Sie sind auf Seite 1von 153

Design Number: A-0857/12

Modification of detailed design


Common designation: GP Vc - LOT 7 - MGP

I. PAVEMENT STRUCTURE
Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. PAVEMENT STRUCTURE

No ITEM DESCRIPTION Unit Qty Unit Price Total

Execution of unbound roadbase of uniformly graded


A1 m3 7,980.00 9.20 73,416.00
crushed stone in a thickness of 40 cm
Execution of base-bearing course of asphalt mixture of
bituminous well graded crushed stone of granulometric
A2 m2 11,550.00 8.69 100,369.50
composition of 0/22S mm with road bitumen in a thickness
of 6 cm
Execution of wearing and sealing course of bituminous
A3 concrete BC 11s of a mixture of silicate stone grains and m2 11,000.00 8.18 89,980.00
road bitumen in a thickness of 40 mm
Execution of precast cement concrete raised kerb of section
A4 m1 1,210.00 11.76 14,229.60
18/24 cm
Execution of concrete gutters B75 (beton C 30/37)
Item includes all work and material required for execution of
A5 gutters width 75 cm, with an inclination of 12,5%, on a m1 561.00 10.23 5,739.03
mechanically compacted grained material, transport,
treatment, protection and curing o

Preparation of weepholes
Work includes preparation of a thin layer of granular stone
A6 material as an extension of the pavement structure base m3 83.00 12.78 1,060.74
course, wide as emergency lane , on both sides of
carriageway . Granular stone material is placed in a layer,

Execution of longitudinal and transverse drainage of depth


A7 up to 1.0 m, on cement concrete unerlay course, with m1 1,015.00 12.63 12,819.45
flexible plastic pipes of 20 cm diameter

TOTAL A: 297,614.32

RECAPITULATION
A. PAVEMENT STRUCTURE
No ITEM DESCRIPTION Total EUR
A PAVEMENT STRUCUTRE 297,614.32
TOTAL I: 297,614.32

BOSNIA I HERZEGOVINA
Construction of the BPC Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 1
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

II. INTERNAL DRAINAGE


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
B. OIL POLLUTED WASTEWATER, SANITARY-FAECAL WASTEWATER
No ITEM DESCRIPTION Unit Qty Unit Price Total
Excavation of soft tock for road drainage collector, 1,0 m in
B1 m3 80.35 0.77 61.87
width, 1,0 m in depth
Excavation of soft rock for road drainage collector, 1,0 m in
B2 width, 1,1 - 2,0 m in depth m3 84.32 0.77 64.93

Excavation of soft rock for road drainage collector, 1.1 – 2.0


B4 m in width, 1,0 m in depth m3 480.03 0.77 369.62

Excavation of soft rock for road drainage collector, 1.1 – 2.0


B5 m in width, 1,1 -2,0 in depth . m3 392.91 0.77 302.54

Excavation of soft rock for road drainage collector, 1,1 -2,0


B6 m in width, 2,1 – 4,0 m in depth m3 37.48 0.77 28.86

B7 Backfill with cohesive soil – with machines m3 967.58 1.28 1,238.50


Transportation of excavated material to a distance above
B8 5,000 m3 69.88 3.07 214.53

Execution of sewage system of polypropylene pipes,


B12 including cement concrete underlaid course, diameter 25 m1 82.00 10.23 838.86
cm
Execution of sewage system of polypropylene pipes,
B13 including cement concrete underlaid course, diameter 30 m1 220.23 17.38 3,827.60
cm
Execution of polypropylene gulley, of circular cross-section
B17 of diameter 40 cm, depth 1.5 – 2.0 m pcs 23.00 76.69 1,763.87

Execution of polypropylene shaft, of circular cross-section


B18 pcs 2.00 127.82 255.64
of diameter 80 cm, depth 1.0 – 1.5 m
Execution of polypropylene shaft, of circular cross-section
B19 of diameter 80 cm, depth 1.5 – 2.0 m pcs 9.00 153.39 1,380.51

Execution of polypropylene shaft, of circular cross-section


B20 of diameter 80 cm, depth 2.0 – 2.5 m pcs 2.00 204.52 409.04

Supply and installation of cast iron frame, of 250 kN bearing


B24 capacity, of circular cross-section of 500/500 mm pcs 46.00 38.35 1,764.10

Supply and installation of cast iron cover, of 250 kN bearing


B25 capacity, of circular cross-section of diameter 600 mm pcs 13.00 38.35 498.55

