34
INSIGHT
Against limit state
design in rock
Dr Philip J N Pells, Adjunct Professor at the University of New South
Wales and director of Pells Consulting, argues against the usefulness
of limit state design in underground construction through rock
tis inappropriate if not meaningless, to
attempt to apply mit state design
‘methods, uch as those encapsulated
in Eurocode 7, tothe design of primary
‘support for tunnels in roc, particularly weak
rock or any rock under high stress. By
reference to some 41 case histories of major
tunnel fares, this article shows that more
‘than 85 percent wee the result of
unexpected geology or hydrogeology. tis
submitted thatthe unknowns and
Uncertainties in geology and hyarobogy
cannot be propery deat with by applying
codified factors to geotechnical parameters.
Its concluded that working stress methods
shouldbe retained fr tunnel support
‘design, and that such design would bene
{ar mor, ftom competent geological and
hydrogeological understanding, than fom
faith in cade factors
Introduction
Limit state design care from structural
engineering where structure, loads,
‘deformations and collapse modes are
reasonably easy 1 know, oF postulate, and
‘can be appropriately factored. The factors
in structural engineering are inked, closely
to fale probability because material
properties, and loadings can be defined
statistically.
‘hore have been great dificutes in
fining iit stage design for geotechnical
|works, and in particular for works where
there fe eubstantial interaction between
‘man-made structure and the ground (eft
Hangzhou metro pit collapse, 2008 and 2). Since the mid-1980s, Limit State
‘Tunnels & Tunneling Intemational FEBRUARY 2011
Codes have been developed in many
Counties fortwo kinds of geotechnical
works, namely piles (AS 2159) and.
retaining structures (AS 4678 and BS
8002), These codes are quite complex,
‘even for these simple types of works
‘where each unit in the ground usually has
conly a few variables, namely
* Uncrained conditions: unit weight,
‘undead shear strength and stiness,
+ Effective stress conltons: unit weight,
‘tfectve stress cohesion and fiction,
rained stiiness.
‘The publication of Eurocode 7 for
Geotechnical Design (and BS EM 1997-1)
has changed the landscape dramatically.
Now ther Is bureaucratic pressure on the
{geotechnical profession to do all design
sing it state methodology.
However, design of primary support for
tunnels in weak rock, r any rock under
righ tress, s substantially more complex
than designing piles or retaining walls. In
this application, mit state design is
inappropriate, and counterproductve.
‘This isnot to say that limit state
methodology Is appropriate inal tunnel
suppor design It probably could be used
for segment design in soft ground tunnels,
but whether it would add any value to
present design procedures is
questionable.
Learning from others.
In 1981, when he viewed what became
Eurocode 7, approacting aver the horzon,
MD Botton ef 1), then aleturer at
Cambridge, produced an enue ate, in
‘which he wrote:
“Weare therfore entering acetic
petlodin which @ concerted input of effort
willbe requied in order to avoid pivotal
piilosophical mistakes which could so
\www-tunnetsandtunnelting.comconstrain designers as to affect the degree
(of security of soll constructions in Europe
for many years”
He made, and justified, some very wise
suggestions forthe way forward, all of
hich seem to have boon ignored. He also
‘noted that, “Deterministic calculations
‘based on abservable mechanisms offer a
‘more reliable route to decision-making in
{geotechnical design than do the
processes of statistic inference," and,
“The omission ofa limit state mode wil
rot be rectified by application of arger
factors against those liit-modes that
have been recognised.”
‘Along sila lines Day, Wong and Poulos
(022) note:
Fora probabilty calculation to work
there is an assumption thatthe actions and
resistances ae independent variables, Le.
that changes tothe lading do not
influence the resistance and visa versa..n
the design of sol retaining structures this is
rot tue because the same sol acts as a
load and a resistance.
A lecture by Dr Colin Smith of the
University of Shetietd fet 3) seeks to
explain how limit state design, according
to Euracode 7, can be implemented for
the two simple problems of bearing
capacity ofa pad footing, and a cantilever
retaining wal. The process isnot simple,
oritutve, ‘The Nicoll Highway collapse of 2004
Smith points out two important points
that are relevant o this article, namely Undefined, calculation factor of safety appliod ina ciferont way.
1. For Utimate Limit State (ULS) analyses, However, tunnel support design must
Eurocode 7 requires fve separate require consideration of QU, STR, GEO, _In passing, Day notes the folowing
checks: UPL and HYD, and is anyway usually lemma when appiying ultimate limit state
EQU: loss of equibrium ctated by allowable movements, namely (ULS) concept to retaining wal desig.
