Sie sind auf Seite 1von 8

NATIONAL INSTITUE OF CONTRUCTION

MANAGEMENT AND RESEARCH, PUNE

SCHOOL OF DISTANCE EDUCATION


 

Post Graduate Programme in Construction Management (PGP CM)


 

Module : 11

Course No. : PGCM 14

Course Title : ESTIMATION AND QUANTITY SURVEYING

Assignment No : 1

Registration No: 217-06-11-50971-2191

Submitted by

SRINATH SRINIVASAN

SRINATH SRINIVASAN        1                                                 217-06-11-50971-2191

                
 
 

INDEX 
Sec. No  Description  Page No

1  Given Task  3 

2  Assumptions & Notes  3 

3  Rate Analysis ‐ Cement Pointing   ‐ 

3.1  Material Requirement  4 

3.2  Manpower Requirement  4 

3.3  Rate Analysis  5 
Rate Analysis ‐ Cement Plastering in 
4   ‐ 
Ceiling 
4.1  Material Requirement  6 

4.2  Manpower Requirement  6 

4.3  Rate Analysis  7 

5  Bibliography  8 
 

 
SRINATH SRINIVASAN        2                                                 217-06-11-50971-2191

                
 
Given Task: 
Do the rate analysis of the following materials, 

1. Cement Pointing 1:4 ‐ Unit 1 Sq. m ‐ Take 100 Sq. m 

2. 12mm Cement Plastering in Ceiling 1:4 with course sand ‐ Take 100 Sq. m 

Note: 

a) Rate Analysis is done considering the location at Chennai 

b) Standard Unit rates in Chennai, 

Sl.  Unit Rate
Description  Unit Qty  Remarks 
No  (Rs.) 
Standard Unit Rates 
PPC Cement Bags 
1  Cement  Bags  1  365.00 
‐ Including GST 
Arcot Sand ‐ 
2  Sand  Cu. m  1  3,045.00 
Including GST 
3  Mason  Day  1  650.00  On Average  

4  Labor  Day  1  475.00  On Average   

c) One bag (50 kg) of cement weighs 1440 kg/cu. m 

d) Volume of 1 bag of cement = 50/1440 = 0.0347 cu. m 

e) Cement should be always measured by weight to avoid variation. 

f) Consider Mason’s Productivity as Key Productivity. 

g) Labor  cost  is  considered  as  per  Central  Public  Works  Department,  Government  of  India 
(Specification), 

The coefficients of mason and labors are as follows per Sq. m area per layer of plaster to be applied: 

 Mason ‐ 0.07435 days 
 Labors ‐ 0.0929 days   

SRINATH SRINIVASAN        3                                                 217-06-11-50971-2191

                
 
Solution: 

Task 1: Rate Analysis for Cement Pointing 1:4 ‐ Unit 1 Sq. m ‐ Take 100 Sq. m 

1. Consider 10 mm Thick Cement Pointing for Flooring 

2. Total Area to be plastered = 100 Sq. m 

3. Thickness of plaster = 10mm = (10/1000) m = 0.010 m 

4. Volume of mortar required = 100 x 0.010 = 1.00 cu. m  

 Add 20% extra mortar for filling joint, depressions and Wastage. 

 Volume of the mortar = [0.20 x 1.00] + 1.00 = 1.20 cu. m (Wet Volume) 

 Increase further by one‐third of the volume to get Dry volume 

 Final Volume of mortar required = [(1/3) x 1.20] + 1.20 = 1.60 Cu. m 

5. Summation of proportion = 1+4 = 5 (10mm Plastering in 1:4, Cement ‐ Sand mortar) 

Cement Requirement 

 Cement required = 1.60/5 = 0.32 cu. m 

 No. of bags of cement required = 0.32/0.0347 = 9.22 bags                         

(Say 09 Bags) ‐ Refer Notes 

 Cement used = 09 x 50 = 450 kgs 

Sand Requirement 

 Total amount of Sand required = [1.60 x (4/5)] = 1.28 cu. m (Say 1.30 cu. m) 

Manpower Requirement: 
Labor  cost  is  considered  as  per  Central  Public  Works  Department,  Government  of  India 

(Specification), refer above notes 

SRINATH SRINIVASAN        4                                                 217-06-11-50971-2191

                
 
The no. of days of Mason required     = 0.07435 x No. of layers x surface area 

= 0.07435 x 1 x 100 = 7.435 days = (Say 8 Days) 

