Sie sind auf Seite 1von 3

Part 2

34 TheStructuralEngineer Professional guidance


November 2016 Temporary Works Toolkit

Temporary Works Toolkit


Part 2: CDM 2015 and The Temporary Works Toolkit is a series
of articles aimed primarily at assisting the
permanent works designer with temporary
the responsibilities works issues. Buildability – sometimes referred
to now as “construction method engineering” –

of permanent works is not a new concept and one always recognised


as vital to the realisation of one’s ideas; it ought

designers with regard to be at the forefront of an engineer’s mind.

www.twforum.org.uk

to temporary works

enhanced risk on site. In the extreme, this could and safety-critical temporary works situations
precipitate failure and affect the well-being of as any larger project.
others. However, there are also other actions The duties falling to PWDs are the same in
which, although lacking the same degree of all cases.
In the second part of the safety concern, could add unnecessary cost
series, John Carpenter or time to a project if not thought through by Statutory obligations
the PWD. The statutory obligations on PWDs arise from
examines the impact of CDM Although safety issues tend to dominate, ill Reg. 9 of CDM 2015. This requires PWDs to:
2015 and temporary works on health associated with temporary works, but
permanent works design. arising from poorly thought-out permanent • eliminate risk or, if not reasonably practicable,
works design, is also an important aspect to reduce risk, so far as is reasonably
which needs to be considered by PWDs. In practicable (SFARP)
this article, the term “safety” is also intended • provide information on significant residual
Introduction to cover ill health. (Ill health is a major concern risks to others (specifically the principal
This article is intended to advise UK permanent generally, as it affects, and kills, many more designer, but required by the principal
works designers (PWDs) of their legal people than do safety-related shortcomings.) contractor)
obligations in relation to temporary works, On many projects, temporary works are,
stemming from the Construction (Design and in effect, a “hidden” element, despite forming The risks here are those which adversely
Management) Regulations 2015 (CDM 2015); a significant cost component: they are not affect the safety of others; however, the
and also to demonstrate more generally the explicitly billed or identified, nor do they feature approach may be used to consider all adverse
wider project benefits of careful consideration. as part of what the client receives on project risks.
Temporary works cover a wide field of completion; hence, they often do not receive CDM 2015, like its predecessors, does not
activity: these are illustrated in Appendix B the same attention as the permanent works at make any distinction between temporary
and C of the Temporary Works Forum (TWf) the design stage. However, attention to detail works and permanent works. Thus, temporary
Client’s guide to temporary works1. can bring commensurate project savings, in works designers (TWDs) will also be following
The definition of temporary works addition to eliminating or reducing unnecessary the above requirements. To do this, they will
adopted by the TWf includes interim states safety risk. require adequate base data on the permanent
of permanent works and the loading of The duty of PWDs to consider safety risk works (in the pre-construction information) on
permanent works by temporary construction in connection with temporary works arises which to base their design, and the means to
loads. under a general duty of care, but specifically coordinate the temporary works design with
under statute and often under contract. PWDs the permanent works.
Safety risks may be employed directly by the client, or by a To discharge this statutory duty, the
The main concern for PWDs in relation to contractor. PWD must:
temporary works is one of safety, i.e. an action It is important to remember that risk does
falling to the PWD which, if not taken at an not respect project size. A loft conversion, or • understand how the structure can be
early stage, could lead to an unnecessary or house extension, is as likely to create complex constructed, and temporary works erected,

