DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
KUALA TERENGGANU,
NO 21 JALAN KP 2/3
KAJANG SELANGOR
Document No ABKT/3/2013
Confidentiality Level Level 1
Copyright Status THIS DOCUMENT CONTAINS CONFIDENTIAL INFORMATION. ALL
RIGHTS (INCLUDING COPYRIGHT, CONFIDENTIAL INFORMATION,
TRADE SECRET AND DESIGN RIGHTS) ARE OWNED BY RCZ
CONSTRUCTION SDN BERHAD. NO USE OR DISCLOSURE IS TO
BE MADE WITHOUT PRIOR WRITTEN APPROVAL OF RCZ
CONSTRUCTION SDN BHD. ALL RIGHTS RESERVED
Legality Status THIS DOCUMENT IS A LEGAL DOCUMENT WHICH IS SUBMITTED
TO AUTHORITIES IN COMPLIANCE TO THE ACTS &
REGULATIONS.
PAGE 2 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
It is certified that the amendments listed below has been incorporated into this SHP.
PAGE 3 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
13.0 Appendices.
(v) ABBREVIATIONS.
No TERM REMARK
1 SHO Safety & Health Officer
PAGE 5 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
(vi) DEFINITIONS.
For the purpose of this SHP the following definition shall apply.
6.1. Accident: An occurrence arising out of or in the course of work which result in fatal
6.2. Dangerous Occurrence: An occurrence which rises out of or in connection with work
PAGE 6 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
6.3. Fatal Injury: An injury leading to immediate death or death within one year from the
date of the accident. For fatal cases, the number of Lost Workdays is 6000 days.
6.4. First Aid: Any one time treatment of minor scratches, cuts, burns, splinters even
6.7. Lost Time: Lost days, consecutive or not, counted from and including the day
The Safety and Health Plan (SHP) was prepared in accordance with Datuk Yahizan
Consultancy Sdn Bhd (DYCSB) safety, health management system requirements and it
The main objective for the issuance of the Safety and Health Plan is to manage the
PAGE 7 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
worker’s safety, health, security and welfare aspect in an effective and efficient manner.
The prevention of down time or stop work order due to fatality or serious accident and ill
health during the construction activities in the Condominium Awan Biru project site will
DYCSB has set a target of ZERO FATAL ACCIDENT for this project. The number of
SERIOUS ACCIDENT should be not more than 2 cases in a year. In this respect the co-
program and activities has been identified to achieve the target set.
The project is for the construction of 2 Blok Condominium Mewah, 35 Tingkat dan Kerja-
2.1 Client.
No 21 Jalan KP 2/3,
Kajang Prima,
43000 Kajang
Selangor.
2.2 Main Contractor.
888, Aras 8,
PAGE 8 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
RM777 Juta
2.5 Subcontractor Civil.
PAGE 9 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
The following documents are referred and should be read with this SHP.
The Safety and Health Policy of DYCSB explicitly outlined our statutory obligations and
responsibility to provide, as far as practicable, a safe and healthy working environment for
PAGE 10 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
The safety of the general public will also be given due attention to protect against any
The Safety & Health Policy demonstrates our sincere intention of complying to the safety
regulations such as, but not limited to the Occupational Safety & Health Act (OSHA 1994),
Factories and Machinery Act (FMA 1967), Environmental Quality Act (EQA 1974) and
Agencies.
It is our policy to ensure all construction work activities are carried out in a safe manner
and well trained, experienced and competent project management personnel and site
Operators of these machineries are to possess the necessary license to operate the
The SHP Policy will be displayed at strategic places in the work site and will be revised as
The project management will establish a safety and health committee organization in the
site that comprised representatives from every subcontractor. Committee members are
selected from the management level, supervisor level and representatives from the
workers.
PAGE 11 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
The safety committee will meet at least once a month to discuss site safety and health
matters, unsafe condition and unsafe act of workers. If there is more than one project site
the safety committee will cross audit the other site on a monthly basis.
