Sie sind auf Seite 1von 9

International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

RESEARCH ARTICLE OPEN ACCESS

Mitigation of Power Interruption in Radial and Grid


Feeder Schemes and Safety of Equipment’s
T. Kannan1, M. Mahendran2
PG scholar1 , Assistant Professor2(Department of EEE)
Department of Electrical Engineering
SCSVMV University, Kanchipuram, Tamilnadu, India

Abstract:
The Continuity of power supply that is reliability of power supply is highly essential for the
development of the country. The electric power is distributed to the consumers through electrical network.
The study involves the analysis of various obstacles for reliable power supply, interruption in electric
power distribution due to defects in relays and circuit. Cost benefit by the prevention and reliability in
power supply.

Keywords— Reliability of power, Mitigation of Interruption, Radial feeders, power transformer and
grid feeders.

Single line diagram of 33kv sub station

1. INTRODUCTION
The power generated at the generating
station should reach the consumers, for which
Transmission and Distribution network is used.
Since electrical equipment’s are involved in the
Single line diagram of 110kv sub station
Transmission and Distribution network the
electric power supply does not reach the
consumer without interruption. The interruptions
of power supply distributions are caused either
intentionally or unintentionally. Intentional

ISSN: 2395-1303 http://www.ijetjournal.org Page 1


International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

interruptions are the load shedding done to match 10. Actuation of high winding temperature due to
the demand and supply that is Demand Side air looking in power Transformer.
Management (DSM). The unintentional 11. Operation on differential relay due to entry of
interruptions are caused by the defects developed rain watershorting of bushing CT Secondary
in the Transmission and Distribution network and leads
equipment’s associated with them. This research 12. Actuation of Oil Surge Relay (OSR) due to
is involved in the area of unintentional rain water and low oil level due to oil leakage
interruptions. This study is focused on the 13. Operation of Power transformer Protection for
interruption in power distribution due to the Power transformer internal fault.
various defects developed in the relays and its B. Current Transformer
circuits. 1. Early pickup of relay due to collapse of
Current Transformer (CT) ratio
II. DEFECT DESCRIPTION 2. Failure of molded type Current Transformer
due to entry of rain water inside the Current
The study is focused on the interruptions
Transformer (CT) through the crack
in radial feeders. Hence the 110KV and 33KV
developed in the molding.
sub stations have been selected for the study. The
3. Simultaneous tripping of adjacent feeders due
study was conducted during 2014-2016 on the
to low insulation resistance value of Current
causes of interruptions in the utility.
Transformer in healthy feeders.
The defect which affects reliability in 4. Failure of Current Transformer due open
power supply is categorized as under. circuiting of secondary.

A. Power Transformer C. Circuit Breaker


1. Non tripping of breaker due to broken spring
1. Actuation of Oil Surge Relay (OSR) due to 2. Non opening of one of the poles in the
internal defect development in Power circuit breaker due to mechanism defect.
Transformer during failure of Lightning 3. Non closing of circuit breaker due to low air
Arrester (IAS) pressure because of failure of AC supply to
2. Operation of differential relay due to compressor motor.
improper harmonic range selection. 4. Non operation of circuit breaker due to
3. Actuation of oil temperature relay due to auxiliary switch defect.
Mercury switch defect. 5. Burning of trip coil in the breaker due to
4. Actuation of Bucholz relay due to shorting continuous DC supply due to mechanism
of leads by entry of rain water and foreign defect and shorting DC leads by foreign
material in the relay junction box. material.
5. Actuation of winding temperature trip due to 6. Flash over of breaker due to low insulation
shorting of leads at Terminal Block (TB) by resistance value.
insects. 7. Non opening of one of the Poles due to
6. Actuation of tripping due to differential relay broken operating rod.
defect
7. Actuation of Bucholz relay due to low oil D. Relays
level by oil leakage.
8. High winding temperature due to wrong 1. Not opening of breaker due to defect in the
selection of winding current Transformer ratio miniature relay.
9. Actuation of pressure relief valve due to DC 2. Failure of relay due to mixing of AC & DC
supply leakage & shorting of leads by rain supply due to failure of control cables
water and birds nest. during Bus fault.

