Beruflich Dokumente
Kultur Dokumente
PARTS PAGE
This document is proprietary of GE Power Services and is for use of developing proposals requested in
this document. By accepting this document, the recipient agrees:
1. To use this document, and the information it contains, exclusively for the above stated
purpose and to avoid use of the information or disclosure of the information to, and use by,
competitors of GE on behalf of the recipient;
Saudi Cement’s Plant is located in eastern province approximately 120 km from Dammam, in the historic
city of Al-Hasa. The Plant consists of three kiln lines that are currently in operation. Line 6, designed for
4,000 tons of clinker per day, was commissioned in 1997, while lines 7 and 8, with a combined capacity to
produce 24,000 tons of clinker per day, were commissioned in 2008. Together these lines have a total
capacity of 28,000 MT of Clinker, equal to 9.2 million tons per year, which is also equivalent to 9.7 million
tons of cement yearly.
Saudi Cement Plant has partial captive power generation facility. Balance of the power requirement
is imported from Saudi Grid.
Current installed power generation equipment includes 3 * Frame 6 GE Gas Turbine and 3 * Alstom
Frame 9D Gas Turbine units. Currently the 3 * Frame 6 gas turbine units are in operation making the
operational capacity of the plant at 99.7 MW (at ambient temperature of 90 deg F).
Currently these Gas Turbines operate with Distillate, HFO and Natural Gas as fuel. For future
operation scenarios, only Natural Gas operation shall be considered.
Project Summary:
Saudi Cement Company is considering to add more power generation capacity and disconnect from
the Saudi grid. Saudi Cement Company is looking for a best value solution to reduce their
dependence on imported power while increasing power production at their current Hofuf site.
The plan is to consider all viable options that help optimize power production by utilizing the existing
GT installations as heat recovery options such as the installation of HRSG to the existing gas turbines
and/or adding waste heat recovery boilers to the existing cement kilns.
GE, being a total plant solution provider, is looking to design the best, most efficient, cost effective
alternative to meet the plant’s needs.
We are looking to partner with a competent local EPC company that is willing to contribute in the
development of the project as well as the eventual implementation on a shared risk/reward basis.
Key to success is to devise a division of work and division of responsibility matrix that is most
conducive to providing an optimal cost effective solution.
Note: The above scope calls for upgrade and new HRSGs for 2 units only. However, the proposal shall
be flexible to include these modifications for all 3 units, if it is determined at a later stage and during
the project phase. Condenser design shall be flexible/ modular to facilitate future expansion.
Major Components
The Facility shall consist of the following major components:
• Frame 6 B unit upgrades as per OEM latest upgrade available. (3 existing gas turbines will be
retained after doing latest upgrades)
• Two-pressure, non-reheat, unfired, horizontal gas flow HRSGs, each equipped with an exhaust
stack with dampers, transitions, expansion joints, and all required auxiliaries
• single flow exhaust, non-reheat condensing steam turbine generators with associated auxiliaries.
• One Distributed Control System (DCS) for the combined cycle facility and balance-of-plant (BOP),
(Customer preferred solution is GE Nexus System). This shall be supplied by GE.
A detailed scope split between GE and EPC shall be agreed upon prior to start of the project.
The BOP support systems include, but are not limited to, the following:
• Electrical Energy evacuation system including unit transformer to be integrated with
existing plant system,
• MV/ LV SWGR system,
• Data acquisition and data analysis,
• Main steam systems, for each of the power islands,
• HP/ LP bypass,
• Feedwater systems,
• HRSG blowdown systems,
• Air cooled condensers and all required auxiliaries,
• Raw water treatment system,
• Fire protection system to be integrated with existing plant system,
• Demineralized water system to be integrated with existing plant system,
• Chemical storage and injection systems for the condensate and feedwater systems,
• Domestic (potable) water system to be integrated with existing plant system,
• Safety Showers for the combined cycle plant,
• New building to house Control room, SWGR, Electronics room,
• New administrative building. Details to be provided at later stage,
• Process waste water system study and integration with existing system,
• Instrument air system study and integration with existing system,
• Service air system study and integration with existing system,
• Permanent Facility communications system study and integration with existing
system,
• Storm water management system study and integration with existing system,
• Sampling system for the new HRSG/ Steam system,
• Emergency power system, including emergency electric power generator study and
integration with existing system,
• Safe shut down system,
• Lighting system study and integration with existing system,
• Lightning protection system for the new system,
Contractor EPC firm shall develop this list further as per design of the CC plant and recommend any other
systems that are necessary for reliable operation of the plant.
