TABLE OF CONTENTS
1. Purpose
2. Scope of Work
4. References:
5. Definitions
6. Resources
7. Safety Precautions
11. Attachments
Prepared by Contractor:
Page 1 of 18
Method Statement for Street Lightning & Allied Works.
1. Purpose:
The purpose of this Method statement is to set guidelines and methodology to be followed with safe
working practices while performing the “street lighting & allied works” and describes the execution
methods, material used, resources, schedule, design basis and reference followed at project site.
2. SCOPE OF WORK
The scope of this document is to set up the work activities in sequence for “street lighting & allied
works” at project Construction of Internal roads and Infrastructure works in Al Shawamekh
Area for Sectors (12,7), Abu Dhabi ,site covering:
Safe Shifting, Handling & Storage of Materials
Excavation
Foundation Casting For Street Light Pole
Installation of Light Pole and Accessories (10m, 14m)
Control Cabinet Installation
Foundation for Lighting Control Cabinets
Connection of the Cables (Power Cables/Lighting Cables)
Pull Box Installation
Earthing
Page 2 of 18
Method Statement for Street Lightning & Allied Works.
4. References:
Contract Specification
Approved Drawings
Bill of Quantities
Approved Material Submittals
Contract Drawings
Standard Specifications
Company IMS Manual
HSE Plan
ADM Specifications for Street Light Poles Section XVI-7 Version 2.0 Clause 1607.04
ADM Specifications on foundations for Light Poles Section XVI-5 Version 2.0 clause 1605
ADM Standard Drawings (10 & 14m Light Poles, Lighting Control Cabinets).
Abu Dhabi Lighting Manual – Issue-1 Part-1 section-A
ADDC Spec. no. S-AA-CIV-GEN
ADDC Spec. S-AAA-STRL- (Rev 0-2011)
ADDC Spec S-AAA-SWG-LV-PILLAR-6&8 Ways (Rev.0-2011)
ADDC Spec S-AAA-STRL-CUB (Rev.0-2011)
Page 3 of 18
Method Statement for Street Lightning & Allied Works.
5. Definitions :
Where the applicable issue, edition or addenda of a Code or Standard has not been specified the latest
edition shall apply.
Page 4 of 18
Method Statement for Street Lightning & Allied Works.
Abbrevations:
MS : Method Statement
ITP : Inspection Test Plan
WIR : Work Inspection Request
IFC : Issued for Construction
CC : Control Cabinet
FP : Feeder Pillar
Page 5 of 18
Method Statement for Street Lightning & Allied Works.
6. Resources :
All materials shall be provided as per approved material submittals. Materials / Tools used during
the execution at site will be certified / calibrated (if required):
Subcontractor approval
Subcontractor approval shall be sought, if any subcontracting jobs involved in this scope.
Equipment
Adequate number of tools & equipment of suitable type / capacity in good working condition will
be deployed. Equipment and vehicles shall be inspected and certified by COMPANY approved TPI
services and certificate of fitness shall be submitted to COMPANY prior to its deployment at site.
All listed tools & equipments shall be calibrated (if applicable) prior to use and must have valid
calibration certificates.
Page 6 of 18
Method Statement for Street Lightning & Allied Works.
Compactors
Cable Trailer
Thrust Boring Machine
Pick-up Truck
Blunt Shovels to remove the stones or any gravel over the cable after laying.
Human Resource
Manpower
i. Project Manager
ii. Project Engineers
iii. Site Engineers
iv. QA/QC Engineer
v. HSE Coordinator/ Officer
vi. Foreman
vii. Surveyors / Asst. Surveyors
Responsibilities:
Project Manager:
To bear overall responsibility for timely and quality execution of works and ensures the
effective use of resources and manpower.
Project Engineers:
To ensure all operations are in accordance with the relevant Project contract specifications
and this method statement and check the accuracy of the works done by the site
engineers.
Site Engineers:
To ensure that all the works are carried out as per the approved shop drawings.
Coordinate with surveyors for accuracy of the work.