Execution of precast cement concrete raised kerb of section


B26 m1 147.64 19.43 2,868.65
15/50 cm
Placing of channel - monoblock of polymer concrete, clear
B27 m1 14.46 483.17 6,986.64
width 300 mm, bearing capacity 400 kN
B29 IMPERMEABILITY TESTING

Testing the impermeability of sewage network and


inspection manholes as well as inlet connections in
accordance
The price of withitem the standard
includes HRN ENof1610:2002
preparation Report onand the
instructions of the designer.
achieved waterproof system,Item includes
certified by thethecontractor
water of
required
works and forother
multiple testing until
authorized the tested
persons who mustsection proves
be present
to be completely
during perforce ofwatertight.
tests and Testing to be
who certify thedone by certified
report.
laboratories qualified according to requirements given in
the standard
Calculated perHRNm' ofEN ISO/IEC
tested 17025:2000, “V” procedure
pipeline m1 220.23 0.51 112.32
(testing by water) in accordance with standard for Placing
*and
inspection manholes
testing of per pc (HRN EN 1610). The price
sewage pipelines pcs 13.00 5.11 66.43
of item includes
* drains per pc all required works, materials, auxiliary tools pcs 23.00 5.11 117.53
and transport for complete testing of overall section, up to
B30 SCANNING OF CONSTRUCTED
the final result. All performed tests COLLECTORS
shall not be separately
calculated,
Scanning of constructed collectorsshall
but any further testing usingbeaat the expense
robot camera of
the
andcontractor
elaboration ofof
works. Final report
the recording by ashall be certified
submitted by the
written
laboratory
survey reportaccredited
and a videofor the execution
recording. Theof recording
tests. to be
submitted on a DVD in mpeg format.
Unit price of item includes all required field investigation
works and office work required for preparation of the
recording.
Calculated per m' of tested pipeline m1 220.23 2.30 506.53

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 2 Construction of the BPC Bijaca , LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

* inspection manholes per pc pcs 13.00 10.23 132.99


* drains per pc pcs 23.00 10.23 235.29
TOTAL B: 24,045.39

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 3 Construction of the BPC Bijaca , LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

C. ROOF DRAINAGE
The specification includes works pertaining to execution of the installations within buildings, “up to 1 m” outside
each of the building engineering structures

No ITEM DESCRIPTION Unit Qty Unit Price Total

Supply and installation of a POLYMER REDUCTION,


C6 plastic pipes of DN 110 and DN 160, for connection of the pcs 6.00 28.12 168.72
rainwater vertical pipes to the PVC Ø 160, DN 160/110

TOTAL C: 168.72

RECAPITULATION

II. INTERNAL DRAINAGE

No ITEM DESCRIPTION Total EUR


B OIL POLLUTED WASTEWATER, SANITARY-FAECAL WASTEWATER 24,045.39
C ROOF DRAINAGE 168.72
TOTAL II: 24,214.11

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 4 Construction of the BPC Bijaca , LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

III TRAFFIC
Note: In cases where certain equipment is specifically named, it is only an indication of the technical
features the offered equipment would need to comply with.
Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
IIIa TRAFFIC
A. TRAFFIC SIGNS
No ITEM DESCRIPTION Unit Qty Unit Price Total

Traffic sign with fasteners, mounting on galvanized post ø


63,5 mm. The sign is made with reinforced frame and a
horizontal reinforcement,made of retro-reflective foil class II,
A.1 type ''High Intensity Grade'' (Stable to ultraviolete
radiation ) applied to aluminium backing plate. Plate
thickness min. 2 mm.
Sign dimension ø 90 cm pc 5.00 58.80 294.00
A.2 Traffic sign ø 60 cm, other same as Item A.1. pc 10.00 35.79 357.90

A.3 Traffic sign T=120 cm, other same as Item A.1. pc 5.00 58.80 294.00

A.6 Traffic sign 60x60 cm, other same as Item A.1. pc 3.00 35.79 107.37

A.7 Traffic sign 90x120 cm, other same as Item A.1. pc 2.00 81.81 163.62

A.10 Traffic sign 60x30 cm, other same as Item A.1. pc 3.00 20.45 61.35

A.11 Traffic sign 60x40 cm, other same as Item A.1. pc 1.00 25.56 25.56

A.19 Traffic sign160 x 120 cm, other same as Item A.17. pc 1.00 204.52 204.52

A.21 Traffic sign180 x 180 cm, other same as Item A.17. pc 2.00 347.68 695.36

A.48 Concrete foundations for the double ø 63,5 mm galvanized


posts, for a double traffic sign. Dimensions 0,8x0,5x0,8 m 250.53
with min. 0,32 m3/post concrete class C16/20 (MB20). pc 7 35.79
A.49 Mounting post and parallel
Concrete foundation postmm
for ø 63,5 ø 63,5 mm withpost,
galvanized anchors.
for one
traffic sign. Dimensions 1,2x0,5x0,8 m with min. 0,5
393.80
m3/post concrete class C16/20 (MB20). Mounting post with
anchor. pc 22 17.90
A.54 Steel posts for bearing traffic signs ø 63,5. Protected 809.28
against corrosion by hot dip galvanizing process m 144 5.62
A.55 Aluminium post, I-profiled 180 mm traffic sign mount. m 22 17.90 393.80