Deliverables:
Deliverables from the EPC firm shall be adequate to provide a complete and coherent proposal to end
user.
Deliverables shall include, at a minimum, the following…
2. Design Basis:
Site Conditions:
The facility shall be designed in accordance with the Site Conditions specified in Appendix A.
Temperatures:
Equipment shall be designed to operate and stand down without damage throughout the
temperature range listed in Appendix A.
Design wind loads shall be in accordance with the requirements set forth in the Saudi Arabia
Building Code and or local governing building code requirements.
Seismic design loads shall be in accordance with the requirements set forth in the Saudi Arabia
Building and or local governing building code. The applicable seismic zone shall be either Zone 4
or Zone 3 for the specific site location. The site shall be assigned a soil profile type as
substantiated by geotechnical data for the specific site. The Importance Factor for seismic shall
be 1.0 (non-essential facility).
OSHA
• Occupational Safety and Health Act (0SHA) - 29 CFR 1910, 1926
American Society of Mechanical Engineers
The following standards of the American Society of Mechanical Engineers (ASME) shall be followed:
• ASME Boiler and Pressure Vessel Code Sections:
I Power Boilers
The following performance test codes may be used as guidance in conducting performance tests if a
shortfall in overall Facility performance requires individual component testing:
• PTC - 4.4 Gas Turbine Heat Recovery Steam Generators
• PTC – 6 Steam Turbines (Alternative Tests)
• PTC -6 (Report) Guidance for Evaluation of Measurement Uncertainty in Performance
Tests of Steam Turbines
• PTC -19.2 Pressure Measurement
• PTC -19.3 Temperature Measurement
• PTC – 22 Gas Turbine Power Plants
Industry Standards
Applicable standards issued by the following industry organizations:
• American Association of State Highway and Transportation Officials (AASHTO)
• American Boiler Manufacturers Association (ABMA)
• American Concrete Institute (ACI)
• American Gas Association (AGA)
• American Gear Manufacturers Association (AGMA)
• American Institute of Steel Construction (AISC)
• American Iron and Steel Institute (AISI)
• Air Moving and Conditioning Association (AMCA)
• American National Standards Institute (ANSI)
• American Petroleum Institute (API)
• American Society for Nondestructive Testing (ASNT)
• American Society for Testing and Materials (ASTM)
• American Society of Heating, Refrigerating, and Air-Conditioning Engineers (ASHRAE)
• American Water Works Association (AWWA)
• American Welding Society (AWS)
Below is summary of required technical compliance plan for Saudi Arabia. The supplier shall ensure to
abide by the required codes and standards as summarized in the below summary sheet. Details of
respective codes can be obtained upon request from TRS team.
4. Performance Guarantees:
Individual system test protocol shall be specified and used to determine system performance &
guarantees.
Bidders are requested to submit their offers on a lump sum turnkey basis for the listed scope of work.
A detailed price breakdown is also required to be submitted along with the proposal.
Bidders are requested to conduct their own site visit to ensure their full understanding of the scope as
well as specific site conditions. Request for a site visit should be coordinated with GE and planned well
in advance.
In general, bidders are expected to perform all needed work to fully complete the project without any
change orders.
The successful bidder shall be required to agree to perform the work with no additions to the
negotiated and agreed upon contract value. Therefore, a thorough evaluation and a site visit are
paramount and mandatory.
8. Bidder responsibilities:
Bidders are responsible for the following tasks:
• Completion of preliminary design of the site layout, civil works, mechanical, system, electrical
system, cabling, piping, and support services
• Issuance of detailed designs and bill of materials (BOM)
• Providing a project construction plan
• Full Establishment and ownership of the project including project and site set up, security,
schedule, and logistics
• Design Engineering, procurement, and construction of the interconnecting piping, pipe racks,
pipe supports, isolation valves, and pipes insulation.
• Design Engineering, procurement, and construction of electrical cables, conduits, cable trays,
required supports, and termination of cables.
• Design engineering and construction of foundations.
• Design engineering, procurement, and construction of the steel support structures as
required.
• Adherence to the project schedule.
• Upon completion, issuing final as built drawings and QA/QC documentation.
Contractor responsibility, depending on each line item is designated according to the following
description:
EPC:
Engineering, Procurement, and construction of the system. But not full ownership. System may
include equipment to be supplied by others and contractor is responsible for the installation of
such equipment including foundation and electromechanical connections.
