Poly Rail Drainage Accelerated Accelerated Schedule 08-Mar-17 00:04

Review

Activity Name Original Remaining Activity % Start Finish 2017


Duration Duration Complete
Feb Mar Apr May Jun Jul
Poly Rail & Drainage Accelerated 85 85 13-Feb-17 10-Jun-17 10-Jun-17, Poly Ra

Project Milestones 102 102 13-Feb-17 10-Jun-17 10-Jun-17, Project

Mobilize 0 0 0% 13-Feb-17 Mobilize


Complete Track 985 to Hydrocarbon Unloading 0 0 0% 28-Mar-17 Complete Track 985 to Hydrocarbon Unloading
Complete Tracks 980 & 981 0 0 0% 22-Apr-17 Complete Tracks 980 & 981
Complete Tracks through Poly 5 Structure 0 0 0% 06-May-17 Complete Tracks through Poly 5 Structure
Complete Storage Tracks 0 0 0% 06-Jun-17 Complete Storage Tra
Demobilize 102 102 0% 13-Feb-17 10-Jun-17 Demobilize
Poly 5 RXR 102 102 13-Feb-17 10-Jun-17 10-Jun-17, Poly 5 R

Concrete Demolition 15 15 16-Feb-17 04-Mar-17 04-Mar-17, Concrete Demolition


Demo Existing Concrete Foundations / Culverts / Duct 15 15 0% 16-Feb-17 04-Mar-17 Demo Existing Concrete Foundations / Culverts / Duct Banks
Track 985 26 26 27-Feb-17 28-Mar-17 28-Mar-17, Track 985
Grade Existing Ballast for 985 7 7 0% 27-Feb-17 06-Mar-17 Grade Existing Ballast for 985
Remove Asphalt at 0+25 road 3 3 0% 07-Mar-17 09-Mar-17 Remove Asphalt at 0+25 road
Install Steel Rail ties through to the Hydrocarbon Unload 7 7 0% 02-Mar-17 09-Mar-17 Install Steel Rail ties through to the Hydrocarbon Unloading Structure
Install Rail through Hydrocarbon Unloading 9 9 0% 06-Mar-17 15-Mar-17 Install Rail through Hydrocarbon Unloading
Install Ballast in 8300 7 7 0% 10-Mar-17 17-Mar-17 Install Ballast in 8300
Raise & tamp 985 10 10 0% 17-Mar-17 28-Mar-17 Raise & tamp 985
Track 980, 981 41 41 07-Mar-17 22-Apr-17 22-Apr-17, Track 980, 981
Muck Ditch & Strip Grass 5 5 0% 07-Mar-17 11-Mar-17 Muck Ditch & Strip Grass
Backfill Ditch & Grade 980 & 981 6 6 0% 13-Mar-17 18-Mar-17 Backfill Ditch & Grade 980 & 981
Lime Stabilize 980 & 981 8 8 0% 17-Mar-17 25-Mar-17 Lime Stabilize 980 & 981
install limestone to 980 & 981 5 5 0% 23-Mar-17 28-Mar-17 install limestone to 980 & 981
Install Ties & Rail to 980 & 981 8 8 0% 28-Mar-17 05-Apr-17 Install Ties & Rail to 980 & 981
Install Ballast to 980 & 981 5 5 0% 04-Apr-17 08-Apr-17 Install Ballast to 980 & 981
Raise & Tamp 980 & 981 12 12 0% 10-Apr-17 22-Apr-17 Raise & Tamp 980 & 981
Track 986,988,989 30 30 03-Apr-17 06-May-17 06-May-17, Track 986,988,989
Install Steel Ties & Rail on 986 988 989 18 18 0% 03-Apr-17 22-Apr-17 Install Steel Ties & Rail on 986 988 989
Install Ballast 986 988 989 18 18 0% 10-Apr-17 29-Apr-17 Install Ballast 986 988 989
Raise & tamp 986 988 989 18 18 0% 17-Apr-17 06-May-17 Raise & tamp 986 988 989
Concrete & Drainage 78 78 20-Feb-17 20-May-17 20-May-17, Concrete & Drainage

Actual Work Critical Remaining Work Su... Page 1 of 3 TASK filter: All Activities
Remaining Work Milestone Jackie Sanders
Poly Rail Drainage Accelerated Accelerated Schedule 08-Mar-17 00:04
Review