STR: faire ofthe structure SLS! Welcome to the word of acronyms "Te earth pressure and pore water
GEO: faltxe ofthe ground and valid logic, but inthis authors opinion, pressure are intereated through
UPL: fale by upktt Impossibie application. ‘equilrium and the laws of physics, Partial
HYD: hydraulic heave, and ‘The substantial cificuties associated factor mi state caleuations apply factors
with mit state design n geotechnical to the soll pressure and the water pressures,
2. The Eurocode 7 factors address Uitimate engineering re described clearly by Day independent to determine the ultimate
Limit State ony, andthe code states (re 4) who concludes: load. Ths utimate load does not represent
(24.844: “it may be verified that a “Te foloving important points must be the tue load atthe init state and has no
sufciently low fraction of the ground understood when using limit state’ code physical mearing, it violates equibrium
strength is mobilsed to keep methods. ‘and the theories that were used to
‘eformatione within the required *The partial factor method was adopted by determine the loads in the frst place.
serviceabity limits, provided this Sructutal design codes asa convenient Ttmay be thought that alli wellin
simplified approach s restricted to ‘way to cary out routine design based on structural engineering, at east where there
design situations where: probabistic considerations. tproduces a isnot stuctura-ground interaction. The
* Avalue ofthe deformation is not ‘more consistent probabily of fale than atc by Alasdair Beal et 5), in the June
requied to check the Serviceabilty the working stress method. 2010 issue of Now Gail Engineer, wil
Limit State (85). ‘The ulate load is a mathematical rapidly dgpel this false view. tis almost a
+ Estabished comparable experience concept. It has no physical meaning horror story, and offerte folowing
‘exists with similar ground, structures + In geotechnical codes the partial factors extracts as examples:
| ‘and application method.” ‘arent based onrelabilty analysis 2s) Language and symbo's
| they rein structural codes. “The most surpeising aspect is that
‘Smith suggests that only STR and GEO are + For geotechnical design the partial factor __—Eurocodes aso attempt to create a new
required for ULS for design of footings and lit state design codes are simply the old technica language for engineering. Al
retaining wal, SLS islet for a separate, traditional design methods, but with the ‘over the word, English-language
wwu:tunnelsandtunneling.com FEBRUARY 2011 Tunnels & Tunneling Intemational | 35.
fefi INSIGHT | LIMIT STATE DESIGN
NI
———— tendon 19p1 | Unepacod okay
2 London 1965 | Urepeced gsooas ra Art fos spat
3 SodhertenSen | 1995 | Urerpeced wet
“4 Ceage-Fa, Sh Aza | 1970 | Unspace jas, i opr alr Fe
5 Manic 1980 | Loca rlaton ged
6 MART, Hong Kong 1983, (Misinterpretation of geology
7 Rerwria 1085 | Urepaced ony
orb 1960 | Unepecit st 7
ose 1901) | Unepecd godoay andhyeiooeday
eu ao apport
io Sead 19812) | Unetpeced wear es gant
11 Sex 1992 | Aster Sen 191)
12 Sed {89() | Aster Secu 1910) E
1a Sood 1n5@) | Aster Secu 1901)
4 as 1005.5 | Estemegrundvete ns and rossi
15 _HeatrowEspess | 1884 | PoavTaragert wranstip aqua rel
16 Munch | i968 ‘Unexpected geology
17 Lon Prose 1005 | Urepecid gota, revat eis King
Te Deeanes, Uc | f098 | Dae evr PEM bono
19 bers 1291-96 | TEM ot mare conpecoecogy
2 Ha [1998 | Wt ae src nes ding conson
21 —Tesgu ShhKorea | 2000 | Unewpected oro and nogeclony
22 CramedTevel RAL 228 | Coleen of nerectnd wet
2 Mateo Meto,Fanee | ANI | Notte
24 Shanghai 2003 Falure of ground freezing iid
25 Heteter Tava, | 1991-2004 Unemected gecogyandycooecogy
26 SMVET,Maiyia | 20032008 Unepected as gosiogy
ar Goes Gy Motrnay | 2008 | Flay recent at abo 35m pm
ana, Snes
2 Kooning Tova | 2005
2) BacekraMero | 2005
& Lara Cova, Senay | 2005 | Fae io dg er fe unepected pay
31 tausare | 0S Unapecd ogy andhydensogy
2 Bacekre 2005 | Unsipected at
8 Kowloon, HongKong_| 2008 | Consucn ero wi sary TEM
3 MK Taree Case, | 2007 | Fale ofroaa, tte usa aan
Cruecaata, Ose
35 Railway Tunnel, ‘2007 ‘Unexpected groundwater oe
ter Merge a |
38 Ronen, Hong Kong | 2207 Conan anor ceed
“aT SaPaso 2x77 | ales account goby
$8 GrdeLre,Shgiboe | 2008 | Lease grand
32 Sbvay Time, | 2008 | Unepected coy and radar
Heros Osho
40 Subway Tunnel, ‘2009 Unexpected geology
Cuca, Geary
“1 BirvaTund, aque | 2010 | Tree capees, Kl won 208, xpeted
| spdogy ari geurdvatr
engineering textbooks and codes have moment, ‘shear, torsion’, and
been writen fr over a century in ‘imposed deformation.