TOTAL A: 4,051.09

B. ROAD AND TUNNEL FURNITURE AND EQUIPMENT


No ITEM DESCRIPTION Unit Qty Unit Price Total

B.2 Retro reflective signs - catadiopters (VIII-3), supply,


transport and mounting - reflective on both sides with red
retro reflective glass, placed on traffic barrier, in the middle, 33.66
on a bolted connection, or on a concrete barrier type New
Jersey.
pc 22 1.53

TOTAL B: 33.66

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 5
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

C. TRAFFIC MARKINGS (HORIZONTAL SIGNS AND MARKINGS)


No ITEM DESCRIPTION Unit Qty Unit Price Total

C.6 Broken centerline, width 15 cm, white, length of full/broken


part - 3/3 m, with retro reflective particles, retro reflection 598.60
class II, according to BAS. U.S4. 223. m 730 0.82
C.7 Broken centerline, width 15 cm, white, length of full/broken
part - 3/3 m, with retro reflective particles, retro reflection 48.88
class II, according to BAS. U.S4. 223. m 52 0.94
C.8 Broken centerline or guiding line, width 10 cm, white, length
of full/broken part - 1/1 m, with retro reflective particles,
retro reflection class II, according to BAS. U.S4. 223. 8.25
m 15 0.55
C.9 Full line, width 20 cm, white, with retro reflective particles,
163.20
retro reflection class II, according to BAS. U.S4. 222. m 170 0.96
C.10 Full line, width 15 cm, white, with retro reflective particles,
retro reflection class II, according to BAS. U.S4. 222. 253.50
m 390 0.65
C.11 Full line, width 10 cm, white, with retro reflective particles,
1,854.00
retro reflection class II, according to BAS. U.S4. 222. m 3090 0.60
C.15 Wide, broken line, for acceleration / deceleration lane, width
50 cm, white, length of full/broken part - 3/3 m, with retro
reflective particles, retro reflection class II, according to 431.43
BAS. U.S4. 223. m 219 1.97
C.21 Stop line, width 50 cm, white, with retro reflective particles,
retro reflection class II, according to BAS. U.S4. 225. 6.40
m 5 1.28
C.24 Traffic direction surfaces - full marking , white, with retro
reflective particles, retro reflection class II, according to 369.75
BAS.U.S4. 230. m2 85 4.35
TOTAL C: 3,734.01

D. SAFETY BARRIERS (GUARD RAILS)

No ITEM DESCRIPTION Unit Qty Unit Price Total

D.2 Single-sided steel safety barrier (OS SSB), tested for class
H2 and working width class W=6 according to EN 1317,1-2. 34,668.40
m 565 61.36
TOTAL D: 34,668.40

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 6
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

E. VARIABLE MESAGE SIGNS


No ITEM DESCRIPTION Unit Qty Unit Price Total

E.8 Supply, transport and installation of fully programmable


information (graphical) display for mounting on gantry
structure above traffic lanes with front panel size
700x220cm.
Display must be contructed as RGB matrix with 24-bit
colour resolution so that all colours of traffic signs according
to valid low regulations can be displayed. RGB diplay
resolution should be 224x64 pixels. Text must be displayed
in Thrue Type format according to BAS U.S4.201 and BAS
U.S4.203.

Programmable displays must be constracted using LED


technology. Fully programmable matrix on display
constructs on black antireflective surface. Displayed
symbols and text must be unambiguous and visible from
150m distance.
Display construction must enable fast replacement of every
damaged LED or any other part susceptible to malfunction
and possibility of networking of every display into Variable
Message Traffic Signalization System on highway.