Activity Name Original Remaining Activity % Start Finish 2017


Duration Duration Complete
Feb Mar Apr May Jun Jul
Form & Pour Approaches at Hydro Carbon unloading 12 12 0% 20-Feb-17 04-Mar-17 Form & Pour Approaches at Hydro Carbon unloading
Form & Pour Approaches at Poly 5 18 18 0% 20-Mar-17 08-Apr-17 Form & Pour Approaches at Poly 5
Form & Pour Drainpads & road approaches 12 12 0% 01-May-17 13-May-17 Form & Pour Drainpads & road approach
Form & Pour Concrete Approach & Install road in 8400 6 6 0% 15-May-17 20-May-17 Form & Pour Concrete Approach &
Form & Pour Headwalls 18 18 0% 01-May-17 20-May-17 Form & Pour Headwalls
Grade Crossing & Roads 30 30 10-Apr-17 13-May-17 13-May-17, Grade Crossing & Roads
Install Concrete Road Crossings 12+50 & 0+25 18 18 0% 10-Apr-17 29-Apr-17 Install Concrete Road Crossings 12+50 & 0+25
Install New Roads 8400 & 8300-2 12 12 0% 01-May-17 13-May-17 Install New Roads 8400 & 8300-2
Site Preperation 78 78 20-Feb-17 20-May-17 20-May-17, Site Preperation
8500-8400 72 72 27-Feb-17 20-May-17 20-May-17, 8500-8400
Lime stabilize 982, 983, 984 6 6 0% 06-Mar-17 11-Mar-17 Lime stabilize 982, 983, 984
Remove Rail 982,983,984 18 18 0% 27-Feb-17 18-Mar-17 Remove Rail 982,983,984
Grade & Install Limestone 982.983,984 7 7 0% 13-Mar-17 20-Mar-17 Grade & Install Limestone 982.983,984
Ditches & Swales 18 18 01-May-17 20-May-17 20-May-17, Ditches & Swales
Regrade Ditches 10 10 0% 01-May-17 11-May-17 Regrade Ditches
Cut Swales in 8300 4 4 0% 12-May-17 16-May-17 Cut Swales in 8300
Cut Swales in 8400 4 4 0% 17-May-17 20-May-17 Cut Swales in 8400
8300-8300-2 66 66 20-Feb-17 06-May-17 06-May-17, 8300-8300-2
Lime stabalize 8300.2 6 6 0% 20-Feb-17 25-Feb-17 Lime stabalize 8300.2
Grade & install limestone 8300.2 6 6 0% 01-May-17 06-May-17 Grade & install limestone 8300.2
Drainage 78 78 27-Feb-17 27-May-17 27-May-17, Drainage
8500-8400 48 48 27-Feb-17 22-Apr-17 22-Apr-17, 8500-8400
Install Partial 8" Drain line 6 6 0% 06-Mar-17 11-Mar-17 Install Partial 8" Drain line
Install 36" Culverts for 985 18 18 0% 27-Feb-17 18-Mar-17 Install 36" Culverts for 985
Install 36 " Culverts 980-981 6 6 0% 13-Mar-17 18-Mar-17 Install 36 " Culverts 980-981
Install 12" & 15" Drain lines 12 12 0% 20-Mar-17 01-Apr-17 Install 12" & 15" Drain lines
Install French Drains 18 18 0% 03-Apr-17 22-Apr-17 Install French Drains
8300-8300.2 18 18 08-May-17 27-May-17 27-May-17, 8300-8300.2
Install Drain basins 9 9 0% 08-May-17 17-May-17 Install Drain basins
Install French Drains 9 9 0% 18-May-17 27-May-17 Install French Drains
Rail Installation 98 98 13-Feb-17 06-Jun-17 06-Jun-17, Rail Installa
Demo existing Rail & Switch 12 12 0% 13-Feb-17 25-Feb-17 Demo existing Rail & Switch

Actual Work Critical Remaining Work Su... Page 2 of 3 TASK filter: All Activities
Remaining Work Milestone Jackie Sanders
Poly Rail Drainage Accelerated Accelerated Schedule 08-Mar-17 00:04
Review

Activity Name Original Remaining Activity % Start Finish 2017


Duration Duration Complete
Feb Mar Apr May Jun Jul
8500-8400 31 31 27-Mar-17 01-May-17 01-May-17, 8500-8400
Track 982,983,984,996 31 31 27-Mar-17 01-May-17 01-May-17, Track 982,983,984,996
Install Ties & Rail 982,983,984,996 24 24 0% 27-Mar-17 22-Apr-17 Install Ties & Rail 982,983,984,996
Install Ballast & Raise & Tamp 18 18 0% 10-Apr-17 29-Apr-17 Install Ballast & Raise & Tamp
Install Bumpers 1 1 0% 01-May-17 01-May-17 Install Bumpers
8300-8300.2 32 32 01-May-17 06-Jun-17 06-Jun-17, 8300-8300
Track 990,991,992,993,994,995 32 32 01-May-17 06-Jun-17 06-Jun-17, Track 990,
Install Steel Ties & Rail on 987 990 991 992 993 9 24 24 0% 01-May-17 27-May-17 Install Steel Ties & Rail on 987
Install Ballast to 987,990,991,992,993,994,995 24 24 0% 08-May-17 03-Jun-17 Install Ballast to 987,990
Raise & Tamp 987,990,991,992,993,994,995 18 18 0% 17-May-17 06-Jun-17 Raise & Tamp 987,990
Demobilize 4 4 07-Jun-17 10-Jun-17 10-Jun-17, Demob
Punch Items 2 2 0% 07-Jun-17 08-Jun-17 Punch Items
Demobe From Site 2 2 0% 09-Jun-17 10-Jun-17 Demobe From Site
Poly 5 RXR 2018 0 0

Actual Work Critical Remaining Work Su... Page 3 of 3 TASK filter: All Activities
Remaining Work Milestone Jackie Sanders