Beruflich Dokumente
Kultur Dokumente
1. To distribute a single load equally over the pile group and thus over a
greater area of bearing potential,
The C.G. of piles should be placed as far as possible in the C.G. of loads
transmitted from the structure to the group of piles.
1. Design must satisfy the punching shear in the vicinity of the individual
piles or shafts
3. The bearing force between the individual piles or shafts and the caps
must not exceed the capacity of either element.
3. Each pile receives the load only vertically (i.e. axially applied );
Ix = Io + A . X2
Eccentricity of load
Thus, the pile cap should be large enough to accommodate those piles which
have deviated from the intended position. The pile cap should extend for a
distance of 100 to 150 mm outside the outer face of the piles in the group.
The pile head at cutoff elevation shall be within 50 mm of plan locations for
bent caps supported by piles, and shall be within 150mm of plan locations for
all piles capped below final grade. The as – driven centroid of load of any pile
group at cutoff elevation shall be within 5% of the plan location of the
designed centroid of load.
No pile shall be nearer than 100mm from any edge of the cap. Any increase in
size of cap to meet this edge distance requirement shall be at the Contractor’s
expense.
Piles shall be installed so that the axial alignment of the top 3m of the pile is
within 2% of the specified alignment. For piles that cannot be inspected
internally after installation, an alignment check shall be made before
installing the last 1.5m of pile, or after installation is completed provided the
exposed portion of the pile is not less than 1.5m in length. The Engineer may
require that driving be stopped in order to check the pile alignment. Aligned
section on a misaligned section shall not be permitted.
2- Column dimensions
B- Design Steps:
Notes:
7-
Design for moment:
Check IS CODES for the vakue of Punching ,shear and bond values.
Compied by Er.T.RangaRajan.