standard tecnical Engle, using the Howeve, Euocodes set out replace
‘aii terms ‘tess this wth anew anguage based onthe
compression, Tension word acto’ which is vena new
26 | Tunnels & Tunneling International FEBRUARY 2011
‘meaning of Toad or imposed
\formation’ In this new language, loads
become ‘rect actions, Impased
deformations are ‘ingrect actions’ and
axial forces, shear forces and moments
become action affects, which may be
‘transverse’, angen and 50 on. Dead
load becomes a ‘permanent dict
‘action’ and imposed loads are ‘variable
iocton actions.”
(W Caleuatons
“Eurocode load combinations iwvalve
Considering each imposed load in turn
as.a ‘leading varable action’, while
other imposed loads and deformations
are applied as reduced ‘accompanying
variable actions. Al the diferent
possible permutations of factors must
then be considered to find which has.
the worst effect.
For those who enjoy calculations and
working with numbers, there is certainly
fun tobe had, However, before the
‘governing equation can be apple the
engineer must identify which variable
‘actions can be considered as being
separate actions inthe calculation and
which cannot, 0 a5 to apply the factors
correctly. This also affcts safety and
‘economy, because the total imposed
load can be vied into separate
‘actions, this reduces the design load and
the stucture’s safety factor. The more
the loading onthe suctur can be
vied up into separate actions, the
lower the saety factor comes."
(i) Geotechnical design
“Eurocode 7 par 1 for geotechnical
{design isthe most raccal and iferent of
all Euocodes. proposes a complete
‘change from past practice, with a new,
‘complex eystom of partial factors
replacing the ractional global safety
factors of geotechnical design.
‘According to Bond (rt 6:
“When Ilast counted, there were 112
partial factors to choose fom in EN
1997-1, with a further 34 converted from
characteristic values to design values by
the application of specific factors:
Eurocode 7 changes almost everthing
that is said about geotechnical design in
‘exiting sol mechanics books and codes
of practon, yet f engineers ae to desion
structures to Eurocodes, they will have to
master it"
‘The show-stopper: problems in
tunnel support design
Following from the above discussion, itis,
‘concluded that there are three reasons
wwu:tunnelsandtunneling.comee
\why limit state design of primary support
for cavers in rock, particularly weak rock
for any rock under high stress Is much
‘more complex than design of ples or
retaining wal.
1. There fs no separation between
‘structure and ‘ground overall
‘behaviour is one of interaction, with the
support elements affecting loading from
the ground and groundwater, and the
‘round and groundwater affecting the
‘support elements.
2. The engineering behaviour of just a
single Geotechnical Unt, a function of
‘many variables, namely:
+ Unit weight
+ Substance stiffness.
«+ Substance strength
‘Number of defect sots.
+ Spacing and continuity of defects.
‘+ Dip and dip rection of each set of
detects
‘Normal and shear stitiess ofeach
defect set
‘Peak cohesion and fiction of each sat
of fects.
+ Water pressures
Frequently thore area least thre defect
sets (bedding, joints and sheers) so the
above list amounts to 38 variables.
‘Some ofthese variables have to be
increased to increase load on the:
support system, some have to be
reduced to ineease load.