PC:
Procurement and construction. Contractor is responsible for procuring the material required for
the job and perform installation such as repair or replacement of an existing system without
modification.
C:
Contractor shall perform inspection, installation, and construction of systems that do not require
material other than consumables and items required for construction.
Refer separate document for Heat balance diagrams for below 6 cases.
1. Peak fire, 15 deg C ambient temperature, EVAP ON.
2. Base Load, 15 deg C ambient temperature, EVAP ON.
3. Peak fire, 32.2 deg C ambient temperature, EVAP ON.
4. Base Load, 32.2 deg C ambient temperature, EVAP ON.
5. Peak fire, 50 deg C ambient temperature, EVAP ON.
6. Base Load, 50 deg C ambient temperature, EVAP ON.
Note:
These Heat balance diagrams are of preliminary nature and can be used for preliminary design. The
HMBD is subject to change based on additional requirements from customer, if any.
o Based on feasibility and power flow study substation 816 to be extended to accommodate a STG
breaker along with bus adapter panel and line and Bus metering along with bus coupler. The
scope shall include the extension of switchgear building. Please refer the attached layout of
substation (816 Main Substation ground floor plan.pdf).
o Spare Transformer outgoing breaker OP8-S16 in substation 816 can be utilized to supply STG and
HRSG load, provide it can cater to the load. Outgoing breaker is rated for 630 Amp as per SLD
The existing 2 EDGs are connected to LV distribution, customer has still requested additional black start
EDG. Rating of Existing EDG is as found on name plate is below
With the addition of combined cycle, adequate additional capability shall be added into the same DC
network. A proper study of DC Power requirement for entire plant shall be included in the scope by
the contractor.
Auxiliary Systems
The auxiliary system refer here is for off base auxiliaries,
Main auxiliary covered were
• Firefighting system
• DM plant
• Fuel oil system (off base)
• Air Compressor
With the addition of combined cycle, adequate additional capability shall be added into the same
auxiliary systems network as appropriate. A proper study of additional requirement of these system
shall be carried out and adequate additional capability shall be included in the scope by the
contractor for all auxiliary systems as required.
Diesel Engine Pump Type- ATURIA PDN 150-400 , 420mc /h , Head 100 m.
Engine-CLARKE JW 6H-UF58,224KW@1800RPM
Fire Water Tank 900 cubic meter
Foam Tank#1 6000 litres
Foam Tank#2 3500 litres
DM plant
There is small RO plant container unit with 2 tube bundle for which capacity is 10 m3 /hr as per P&Id, as
per the manual it is 70 m3/hr which is not correct.
Water treatment system water source is underground water or reservoir water which is received thru
cement Plant.
There is following dosing unit for the RO water
• Antiscalent Dosing
• Acid Dozing
• Pre-Chlorination dosing
• De Chlorination Dosing
DM plant is installed for the chiller installed for fuel gas compressor station.
There are 2 Storage tank one DM water storage tank and another make up water storage tank both
capacity 220 m3/Hr.
At 59 deg F.
Operation Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON
Fuel NG NG NG NG NG NG NG NG NG
Ambient Temp (deg F) 59.0 59.0 59.0 59.0 59.0 59.0 59.0 59.0 59.0
RH (%) 30% 30% 30% 30% 30% 30% 30% 30% 30%
Atmosphereic Pressure (PSIA) 14.48 14.48 14.48 14.48 14.48 14.48 14.48 14.48 14.48
CTIM (deg F) 46 46 46 46 46 46 46 46 46
Load Peak 100% 90% 80% 70% 60% 50% 40% 30%
Generator Output (KW) 43510.6 41612.6 37320.4 33173.6 29026.9 24880.2 20733.5 16586.8 12440.2
Exh Flow (lbs/se) 312.1 311.9 270.3 249.5 249.2 248.9 248.6 248.3 248.1
Exh Temp ( deg F) 1038.0 1004.7 1066.9 1085.0 1001.1 921.8 847.3 778.1 715.0
Exh Energy (MM btu/hr) 287.8 276.8 257.3 242.0 219.9 199.4 180.5 163.2 147.8
Exhaust Pr Drop (inch H2O) 12.9 12.7 9.8 8.4 8.1 7.8 7.5 7.2 7.0
Exhaust Nox ( PPM) 162.8 154.9 144.9 137.1 120.3 105.8 93.3 82.5 73.1
Exhaust Gas Composition
Argan (%) 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9%
N2 (%) 74.8% 74.9% 74.8% 74.8% 75.0% 75.3% 75.5% 75.7% 75.9%
O2 (%) 13.4% 13.7% 13.3% 13.3% 14.0% 14.7% 15.4% 16.0% 16.6%
CO2 (%) 3.4% 3.3% 3.5% 3.5% 3.1% 2.8% 2.5% 2.2% 1.9%
H2O (%) 7.4% 7.2% 7.6% 7.6% 6.9% 6.3% 5.7% 5.1% 4.6%
At 90 deg F.
