Beruflich Dokumente
Kultur Dokumente
Khalil Elahee
Faculty of Engineering, University of Mauritius, Réduit, Mauritius
kerosene (Nicolay). The latter, using a 76 MW gas even more expensive when compared to bagasse at
turbine, is normally reserved for emergency pur- market prices. The latter is fully utilised but the effi-
poses and is occasionally run for peaking only, ciency of its conversion can be improved by the
given that its cost is at least four-fold higher. introduction of high pressure cogeneration plants.
It is to be noted that the distribution losses Together with the use of other biomasses like cane
amount to about 10% (CEB, 2008). The total tops and leaves, at least three times more electricity
installed capacity is now 504 MW, including can be produced using currently available technol-
allowance for maintenance, repairs and a 10% ogy (Autrey et al., 2006). This will ensure also a
spinning reserve (Hansard, 2009b). Currently more stronger substitution of coal, used during the inter-
than 60% of electricity is generated by the IPPs, the crop season, by renewable biomass. Figure 4 shows
CEB being responsible mostly for the semi-base the energy mix for power generation for 2008. The
and peak load power supply areas. Much of the wind power indicated is negligible and refers to the
CEB capacity is not fully exploited because of bind- island to Rodrigues.
ing contracts with IPPs to give priority to their base-
load supply and because of the dependence on 1.2 Demand-side management
rainfall for hydropower. In 2009, the amount of power generated was
It is to be noted that fuel oil and kerosene used almost the same as in 2008. Moreover, the peak
by CEB are more costly compared to coal, and demand moved to the morning during the summer
energy-intense manufacturing and agricultural sec- ensure energy efficient practices related to appli-
tors. ances and buildings respectively.
DSM can be the key to meeting the energy iii) Solar-water heating, including in air-condition-
demands, including morning peaks during week- ing and refrigeration, sustainable design of
days in summer, provided the following specific ori- buildings and energy-efficiency improvement in
entations are urgently adopted: industry and tourism should a full priority by the
i) The Energy Management Office to facilitate private sector.
DSM in all sectors, already announced by the iv) The onus should no more be on the CEB to pro-
Government in the 2010 Budget, should be set vide 100% of electricity needed by industrial,
up without delay (MoF, 2009). hotel and commercial promoters. The latter
ii) The Energy Efficiency Act under preparation and should be required to ensure optimal design and
the Building Code should be promulgated to energy use on their facilities, including the
implementation of Energy Management pro- have had an estimated extra cost of 5%. The 15
grammes and recourse to renewable energy. MW coal/bagasse project scheduled for 2008 did
New cities and similar projects should be sub- not happen. Thus far, no project has been complet-
jected to strict environmental standards, includ- ed. The current intention of the CEB to promote the
ing energy use. The proposed Land-Based construction of a 110 MW coal-fired plant and to
Oceanic Industry (MLBOPL, 2009; MRC, 2010) invest in a 30 MW fuel oil-fired plant implies that
is an example of such a new approach where the Base Scenario is very much the one on course,
promoters are responsible for sustainable energy albeit with a delay of two, if not three years.
input. The Compromise Scenario would have also
v) Pricing policy for energy, including Time-of-Use included the closing down of the 20 MW Beau
Tariff for electricity and feed-in tariffs, as well Champ plant in 2009 and its replacement by an
energy taxes should be integrated within a MID equivalent power plant in FUEL in 2009. This did
Business Framework, together with incentive not happen. A 20 MW Waste-to-Energy project and
packages for sustainable energy. a 25 MW wind farm, concomitant with the
Compromise Scenario and expected to start oper-
3. New MID scenario ating in 2009, are also behind schedule. In fact, the
In 2007, the Outline Energy Policy (OEP, 2007c) former has now been degraded to a 7 MW propos-
was published focusing on changing the depend- al and is subject to much controversy just like the
ence of the country on oil to one on coal. The coal-only power plant.
Compromise Scenario shown in Table 2 was the The concept of Maurice Ile Durable (Mauritius
one retained by the CEB. The All Sugar Cane Sustainable Island, MID) started to be formally
Scenario was rejected on the basis that it would implemented in 2008. At the heart of the MID