“Then there may be two to six
Geotechnical Unis, giving 76 to. 228
variables, each which has tobe factored,
somehow,
3, Ground reinforcements, such as
‘ntansioned ful grouted bots or cables,
‘are neler ‘structure’ nor ‘round’, but
‘serve to modify the ground behaviour
\www:tunnelsandtunneling.com
Given the above, its no wonder that
thece fe no specific Limit Design Code for independent strength factors ofall equal
design of primary suppor for cavers i
rock. However, Eurocode 7 isa ‘catch
‘code, and there are major tunneling
projects in Australia, and, no doubt,
elsewhere inthe World, curently under an unrealistically occurrence (assuming
‘design, ostensibly, according to this code, all have an equal probabilly is 0.0018 =
‘The wrlterhas examined the procedures 1x10-15, which isan unrealistically low
‘set outin the design manual for one such _probabilly of occurrence for design,
project, and concludes thatthe
methodology is non-sensical
‘As a small example; folowing to
Eurocode 7, the dead load is supposedly variables, as discussed above itis faity
factored up by 1.35 by inereasing the unit obvious that we are likely to find
weight of the rock. However, as any
trained rock mechanics engineer knows, to the reasonableness of the probability of
the load on tunnel supports a function of failure of our final design. Notwithstanding
the horizontal stresses as much as the
fverburden stresses; and also the relative fundamental reason wy limit state
sifness ofthe rock mass and the
support; and also the sequence of
‘suppot Installation asthe face advanck
Factoring the unt weight by 1.95 does
factor the load by 1.35. And factoring t
‘natural horizontal stress by 1.35 wil, in
‘some situations, lead toa lesser load on of Hong Kong (ef 8), and also taken from
the support, not greater. Again, a8 any
trained rock mechanies engineer knows, _eccurred betwoon 6
‘this wil depend on whether, inthe
deintions of Lauffer (ret 7), we are
‘dealing with loosening pressures’, or
"tru rock pressures’
‘Then there isthe Isve pointed out by conditions, three to management coupled
Wong, Day and Poulos (rt 2:
"The code requires that the design
resistance is equal tothe characteristic construction.
strength of the material multipied by
teach of the factors in series, The
problem with this appraach is that basio the Wison tunnel in Hawai, can the falure
statistics demonstrates thatthe
probability of such a design value
‘eccurring Is miniscule. For example, fa gasin the ground.
strength factor of 0.8 is meant to
represent a 0.1 per cent (0.001)
probabilly of a more adverse value
LIMIT STATE DESIGN | nscit
Above: The comer of the residential
building directly over the collap
Lote Plan diagram of the Lane Cove tunnel
project wit the collapse site shown
‘occurring, then if there are five
in t0.0.8, the resuitant strength factor Is
‘all’ 0.85 = 0.3, and the probability of
foccurrence (assuming all have an equal
probability is 0.0015 = 1x10-15, which is
particularly remembering thatthe loads
will also be factored up.”
we have between 76 and 228
‘ourselves in unknown terior in respect
this dificult, there is even more
phitosophyy should not be applied to
tunnel support design. This is geological
ee, uncertainty.
not Table 1 summarises major tunnel
the failures, documented by the Civil
Enginoering and Development Department
the writer's own experience. The failures
11964 and 2010, some with trl loss
fife, al with great financial pain. Of these
41 fallures, 35 @5 per cont) are ascribed to
Unexpected geological or hycrogeological
with design, and thre to construction
tears, Al the failures occurred during
Jacobs (re 9} discusses five other
significant tunnel failures. In only one case,
bo ascribed to flawed design The other
{allures elated to geology, to water and to
Eurocode 7 protagonists may argue
that because about 85 per cent ofthe
major tunnel failures, documented in
FEBRUARY 2011 Tunools & Tunnating Iniornatonal | 97fh INSIGHT | LIMIT STATE DESIGN
“Table 1, were caused by unexpected
ology or hydrogeotogy, we should
apply @ factor to geology. But this is
Impossible. Firstly, how do you apply a
factor to something of whose existence
you are ignorant. Secondly, how does
‘one apply sensible factors to all the
parameters listed when itis not clear
which changes are adverse. Thirdly, given
that the fundamental intent of imi state
design procedures, such as Eurocode 7,
is to achieve a known low probabilty of
failure, how do we know what factors to
select when we have no way of knowing
what isthe lkaly failure probabilty of the
final design
Given the above facts, we have two
choices,
‘We could, nat unreasonaby, adopt the
view of Nassim Taleb (et 10), that the
‘geological and grouncivater conditions that
led to the fares in Table tare ‘Black
‘Swans'- unexpected, unpredictable,
utiors, carrying extreme impact With the
Botton, MLD. Limit Stato Design in Geotchnical
Engineering, Ground Engnecting, September 198
ay, R.A, Wong, PK. and Poulos, HG. “Ften
years of geotechnical mit state signin
‘Ausra. Prt |= Retaining structures". Proc. 10th
‘Australia-New Zealand Geomechanics Con. Aust.