QA/QC Engineer:
To ensure that the works are carried out as per the specifications. Necessary tests are to
be carried out and results are to be provided to the Engineer.
HSE Officer/Coordinator:
To ensure that the works are carried out in a safe manner. Give necessary guidelines to the
workforce and facilitate safe working condition.
Foreman:
To ensure to carry out the work with proper control over labors and equipment’s.
Coordinate with surveyor for accuracy of the work.
Page 7 of 18
Method Statement for Street Lightning & Allied Works.
7. Safety Precautions :
Objective
To ensure that all safe practices are adhered to, as per standard operating procedures, Safety
Management Plan and contractual obligations while works are being carried out.
All Personnel involved in the activities covered in the scope of this method statement
shall follow the requirements of Health & Safety Construction Management Plan and
Construction Environment Management Plan.
All safety measures and Employer safety procedures shall be implemented.
All safety measures and precaution shall be taken as defined in the Safety Policy of
Company and/or as required by Client/ Engineer/ other concerned department.
Ensure that everybody within the work site shall wear proper personal protective
equipments (PPE).
Conduct daily tool box meeting for mutual understanding of the works.
Conduct regular or daily check of equipments or machinery prior to use.
Encourage all workers to consider health, safety and environment requirements in their
activities and provide proper facilities, equipments and safety gear ensuring its correct
use.
Provide safe access, gantries and adequate lighting where required & carries out regular
safety inspections and safety audits.
All drivers shall have valid license from UAE, and Third Party Certificates
All work permits (as applicable) shall be obtained prior to commencing any work.
(Refer to Sec – 5.2 Project Permit to work Procedures in OHS CMP – Rev 01).
Barricades and Warning signs to be provided for excavation at site / work area.
Spill prevention control measures are put in place as per Construction Environmental
Management Plan (CEMP) requirement.
All waste is managed as per CEMP requirement.
All waste water handling procedures be adopted specific for this activity if required as
per CEMP obligations.
MSDS Sheet will be provided for all chemicals going to use.
Excavation inspection Checklist to be implemented.
Page 8 of 18
Method Statement for Street Lightning & Allied Works.
Emergency Procedure
Minimum Personnel protective equipment to be worn by all staff and operatives on this site to
carry out the tasks of this method statement are:
Safety Helmet
Safety Boots
High Visibility vest
Safety goggles
Safety Gloves as and when required
Dust mask as and when required
Ear protection as and when required
Page 9 of 18
Method Statement for Street Lightning & Allied Works.
Page 10 of 18
Method Statement for Street Lightning & Allied Works.
8.1.11 Warning signs shall be erected in advance for loading/unloading area like Men at Work, Lifting
under progress etc.
8.1.12 Necessary safety barricades and warning signs shall be provided in advance for the
loading/unloading area like Men at Work, Lifting under progress etc. according to the Client/
company policy and local regulation requirements to prevent unauthorized access.
8.1.13 Provide tag line for controlling the movement during lifting.
8.1.14 Trained/approved Rigger shall be provided during loading/unloading of equipment.
8.1.15 The Equipment to be transported to the construction site shall be placed on the trailer and should be
settled at the appropriate position.
8.1.16 The equipment should always be transported, Loaded and unloaded in vertical position
8.1.17 Equipment shall be stores securely on even surface and in a safe place to avoid any physical
damage/injury.
8.1.18 Equipment shall be inspected for capacity, dimensions & type as per approved Material submittal,
datasheets and visually for any damages.
Page 11 of 18
Method Statement for Street Lightning & Allied Works.
8.2.1.9 All proposed/ approved locations for installation of equipments shall be properly leveled, rammed
and compacted, as applicable subject to the work requirements and scope of work.
8.2.2 Excavation
8.2.2.1 Prior to start of any excavation, the area shall be checked for existing services / Utilities by
obtaining the approvals and relevant drawings. All services / obstruction discovered shall be
recorded, marked and informed to the concerned.
8.2.2.2 Excavation for the street light pole will be as per approved drawing and shall be done by drilling
machine to make bore holes.
