Beruflich Dokumente
Kultur Dokumente
1970’s to develop at least one these with a platform and 3 overlying the reservoir were prepared based on the computed
wells. The platform was abandoned after only 67000 bbls of stress concentrations.
cumulative production. In many cases the wells seemed to
have failed because of catastrophic failure of the sand face and Instability was assumed to be a primary influence on drilling
sanding off of the productive interval. Although sand control times. The initial estimate of stress state could then be refined
through gravel packs had been installed on two wells, these by comparing the historical drilling times and predictions of
wells had also failed for indeterminate reasons, but possibly wellbore instability in the Nariva Shales. Finally, new data
through poor gravel pack design. One well in the southern part were collected from well ABM 148, including 4-arm caliper
of the block, ALS-14, has been producing sand free in natural logs and a leak-off test. Despite the approximately 50º
flow for 15 years at rates in excess of 200 bopd. The well has deviation, the data from this well allowed further refinement
recently been put on artificial lift. of the stress description.
Once again sand production appeared to be a key risk to
the successful exploitation of the block. However, VPTL’s The Brighton Marine stress conditions correspond to strike-
ability to properly plan for sand control was limited by lack of slip faulting with a strong overpressure in the Nariva Shales.
access to relevant data including cores and lack of ability to The derivation of the (pre-production) stress state is described
accurately predict reservoir section. in detail in Harper and Chambers (in press). The stress state is
VPTL was committed to a substantial work programme to summarised in Table 1.
appraise and understand the block. Six wells were planned and
acquiring good production test data was an imperative. There The Pt. Ligoure field includes a major, active strike-slip fault
was a significant risk that the production tests would be with some 7 miles strike-slip displacement and 5500 ft vertical
compromised by inappropriate or poorly designed sand control displacement. Pore pressure in the field varies far more than
installation. Data acquisition and careful sand control design the pore pressure in the overpressured Nariva shales of the
was an imperative. Brighton Field. A variation occurs both from one geological
In summary, the offset well data pointed strongly to a formation to another and geographically within the field. The
requirement for sand control at initial completion, but the pore pressure range is approximately 0.45 – 0.85 psi/ft. Leak-
requirements for production testing pointed to making every off tests conducted by Venture have revealed that the
possible attempt to avoid it, at least during the production magnitude of the least principal stress (horizontal) varies to
testing phase. some extent but not to the extent of the pore pressure
variation. Therefore, the principal effective stresses, which
The Process Used control sand failure, vary considerably throughout the field
This paper describes the process used by VPTL to manage and can be much higher than the effective stresses acting in
around the potential sand control problem in both Brighton the Nariva shales. Apart from this variation, the stress state in
and Point Ligoure. Refer to Figure 2. the Pt. Ligoure field is broadly similar to that deduced for the
Brighton Marine field.
Geo-mechanics Study
The Brighton Marine and Pt. Ligoure fields’ stress states were
described by combining geomechanical, geoscientific and Sand Production Prediction Study
drilling data. The database consisted of drilling summaries and A review of the reservoir, well and operating conditions was
a small amount of available core material from the 1960’s. undertaken to in order to determine the causes of sanding.
The only 4-arm caliper data available was that acquired by Using data and information from the Geomechanical study
VPTL during drilling in 2001-2002 and this was incorporated described above, it was identified that the causes of sanding
into the overall understanding. This study was initiated to were directly related to the following:
better understand drilling hazards and constraints. A
significant historical difference in drilling performance • High in-situ stress anisotropy as the fields are located
depending on well azimuth was noted with wells drilled in an area where a strike-slip stress regime is present.
towards 140° or 320° taking on average a longer time to drill
than those 50° or 230°. • Reservoir rock that has low to moderate strength but
is not unconsolidated.
275 wells were drilled some 40 years ago in the Brighton field.
No leak-off test data were available and so a first estimate of This review was carried out for Brighton and Point Ligoure
the principal stress magnitudes was made by combining fields using a Sand Production Management System to
regional seismic focal plane solutions, geological data and determine the critical operating conditions in these fields. A
examples of lost circulation in the early wells. Stress azimuth number of faults are present in the area and the fields are just
was estimated by orientating old core and measuring the time- south-east of the Caribbean plate making its effect be felt on
dependent strains following a series of diamond saw cuts. the stress field. The offshore extension of the present day
Based on this first estimate, the wellbore stress concentrations active Central Range Fault System lies immediately north of
were estimated for the wide range of deviations and well the Brighton Marine Block and the also active Los Bajos fault
azimuths of 275 wells drilled some 40 years previously. crosses through the Point Ligoure Block. The following graph
Predictions of wellbore instability in the thick Nariva shales illustrates the effect of the Los Bajos fault on the minimum
horizontal stress in the Point Ligoure field.
SPE 81034 3
3000
be made. The initial studies gave VPTL confidence to
4000 Los Bajos approach the potential sand production problem using a
management approach as opposed to the traditional control
5000 strategy used in the area. There were a number of benefits that
could be realised from implementing a sand management
Min Horz Stress= (Depth - 2203.3) / 0.9713
6000 system for these fields, these were:
Significant reduction in the CAPEX since no sand
7000
control equipment was required.