TSE59_34-36 temporary works part 2.indd 34 20/10/2016 12:24


www.thestructuralengineer.org

35

used and dismantled safely (Box 1) principal designer, or from a contractor


• determine if, by altering or supplementing (including where sensible and feasible, the
the permanent works design in some way Box 2. Eliminating or reducing temporary works coordinator (TWC), as set
(SFARP), risk arising from construction, use temporary works risk out in BS 5975:2008+A1:20115).
or dismantling of temporary works can be The PWD should be aware that even
eliminated or reduced (Box 2) There are a number of ways in which common-place designs, such as a multistorey
• consider what useful information should be temporary works risk may be eliminated flat slab, can present difficulties to contractors
passed on to the contractor (via the or reduced by alterations to the if not thought through, e.g. in terms of propping
pre-construction information) (Box 3) permanent works design. The PWD may: constraints and safe temporary loading.
• consider ways of facilitating lifting
In considering the above, it is not intended • provide a moment connection (even Information
to restrict the contractor in how the facility is if not needed in the final structure) so The key issue here is to distinguish between
constructed (unless there is good reason to as to allow for a predictable temporary general information of which the contractor will
do so). Nor is it intended to take responsibility situation already be aware by virtue of being a capable
for site matters. The aim is to explain the • make provision for predictable contractor, and “significant residual risk data”
PWD’s thinking, remove or reduce unnecessary temporary works cast-in elements which the contractor will find of use – either in
obstacles, and provide information. It is then • add bracing or reinforcement to the actual construction, use or dismantling of
for the contractor to ensure the safety of the accommodate predictable interim the temporary works, or in its design (Table 2).
method eventually adopted. conditions
To do this, the PWD clearly needs to have • enhance the strength of a member so as Contractual obligations
a good understanding of contemporary to accommodate predictable temporary Contractual arrangements
construction techniques, including the loading Notwithstanding statutory obligations,
associated likely temporary works solutions, • ensure adequate space is provided for the manner in which the project team is
and to know the critical aspects of the predictable temporary works items assembled can have a significant effect upon
permanent works design, e.g. an interim • consider issues associated with the management of risk and the transfer of
stage of possible instability, reliance on demolition-related temporary works information. The PWD needs to be aware of
adjacent structures, or limits to deflections or how the chosen arrangements may impede
movements. the necessary actions.
Clear thinking and action in this regard will Risk management On design-and-build projects (or similar
help in the management of safety risk, but also Unfortunately, neither CDM 2015, nor the arrangements), the contractor has contractual
in the management of other business-related accompanying guidance2 published by the control over all designers. The PWD is
risks, e.g. programme or unexpected costs. Health and Safety Executive (HSE), explain therefore able to ensure that the permanent
how the PWD determines whether the risk- works design takes account of construction
Cooperation, coordination and management action taken is compliant. This issues, as they are able to make direct contact
communication is a long-standing deficiency and is discussed with the relevant contractors and TWDs.
The PWD must cooperate, coordinate and elsewhere3,4. In the absence of such advice, it This allows a design, and the provision of
communicate with others in respect of is suggested that: information, which suits those who are going
temporary works (safety) issues, as for any to design and construct the works. The PWD
other aspects of the design, where reasonably • the PWD follows contemporary industry should be pro-active in this regard and should
practicable. Taking these actions will also assist practice where available; if it is available, but also expect to have contact with the principal
in other regards (Table 1). not adopted for good reason, the PWD should designer and, when appointed, the TWC.
However, much depends upon the provide an explanation for record purposes However, on projects where the client
nature of the contractual arrangements • where no contemporary advice is available, appoints PWDs and contractors separately,
(discussed further on). Where the contractual the PWD uses engineering judgement the process is more complex. In these cases,
arrangements militate against this, e.g. by the stemming from capable individuals
timing of appointments, the PWD should ensure
that reasonable alternative action is taken. In short, the PWD should ask: If I was
the constructor or the TWD, what would I Box 3. What information should
reasonably expect, or want to know, so that I be passed to the contractor?
could proceed safely, but also economically?
What must be avoided, without exception, is Passing useful information to the
Box 1. Understanding the overtly dangerous situations occurring on site contractor is a very important aspect
construction process as a result of poor design consideration. of a project (and is discussed in more
Careful consideration of the construction detail further on in the article). As a
There may be a number of ways sequence and the associated temporary minimum, the suggested construction
in which the structure could be works, and using this to identify associated sequence should be illustrated
constructed, and the temporary works hazards and risks, will then allow consideration (generally as an option) unless it is
erected, used and dismantled safely, of whether any of these may be eliminated or obvious to a capable* contractor, with
but the PWD must have identified at reduced. A useful model for this, conducted no significant issues which might
least one likely and feasible method, if possible in a group with a facilitator, is ERIC be unexpected.
and understand the manner in which the (eliminate, reduce, inform, control). Such a * “Capable” is the term used in CDM 2015. It
permanent works design impinges on facilitator should be capable in temporary replaces “competence”, having regard also to
this, or vice versa. works design and construction techniques; resource, which was used in CDM 2007.
they could be from the design team, the