Communication interface should be serial protocol


according to TLS and electricaly compatible with RS485
standard, possibility of programable (remote) LED intensity
regulation from 1% to 100%.
Maksimum light intensity of display according to EN
12966:1 (class L3):
- minimum 3100 cd/m2 for red colour,
- minimum 3270 cd/m2 for green colour,
- minimum 1240 cd/m2 for blue colour,
- minimum 7440 cd/m2 for yellow colour,
- minimum 12400 cd/m2 for white colour;
- front panel reflection of display has to be according to
class R2 of EN 12966-1 standard.
Display has to be equpped with thermostatic and hidrostatic
regulator in coupling with heater for conditioning
themperature and humidity operating terms and reliable
operation within theperature range from -40ºC to +70ºC
according to classes T1, T2 i T3 of EN 12966-1 standard.

Validity control check of each LED regardless of sign


activation status or point ("cold state" error detection) locally
and remote. Compliance to classes L3, C2, R2, B2, T1, T2,
T3, P2, D3 of EN 12966-1:2007 Road vertical signs - Part
1: Variable message traffic signs, should be proved by VMS
production technology certificate published by certificate
authority for EN 12966 standard.

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 7
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


E.8 Manufacturer need to apply declaration of conformity for
electronic device safety regulations which needs to be
proved by testing reports from authorized laboratories in
BiH and made for variable message sign products accordint
to: BAS HD 384.4 Electrical Installations of Buildings – Part
4: Protection for Safety.
Conformity to electromagnetic compatibility needs to be
proven with declaration published by laboratory authorized
from Ministry of Foreign Trade and Economic Relations.
Authorized laboratory publishes conformity based on
measurements for variable message sign products with
technology as signs in cost list according to EN
50293:2000 Electromagnetic compatibility - Road traffic
signal systems.
pc 4 68,986.06 275,944.24
E.9 Supply, transport and installation of fully programmable
information (graphical) display for mounting on gantry
structure above traffic lanes with front panel size
700x165cm.
Central part of display should be constracted as
monochromatic matrix with 8-bit intensity resolution of every
pixel and phisical matrix resolution 120x64 pixels. Matrix
must have possibility to display minimum 3 rows of text in
"True Type" font according to BAS U.S4.201 i BAS
U.S4.203 with character size of 320mm. Matrix must be
enabled to display uppercase and lowercase letters without
overlapping of rows and with distance between rows
defined by true type font. On central matrix must be
possibility to display graphic in 120x64 resolution with 8-bit
luminous intensity resolution of every pixel.

Polychromous displays should be constructed as RGB


matrix with 24-bit colour resolution so that in this part of
display all colours necessary for traffic signs according to
valid low regulations can be displayed. RGB diplay
resolution should be 56x64 pixels. Besides display of traffic
sign pictograms in lower part of field must be possibility to
display variable text messages in one row. Text display
must be in True Type font according to BAS U.S4.201 and
BAS U.S4.203.

Other same as in E.8. pc 1 59,346.67 59,346.67


TOTAL E: 335,290.91

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 8
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

F. MEASURING AND CONTROL EQUIPMENT


No ITEM DESCRIPTION Unit Qty Unit Price Total
F.1 ROAD TRAFFIC STATION (RTS) in the PVC box - supply,
delivery and installation of the station with the monitor and
keyboard for manual operation. The stations gather and
process the traffic data on a tunnel or road section,
including the data on the environment and the data on the
state of the pavement from the sensors. On the basis of
predetermined parameters and data processed, they
control the operation of executive elements (variable
message signs), control signalling and tasks execution on
local level. On a higher level, they transmit data to the
central road traffic computer and receive tasks from
operative dispetching officer.

Software and hardware have to support work with functional


groups as follows:
- FG1 (data collecting about traffic)
- FG3 (collecting of meteorology data)
- FG4 (variable traffic signalization)
- FG6 (state of RTS)
- FG7 (devices remote control)
- FG254 (system control of RTS)
Software has to support three maner of the work:
a) local
b) automatic
c) remote
Device will have power distribution for supplying of
equipment which will be controlled.
For purpose of supplying, power part will have:
- differential protective device 40/0,3 A with device for
automatic switch on
- service socket outlet 220V, 10A with protective contact
- board heater with thermostat
- board lighting with switch installed on board door
- serial clamps
- cable holes for cable entering

Device will have overvoltage protection for power cables


and signal cables.
Reliable operating on operational temperature from -40°C
to +70°C
RTS housing protection rate IP55.
Device safety requirements according to BAS EN60950-22
Information technology equipment - Safety - Part 22:
Equipment installed outdoors.
Electromagnetic compatibility according to BAS EN61000-
2, BAS EN61000-6 and BAS EN55022 class B. pc 3 16,670.16 50,010.48

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 9
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


F.2 ROAD TRAFFIC SUBSTATION (RTSS) in the PVC box -
supply, delivery and installation of the substation with the
monitor and keyboard for manual operation. The
substations gather the traffic data on a certain road section,
including the data on the environment and the data on the
state of the pavement from the sensors, and/or they control
the operation of executive elements (variable message
signs), they process these data and send them to the RTS.
In case that of a broken connection with the RTS, the
executive element must be in the "last position".