0 500 1000 1500 2000 2500 3000 3500 4000 4500
Improved productivity as PI was not to be
MIMIMUM HORIZONTAL STRESS [psi] affected by the sand control method and as the
wells produced, sand existing skins would
Determination of the in-situ field stresses was carried out decrease.
using drilling data from across the field, while a strength Rock strength contrast was sufficient to allow a
model was based on sensitivities to log parameters where selective perforation strategy to be implemented
available. The results were later re-calibrated when additional successfully.
log data became available with the drilling of new wells. The In most wells, crude viscosity and flow rates
in-situ stress regime present in the area was found to be a would allow the produced sand to be transported
strike-fault regime indicating that to surface.
the significant stress anisotropy present in the rocks and in 9-5/8” casing across the Blanket Sand and was again
theory should help reduce propensity to produce sand. perforated using 6” TCP guns at 12 shots per foot and 60 deg
However, available technology did not have the ability to phasing, in the same reservoir compartment as ABM 148. This
orient the perforating guns in the non-horizontal well-bores well was only logged using MWD and therefore shear sonic
and so orientated perforating was not persued. was not acquired. However, an SPP log was still generated and
Reservoir interval to be perforated was selected based on used to confirm perforated interval. This well has been on
two main considerations: production since September 2002 at around 250 bopd and has
Rock strength yet to produce sand.
Critical draw-down pressure
Other factors such as water production and depletion were ABM 151
also considered in the selection process. Stress distribution This well was drilled in a different part of the field and is a
around the well-bore was determined to determine the free-standing well connected to the production facilities by
magnitude of the stress anisotropy present and how it could 3000’ of flow-line. It is even more important to avoid sand
affect perforation cavity stability. production on free-standing wells since flow-line blockage can
Deep penetrating charges using TCP were considered to be easily occur. This part of the field is close to virgin reservoir
the optimum for these conditions; proposed orientation went pressure.
along with the identification of the in-situ field stresses acting Again wireline logs were not run, in order to save cost and
in the area. Table 2 presents the general recommendations for rig time. This time the Blanket sand was completed in 7” liner.
selective perforating in the Brighton field. The completion was run using the rig but the well was not
perforated using TCP. This was to save rig time. Instead the
Blanket sand was perforated using low debris through tubing
Type Charge Density Phasing
Underbalance perforating guns using a lift boat after the rig had moved off.
TCP >22g 4-8 spf 90 deg
<200 psi An SPP log was generated for a nearby exploration well
above critical drilled earlier in the programme. This well, G-10 had similar
pressure formations at similar depths plus the full suite of wireline logs
Table 2 General Perforating Recommendations for was run including DSI. This SPP log is shown in Figure 6.
Brighton It can be seen that in this case the Blanket Sand is again
robust. However, in contrast to ABM 148, the overlying
In practice both TCP and through tubing guns were used stringers should also be able to produce sand free at significant
for perforating the various wells. depletion and draw-down pressures.
Based on the SPP log the stringers above the blanket sand
Brighton Results will be added in the near future. This is expected to result in an
To date VPTL have completed 3 Brighton wells in the prolific increase in production of 250 BOPD.
Blanket sand; ABM 148, ABM 150 and ABM 151. This well has been on production since October 2002.
To date only traces of sand have been produced by this
ABM 148 well. This has been confirmed by analysis of wellhead
ABM 148 was targeted at a deeper play and so had 9-5/8” samples.
casing set through the Blanket sand. The section below was
abandoned following mechanical difficulties. The full suite of Overall Result for Brighton
logs required for the SPP log were run over the blanket and Three Blanket Sand producers are on production at very
stringer sands on this well. The SPP log and perforated high draw-down but with no sand production consistent with
interval are shown in Figure 5. The well was completed using the prediction of the SPP log.
6” tubing conveyed perforating (TCP) guns with 90 degree Production from stringer sands may produce sand in some
phasing and deep penetrating charges at 12 shots per foot. cases but the SPP log can be used to manage this in order to
The well has been on production with gas lift since perforate selected thin sands.
December 2001. Bottom hole pressure surveys have confirmed
that the flowing bottom hole pressure is only 200 psi. Point Ligoure Results
The SPP log predicts that the blanket sand interval Four of the wells drilled by VPTL in the Point Ligoure Block
perforated will not produce sand even when depleted and have been tested to a floating production barge. These wells
drawn down. This is consistent with the results of the initial 12 were ALM 20ST, ALM 22, ALM 25, ALM26.
months of production from this interval.
Note that the SPP log predicts that critical draw-down for ALM 20ST
the stringer sands in this well is above the present draw-down The SPP generated for this well together with the perforated
if stringer sands were to be added. They have not therefore interval is shown as Figure 7. The well was completed in the
been added. Forest Sandstone from 4671 - 4755 feet. A full suite of logs
including the DSI(sonic) were run on this well.
