Sie sind auf Seite 1von 3

REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF AGRARIAN REFORM PREFINAL


MinSAAD INSPECTION
Mindanao Sustainable Agrarian and Agriculture
Development Project
REPORT
SUBPROJECT NAME INSPECTION DATE
Malagap Communal Irrigation System January 17, 2018
SUBPROJECT ID NO. SUBPROJECT LOCATION RESETTLEMENT AREA
15-5060604001-005A Malagap, Banisilan, Cotabato North Cotabato SA 1
TYPE OF ACTION START DATE ACTUAL COMPLETION DATE
Final Inspection Subproject Acceptance February 1, 2017 January 10, 2018
CONTRACTOR NAME IMPLEMENTING AGENCY
Cofejok Construction and Supply NIA Cotabato IMO, Kidapawan City
ITEM PARTICULAR FINDINGS RECOMMENDATION REMARKS
1 LEFT MAIN CANAL 1. Irregularities of 1. Repair/retouch and/or
concrete surfaces, rectify any irregularities of
stone-like holes and concrete surfaces and
1. LMC Sta. 0+000 hairline cracks of canal cracks.
- 0+454 walls.
2. Provide adequate backfill
2. LMC Sta. 1+323 2. No backfill on some on the canal lining and
– 1+398; 1+665 portions of the canal other structure as
– 1+800 lining. planned.

3. LMC Sta. 2+012 3. Silted lined canal and 3. Silts and debris are
– 2+331 no backfill on some recommended to be
portion of the lined removed by the
4. Check with T.O. canal from Sta. 2+012 contractor.
R at LMC Sta – Sta 2+331
1+713 4. Carefully remove form
4. No Structural Backfill lumbers at the grooves of
not removed form the inlet and outlet of the
lumbers at the grooves T.O. to prevent cracks on
of the inlet and outlet the structure
of the turn-out

2 RIGHT MAIN 1. Irregularities of 1. Repair/retouch and/or


CANAL concrete surfaces, rectify any irregularities of
stone-like holes and concrete surfaces and
1. Sta. 0+147 – hairline cracks of canal cracks.
0+457; 0+463 – walls.
0+649; 0+654 – 2. Silts and debris are
0+780 2. Silted line canal recommended to be
removed by the
Lat. A RMC Sta. 3. All lining sections have contractor.
0+000 – 1+805 no structural backfill
3. Provide adequate backfill
2. Lat. A RMC Sta. on the canal lining and
0+680 – 0+740 other structure as
planned.
3. Lat. A RMC All
Canal
Structures
3 Elevated flumes 1. Contraction/expansion 1. Apply asphalt sealant as
joints are not applied per drawings
with asphalt sealant
2. Repair/retouch and/or
2. Bank protection of rectify the said cracks
existing elevated flume
at LMC Sta. 1+398 is
found with cracks at
the right portion of the
bank protection

3. Elevated flume at LMC


Sta. 1+962 – 2+012

4 Dam Works Steel gates have no chain 1. Install chain block on both
block installed left and right steel gates.

5 Other issues and The inspectorate team was NIA and contractor to conduct
concerns not able to test run the as-built survey and when
system. However, found insufficient in elevation,
according to IA members rectify canal wall height.
during the exit meeting,
the level of water
overflows at LMC Sta. 0+
000 to Sta. 0+100 before
reaching the further
stations.

FIGURES/PHOTO DOCUMENTATION

Figure 1 Rehabilitation works on the dam piers are done. Figure 2 Rehabilitation works on the dam piers are done.

Figure 3 Towers/sheds for the operating wheel are not yet installed.
INSPECTORATE TEAM

ENGR. DIONY J. ANABO


MinSAAD Consultant for Irrigation/PHF
ENGR. BENNETTE JAE SOLEDAD
PPMO RI Coordinator – North Cotabato
ENGR. IAN JAN N. DALISAY
MPMO Rural Infrastructure Specialist

NOTED

ENGR. ROGER B. TABAÑAG


DAR MPMO Rural Infrastructure Component Manager

Das könnte Ihnen auch gefallen