Other same as F.1. pc 2 11,397.21 22,794.42


F.4 Traffic counter (TC) as upgrade to RTS/RTSS - Supply,
transport and installation. TC’s task is gathering traffic flow
data and sending data to RTS/RTSS.
Local traffic data collected from inductive loop detectors
contain vehicle categorization. Vehicles are categorized in 9
classes according to TLS directions.
Traffic counter should be constructed according to
TLS2002. pc 3 3,572.40 10,717.20
F.5 INDUCTIVE LOOPS for registering vehicles, installed into
the pavement, with two feeds to the counting device. The
feeds of electric wire insulated with silicone rubber. Included
is cutting the grooves in the asphalt and after installation
closing the grooves with epoxy resin. Alternatively, laying
the loops immediately prior to asphalting of the finishing.
Acording tipe 2 TLS2002
pc 7 1,258.80 8,811.60
F.9 Supply, transport and installation of industrial ethernet
switch in RTS for connecting devices of traffic-infomation
system with ethernet network of Remote And Control
Management System, device for DIN rail mounting with
power supply modul.
pc 3 799.66 2,398.98
F.10 Supply, transport and installation of industrial ethernet
switch for connecting of RTS and RTSS and for connecting
of RTS with licence place recognition devices. pc 2 799.66 1,599.32
F.11 Supply, transport and installation of signal converters, MM
optic/RS485 (RS-232) pc 2 357.39 714.78
F.13 Supply, transport and mounting of PTZ camera mounted on
public lighting pole, gantry structure extension, individual
pole or tunnel ceiling, complet with 30x zoom objective with
auto iris and auto focus, motor for rotation via telemetric
receiver, housing, heater and console. Possibility of 22x
optical and 10x digital zoom, remote control with keyboard,
resolution 480 TV lines, rotation 360°, working temperature
from -25°C to 50°C, automatic white colour balance,
sensitivity minimum 0,5 lux. Camera for traffic surveillance.
Housing protection rate minimum IP66.

pc 2 2,311.04 4,622.08

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 10
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


F.14 Suppla, transport and mounting of colour 1/2'' CCD camera
with Machine Vision Procesor (MVP) for traffic survelliance.
MVP will be mounted in 19'' rack cubicle placed in Remote
Control Center and serve for incident detection like:
stopped vehicle detection, wrong way detection, smoke
detection etc. Camera sensitivity minimum 0,37 lux.
Camera objectiv lens with zoom characteristics 10-30mm
f1.4. Possibility of MVP networking thru TCP/IP. Complet
with stainlees steel housing, heater and console. Housing
protection rate minimum IP66.

pc 2 3,797.88 7,595.76
F.16 Video-box on road route with special key, lock and cable
fastening systems. Supply, transport and installation of
video-box for mounting on gantry structure or cantilever
with installed equipement: 2x automatic circuit breaker 2A
C, RCCB, overvoltage protection 230V, 200-280V rms
single-phase with infomational panel about protection status
and deterioration, forseen place for optical modem and his
power supply modul and cassette for Fibre Optic cables.

pc 1 691.78 691.78
F.17 Video cubicle with special key, lock and cable fastening
systems. Supply, transport and installation of video cubicle
for mounting on pad footing with installed equipement: sa
ugrađenom opremom: 3x automatic circuit breaker 2A C, 1x
automatic circuit breaker 4A C, RCCB, overvoltage
protection 230V, 200-280V rms single-phase with
infomational panel about protection status and
deterioration, forseen place for optical modem and his
power supply modul, telemetric receiver, optical modems
housing and cassette for Fibre Optic cables.
pc 2 739.84 1,479.68
F.18 Supply, transport and installation of Optical Multimode
Transmitter for transmission of 1x video signal via one
multimode optical fibre, 9-bit digital linear PCM coding
without compression, optical budget 21dB on 850nm
wavelenght. Standalone device. Device working
temperature from -40ºC to +70ºC.
pc 2 1,768.56 3,537.12
F.19 Supply, transport and installation of Optical Multimode
Receiver for reception of 1x video signal thru one
multimode optical fibre, 9-bit digital linear PCM coding
without compression, optical budget 21dB on 850nm
wavelenght. Device forseen for mounting in housing.
Device working temperature from -40ºC to +70ºC.
pc 2 1,837.58 3,675.16
F.20 Supply, transport and installation of Optical Multimode
Receiver for reception of 3x video signals thru three
multimode optical fibres, 9-bit digital linear PCM coding
without compression, optical budget 21dB on 850nm
wavelenght. Device forseen for mounting in housing.
Device working temperature from -40ºC to +70ºC.
pc 1 1,642.78 1,642.78
F.23 Supply, transport and installation of device for coding and
transmission of 4x video signals. Possibility of reception
and coding of PAL video signal with MPEG-4 compression
algoritham in D1 format and one duplex data channel with
RS232/RS485 electrical compatibility. Output interface
RJ45 for transmission of singnal thru UTP cable.
Standalone device, complet with power supply module.
Device working temperature from -40ºC to +70ºC. Entry
includes device configuration, network settings with
inspection and testing.
pc 1 4,671.67 4,671.67

