Sie sind auf Seite 1von 6

MECHANICAL ENGINEERING

Large ethylene furnaces:


changing the paradigm
The past decade has seen ethylene plants increase capacities to more than
1 million tonnes a year. The largest ethylene plant in the world, at 1.3
million tonnes, is being built, yet only six furnaces are required to meet this
capacity, making these the largest-ever ethylene pyrolysis furnaces
John R Brewer
Stone & Webster Engineering Corporation

A
s ethylene demand continues to a mature technology
grow, the economics of scale are but the past decade has
causing owners to invest in larger witnessed some dra-
ethylene plants. For example, Stone and matic changes in ethy-
Webster, is building the largest single lene furnace size.
train ethylene plant in the world for the In the past 30 years
Nova/Union Carbide joint venture in there has been a steady
Alberta, Canada. It has a nameplate increase in furnace
capacity of 1.3 million tonnes/year. capacity from all
Plants of this size raised the question of designers, and the aver-
the furnace design philosophy, which age size of a USC fur-
has spurred the development of new nace has increased
design concepts, some of which have from the typical 40 000
entered service. tonnes/year in the
This article reviews the developments early 1970s to current
leading to the commercialisation of large designs of 175 000–
furnaces and cites recent developments 200 0000 tonnes/year,
of Stone and Webster’s Ultra Selective making these furnaces
Conversion (USC) technologies. essentially the largest
Pyrolysis furnace design is considered in the world. The trend
of this increase is
Capacity increase of shown in Table 1.
Larger designs and
USC furnaces
therefore minimum
furnace count reduces
Year Ethylene both the total installed
(000t/yr)
cost and subsequent
1970 30–40
maintenance costs.
1980 50–60 Some clients with Two large liquid crackers with independent cell operation
1990 80–90 expanded ethylene
1995 110–150 plants of less than 1 million tonnes liquid feed ethylene plants being built
1999 150–200 have furnace counts in the range of 12 on the Gulf Coast (approximately
Future 250–300+ to 15 ethylene crackers. 900 000 tonnes/year), Stone and Web-
These clients have commented that ster already has the largest liquid feed-
at any particular time the maintenance stock pyrolysis furnace in operation,
Table 1 crew will be working on a furnace for capable of producing 175 000+
one reason or another, thereby increas- tonnes/year. By application of these
ing the plant maintenance costs. proven design concepts, the largest gas
Furnace intensification Until recently, ethylene furnaces feedstock furnaces were designed to pro-
with a capacity of 100 000 tonnes/year duce 200 000+ tonnes/year of ethylene.
Year Volumetric heat release were generally regarded as a practical
(Btu/ft3/hr) size to meet operational requirements. Selectivity and conversion.
1996 9400 However, this would have required 13 Concurrent with furnace capacity
1997 9800 to 14 furnaces to be designed to meet increases there has been the increase in
the plant capacity of 1.3 million severity of cracking for all feedstocks.
1998 10 000
tonnes/year. By installing only six fur- Virgin naphthas that used to be cracked
2000 16 700
naces to meet this demand the total at methane to propylene weight ratio of
Future 25 000 installed cost and subsequent mainte- 1.1 to 1.3 can now operate at severities
nance costs – a factor often ignored – is of 1.3 to 1.5 M:P. Stone and Webster
Table 2 reduced. Although there are other large ethane crackers are designed to operate