The objective for the setting up of the site safety and health committee organization is to
safe work procedures, accident prevention initiatives and to gather feedbacks of health
Members from the committee will conduct site safety inspection in other project sites to
recommended by the committee members to address any weakness found in the safety
Committee members will undergo periodic training in safety and health matters in NIOSH
in order to upgrade and increase their understanding of occupational safety and health
The responsibility of all site personnel, workers and subcontractors towards self
regulation and complaint to the relevant safety and health Acts and regulations are clearly
defined in the SHP. The SHP also define the responsibility of the general public and
visitors to the worksite in term of wearing appropriate PPE and ensuring personal safety.
PAGE 12 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
Responsible overall for all matters concerning health, safety, security and welfare
regulations such as, but not limited to the Factories & Machinery Act 1967,
Occupational Safety and Health Act 1994, Environmental Quality Act 1974 and
inspections and programs in each project site as outlined in the Safety & Health
Plan.
PAGE 13 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
Responsible for ensuring Project Directors, Project Managers, Safety & Health
Officers and Site Safety Supervisors are familiar with the Safety Plan
Responsible for conducting safety induction and safety training for Project
Directors, Project Managers, Safety & Health Officers, Site Safety Supervisors
Responsible for the updating of Safety & Health Plan as and when necessary.
Responsible for ensuring the safety of public and neighbors near the work site
safety regulations such as, but not limited to the Factories & Machinery Act 1967,
Occupational Safety & Health Act 1994, Environmental Quality Act 1974 and other
and Agencies.
Responsible to implement the safety activities and safety programs in the work
regulations, unsafe act of workers, unsafe condition in the workplace and to take
PAGE 14 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
Responsible to be the secretary of the project and special safety and health
manhours worked, accident frequency rate, severity rate and details of safety
programs implemented.
officers during site inspection, audit activity and other safety programs.
Responsible to carry out other duties as and when necessary to ensure the
health, safety, security, welfare and environmental aspect in the worksite is given
appropriate attention.
as, but not limited to the Factories & Machinery Act 1967, Occupational Safety &
Health Act 1994, Environmental Quality Act 1974 and other applicable statutory
Responsible to implement the safety activities and safety programs in the work
PAGE 15 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
regulation, unsafe act of worker, unsafe condition in the workplace and to take
All workers must abide by the safety regulations such as, but not limited to the
Factories & Machinery Act 1967, Occupational Safety & Health Act 1994,
Environmental Quality Act 1974 and other applicable statutory obligations by Local
Workers are to work in safe manner and to avoid personal injury and serious
Workers must report site accident, near miss or damage to property or equipment
7.6 Subcontractors.
PAGE 16 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
All subcontractors must abide by the safety regulations such as, but not limited to
the Factories & Machinery Act 1967, Occupational Safety & Health Act 1994,
Environmental Quality Act 1974 and other applicable statutory obligations by Local
Subcontractors are to prepare their own SHP and to follow all site regulations.
7.7 Visitors.
All visitors must abide by the safety regulations such as, but not limited to the
Factories & Machinery Act 1967, Occupational Safety & Health Act 1994, RZCSB
Safety & Health Plan and other applicable statutory obligations by Local
Visitors must register with the security guard at the main gate and to fill-in
safety helmet, safety belt and safety boots when entering work site.
Visitors are not allowed to enter construction areas without being escorted by
supervisors.
Visitors are to ensure personal safety and not to create unnecessary danger to
DYCSB will not be held liable for any personal injury, fatality or unforeseen
PAGE 17 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
Deep Excavations
Piling Works.
Noise Exposure
Work at Height
Fire Hazard
Machinery Safety
Electrical Safety
Roof Work
Welding Activity
The objective for this safety control measures is to identify safe work procedures, best
safety practices, accident prevention initiatives and suitable control measures that will be
implemented in the site for the various trade workers and in all workplaces. The safety
PAGE 18 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
arrangement will be improved as construction work progress and as more hazard are
Various safety programs and activities will be implemented so as to create a high level of
awareness among workers, secure compliance to the Act and regulations and to ensure
All workers will be involved in the safety program and accident control measures. Full co-
operation is vital for this program to succeed and the activities will be revised accordingly
to suit the construction progress. This is to ensure the project is completed without
Dangerous and high risk construction activities will be formally subjected to a stringent
hazard identification process prior to the commencement of the work. The purpose is to
identify the level of hazard and the degree of risk associated with each particular job and
then to determine appropriate safety control measures to prevent any untoward accident
happening.