Geomechanics. Society, 2 596-601, 2007. And
“Part 2= Foundations”. Pro. 10th Austraia-Now
Zealand Geomechanics Con, Aust.
‘Geomechanics. Society, 2: 602-607, 2007.
‘Smith, C. Practical Appication of Geotechnical
Lint Analyt in Limit State Design, University of
‘Shot, 2008
Day, LA. Limit Stato Dosign for Structures and
Gootechnics. What doos it realy mean? University
‘of Quoensiand, 1958.
Bea, AN. Eurocodes in tain: The questions that
‘il need answering, Now Civil Engineer
Intemational, 08.2010, p25
Bond, A When aninessible force meets an
Jmmovablo object. GeoDring Intemational
(04.2007, p22.
Lauteg H, Gobrgaklasainung fur de Stallenbau
Geologie und Batnesen, Vol 24, No.1, 1952
Chil Engineering and Development Department.
Catalogue of Notable Tunnel Falues Case
Histories (up to December 2008), Hong Kong
Institution of Engineers, 2008.
Jacobs, JD. Some Tunnel Falls and what they
hhave Taught. Hazards in Tunneling and on
Falsowerk. Inst. Of Cl Engineers, London, 1975,
"Nassim Nicholas Taleb. The Black Swan. Random
House, New York, 2007
Above: The Pinheios station cavern and shaft collapse in Sao Paulo in January 2007
"Black Swan’ view we may as wel shrug
‘ur shoulders and hope.
‘Or we take my view that it is blatantly
‘obvious that our profession should be
‘concentrating on the proper training of
engineering geologists, namely geologists
‘who propery understand rock mechanics,
‘and we should rly on these people, and
not be trying to apply meaningless factors
to, often, quessed geotechnical
parameters.
Inthe first drafts of this article I set out
to document, what thought was, a
‘sensible path for using the principles of
Eurocode 7 inthe design of tunnal
‘support. These were the procedures that |
had documented to introduce into a major
‘Australian project which was locked into
Eurocode 7. They included consideration
(0 80 factors fr the geotechnical
parameters, not including the orientations
of joins, faults and bedding, and ground
water pressures.
However, when came to thi nal atl
hha to cut that out. My reasons ar threeold,
Firstly, the only way could achieve
‘something sensible out of Eurocode 7 was
to reduce itto something itis not, namely a
system of partial factors of satel.
‘Secondly, was wrong in my
‘assessment of the factors - the reason
boing as set aut by Wong, Day and Poulos
(2007), and quoted above. The
‘combination of al the factors gave a
ridiculously low probability, but @
‘meaningless one, because the real issue
was uncertainty inthe structural geology
‘Thirdly, | found myself being sucked
Into the very place that should be
rejected. This isthe place where
tenginoers consider that geologists and
88 | Tunnels & Tunneling Intemational FEBRUARY 2011
hydro geologists have limited value, and
the laws of physics ae insufficient, oF too
ficult. And so we produce bureaucratic
procedures to hide behind, and to make
‘ourselves more comfortable,
Parting comment
‘Agquote, attributed to Bran Simpson,
‘encapsulates the issue
An understanding of limit state design
‘can be obtained by contrasting it with
‘working state design:
+ Working state design: Anaiyse the
expected working state, then apply
‘margins of safety
+ Limit state design: Analyse the
Unexpected states at which the structure
has reached an unacceptable nit
‘Make sure the init states ae urwealistic
(erat least unticey,”
“The issue is that selection of meaningful
“unexpected and ‘unrealistic’ states is
Impossible, or meaningless. For design of
tunnel suppor, which, in weak rack, or
rock under high stress, s dominated by
‘geological materials and geological
structures, and wth the loading of the
‘suppor being a function ofthe mass
sitfness of the ground and the stfiness of
the suppor elements.
We should, in fact we must, retain
working state design, based on the
‘expected. The expacted should be
‘based on detailed site investigations
Imorpreted by the best engineering
geologists, of whom there are too few.
‘Then we must propery use the
Observational Method, by whatever name
we chose to cal, even the New
Australian Tunneling Method!
www-tunnelsontine info