111
P T Q SPRING 2000
MECHANICAL ENGINEERING

with conversions above 72 per cent designs allowing more radiant surface clients, usually varying the firing ratio
ethane conversion compared to 60 to in the same firebox without the sacrifice between 50/50 to 80/20 on the floor to
65 per cent ethane conversion a few of radiant efficiency or runlength. This wall burners. However, demonstrated
years ago. design was incorporated into an addi- wall burner technology is still only in
Such high conversions require oper- tional furnace for a European client the 1.5 to 2 million Btu/hr range where-
ating temperatures that not only test which enabled a capacity increase of 35 as the early floor fired furnace designs
the radiant metallurgy but the associat- per cent over the existing furnace had floor burners that were limited to 6
ed convection and quench exchanger design for the same runlength using the million Btu/hr.
systems. These must be now capable of existing foundations and available plot With the furnace intensification pro-
continuous operation at these higher space as the original design. gramme, burner size has increased to
temperatures and higher coking rates. Reliability and operational life of the heat releases as high as 15 million
Furnace intensification furnaces seems to be one of those items Btu/hr per floor burner. With large fur-
This is a concept to achieve more capac- that has a low priority during the selec- nace designs the advantages of floor fir-
ity for a given firebox volume without tion of the furnace technology. Owners ing are obvious. Using the large
sacrificing furnace reliability. While who have selected alternative technolo- operating liquid (175 000+ tonnes/year)
most of the furnace designers have gies are sometimes disappointed by the furnace as an example, the fired duty is
tended towards higher capacity fur- furnace operational results; yet most approximately 500 million Btu/hr fur-
naces this has often been at the expense owners concede that the hot end sec- nace. Assuming a maximum heat
of shortened coil life or increased trans- tion is one of the highest operational release of 8 million Btu/hr per floor and
fer line exchanger fouling. cost areas on an ethylene plant. an 80/20 floor to wall split, the floor
With the latest USC technology, it is To this end, the focus has been on burner count would be on the order of
possible to install more radiant coil sur- maintaining a high on-stream factor. 50 and the wall burner count would be
face without compromising the furnace With a smaller number of larger fur- 60 to 80, depending on the selected
reliability. The technology’s furnace naces, reliability is an even more impor- heat release.
intensification trend is shown in Table tant consideration and these areas of This compares to the actual design
2. An example of this is the second-gen- operational or maintenance concerns where 64 floor burners were selected.
eration U-coil design. This arranges the have been addressed. With furnace intensification, the burner
radiant inlet and outlet tubes adjacent One focus area was to design furnaces count could be as reduced to 32 burn-
to each other in a symmetrical arrange- that are 100 per cent floor firing. Prior ers. Clearly the operability and mainte-
ment. to the late 1980s the company’s fur- nance of the floor burners is much
Using this new mechanical arrange- naces were partially floor and wall fired easier since all burners are located at
ment, the radiant tubes can be located and, indeed, Stone and Webster still grade. This capacity increase has been
closer together than conventional designs furnaces at the request of paralleled by the reduction of NOx

112
P T Q SPRING 2000
MECHANICAL ENGINEERING

A grassroots plant with four furnaces working with independent cell operation. Seven of the eight radiant cells meet the plant capacity