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 11
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total

F.24 Supply, transport and installation of ethernet switches for


connecting video system devices with ethernet network of
Remote And Control Management System. Two optical
connectors and 4x10/100Base-TX connectors. Standalone
device, complet with power supply module. Device working
temperature from -40ºC to +70ºC. Entry includes device
configuration, network settings with inspection and testing.

pc 2 650.01 1,300.02
F.26 Supply, transport and installation of ethernet media
converters. pc 2 125.01 250.02
F.27 Supply, transport and installation of standard optical
transmitter for transmission of ethernet signal through two
multimode optical fibres. pc 10 175.02 1,750.20
F.29 Supply, transport and installation of power supply devices
for flickering traffic lights. pc 10 255.65 2,556.50
TOTAL F: 130,819.55

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 12
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

J. DUCTS FOR POWER AND SIGNALING CABLES:


No ITEM DESCRIPTION Unit Qty Unit Price Total
J.1 Staking out of the power and signal cable route. m 1,700 0.51 867.00
J.2 Excavation of a cable trench, installation of pipes at a
certain depth and placing the earthing strip. m³ 544 21.53 11,712.32
J.3 Excavation of the road part for placement of the installation
ducts at a certain depth and placing of earthing strip.
m³ 25 24.03 600.75
J.6 Supply, transport and backfilling of sand into the previously
dug trench.
The same sand is used for backfilling of cables and
installation pipes with an additional layer app.10 cm thick.
m³ 70 19.07 1,334.90
J.7 Supply, transport and placing of plastic installation pipes m 1,600 2.56 4,096.00
J.8 Supply, transport and placing of installation pipes type
PEHD Ø110 mm. m 160 3.83 612.80
J.10 Supply, transport and placing of plastic cable shield into the
ditch, type H-W/12, length 1 m. pc 1,700 0.41 697.00
J.11 Supply, transport and placing of a red PVC warning strip -
warning on presence of electricity cable m 1,700 0.10 170.00
J.12 Supply, transport and placing of a yellow PVC warning strip
- warning on presence of telecommunication cables. m 1,700 0.10 170.00
J.13 Backfilling of trenches with fragmented earth in layers, with
compaction and placing of FeZn earthing strip. m 250 4.96 1,240.00
J.14 Supply, transport and placing of galvanized steel wire Ø2,7
mm through already placed PEHD pipes. m 1,700 1.33 2,261.00
23,761.77
K. INSTALLATION WORKS AND MATERIAL FOR ELECTRICAL INSTALLATIONS

No ITEM DESCRIPTION Unit Qty Unit Price Total

K.2 Supply, transport and placing of steel galvanized strip for


grounding (earthing), Fe-Zn 30x4 mm² into the created
trench. m 250 2.91 727.50
K.3 Making ground junction between earther and steel
galvanized strip with cross-connectors inside of trench. pc 5 3.32 16.60
K.4 Making ground junction between earther and P/F-Y
connductor with cross-connectors inside of trench. pc 5 3.32 16.60
K.5 Supply, transport and placing of power conductor P/F-Y 6
mm² for earthing of the zero conductor and earthing of the
cable shields (for joint earthing procedure). m 125 2.40 300.00
K.6 Supply, transport and placing of cable clamps 6 mm² and
preparation of finishing cable clamps for connection of
connection of metal parts of the distribution box, earthing of
metal parts of light traffic signals, video cameras and other
electronic equipment on portals or cantilevers. pc 10 2.51 25.10
K.7 Supply, transport and installation of power conductor P/F-Y
16 mm² for connection with earthing strips (for joint
earthing.) m 125 3.83 478.75
K.8 Supply, transport and installation of cable clamps 16 mm²
for connection of metal elements of the distribution box,
earthing of the metal parts of changeable light signals,
video boxes and other elements of the traffic info system.
m 5 4.96 24.80