The selection of suitable type of personal protective equipments for each the job is also
decided based on the result of the risk assessment process. HIRAC and Job Safety
PAGE 19 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
New workers reporting for work on the first day are required to attend the First Day at
Work Safety Induction program conducted by the Safety & Health Officer or Safety
Supervisor before being allowed to start work in the worksite. Workers will have to sign an
Workers, irrespective of trade and work scope are to sign the Undertaking Letter which
recorded their personal undertaking and self commitment to ensure personal safety,
wearing of appropriate personal protective equipment required of their trade jobs. The
undertaking program also ensures a sound understanding of safe work culture, personal
requirements
Subcontractors selected to work in the project site will have to submit latest Safety
Performance Indicator record which indicate the past 3 years accident statistic, safety
In order to show full commitments and serious intention of complying to the safety
regulation and to prevent accidents, subcontractors are to sign the Safety Pledge
document.
PAGE 20 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
In order to comply to Regulation 26 of the Factory & Machinery Act (BOWEC 1986),
subcontractors who employ more than 20 workers have to appoint a part time safety
supervisor to perform safety supervision at least for 5 hours per week in the work site.
The safety supervisor will become member of the safety committee organization.
Workers must attend the compulsory Safety Induction for Construction Worker training
before starting work in the construction site and to be in possession of either a Safety &
Health Induction for Construction Workers card from the National Institute of Occupational
Safety & Health (NIOSH) or to posses a Green Card issued by the Construction Industry
The possession of the NIOSH Card or Green Card does not absolved the workers from
complying to other safety regulation such as OSHA 1994, FMA 1967 or site requirements
imposed by DYCSB.
The main objective of the Morning Exercise program is to enable the site management to
check on the total numbers of workers present and also to remind them of their
objectives are:
PAGE 21 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
Foreign workers intending to work in the project site has to produce their original passport
and work permit for security checking before the issuance of a security pass. Only
workers possessing valid passport and valid work permit in the construction sector will be
A release letter from the original permit holder is required if the worker changes employer.
The worker also needed to be covered under foreign worker compensation scheme or
Local workers need to produce their identity card and photograph when applying for
security pass.
Safety information and current matters concerning health, safety, security, welfare and
environmental issues involving the workers is disseminated to all workers present during
the safety briefing each morning. Workers are also informed of accidents in other site in
PAGE 22 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
the effort of sharing information and also to learn from past mistakes so as to prevent a
Workers are encouraged to give feedbacks and ideas to improve the work site condition,
welfare facilities and other personal issues. A feedback box will be placed at strategic
location for the workers to write in their suggestions, comments and complaints.
Feedbacks from the workers are addressed immediately to ensure high morale and spirit
of co-operation among workers. A Feedback Box will be placed at site office for workers
All workers are to be briefed on the need of safety control measures, accident prevention
initiatives and also compliance to site safety requirements. This is to ensure their
personal safety and other workers working nearby are given top priority. The tool box
Proper record of the safety issues discussed is keep for inspection. Personal protective
equipments and necessary tools used are checked for suitability and safe usage.
PAGE 23 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
type for usage during the course of work, such as safety helmet, safety boot, visor,
earplug, dust mask, safety belt and safety harness. Proper record of PPE distribution to
all workers is kept for inspection purposes. The Personal Protective Equipments are to be
The Safety & Health Officer and Safety Supervisor will conduct daily safety inspection in a
continuous effort of providing a safe and healthy working environment, identifying unsafe
act of the workers, unsafe condition in the workplace and also to detect other non-
taken to rectify the unsafe condition and to correct the unsafe action of worker.