where design guarantees of 70mg/Nm3 water quality, the SLE modules are direct radiation. This concept is well
can be achieved with floor burner designed to be either removed and a tried and was the design of choice for
designs. new SLE tube installed or repaired in many furnace designers. Some even use
Floor burners are inherently more sta- place. a double row of tubes to increase the fur-
ble when the furnace is operated beyond The individual double pipe elements nace capacity, although this can be at
its design throughput and turndowns as can be removed without having to cut the sacrifice of efficiency.
high as 10:1 means that no burner needs any of the primary inlet headers. Using An alternative configuration is the
to be turned off for decoking or other the close coupled roof mounted SLE open radiant cell concept derived from
turndown conditions. The addition of exchangers has proven to be superior in refinery heaters, which has been adapt-
automatic damper control means that achieving long exchanger runlengths ed to ethylene furnaces. Generally, two
the all burner air registers can be operat- between mechanical cleaning with all or more rows of vertical tubes are placed
ed from the control room without using feedstocks compared with other transfer in a single firebox and heated with a
an outside operator. line exchanger types. combination of floor only or floor and
Another focus point has been the For gas cracking furnaces, especially wall burners.
quench system. After the double pipe where the plot space is limited, the USX- This concept has merit for specific
USX technology patent expired, other Omega-P exchanger has been used. This applications but the convection section
designers have incorporated this proven is a larger diameter, usually roof mount- design requires special consideration to
concept into their own furnace designs. ed, double pipe exchanger that allows ensure that the direct radiation view fac-
In conjunction with Borsig, Stone and the cracked gas effluent to be reduced to tor to the shock tubes in the lowest por-
Webster has developed furnace design close to the saturated boiler feedwater tion of the convection section is
using multiple USX type tubes called temperature in a single unit. This com- correctly calculated.
Selective Linear Exchanger (SLE) where plements the traditional USX/TLX. This concept has been used for a
modules in excess of 40 tubes can be With large furnaces, the available European client where the foundations
installed without using special site weld- space on the furnace is increased and for were already installed. Using this and
ing techniques. gas cracking furnaces this has led to larg- other design concepts the plot capacity
Unlike previous SLE designs, where er shell and tube exchangers for sec- compared to the existing wall fired twin
double pipe exchangers were welded to ondary heat recovery to be considered. cell furnaces was increased by over 35
a common oval header, the SLE design Thus it is possible to combine both the per cent. Variations to this design
follows the USX design principles of BFW preheating with the steam raising include a double row of tubes in the fire-
individual replaceable exchangers. For section into a single shell. The advan- box with the burners either side of the
large SLE modules, flow distribution of tage of this design is the elimination of radiant coils coupled to an offset con-
the boiler feedwater is critical to prevent an additional piece of equipment and a vection section.
dead areas or local water deposits. Use of reduction in the total quench system An additional advantage of minimis-
the patented turbo flow chamber by pressure drop. ing the furnace count is that the overall
Borsig virtually eliminates this concern. Single cell, open cell or twin cell fur- plot space can be dramatically reduced.
With a specially designed three-layered naces With the use of three-dimensional com-
refractory system in conjunction with a Most owners are familiar with the most puter modelling tools, these large fur-
mechanical ring seal, the heat loss of the common pyrolysis furnace configura- naces have been placed as close as 2m
SLE inlet nozzle is controlled to prevent tion in which individual single radiant while maintaining good access around
localised mechanical failure. cell furnaces are arranged in a back to the furnace. Some argue that this is too
The mechanical ring seal prevents back mirror image in pairs with typical- close but they tend forget that the tradi-
hydrocarbon from entering the refracto- ly one metre or more between each fur- tional pair of furnaces orientated in a
ry lined inlet head. While operators still nace convection section. The back-to-back configuration were only
find ways to damage equipment, for convection section is offset from the approximately 1m apart. As plants have
example loss of the steam drum level or radiant section to protect and shield the increased in size, it has been determined
an inadequate control of the boiler feed- lower row of convection tubes from that large single radiant cell furnaces are