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 13
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


K.9 Earthing of the metal parts of changeable signals and metal
parts of posts with lighting of the static traffic signs. pc 5 8.28 41.40
K.10 Earthing of the power and signal cable shields on both
cable ends. pc 10 8.28 82.80
K.12 Supply, transport and placing of power cables PP00-Y
3x2,5 mm² . m 850 2.40 2,040.00
K.13 Supply, transport and placing of power cables PP00-Y
5x2,5 mm². m 250 3.22 805.00
K.14 Supply, transport and placing of power cables PP00 4x6
mm² . m 300 5.16 1,548.00
K.15 Supply, transport and placing of power cables PP00 4x10
mm² for power supply of traffic control stations and traffic
control substations. m 400 8.13 3,252.00
K.25 Supply, transport and installation of pole distributors for el.
Supply of VMS at portals and lights for other signs placed
at portals. pc 5 207.07 1,035.35
K.26 Supply, transport and mounting of OG junction boxes for
power supply distribution of signs and distribution of signal
cables (IP protection rating of junction boxes IP65
according to EN 60529) pc 5 53.84 269.20
K.38 Costs of transport of material up to place of installation or
mounting. set 1 248.49 248.49
K.39 Costs of transport of material up to place of installation or
mounting. set 1 255.65 255.65

TOTAL K: 11,167.24

L. IMPLEMENTATION WORKS AND MATERIAL FOR SIGNAL INSTALLATIONS


No ITEM DESCRIPTION Unit Qty Unit Price Total
L.1 Supply, transport and installation of coaxial signaling cable
R59B/U LSF for transmission of a video signal. m 70 4.14 289.80
L.2 Supply, transport and installation of signaling cable TK
6x2x0,6 mm for operation of video system rotational
cameras. m 40 3.73 149.20
L.3 Supply, transport and installation of signaling cable J-Y(St)Y
4x2x0,6 mm for connection and transmission of data
between traffic control stations and traffic control
substations, VMS and measuring devices, as well as
connection and transmission of data between the video
system cameras and video distributors at shorter distances.
m 200 3.48 696.00
L.6 Installation of copper signaling cables into the placed
installation ducts. m 1,700 0.82 1,394.00
L.7 Supply and transport of cable clamps for external mounting
on the TC cable 5x4x0.8 mm. pc 5 72.91 364.55
L.8 Ending of TC cable in the Traffic Control Stations and the
Traffic Control Sub Stations and boxes. pc 5 28.99 144.95
L.10 Supply, transport and installation of a Multimode Fiber Optic
cable with 6 optical fibers in the cable installation ducts.
m 740 1.89 1,398.60
L.11 Supply, transport and installation of a Multimode Fiber Optic
cable with 12 optical fibers in the cable installation ducts.
m 700 2.40 1,680.00
L.13 Making of measurement protocol, testing before and after
placement and making of test documentation for multimode
optical fibre cables. set 1 496.98 496.98

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 14
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


L.14 Making of measurement protocol, testing before and after
placement and making of test documentation for
singlemode optical fibre cables. set 1 496.98 496.98
L.16 Supply, transport and installation of a cassettes and and
fibre pigtails for reception of Multimode Fiber Optic cables
in the Road Traffic Stations. set 5 215.36 1,076.80
L.17 Supply, transport and installation of St connectors for the
Multimode Fiber Optic cable (set per unit). set 10 157.38 1,573.80
L.18 Supply, transport and installation of a terminal box with
inter-connectors and Fiber pigtails for the Multimode Fiber
Optic cable (connection of a Road Traffic Station and switch
of Remote And Control Management System) in
transformer stations. set 2 240.20 480.40
L.21 Execution of connection of net remote communication
equipment to the main switch of Remote And Control
Management System in the transformer station. set 2 82.83 165.66
L.22 Making extensions on multimode optical fibre cables. pc 7 45.56 318.92
L.25 Set of spare parts for Multimode Fiber Optic cable. set 1 511.29 511.29
TOTAL L: 11,237.93