The no. of days of Labor required     = 0.0929 x No. of layers x surface area 

= 0.0929 x 1 x 100 = 9.29 days 

The no. of days of Labor required (Mixing)   = 0.0929 x 1.60 

= 0.148 Days 

Total no. of days of Labor required      = 9.29 + 0.148 = 9.438 Days 

Rate Analysis for Cement Pointing 1:4 ‐ Unit 1 Sq. m ‐ Take 100 Sq. m 
 
Item  Unit Rate  Amount 
Description  Unit  Qty  Remarks 
No.  (Rs.)  (Rs.) 
PPC Cement Bags ‐ 
1  Cement  Bags  9  365.00  3,285.00 
Including GST 
Arcot Sand ‐ Including 
2  Sand  Cu. m  1.30  3,045.00  3,958.50 
GST 
3  Mason  Day  8  650.00  5,200.00    
Considering Mason’s 
4  Labor  Day  8  475.00  3,800.00  Productivity as Key 
Productivity 
Cost for Men & Material     16,243.50    
Over Heads (Water, Wastage, Tools & Plants, Transportation & 
   1,624.35    
etc.) ‐ 10% 
Contractor's Profit ‐ 10 %     1,624.35    

Total Cost (Rs.) for 100 Sq. m     19,492.20    

Total Cost in Round Off (Rs.) ‐ for 100 Sq. m     19,492.00    

Total Cost in (Rs.) ‐ for 1 Sq. m     194.92    

   

SRINATH SRINIVASAN        5                                                 217-06-11-50971-2191

                
 
Task 2: Rate Analysis 12mm Cement Plastering in Ceiling 1:4 with course sand ‐ Take 100 Sq. m 

1. Total Area to be plastered = 100 Sq. m 

2. Consider Plastering in Ceiling for Ground Floor Building. 

3. Thickness of plaster = 12mm = (12/1000) m = 0.012 m 

4. Volume of mortar required = 100 x 0.012 = 1.20 cu. m  

 Add 20% extra mortar for filling joint, depressions and Wastage. 

 Volume of the mortar = [0.20 x 1.20] + 1.20 = 1.44 cu. m (Wet Volume) 

 Increase further by one‐third of the volume to get Dry volume 

 Final Volume of mortar required = [(1/3) x 1.44] + 1.44 = 1.92 Cu. m 

5. Summation of proportion = 1+4 = 5 (12mm Plastering in 1:4, cement ‐ sand mortar) 

Cement Requirement 

 Cement required = 1.92/5 = 0.384 cu. m 

 No. of bags of cement required = 0.384 / 0.0347 = 11.06 bags                         

(Say 11 Bags) ‐ Refer Notes 

 Cement used = 11 x 50 = 550 kgs 

Sand Requirement 

 Total amount of Sand required = [1.92 x (4/5)] = 1.536 cu. m (Say 1.55 cu. m) 

Manpower Requirement: 

Labor  cost  is  considered  as  per  Central  Public  Works  Department,  Government  of  India 

(Specification), refer above notes 

SRINATH SRINIVASAN        6                                                 217-06-11-50971-2191

                
 
The no. of days of Mason required     = 0.07435 x No. of layers x surface area 

= 0.07435 x 1 x 100 = 7.435 days = (Say 8 Days) 

The no. of days of Labor required     = 0.0929 x No. of layers x surface area 

= 0.0929 x 1 x 100 = 9.29 days 

The no. of days of Labor required (Mixing)   = 0.0929 x 1.92 

= 0.178 Days 

Total no. of days of Labor required      = 9.29 + 0.178 = 9.468 Days 

Rate Analysis for Cement Sand Plastering 1:4, 12 mm Thick Ceiling Finish  
 
 Item  Unit Rate  Amount 
Description  Unit  Qty  Remarks 
No.  (Rs.)  (Rs.) 
PPC Cement Bags ‐ 
1  Cement  Bags  11  365.00  4,015.00 
Including GST 
Arcot Sand ‐ Including 
2  Sand  Cu. m  1.55  3,045.00  4,719.75 
GST 
3  Mason  Day  8  650.00  5,200.00    
Considering Mason’s 
4  Labor  Day  8  475.00  3,800.00  Productivity as Key 
Productivity 
Cost for Men & Material     17,734.75    

Over Heads (Water, Scaffolding Materials, Wastage, 
   1,773.48    
Tools, Transportation & etc.) ‐ 10% 

Contractor's Profit ‐ 10 %     1,773.48    

Total Cost (Rs.) for 100 Sq. m     21,281.70    

Total Cost in Round Off (Rs.) ‐ for 100 Sq. m     21,282.00    

Total Cost in (Rs.) ‐ for 1 Sq. m     212.82    

SRINATH SRINIVASAN        7                                                 217-06-11-50971-2191

                
 
Bibliography: 
 
 NICMAR lesson book ‐ Estimation & Quantity Surveying 

 Central Public Works Department, Government of India (Specification) 

 Other miscellaneous hand books on Estimation & Quantity Surveying. 

SRINATH SRINIVASAN        8                                                 217-06-11-50971-2191

                
 

Das könnte Ihnen auch gefallen