Unsafe act of workers, unsafe conditions in the work site and other non compliances are
recorded in the Daily Safety Inspection Report and the issues are deliberated during the
A daily meeting session is attended by the site manager, planning manager, safety &
progress issues and safety matters. The Daily Safety Inspection Report is presented to all
PAGE 24 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
Job Safety Analysis will be prepared for high risk job and dangerous work activity to
clearly state the role of specific personnel involved, work sequence, machinery used and
the potential hazards identified. Safety control measures will be implemented in order to
ensure the safety of all workers and also to protect the general public during the
construction activities.
competent scaffolder who is registered with the Department of Occupational Safety &
Health (JKKP). Design erection for structures of more than 15 meters high is by
Scaffold erection are to be inspected on a weekly basis and also after heavy rain. It is to
be green tagged to show the safe status and unsafe scaffold structures are to be red
tagged. The scaffolding erections are to be maintained in good condition and proper
When job activities involved working on top of roof, ceiling level or at height of more than
2 meters workers must wear fall hazard protection such as safety harness. Safety
PAGE 25 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
harnesses are to be of approved type and are checked for wear and tear. A permit to work
Mobile work platform is to be used for performing high level mechanical, electrical, wiring,
air condition, ducting and ceiling works. The mobile working platform must be erected
Green safety tag and an identification tag of the owner of the mobile platform must be
attached onto the work platform. Timber ladders are not allowed to be used as it has
caused numerous falls due to bad condition of timber and low quality construction.
Work areas at edge of slab will be barricaded with either timber barricade, galvanized iron
pipe barricade or wire rope barricade in order to prevent workers from falling down below.
Safety net will be installed at the barricade to give a sense of safety to workers. SOP for
work at edge will be implemented to ensure work at edge of slab is done in a safe manner
with adequate PPE worn and other safety measures are in place.
Workers are to use safety belt as restraining belt when working at edge of slab in order to
establish a safe working zone and warning mechanism. Suitable warning signages are to
PAGE 26 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
All workers are reminded daily of the dangers during the morning safety briefing and
toolbox meeting. Safety netting is to be provided to secure the perimeter of the work
Adequate safety control measures will be implemented to ensure safe condition for
working in deep excavation especially for safe access into and egress out of the
excavated area. Workers going into deep excavation are to hang their security pass onto
the security pass board before entering the deep excavation and later picking it up as
they come out of the excavated area. This is to ensure every worker is accounted for after
work is completed. The stability of nearby buildings and slope condition are closely
Earth disposal permit needed to be applied from the Local Authority and road cleanliness
is to be considered. The top of dump trucks need to be covered before leaving work site.
Operators of construction machinery of any class are to posses approved license from
PAGE 27 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
Operators of these machineries are to check the overall machinery condition and the
safety mechanism system of the machinery on a daily basis by using the machinery
checklist. All vehicles used in construction site must be registered with the appropriate
Authority. The heavy machineries must be in good working condition and safe to use. The
Lifting machinery such as skylift, scissor, lift, mobile crane, tower crane, derrick crane and
crawler crane must be in good working condition, safe to use and have a valid Permit
Mesin Angkat (PMA) from the Department of Occupational Safety & Health.
Operators of all type of cranes must be competent and possess valid Sijil Operator Krin
license (SOK) from DOSH and they are to sign an undertaking letter to acknowledge their
Operators are to check the crane daily before start using and to fill-in the detail in the
experienced signalman. The lifting area and possible drop zone of equipment and
materials are to be barricaded and signage posted to warn workers of lifting dangers.