113
P T Q SPRING 2000
MECHANICAL ENGINEERING

generally not economical, and the com- sections, the convection section length
pany has adapted its USC design con- would need to be increased. This low-
cepts into a floor fired twin radiant cell ers the overall transfer coefficient “To respond to the pressure
arrangement. With this design two radi- which increases the convection section
ant cells are centred either side a com- tube length and thus capital cost of the
to reduce capital cost and
mon convection section. furnace. maintain plant integrity, the
The advantages of this design are By contrast, dividing the radiant sec-
twofold. The convection is married to tion into two 30m radiant cells
independent cell cracking/
the two radiant cells more efficiently improves the flue gas distribution (it is cell decoking concept was
and the individual radiant sections can even superior to the traditional offset
allow for different hydrocarbon feeds to convection section with the single radi- developed. Unlike previous
be cracked in each radiant cell. ant cell design) and minimises capital designs that had tried to
An example is the largest liquid cost. Adaptation of the twin cell
cracking furnace that has been in oper- arrangement has added flexibility over crack a full range of
ation for over a year on the Gulf Coast. both the single cell and open cell con- feedstocks in a single cell . . .
In this design, two radiant sections each cepts and is especially useful when used
approximately 30m in length are with Stone and Webster’s independent this design concept
matched to a convection section cell operation. segregated the different
approximately 22m long. An equivalent Concerns over shipping weights and
single cell furnace would require that module handling for construction has feedstocks in two
the radiant section length be approxi- proven to be unfounded. Erecting these independent radiant cells”
mately 60m long to install all the same furnaces in North America, the drive to
radiant coils in a single firebox of the modularise the design to minimise the
same design. construction fieldwork has proved to be
This combination results in poor flue very cost effective. Essentially, the especially scaffolding, which is often a
gas and heat distribution due to the quantity of pieces handled by the con- major expense.
large disparity between the radiant box struction contractor is not much greater For the large gas crackers, although it
length and convection section length. for the large furnace compared to a fur- was not considered economical to ship
The number of individual convection nace a third or half the size. complete single furnace modules due to
passes cannot be reduced as this incurs If the large furnace is modularised local restrictions, the furnaces were par-
an excessive process side pressure drop. into a single shippable unit or even a tially modularised into large pieces.
Further, to overcome the poor ratio small number of large modules, this has This drives down contraction man-
between the radiant and convection a direct effect on all construction trades, hours and reduces the overall furnace
project schedule, which has led to con-
sider schedules for single furnaces in the
9 to 11 month ranges in areas where
these techniques can be used.
Independent cell operation and spar-
ing philosophy
The owner and furnace designer often
have different views on sparing philoso-
phy. The traditional ethylene plant has
a large number of smaller furnaces usu-
ally with a dedicated spare furnace and
sometimes a dedicated furnace to crack
the recycle streams.
To respond to the pressure to reduce
capital cost and maintain plant integri-
ty, the independent cell cracking/cell
decoking concept was developed.
Unlike previous designs that had tried
to crack a full range of feedstocks in a
single cell, generally reducing the
throughput of the ethylene furnace,
this design concept segregated the dif-
ferent feedstocks in two independent
radiant cells.
This design has resulted in a grass-
roots ethylene plant being built with
only four installed furnaces. Each fur-
nace is designed with two radiant cells,
a common convection section, com-
mon induced draft fan and common
steam system. The furnaces crack any
combination of naphtha, LPG or recycle
ethane/propane in any radiant cell.
Nameplate capacity is achieved by
any seven of the eight radiant cells,
with the eighth cell designated as the

114
P T Q SPRING 2000
MECHANICAL ENGINEERING

spare, which is assumed to be in hot owner tends to operate all the cells con- crackers provided similar capacity
steam standby or decoke mode. currently, using a rolling decoke method increase on a plant that had seven small-
In previous designs, eight smaller fur- to individually decoke the coils in each er revamped units, cracking gas through
naces would have been selected, which furnace cell. These furnaces have been in naphtha in any of the cells provided cou-
would have included one spare furnace. A operation for over five years and have pled with decoke back to the firebox.
quick comparison shows that in this sce- demonstrated they can crack any combi-
nario, eight steam drums, eight induced nation of naphtha and recycle Multi-zone cracking.
draft fans, plus the time to erect eight fur- ethane/propane in any radiant cell with- In response to client requests for feed
naces is required. out loss of plant capacity. flexible furnaces, a concept called Multi-
While these items are smaller in size, Large furnaces have the advantage of Zone Cracking has been developed. This
this does not compensate for the providing a high capacity on a smaller is an extension of the proven indepen-
economies of scale achieved by four larg- plot area, and independent cell operation dent zone-cracking concept. By sub-
er furnaces. In both cases the same num- has been incorporated in plant expansion dividing each radiant cell into two or
ber of radiant coils and quench furnaces, where the additional furnace more smaller zones, the furnace can be
exchangers are installed. The advantage capacity is a substantial portion of the designed to crack different feedstocks
of this design is that the spare capacity existing plant. For example, two high without the loss of feed flexibility.
was incorporated into a larger furnace conversion gas-cracking furnaces were With client inquiries now requesting
design without sacrificing feed flexibility. installed into an existing Stone and Web- ethylene plants approaching 1.5 million
To meet the environmental require- ster Gulf Coast plant. tonnes/year and minimum furnace
ments, the decoke effluent was routed The capacity of the two furnaces count, this concept will make it possible
back to the firebox. This created an addi- almost equalled the original plant size. to offer furnaces that have a capacity of
tional challenge, namely how to decoke Thus, taking a full furnace off for decok- 300 000+ tonnes/year. Each radiant sec-
one radiant cell (50 per cent of a single ing was considered a risk for upsetting the tion can be decoked using the indepen-
furnace), while the other cell was crack- recovery section of the plant. Using inde- dent cell-decoking concept.
ing a liquid or gas feedstock at its respec- pendent cell operation only one quarter Using the furnace intensification and
tive design rate. This was achieved by of the new installed furnace capacity is combing this with the new U-coil design,
upgrading portions of the convection sec- disturbed during a decoke cycle. the furnace footprint for a 300 000
tion to account for the heat imbalance of This is similar to decoking an existing tonnes/year feed flexible liquid-gas is
the furnaces, which had the effect of furnace. The compact furnace footprint approximately 15 per cent shorter than
making the furnaces more mechanically allowed two large furnaces to be installed the current 175 000 tonnes/year liquid
robust than a comparable single cell where only two smaller single cell fur- furnace that five years ago was consid-
design for only a small overall incremen- naces had been previously considered. ered state of the art design. Combing all
tal increase in capital cost. In reality, the Similarly, the two large Gulf Coast liquid of the current known design features

