.09 38.09 2.88 0.57 13.97

lack of adequate manpower 2.62 1.08 36.99 2.92 0.98 26.88

lack of contractor experience 2.64 1.06 42.79 2.53 1.02 39.29

lack of coordination between design and contractors 2.72 0.94 33.35 2.84 0.95 35.49

late design work 2.93 0.73 31.3 2.40 0.88 30.47

level of competitors 2.43 0.78 29.24 2.70 1.03 42.98

long period between design and time of implementation 3.19 0.92 30.43 3.01 0.88 27.65

manipulation of suppliers 2.52 1.01 43.25 2.40 1.16 46.79

152904-6868-IJET-IJENS © August 2015 IJENS


IJENS
International Journal of Engineering & Technology IJET-IJENS Vol:15 No:04 41
mistakes in design 2.64 0.94 31.6 2.97 1.1 42.11

number of competitors 2.35 0.98 39.53 2.53 1.03 44.79

number of projects going at the same time 2.47 0.8 31.49 2.57 0.85 35.32

payments cost overrun 3.71 1.09 34.86 3.10 0.91 24.12

poor financial control on site 2.72 0.98 37.13 2.66 1.25 46.07

poor labor productivity 2.76 0.9 28.15 2.46 0.66 17.33

poor relationship between managers and labors 2.68 1.05 36.72 2.88 1.12 42.29

poor resource management 2.27 0.98 40.88 2.44 0.95 42.96

project location 1.93 1.02 40.41 2.57 0.66 36.32

rework 2.81 1.25 44.29 2.84 0.94 30.47

social and cultural impacts 1.64 0.89 40.88 1.57 1 29.68

unreasonable project time frame 2.85 1.06 39.33 2.57 46.11

1.6
1.4
Standard deviation (Sn)

1.2
1
0.8
0.6
0.4
0.2
0
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50
Mean (X')

Fig. 2. The cause‘s mean vs standard deviation for severity responses

152904-6868-IJET-IJENS © August 2015 IJENS


IJENS
International Journal of Engineering & Technology IJET-IJENS Vol:15 No:04 42

1.6
1.4

Standard deviation (Sn)


1.2
1
0.8
0.6
0.4
0.2
0
0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50
Mean (X')

Fig. 2. The cause‘s mean vs standard deviation for frequency responses

CONCLUSION [4] Assaf, S. and Al-Hejji, S. (2006). Causes of Cost overrun in large
construction projects. International Journal of Project
Cost performance of a project is usually a particularly
Management , 24, 349-357.
important consideration for the construction parties. Often, the [5] Cordsman, A. (2000), ‗Saudi Arabia enters the 21st century V:
most troublesome construction disputes involve cost overrun economic, demographic and social challenges‘. Center for
and failure to complete the work in the specified budget. Strategic and International Studies, 1800 K Street NW,
Washington DC 20006.
Many variables have an impact upon cost overrun in
[6] Enshassi, A.; Mohamed, S.; and Madi, I. (2005). Factors affecting
construction project in Saudi Arabia. A questionnaire survey accuracy of cost estimation of building contracts in Gaza Strip.
was undertaken of 43 contractors working on construction Journal of Financial Management of Property and Construction,
projects in the Northern Province of Saudi Arabia. 34 cost 10(2): 115 – 125.
[7] Enshassi, A.; Mohamed, S.; Madi, I. (2007). Contractors‘
overrun causes were identified through literature review. The
perspectives towards factors affecting cost estimation in Palestine.
risk matrix for the considered causes was identified according Jordan Journal of Civil Engineering, Volume 1, No. 2.
to their perceived severity and frequencies of occurrence. [8] Faridi, A. and El-Sayegh, S. (2006), 'Significant causes causing
Three zones were considered in the risk matrix: red, yellow, cost overrun in the UAE construction industry'. Construction
Management and Economics, 14, 1167-76.
and green. The results showed that 5 causes are located in the
[9] Flyvbjerg, B. H.; Holm, M.; and Buhl, S. (2003). Underestimating
red zone, 28 causes are located in the yellow zone, and 1 cause costs in public works projects, error or lie. Journal of the American
is located in the green zone of the risk matrix. Planning Association, 68(3), pp 279-292.
[10] Iyer, K.C. and Jha, K.N. (2005). Factors affecting cost
performance: evidence from Indian construction projects.
The study concluded that the top cost overrun causes in
International Journal of Project Management, 23(4): 283-295.
construction projects in Saudi Arabia from contractors‘ [11] Kaliba, C.; Muya, M.; and Mumba, K. (2009). Cost escalation and
perspective are: bid award for lowest price, frequent changes schedule delays in road construction projects in Zambia.
in design, improper planning, long period between design and International Journal of Project Management, 27, 522–531.
[12] Koleola, O. and Henry, O. (2008). Factors Affecting the Accuracy
time of implementation, and payments delay. The statistical
of a Pre-Tender Cost Estimate in Nigeria. Journal of Cost
analyses showed that the data has good compactness, Engineering, 50(9): 32 – 35.
indicating a good data consistency and agreement between the [13] Nega, F. (2008). Causes and effects of cost overrun on public
respondents on the severity and frequency of occurrence of the building construction projects in Ethiopia. Master thesis, Addis
Ababa University, Addis Ababa, Ethiopia.
identified cost overrun causes. [14] Odeck, J. (2004). Cost overruns in road construction—what are
their sizes and determinants? Transport Policy, 11, pp 43–53.
REFERENCES [15] Shehu, Z., Endut, I., Akintoye, A. and Holt, G. (2014). Cost
[1] Al-Momani, A., (1996), ―Construction cost prediction for public overrun in the Malaysian construction industry projects: A deeper
school buildings in Jordan‖, Construction Management and insight. International Journal of Project Management, 32 (8),
Economics, vol. 14, pp 311-317. 1471 – 1480.
[2] Al-Zarooni, S and Abdou, A (2000) Risk management in pre-
design stage and its potential benefits for UAE public projects. In,
28th World Congress on Housing Challenges for the 21st Century,
15-19 April, Abu Dhabi, UAE, 109-18.
[3] Amehl, O.; Soyingbe, A.; and Odusami, K. (2010). Significant
factors causing cost overruns in telecommunication projects in
Nigeria. Journal of Construction in Developing Countries, Vol. 15.

152904-6868-IJET-IJENS © August 2015 IJENS


IJENS

Das könnte Ihnen auch gefallen