Beruflich Dokumente
Kultur Dokumente
Abstract:
The Continuity of power supply that is reliability of power supply is highly essential for the
development of the country. The electric power is distributed to the consumers through electrical network.
The study involves the analysis of various obstacles for reliable power supply, interruption in electric
power distribution due to defects in relays and circuit. Cost benefit by the prevention and reliability in
power supply.
Keywords— Reliability of power, Mitigation of Interruption, Radial feeders, power transformer and
grid feeders.
1. INTRODUCTION
The power generated at the generating
station should reach the consumers, for which
Transmission and Distribution network is used.
Since electrical equipment’s are involved in the
Single line diagram of 110kv sub station
Transmission and Distribution network the
electric power supply does not reach the
consumer without interruption. The interruptions
of power supply distributions are caused either
intentionally or unintentionally. Intentional
interruptions are the load shedding done to match 10. Actuation of high winding temperature due to
the demand and supply that is Demand Side air looking in power Transformer.
Management (DSM). The unintentional 11. Operation on differential relay due to entry of
interruptions are caused by the defects developed rain watershorting of bushing CT Secondary
in the Transmission and Distribution network and leads
equipment’s associated with them. This research 12. Actuation of Oil Surge Relay (OSR) due to
is involved in the area of unintentional rain water and low oil level due to oil leakage
interruptions. This study is focused on the 13. Operation of Power transformer Protection for
interruption in power distribution due to the Power transformer internal fault.
various defects developed in the relays and its B. Current Transformer
circuits. 1. Early pickup of relay due to collapse of
Current Transformer (CT) ratio
II. DEFECT DESCRIPTION 2. Failure of molded type Current Transformer
due to entry of rain water inside the Current
The study is focused on the interruptions
Transformer (CT) through the crack
in radial feeders. Hence the 110KV and 33KV
developed in the molding.
sub stations have been selected for the study. The
3. Simultaneous tripping of adjacent feeders due
study was conducted during 2014-2016 on the
to low insulation resistance value of Current
causes of interruptions in the utility.
Transformer in healthy feeders.
The defect which affects reliability in 4. Failure of Current Transformer due open
power supply is categorized as under. circuiting of secondary.
The Power Transformer breather, oil The AC and DC cables should be laid
condition and IR values should be checked separately to avoid mixing of AC and DC supply
periodically and maintained in good condition and to prevent relay failure.
and the Power Transformer over loading should
The delay timings of the relay should be
be avoided to prevent the development of internal
selected properly to avoid backup tripping. The
fault in Power Transformer.
relay current rating should be selected according
to the fault level of the area to prevent the
3. SF6 Gas pressure maintain 6.5kgf/cm2 if 6. Ammeter loading checked and again open
low tapping of sf6 gas done the breaker
4. Gas leakage checked and arrested 7. Cable duct maintained neatly and clean
5. Single phase preventer contactor and eaten waste not through inside control
maintain 3 phase supply room.
6. Closing and tripping coil changed by new 8. Relay calibrated every year periodically
one 9. Lighting spike provided
7. 110 volts DC supply maintained in trip 10. Plunger adjustment done
and close coil of breaker
8. Clamps and 110KV Jumpers in Tightness
condition
110 KV & 33KV CURRENT
9. Clamp tightness and providing hot-zip
TRANSFORMER DEFECTS AND REMEDY
zinc coated bolt & nuts
10. Sequence closing of breaker poles 1. Current Transformer secondary saturates
maintained with removing dust etc. 2. Current transformer busted
11. Proper lubrication done in auxiliary 3. Oil leakage
contacts of breaker 4. Low IR value
12. Lighting spike provided 5. Insulator broken
13. Changing of low IR values Insulator 6. Proper measuring CT erected
14. New T&C switch provided 7. Loose connection of cables
15. Proper authorization experience operators 8. Secondary side of loading improper rods
with conduction safety glass provided. Minimum loading transformer
9. Glow in current transformer clamps
33KV BRAKER DEFECTS AND REMEDY 10. Current transformer firing
1. Spring charging motor problem
2. Motor charging limit switch problem
3. Dummy closing of breaker REMEDY
4. SF6 gas leakage, low gas
5. Vacuum interrupter damaged 1. Current transformer secondary short
6. Circuit breaker during open condition 1no circuited
of breaker phase not opening 2. Limit the loading amps
7. Protection cable damaged due to rats 3. Gasket provided newly and oil leakage
8. Relay closing and tripping problems arrested.
9. Burst breaker insulator 4. Improve the IR value
10. Trip and close coil plunger adjustment 5. Correct ration of C.T. Erected
problem 6. Quality Insulator provided
7. Tightness of cable with duct.
8. Ct rods provided according of loading
9. Clamps changed and provide new bolt &
33KV BRAKER CLOSING REMEDY nuts with zinc coated
1. Damaged spring changed 10. Tree clearance, periodical oil changing
2. Limit switch changed by new one done.
3. Adjusting of travel time
4. SF6 gas tapped, gas leakage arrested
5. New vacuum interrupter provided
D. Relay
1. IS 3842 (Part I) – 1967,
2. IS 3842 (Part XII) – 1976
E. Battery
IS 8320 – 1976
F. Lighting Arrester
REFERENCE
Equipment’s preventive techniques
(1). Billinton.R, Vohra P.K. Kumar. S: Effect
Defects in Equipment of Station Originated outages in a composite
system adequacy Evaluation of the IEEE.
1. Power Transformer Reliability Test system. IEEE Trans, Power
2. Current Transformer Apparatus and systems, Vol: PAS-104, Issue :
3. Circuit Breaker 10, Pages : 2649-2656, 26 Feb-2007.
4. Relays
(2). Billiton.R, Wojezynskri.E, Distributional
5. Battery Variation of Distribution System reliability
6. Lightning Arrester Indices, IEEE. Trans, Power Apparatus and
7. Sub Station Earthing Systems, Vol: PAS-104, Issue:11, Pages : 3151-
8. Bus Fault 3160, 26 Feb-2007.
9. Line Crossing
(3). Wojczynski.E, Billiton. R. Effects of
Nature of Defect Distribution System reliability Index distribution
upon Interruption Cost / Reliability worth
Estimates. IEEE Trans, Power Apparatus and
1. Miniature Relay Defect
Systems, Vol: PAS-104, Issue: 11, Pages: 3229-
2. Mixing of AC & DC Supply in Relay 3235, Feb 2007
3. Early pickup due to Relay defect
4. Protection Wiring Defect (4). Reliability and Continuity of Supply. 9th
5. Relay fixing Defect International Conference, Electrical Power
Quality and Utilization, Barcelona, 9-11 October
6. Non Coordination of Relay Timings
2007.
7. Relay Programmer Error
(5). Improving Distribution System
Reliability using Distribution Automation Based
on Coordination between Auto recloser,
UTILITY SPECIFICATION Sectionaliser and Limit Fuses. CIRED, 19th
(1). Number of Substations International Conference on Electricity
110/11KV : 13Nos Distribution, Vienna 21-24 May 2007, Paper
0278.