TSE59_34-36 temporary works part 2.indd 35 20/10/2016 12:24



Part 2

36 TheStructuralEngineer Professional guidance


November 2016 Temporary Works Toolkit

suggest others if this is the case


Table 1: Cooperation, coordination and communication actions for the PWD
• contractors may differ in their individual
Cooperate Assisting the principal contractor, via the pre-construction approach to construction, but the PWD should
information and the principal designer as required, to understand be able to obtain relevant generic advice
the intricacies of the permanent works design; and considering • a TWC may be a useful source of advice
options to assist in the build process if appointed at the relevant stage and if
specifically competent in design matters7
Coordinate Taking steps to ensure the permanent works design is compatible • TWDs may be a useful source of advice if
with temporary works needs appointed at the relevant stage
• the TWf cannot give project-specific advice,
Communicate Ensuring that appropriate communication channels are available,
and used but its website (www.twforum.org.uk) contains
a range of useful information

depending upon the specific arrangements Contractual provisions The PWD will need to decide whether, if no
and timings, the PWD may not be able to make The PWD should give careful consideration contractual route is available, to obtain advice
direct contact with the principal contractor, still as to what contractual provisions should be on a pro bono basis; or, perhaps for the more
less the subsequent subcontractors or TWDs. included in the construction contract. General complex or safety-critical project, to seek
If this is so, the PWD should: provisions, which may need to be particular- funds to engage one of the advisers listed
ised for a specific project, are set out in here to provide a consultancy service.
• discuss any specific issues with the principal PAS 88116.
designer, if appointed Further details
• seek advice from other contractors/TWDs if Sources of advice for the PWD An extended version of this article is available
there is any doubt about the likely method of When necessary, the PWD is able to obtain on the TWf website at www.twforum.org.uk/
construction or other temporary works issues advice from a number of sources: publications/public-twf-documents/.
• ensure adequate information is provided
on the drawings for the benefit of those • the principal designer will not necessarily be John Carpenter, FICE, CFIOSH is a past
contractors yet to be appointed competent in this area but should be able to Secretary of the TWf and of SCOSS. He is
the technical author of the imminent PAS 8811
Table 2: Examples of useful information for contractors and designers (reference 6) and has published widely for the
Institution on risk matters.
Ground conditions Provision of site investigation (SI) data. The PWD should also
and design give consideration, when setting up the permanent works SI,
characteristics as to whether additional tests or data collection (including
(affecting safety actions required to determine contaminants and the like) REFERENCES:
and health) will assist in the design of predictable temporary works or 1) Temporary Works Forum (2014)
the protection of associated workers. This may require an Client’s guide to temporary works [Online]
extended SI time period Available at: www.twforum.org.uk/media/58911/
twf2014.02_client_guide_26_january_2015_final.pdf
Restrictions on Essential information in order to plan and design the (Accessed: October 2016)
horizontal/vertical temporary works 2) Health and Safety Executive (2015) L153:
movements and Management of health and safety in construction
deflections to [Online] Available at: www.hse.gov.uk/pUbns/
existing assets or the priced/l153.pdf (Accessed: October 2016)
permanent works 3) Carpenter J. (2014) Construction design dilemma:
CDM2015 [Online] Available at: www.shponline.
Maximum loads to The PWD should have regard to predictable temporary loads co.uk/construction-design-dilemma-cdm2015/
be applied to existing on the permanent works and accommodate these into the (Accessed: October 2016)
assets or to the design, where reasonably practicable. Data on this may be 4) Carpenter J. (2016) ‘Construction Design: Moving
permanent works obtained from a number of sources, including industry bodies Forward’, SHP, 34 (1), pp. 41–43 [Online] Available
(e.g. the BCSA or the TWf) or contractors* at: www.shponline.co.uk/moving-forward-on-
cdm2015/?cid=searchresult (Accessed:
How interim strengths For example, the early strength of concrete floors October 2016)
are to be determined 5) British Standards Institution (2008) BS
5975:2008+A1:2011 Code of practice for temporary
Interim stages of Essential information in order to plan and design the works procedures and the permissible stress design
construction involving temporary works of falsework, London, UK: BSI
potential instability 6) British Standards Institution (In press) PAS
8811 Temporary works – Major infrastructure client
Party wall details The contractor should be informed of all party wall matters, procedures – Code of practice
including the name of the party wall surveyor, existing party 7) Temporary Works Forum (2012) Competencies
wall details, investigations and the like of the TWC [Online] Available at: www.twforum.org.
uk/publications/public-twf-documents/ (Accessed:
Traffic flows As traffic management can be defined as temporary October 2016)
works, useful information would be traffic flows, speed
and use restrictions to allow the traffic management to be FURTHER READING:
sensibly designed Carpenter J. (2011) Designing for safer concrete
structures, London, UK: MPA Concrete Centre
* Examples include the inability of a suspended floor slab to take predictable temporary works propping loads
(supporting the next floor). However, it would be better if the PWD eliminated the problem by increasing the
strength of the slab A range of other useful information is also available
on the TWf website at www.twforum.org.uk.

TSE59_34-36 temporary works part 2.indd 36 20/10/2016 12:24

Das könnte Ihnen auch gefallen