8.2.2.3 Before proceeding with all the site activities NOC’s / Permit to Work and other necessary
approvals from all concerned authorities shall be secured.
8.2.2.4 The Excavated material shall be kept at least +2 m away from the trench edge.
8.2.2.5 The necessary safety barricades and warning signs / lights shall be provided / fixed on site
according to the safety requirements.
8.2.2.6 The necessary work arrangements shall be followed, if work will continue near by the traffic.
8.2.2.7 Wherever there is existing services/ Utilities, shall be protected with the utmost care, if applicable.
Page 12 of 18
Method Statement for Street Lightning & Allied Works.
shall be finished smooth with a steel trowel or given a rubbed surface finished.
8.2.3.9 After drilling/while drilling bentonite shall be used if required to avoid pile collapse.
8.2.3.10 After completion of drilling sounding shall be done to verify the required depth of borehole.
8.2.3.11 The fabrication of steel cage shall be carried out as per approved drawings and approved steel.
8.2.3.12 Size and spacing for cage stiffeners and spiral rings shall be verified.
8.2.3.13 The reinforcement steel cage shall be placed and secured symmetrically about the axis of the
foundation and shall be securely blocked to clear the sides of the casing.
8.2.3.14 The method of storing and handling of casings shall be such as to avoid injury to the casings.
8.2.3.15 After lowering the cage into the bore with safe manners, concrete with approved grade shall be
pouring into bore and required tests of concrete shall be done before concreting.
8.2.3.16 PVC electrical raceway or conduit of the size indicated on the Drawings shall be installed in the
foundations, as indicated on the Drawings.
8.2.3.17 Anchor bolts and PVC raceway or conduit shall be located securely in position during the placing
of foundation concrete.
8.2.3.18 Level of the concrete base to be checked by the leveling scale, to ensure that the foundation is
leveled and aligned as per the requirement.
8.2.3.19 The top of the foundations shall be constructed level to provide a proper horizontal surface for
erecting all light poles.
Page 13 of 18
Method Statement for Street Lightning & Allied Works.
8.2.4.10 The gap between the base plate of pole and the foundation shall be filled with cement grout, as per
the approved documents. Cabling works shall be done according the approved documents
8.2.4.11 Coordination and shut down works shall be submitted to the Concerned Engineer / authority
sufficiently in advance to arrange shutdown of power supply where required.
Page 14 of 18
Method Statement for Street Lightning & Allied Works.
8.3.5 Earthing
8.3.5.1 Earthing of all installed equipments will be carried out as per instructions of the Employer /
Concerned Authority, to comply with Standard Regulations and approved shop drawings.
8.3.5.2 All end poles of each circuit and equipments shall be earthed.
Page 15 of 18
Method Statement for Street Lightning & Allied Works.
9.1 GTGC - EPD shall provide and maintain a Quality Control (QC) program by functional area which
shall assure that all services and supplies submitted to the client/ consultant for acceptance conform
to contract requirements.
9.2 GTGC - EPD shall perform all inspections and verifications necessary to substantiate conformance
and also shall submit official Inspection Request Notification on completion of each stage well in
advance otherwise required.
9.3 Succeeding activity shall not commence unless GTGC-EPD obtained clearance for the previous
activity from the Client’s Engineer.
9.4 GTGC - EPD Quality Control Inspector is responsible to verify all the construction activities as per
approved ITP’s in coordination with the Client representative in a timely manner.
9.5 Visual inspection of materials shall be carried out at warehouse/ Yard. Thorough inspection of
materials and consumables as per work progress and manufacturer’s delivery notes will be taken.
Any defect will be reported to Concerned prior to transport to site.
9.6 Quality records shall be maintained to each stage of the work and documented as defined in the ITP
till the completion of the works.
Page 16 of 18
Method Statement for Street Lightning & Allied Works.
NIL
11. ATTACHMENTS
Page 17 of 18
Method Statement for Street Lightning & Allied Works.
Page 18 of 18