Working in confined spaces such as in manholes, boilers and in tunnels will be subjected
to a permit to work system and a written safe work procedures which complies to all the
PAGE 28 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
The air quality, oxygen level and toxic gas level inside the confined space must be tested
by an Authorized Gas Tester registered with the Department of Occupational Safety &
Health prior to entering. Sufficient training will be conducted for the inexperience workers
Additional safety precautions will be provided such standby person stationed at the
entrance of manhole and implementing the buddy system working inside the confined
space. Necessary safety equipment such as safety line, SCBA, emergency rescue
equipment and adequate number of ventilation machines will be provided inside the
sheet information file. Personnel involved are to be adequately trained and provided with
level of 90 dB (A) or exceeding the limits specified in the First Schedule or exceeding the
PAGE 29 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
daily noise dose of unity as specified in Factories and Machinery (Noise Exposure
Regulation –1989). Ear protection such as ear plug and ear muff will be provided to
Adequate number of portable fire extinguishers will be placed at strategic locations in the
work site, kongsi area and also in the site office for use in case of fire break out. Fire
Drills will be conducted regularly to familiarize site workers with the correct usage of fire
extinguishers.
Smoking of cigarettes while working or in the working area is strictly prohibited except at
designated place that have been provided with cigarette box and fire extinguishers.
network between safety personnel and others during working hours and emergency
period.
Telephone contact number of all staff will be displayed in the office for emergency
A detailed and comprehensive report of all construction activities involving health, safety,
welfare, manpower record, accident statistic and other relevant matters will be prepared
PAGE 30 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
and submitted to the management on a monthly basis. The report will also be submitted
Weekly general housekeeping activity will be conducted in the work site to ensure overall
All workers and site staff are to attend this event after morning exercise.
Fatal, serious accident or dangerous occurrence in the site will be reported to the
The company planned to achieve a Zero Fatal Accident target for this site and plan to
complete the work activities without any fatal, serious accident and downtime due to stop
work orders. The co-operation of all workers are vital to prevent work site accidents and
PAGE 31 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
A formal Permit to Work System will be enforced for specific high risk job and dangerous
work such as working in live plant, blasting work, working in confined space, deep
Accident preventive measures will be put in place to prevent accident from occurring with
the standby of emergency rescue personnel and rescue equipments readied for any
eventuality.
Small openings on the floors that are intended for mechanical pump and other electrical
equipments are to be covered with reinforcement bars. Plywood and red painted over will
make the hole visible and safe from accidental fall through.
Horizontal safety nets are used to cover-up large size concrete floor openings and
galvanized iron pipe vertical barricades are erected around the opening to prevent fall
down accidents. Adequate warning signage is posted to warn of fall through hazard.
to share important information about workplace hazard and impart knowledge about
themselves.
During the safety campaign period five most safety conscious workers from among the
workforce will be selected to receive certificate of appreciation and token. The workers
PAGE 32 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
are chosen based on their compliance of safety regulations such as the wearing of
Workers are also invited to produce safety slogan and best safety slogan are chosen to
Site personnel, supervisors and other staff will be trained as and when required in order
to perform their duties effectively and efficiently. The training are conducted internally by
Adequate training for new workers will be given and they will be supervised by
experienced supervisors to ensure their personal safety. Overseas training are also
provided to selected staff to enhance their knowledge and expertise in selected field.
As required by the Occupational Safety & Health Act 1994, Safety & Health Officers will
be sent for the Continuous Education Program training at the National Institute of
PAGE 33 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.
As construction activity progress daily the site safety control measures must be in sync to
ensure the safety of workers as well as for the prevention of accident onto the general
public.
An emergency response plan will be prepared to provide clear guideline for taking
immediate action when an accident happens. The emergency plan contains detail of the
person responsible for accident response and fire emergency response action and
reporting.
The top management will conduct a management audit at the project site at least four
times per year in an effort to audit the construction work process and also to review the
safety management system aspect. Shortcoming in the safety management system will
be rectified and suitable process will be implemented to ensure the safety management
Continuous safety and health audit exercise by external auditors are scheduled to add
inputs and justification to the safety and health programs and activities being
implemented. New program and activities will be carried out to ensure effective and
PAGE 34 of 35
Control Copy:1 DYCONSULTANCY SDN BHD Date: March 8, 2013
Rev: 0 All Right Reserved.
DYCONSULTANCY S/B SAFETY & HEALTH PLAN ABKT/3/2013
Project Condominium Awan Biru Doc. No
Kuala Terengganu.