ISSN: 2395-1303 http://www.ijetjournal.org Page 2


International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

3. Early pickup of relay due to relay defect. I. Line


4. Operation of relay in the healthy feeder due
to loose connection in the protection wiring Crossing of different voltage rating lines
‘L’ point during fault in the other feeder. with insufficient clearance causes tripping of
5. Non operation of relay due to relay fixing healthy line due to mutual induction.
mechanical arrangement defect.
III. DEFECT PREVENTING TECHNIQUES
6. Backup relay pickup due to non-
coordination of relay timings. The preventing techniques for the defects
7. Non operation of relay when the fault described above are narrated below.
current exceeds the current rating
programmed in the relay. A. Power Transformer

E. Battery The actuation of oil Surge relay and


1. Non clearing of fault by circuit breaker due Bucholz relay due to entry of rain water and
to weak battery because of failure of charger foreign material can be prevented by arresting the
fuse. entry of water and foreign material by closing the
2. Not tripping of circuit breaker due to weak junction box cover with good quality gasket and
battery. by providing the proper size gland for the cable.
3. Non opening of one of the Poles due to The gaps in the cable entry point should be
broken operating rod. closed by using M seal. The side entry of the
Cable in the junction box to be shifted to the
F. Lightning Arresters bottom in order to avoid the rain water entry
1. Failure of Lightning Arresters (LAS) through cable.
leading to On Load Tap Changer (OLTC) The actuation of Oil Surge Relay (OSR)
defect in Power Transformer. and Bucholz relay due to oil leakage can be
2. Failure of Lightning Arrester (LAS) prevented by periodically checking the oil level
causing tripping of breaker. in the Power Transformer and topping up if
3. Low insulation resistance value of required to the correct level.
Lightning Arrester (LAS) causes tripping of
circuit breaker. The actuation of oil Surge relay due to the
defect developed in the On Load Tap Changer
G. Sub Station Earthing (OLTC) by the failure of lightning arrester can be
Weak earthing causes failure of control prevented by periodically testing the lightning
cables during bus fault. arrester for its healthiness and by replacing the
lightning arrester if found weak.
H. Bus Fault
The entry of rain water in the secondary
1. Failure of bus insulator causes tripping of side junction box of bushing Current
circuit breaker. Transformers can be prevented by providing
good quality gasket and fixing the covers firmly
2. Bus fault causes damage of Current without any gaps. There by the shorting of
Transformer (CT) cable at junction box secondary leads of Bushing Current Transformer
and control cable due to high fault current by rain water and the mal operation of
spreading in the SS equipments. differential relay can be prevented.
The harmonic setting in the differential
relay should be selected based on the harmonics

