exam questions

Exam Questions
1. Which of the following is NOT a Project Constraint?
A. Quality
B. Scale
C. Time
D. Cost
2. A project manager is running a data center installation project. He finds that his stakeholder is
angry because he’s run over his budget because the staff turned out to be more expensive than
planned. The stakeholder’s unhappy that when the project is over, the servers won’t have as much
drive space as he needs. Which of the following constraints was not affected by this problem?
A. Quality
B. Resource
C. Time
D. Cost
3. Which of the following is NOT an example of operational work?
A. Building a purchase order system for accounts payable
B. Submitting weekly purchase orders through a purchase order system
C. Deploying weekly anti-virus software updates
D. Yearly staff performance evaluations
4. You’re managing a project to build a new accounting system. One of the accountants in another
department really likes the current system and is refusing to be trained on the new one. What is
the BEST way to handle this situation?
A. Refuse to work with him because he’s being difficult
B. Appeal to the accountant’s manager and ask to have him required to take training
C. Get a special dispensation so that the accountant doesn’t have to go to the training
D. Work with him to understand his concerns and do what you can to help alleviate them without
compromising your project
5. Which of the following is used for identifying people who are impacted by the project?
A. Resource List
B. Stakeholder Register
C. Enterprise Environmental Factors
D. Project Plan

54   Chapter 2
Download at Boykma.Com
organizations, constraints, and projects

Exam Questions
6. Your manager asks you where to find a list of projects that should be managed together. What is
the BEST place to find this information?
A. Project Plan
B. Project Charter
C. Portfolio Charter
D. Program Charter
7. You want to know specifically which business goal a group of projects and programs are going to
accomplish. Which is the best place to look for this information?
A. Project Plan
B. Project Charter
C. Portfolio Charter
D. Program Charter
8. A project coordinator is having trouble securing programmers for her project. Every time she asks
her boss to give a resource to the project he says that they are too busy to help out with her project.
Which type of organization is she working in?
A. Functional
B. Weak Matrix
C. Strong Matrix
D. Projectized
9. A project manager is having trouble securing programmers for her project. Every time she asks
the programming manager for resources for her project, he says they’re all assigned to other work.
So she is constantly having to go over his head to overrule him. Which type of organization is she
working for?
A. Functional
B. Weak Matrix
C. Strong Matrix
D. Projectized

you are here 4   55


Download at Boykma.Com