ABM 150 The well was completed and perforated with 4-5/8” TCP
ABM 150 was targeted as a blanket producer based upon guns at 4 SPF and 90 degree phasing. A short clean-up flow
the success of ABM 148. The well was again completed with was conducted with the rig. The well produced a total of 1121
bbls of oil before cutting to water. It was then shut-in. No sand
SPE 81034 5
was produced. The maximum draw-down on this formation across the perforated interval in weeks rather than years. It
was maintained well below the critical draw-down pressure by was possible to validate the prediction that sand would not be
careful manipulation of the test choke. produced, even at large draw-downs in a very short space of
time.
ALM 22
This well was initially completed and tested at 5900 feet in The method explained why sand was produced on ALM-22.
the Cruse Formation. The interval depleted on test. No sand
was produced despite a final draw-down of 1200 psi. It is unclear why sand was not produced under the extreme
A short DST was conducted on a shallow interval behind conditions of depletion on wells ALM-23 and ALM-26
13-3/8” and 9-5/8” casing between 3473 and 3522’. Intervals however, rock strength data is log derived and actual strength
of low rock strength as indicated by the SPP log were avoided might be higher than what it was originally estimated,
within this gross interval. This interval flowed 16° API oil and explaining these events. A strengthening effect in the near
during the DST only a trace of sand was observed. The well wellbore area as a result of the high stress anisotrophy may
was subsequently killed with brine and completed and re- also have contributed.
perforated. The SPP log for this shallow interval is shown in
Figure 8. The log demonstrates a good example of selective Well ALM 20ST rapidily water out which allowed validation
perforating in order to avoid a high risk interval. of the impact of water production on the prediction. No sand
The well was then connected to the production barge but was observed under 100 % water production.
would not flow. An attempt was made to lift the well in using
Nitrogen. This resulted in a very large draw-down in excess of Acknowledgements
1300 psi being excerpted on this low strength formation. The Tim Harper, Geosphere UK conducted the Geomechanical
SPP log predicts a sand face failure that seems to have studies used as input into the Sand Production Prediction
occurred. The well appeared to sand up rapidly which was Model.
confirmed by tagging with a sand bailer.
Ronald Daharu SPE, Venture Production Trinidad, Reservoir
ALM 23 Engineering support and review of paper.
This well was completed and tested in a Forest Sandstone
interval 4310’-4360’. Referring to Figure 9, this interval References
includes rock with a predicted critical draw-down pressure of Harper, T.R., Chambers, J.L.C., in press. Stress state and its
less than 500 psi. In this case it was decided to perforate the influence on drilling and secondary migration in the Brighton
entire clean sandstone interval since the pay was limited and field, Trinidad submitted to the Geol. Soc. Lond., Spec. Pub.
attempt to control the draw-down by careful choke Oil and gas in compressional belts.
manipulation. This well was tested for 25 days to the
production barge that depleted the test interval. The final
bottom hole flowing pressure at the perforated interval at the
end of the test is estimated to be 850 psi. The depletion of the Abbreviations
interval was of the order of 1400 psi. The model predicts sand bbls = barrels
failure under these conditions, however this does not appear to bopd = barrels of oil per day
have occurred. The model would therefore appear to be g = grams
conservative on this occasion since no sand was detected ppg = pounds per gallon
during the test. psi = pounds per square inch
psi/ft = pounds per square inch per foot
ALM 26 spf = shots per foot
Initial completion was perforated with TCP guns from SPP = sand production prediction
6120-6220’ in a Cruse reservoir. The SPP log for this interval TCP = tubing conveyed perforating
is shown in Figure 10. Critical draw-down pressure is in VPTL = Venture Production Trinidad Limited
excess of 750 psi over almost all of the interval with one or
two spikes weaker intervals still above 500 psi. Again, this
depleted on test without producing sand. Further intervals
were perforated using through tubing guns. The zones also
depleted rapidly on test but again, no sand was produced.
Maximum draw-down estimated at the end of the test is
around 800 psi.
Conclusions
The results obtained from the VPTL 2001/2002 drilling
programme validate the sand production prediction process
used to minimise the chances of sand production on the wells.
The accumulations were depleted rapidly and therefore it was
possible to see the effect of depletion and large draw-down
6 SPE 81034
Figure 1 Map of Brighton and Point Ligoure Fields Figure 4 Typical SPP Log
Gulf of Paria, Trinidad
Geomechanics
Geomechanics-
Well-bore
well-bore Stress
stress study
Study 148
Weak stringer
Sand prediction sand
study
Gather data
during drilling
Well specific
sand prediction log
Perforated interval
Select perforated interval 3008-3098’
using SPP log
Perforated interval
ALM 26
Perforated interval Estimated Draw-down 6120-6220’
4670-4754’
ALM 20ST
Perforated intervals
3473-3482, 3501-3522’ ALM 22
ALM 23
Perforated interval
4310-4360’