ISSN: 2395-1303 http://www.ijetjournal.org Page 3


International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

generated in the area of use to prevent the mal B. Current Transformer


operation of differential relay. Further, the
differential relay should be tested periodically to The Current Transformer (CT) should be
confirm its healthiness. If found defective, it tested periodically to confirm its healthiness. If
should be replaced to prevent mal operation of the CT is found weak or defective, it should be
differential relay. replaced to prevent early pick up of relay due to
collapse of CT ratio, simultaneous tripping of
The Thermometers should be tested adjacent feeders due to low insulation resistance
periodically to confirm its healthiness and if any (IR) value of CT and failure of CT due to open
one of the components found defective, it should circuiting of secondary side.
be replaced to prevent unnecessary tripping.
Incase of moulded case Current
The leads at the terminal blocks (TB) Transformer, it should be examined periodically
should be covered to prevent the shorting of leads to find out if there is any cracks. If any crack is
by insects and the consequent mal operation of developed either it should be closed with M seal
winding temperature trip. or the CT should be replaced depending upon the
condition of crack to avoid entry of rain water
The correct winding temperature Current and subsequent failure of CT.
Transformer (CT) ratio should be selected to
avoid the false tripping of high winding C. Circuit Breaker
temperature.
The breaker should be periodically
The power Transformer should be checked for its correct operation and its
periodically checked for uniformity of healthiness. If any part is found defective, it
temperature in the Transformer. If any not should be replaced and mechanism defect should
uniformity is found, the air locking in the be attended and lubricated for its free operation
Transformer should be released to avoid high to prevent the mal functioning of breaker. Incase
winding temperature. of pneumatic breaker the compressor operation
and AC supply availability to motor should be
The DC leads in the protection wiring of checked and if any defect is noticed it should be
the power transformer pressure relief valve attended immediately to avoid non operation of
(PRV) should be properly insulated to prevent breaker due to low air pressure.
shorting of leads by DC supply leakage. The rain
water entry should be arrested by using good D. Relay
quality gaskets for the cover and proper size
gland for the cable and there by the mal operation The relay and its wiring should be
of PRV can be prevented. The PRV should be periodically tested to confirm its correct
provided with cover to avoid the operation of operation and if any defect is found it should be
PRV by birds. rectified to prevent mal operation of relay.

The Power Transformer breather, oil The AC and DC cables should be laid
condition and IR values should be checked separately to avoid mixing of AC and DC supply
periodically and maintained in good condition and to prevent relay failure.
and the Power Transformer over loading should
The delay timings of the relay should be
be avoided to prevent the development of internal
selected properly to avoid backup tripping. The
fault in Power Transformer.
relay current rating should be selected according
to the fault level of the area to prevent the

ISSN: 2395-1303 http://www.ijetjournal.org Page 4


International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

programme locking of relay due to over current I. Line Crosing


during fault.
The crossing of line should be erected
E. Battery with clearance as per standard to avoid
simultaneous tripping of breakers due to mutual
The battery should be maintained induction.
periodically and its charging condition should be
monitored continuously and the defect if any
found should be attended immediately to prevent
the non tripping of breaker during fault due to 110KV SIDE DEFACTS CAUSE AND
weak battery. REMEDY

F. Lightning Arrester 110KV CIRCUIT BRAKER WAS NOT


CHARGED DUE TO THE FOLLOWING
The Lightning Arrester (LAS) should be DEFECTS
tested periodically to confirm its healthiness and
its correct operation. If any defect is noticed 1. Air pressure operating mechanism air
during test, it should be attended or if required leakage
LAS should be replaced to prevent development 2. Low air indication i.e. Below 14kgf/cm2
of defect in Power Transformer OLTC during 3. Gas leakage
failure of LAS, tripping of breakers due to failure 4. Low gas alarm and lockout condition
of LAS. 5. Single phase supply instead of and phase
supply
G. Substation Earthing 6. Closing and tripping coil worn out
7. DC supply less than recommended DC
The Substation earthing should be Voltage
periodically measured to confirm its healthiness. 8. 110KV breaker clamps, jumpers are
If any of the earth pit resistance value is more, it loosen condition
should be attended immediately and all the earth 9. Heavy glow ideal charging
pit resistance should be maintained low by proper 10. Pole Discrepancies occur during close
watering to prevent spreading fault current in the 11. Breaker mechanism auxiliary contacts
SS equipment and to prevent control cable from making problem
damage. 12. Lighting one the breaker insulator pet
coat broken condition
H. Bus Fault
13. Low IR values of Insulators
The insulation resistance of all the 14. Breaker T&C Switch was not working
supporting insulators in the substation should be properly
measured periodically for confirming its 15. Mal operation of charging of breaker
healthiness. If any of the insulators is found without removing earth rods provided
defective, it should be replaced immediately by
healthy one avoid unnecessary tripping of circuit CIRUIT BREAKER REMEDY
breaker and supply interruption and to prevent 1. Air pressure pipe line, leakage completely
control cable from damage during failure of avoid. Every weakly with soap solution
insulator. air leakage checked
2. Air pressure increased by running of
compressor motor and maintaining air
pressure above 14kgf/cm2