115
P T Q SPRING 2000
MECHANICAL ENGINEERING

from various operating furnaces, it is of the furnace for easy maintenance revamps. With over 100 floor fired fur-
practical to design and furnace approach- access. As the power requirement naces in operation varying in height
ing 350 000 tonnes/year while using increased, the use of the common 415V from 10m to 15m and length from 9m
proven technology. This is larger than motor is no longer feasible. to 30m, many of the features have been
some plants built in the past 10 years. Using variable frequency speed drives proven by actual operation.
rather than inlet vane control and min- These improvements have translated
Furnace control. imising the number of observation into greater furnace availability while
There are probably as many opinions on doors located on the radiant firebox reducing capital and maintenance costs.
ethylene pyrolysis control as there are walls to reduce air leakage, the operator
This article is based on a paper presented at
furnace types. On the new U-coil design, can achieve close control with high effi-
the DeWitt World Petrochemical Review,
the furnace was designed to crack a ciency over the wide operating modes.
Houston, Texas, March 1999.
heavy feedstock and naphtha in each There have been no operational debits
half of the furnace coils. associated with design features.
The control was designed to set the In conclusion, the technical features John R Brewer is chief engineer, Fired
base load 100 per cent floor firing to described can be equally applied to new Heater and Furnace Division, with Stone
match the heavy stock and vary the grassroots furnace designs or furnace & Webster, Houston,Texas.
naphtha feedrate to the required severi-
ty to achieve the equivalent firing rate.
For the naphtha, only two control
valves were required but for the heavy
feedstock, one valve per convection pass
was supplied.
For feed flexible furnaces, one control
valve is generally recommended for
each convection section pass. With the
large gas cracker, one control valve was
used to every two convection passes.
The company has also installed indi-
vidual pass control and zone floor firing
for some clients who want the ultimate
in furnace operation flexibility and con-
trol. With these large furnace designs,
there is more available room to allow
the installation of control valves and
other ancillary equipment, which is
often located on a separate pipe rack,
without sacrificing maintenance access
or operability. For independent cell
operation, only oxygen analyser and
one draft controller is required to con-
trol the furnace. Essentially, the furnace
operates as a single unit and the draft
variation of individual radiant fireboxes
does not affect the floor-fired operation.
Effect of equipment sizes on the large
furnace.
The large furnace capacity had a design
philosophy impact on two pieces of
equipment, the burner capacity and
induced draft sizing. Initially, the large
furnaces using previously proven design
parameters were designed. Thus, the
selected burners were in the 7–9
tonnes/hr range.
With furnace intensification, conven-
tional burner sizing set the firebox
length thus floor burners up to 16 mil-
lion Btu/hr were tested to see what prob-
lem if any this would cause. Although
the final burner selection was less than
16 million Btu/hr extrapolating the next
large furnace design with burners in the
range of 16 to 20 million Btu/hr is pos-
sible. From a NOx aspect, the burners
provided the lowest NOx numbers with-
3
out catalyst at 70mg/Nm . For induced
draft fans, the physical size of the fan
was not an issue. With long firebox
lengths, the fans were located at the end

117
P T Q SPRING 2000

Das könnte Ihnen auch gefallen