Operation Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON
Fuel NG NG NG NG NG NG NG NG NG
Ambient Temp (deg F) 90.0 90.0 90.0 90.0 90.0 90.0 90.0 90.0 90.0
RH (%) 30% 30% 30% 30% 30% 30% 30% 30% 30%
Atmosphereic Pressure (PSIA) 14.48 14.48 14.48 14.48 14.48 14.48 14.48 14.48 14.48
CTIM (deg F) 69 69 69 69 69 69 69 69 69
Load Peak 100% 90% 80% 70% 60% 50% 40% 30%
Generator Output (KW) 40438.5 38624.1 34640.2 30791.2 26942.3 23093.4 19244.5 15395.6 11546.7
Exh Flow (lbs/se) 295.9 295.7 259.3 239.5 239.3 239.0 238.8 238.6 238.4
Exh Temp ( deg F) 1060.8 1027.4 1082.8 1101.0 1020.2 943.6 871.4 804.4 742.9
Exh Energy (MM btu/hr) 273.1 262.6 245.2 230.9 210.3 191.2 173.5 157.3 142.6
Exhaust Pr Drop (inch H2O) 11.7 11.5 9.1 7.8 7.5 7.2 7.0 6.7 6.5
Exhaust Nox ( PPM) 145.8 138.8 129.3 122.0 107.6 95.1 84.2 74.8 66.6
Exhaust Gas Composition
Argan (%) 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9%
N2 (%) 73.9% 74.0% 73.9% 73.9% 74.2% 74.4% 74.6% 74.8% 75.0%
O2 (%) 13.2% 13.5% 13.1% 13.1% 13.8% 14.5% 15.2% 15.8% 16.4%
CO2 (%) 3.4% 3.3% 3.4% 3.4% 3.1% 2.8% 2.5% 2.2% 1.9%
H2O (%) 8.6% 8.3% 8.6% 8.6% 8.0% 7.4% 6.9% 6.3% 5.8%
Operation Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON Evap ON
Fuel NG NG NG NG NG NG NG NG NG
Ambient Temp (deg F) 122.0 122.0 122.0 122.0 122.0 122.0 122.0 122.0 122.0
RH (%) 30% 30% 30% 30% 30% 30% 30% 30% 30%
Atmosphereic Pressure (PSIA) 14.48 14.48 14.48 14.48 14.48 14.48 14.48 14.48 14.48
CTIM (deg F) 93 93 93 93 93 93 93 93 93
Load Peak 100% 90% 80% 70% 60% 50% 40% 30%
Generator Output (KW) 37149.9 35415.6 31762.6 28233.5 24704.2 21175.1 17645.9 14116.7 10587.5
Exh Flow (lbs/se) 278.2 278.1 246.5 228.1 227.9 227.7 227.5 227.3 227.2
Exh Temp ( deg F) 1085.4 1052.0 1100.8 1119.2 1041.6 968.0 898.5 833.7 773.7
Exh Energy (MM btu/hr) 259.2 249.1 233.6 220.5 201.4 183.5 167.1 151.9 138.1
Exhaust Pr Drop (inch H2O) 10.4 10.3 8.3 7.1 6.9 6.6 6.4 6.2 6.0
Exhaust Nox ( PPM) 108.9 103.6 96.4 90.8 80.5 71.6 63.7 56.9 50.9
Exhaust Gas Composition
Argan (%) 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9% 0.9%
N2 (%) 72.1% 72.2% 72.1% 72.1% 72.3% 72.5% 72.7% 72.9% 73.1%
O2 (%) 12.7% 13.0% 12.7% 12.7% 13.4% 14.0% 14.7% 15.3% 15.8%
CO2 (%) 3.4% 3.3% 3.4% 3.4% 3.1% 2.8% 2.5% 2.2% 1.9%
H2O (%) 11.0% 10.7% 11.0% 11.0% 10.4% 9.8% 9.3% 8.8% 8.3%