ISSN: 2395-1303 http://www.ijetjournal.org Page 5


International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

3. SF6 Gas pressure maintain 6.5kgf/cm2 if 6. Ammeter loading checked and again open
low tapping of sf6 gas done the breaker
4. Gas leakage checked and arrested 7. Cable duct maintained neatly and clean
5. Single phase preventer contactor and eaten waste not through inside control
maintain 3 phase supply room.
6. Closing and tripping coil changed by new 8. Relay calibrated every year periodically
one 9. Lighting spike provided
7. 110 volts DC supply maintained in trip 10. Plunger adjustment done
and close coil of breaker
8. Clamps and 110KV Jumpers in Tightness
condition
110 KV & 33KV CURRENT
9. Clamp tightness and providing hot-zip
TRANSFORMER DEFECTS AND REMEDY
zinc coated bolt & nuts
10. Sequence closing of breaker poles 1. Current Transformer secondary saturates
maintained with removing dust etc. 2. Current transformer busted
11. Proper lubrication done in auxiliary 3. Oil leakage
contacts of breaker 4. Low IR value
12. Lighting spike provided 5. Insulator broken
13. Changing of low IR values Insulator 6. Proper measuring CT erected
14. New T&C switch provided 7. Loose connection of cables
15. Proper authorization experience operators 8. Secondary side of loading improper rods
with conduction safety glass provided. Minimum loading transformer
9. Glow in current transformer clamps
33KV BRAKER DEFECTS AND REMEDY 10. Current transformer firing
1. Spring charging motor problem
2. Motor charging limit switch problem
3. Dummy closing of breaker REMEDY
4. SF6 gas leakage, low gas
5. Vacuum interrupter damaged 1. Current transformer secondary short
6. Circuit breaker during open condition 1no circuited
of breaker phase not opening 2. Limit the loading amps
7. Protection cable damaged due to rats 3. Gasket provided newly and oil leakage
8. Relay closing and tripping problems arrested.
9. Burst breaker insulator 4. Improve the IR value
10. Trip and close coil plunger adjustment 5. Correct ration of C.T. Erected
problem 6. Quality Insulator provided
7. Tightness of cable with duct.
8. Ct rods provided according of loading
9. Clamps changed and provide new bolt &
33KV BRAKER CLOSING REMEDY nuts with zinc coated
1. Damaged spring changed 10. Tree clearance, periodical oil changing
2. Limit switch changed by new one done.
3. Adjusting of travel time
4. SF6 gas tapped, gas leakage arrested
5. New vacuum interrupter provided

ISSN: 2395-1303 http://www.ijetjournal.org Page 6


International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

IV. TESTING AND MAINTENANCE IS 3070 (Part I)


STANDARDS
G. Earthing
The following Standards are to be adapted
for preventing the defect in the power apparatus IS 3042 – 1966
and relays
H. Insulators
A. Power Transformer IS 2544-1973
1. IS 2026,
I. Line crossing
2. IS 2026 (Part I, II) – 1977
IE Rule 77 & 78 – 1956
3. IS 2026 (Part III) – 1981,
4. IS 2026 (Part IV) – 1999
V. NUMERICAL AND GRAPHICAL
5. IS 335-1993, RESULTS

6. IS 9434 – 1979 The study was conducted in utility during


2014-2016. The interruptions due to the various
7. IS 10593 -1983 causes detailed above were analyzed. The
techniques for the prevention of above defects
were also analyzed. The units due to unwanted
interruption and its cost were arrived. Similarly
B. Current Transformer
the costs of preventive techniques were also
1. IS 2705 – 1992 arrived based on the standard material cost &
labour cost. The saving due to the adaptation of
C. Circuit Breaker preventive techniques are furnished in the
following table
1. IS 13118 – 1991
2. IEC 56 - 1987
Single chart for cost of Energy lost in %
3. IEC 71 - 1972

D. Relay
1. IS 3842 (Part I) – 1967,
2. IS 3842 (Part XII) – 1976

E. Battery
IS 8320 – 1976

F. Lighting Arrester

ISSN: 2395-1303 http://www.ijetjournal.org Page 7


International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

the equipment’s. In turn it avoids the defect in the


equipment’s. The prevention of defects would
give reliability of power supply and would give
cost benefit to the utility.

REFERENCE
Equipment’s preventive techniques
(1). Billinton.R, Vohra P.K. Kumar. S: Effect
Defects in Equipment of Station Originated outages in a composite
system adequacy Evaluation of the IEEE.
1. Power Transformer Reliability Test system. IEEE Trans, Power
2. Current Transformer Apparatus and systems, Vol: PAS-104, Issue :
3. Circuit Breaker 10, Pages : 2649-2656, 26 Feb-2007.
4. Relays
(2). Billiton.R, Wojezynskri.E, Distributional
5. Battery Variation of Distribution System reliability
6. Lightning Arrester Indices, IEEE. Trans, Power Apparatus and
7. Sub Station Earthing Systems, Vol: PAS-104, Issue:11, Pages : 3151-
8. Bus Fault 3160, 26 Feb-2007.
9. Line Crossing
(3). Wojczynski.E, Billiton. R. Effects of
Nature of Defect Distribution System reliability Index distribution
upon Interruption Cost / Reliability worth
Estimates. IEEE Trans, Power Apparatus and
1. Miniature Relay Defect
Systems, Vol: PAS-104, Issue: 11, Pages: 3229-
2. Mixing of AC & DC Supply in Relay 3235, Feb 2007
3. Early pickup due to Relay defect
4. Protection Wiring Defect (4). Reliability and Continuity of Supply. 9th
5. Relay fixing Defect International Conference, Electrical Power
Quality and Utilization, Barcelona, 9-11 October
6. Non Coordination of Relay Timings
2007.
7. Relay Programmer Error
(5). Improving Distribution System
Reliability using Distribution Automation Based
on Coordination between Auto recloser,
UTILITY SPECIFICATION Sectionaliser and Limit Fuses. CIRED, 19th
(1). Number of Substations International Conference on Electricity
110/11KV : 13Nos Distribution, Vienna 21-24 May 2007, Paper
0278.

33/11 KV : 18Nos. (6). Interruptions and Supply Continuity in


Distribution and Transmission Systems, CIRED,
VI. CONCLUSION Vienna 21-24 May 2007, Mark Megranaghan,
Electric Power Research Institute.
Various factors attribute to the defect in
power system. The proper research involves the (7). Reliability of Electric Supply Structure-
study of various cause and obstacles for the Case Study-Hard book of power Quality Edited
reliable and continuous power supply. The by Angelo Baggini, John Willey & Sons Ltd.
preventive methods improve the performance of

ISSN: 2395-1303 http://www.ijetjournal.org Page 8


International Journal of Engineering and Techniques - Volume 3 Issue 2, Mar – Apr 2017

(8). Switchgear Protection and Power Systems


by Sunil.S.Rao. Khanna Publishers, Delhi -
110006 Eleventh Edition.
(9). Electrical Power by Dr. S.L.Uppal,
Khanna Publishers, Delhi – 110006 Thirteen
Edition.
(10). Electric Power Distribution by A.S.
Pabla, Tata McGram Hill Publishing Company
Limited, New Delhi, Fourth Edition.

ISSN: 2395-1303 http://www.ijetjournal.org Page 9

Das könnte Ihnen auch gefallen