No ITEM DESCRIPTION Unit Qty Unit Price Total


M.4 Supply, transport and mounting of motorway gantry type
"PPI 1500-3", 15m range with work track, ladders, fall down
protection and preparation for the accessories girder (CCTV
camera) , III. wind zone. pc 5 14,980.85 74,904.25
Workshop steel structures production , includes the
purchase of materials, preparation of steel structures
according to base material design (hot rolled profiles)
structural steel CN 24-B1 (Č.0361) with a pilot installation.
Corrosion protection with Hot galvanization process and
additional epoxy based pait protection of lower column part
till 1,0 m height, construction transport from workshop to
Galvanazing plant and construction site. Construction
mounting on site.
M.15 CCTV girder – central tunnel mounting. Supply, transport
and mounting. pc 3 196.85 590.55

TOTAL M: 75,494.80

N. DOCUMENTATION AND TESTING


No ITEM DESCRIPTION Unit Qty Unit Price Total
N.1 Book of quality atests (declarations of conformity for
equipement). Refers to : set 1 255.65 255.65
Traffic signalisation and road equipement pc 1 102.26 102.26
SDUN and local area network – LAN pc 1 102.26 102.26
Cable duct and power supply pc 1 76.69 76.69
Load bearing structures pc 1 102.26 102.26
Protective wire fence pc 1 51.13 51.13
N.2 Preparation of test protocols for varriable message
signalization and measuring and control equipment on
section and in tunnel, with preparation of test documents. set 1 255.65 255.65
N.3 Measurment and testing of power cables with written
reports. set 1 102.26 102.26
N.4 Measurment of earthing resistence with written reports. set 1 76.69 76.69
N.5 Implementation of as-built documentation with manuals for set 6 76.69 460.14
N.6 operation
Report forand maintenance.
functional testing and system initialization. set 1 102.26 102.26
TOTAL N: 1,687.25

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 15
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

RECAPITULATION
IIIb. TRAFFIC
No ITEM DESCRIPTION Total EUR
A. TRAFFIC SIGNS TOTAL 4,051.09
B. ROAD EQUIPEMENT TOTAL 33.66
C. TRAFFIC MARKINGS (HORIZONTAL SIGNS AND MARKINGS) TOTAL 3,734.01
D. SAFETY BARRIERS (GUARD RAILS) TOTAL 34,668.40
E. VARIABLE MESAGE SIGNS TOTAL 335,290.91
F. MEASURING AND CONTROL EQUIPMENT TOTAL 130,819.55
J. DUCTS FOR POWER AND SIGNAL CABLES TOTAL 23,761.77
IMPLEMENTATION WORKS AND MATERIAL FOR ELECTRICAL INSTALLATIONS
K. 11,167.24
TOTAL
IMPLEMENTATION WORKS AND MATERIAL FOR SIGNAL INSTALLATIONS
L. 11,237.93
TOTAL
M. LOAD BEARING STRUCTURES TOTAL 75,494.80
N. DOCUMENTATION AND TESTING TOTAL 1,687.25
TOTAL IIIa: 631,946.61

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 16
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

IIIb TRAFFIC INFORMATION SYSTEM


Note: In cases where certain equipment is specifically named, it is only an indication of the technical
features the offered equipment would need to comply with.

A. VARIABLE MESSAGINING TRAFFIC SIGN EQIPMENT

No ITEM DESCRIPTION Unit Qty Unit Price Total


Acquirement and delivery of variable message traffic sign that
consist of:
- Traffic lane sign
Traffic lane sign – PZ VII09 and PZ VII10, housing dimensions
70x70 cm. Possibility of displaying two signs PZ VII09 (red cross,
dimensions 60x60 cm) and PZ VII10 (green arrow, dimensions
49,5x60 cm) on same black colored matrix. Signs must be
produced with minimum three rows of led, red cross (PZ VII09) –
red colored LED, green arrow (PZ VII10) – green colored LED.
Technical specification
- Maximum light intensity of LED variable sign mast be: 3100
cd/m2 for red color i 3720 cd/m2 for green color.
autonomous programmable microprocessor control unit in each
sign
Validity control check of each LED regardless of status of
activation of sign (error detection in “cold” state)
Autonomous power supply for each sigh
Independent current power source for each LED, which ensures
independence of light emission intensity of sign from power
fluctuation and displayed symbol

A.2
Error notice on local control panel and on remote central computer
of LED malfunction
Possibility of quick replacement of each malfunctioned LED and
other parts which are often subject of malfunction
Possibility of connectivity to payment system through serial
connection (RS-485) using TLS/FG4 protocol
Adjustable temperature control by means of thermostat and heater
in each sign
Adjustable light intensity control (1-100%) from GUI of control
program and in relation to surrounding environment light intensity.
Temperature operating range (-400C + 700C).
Electrical safety in accordance with HD 638 and HD 384
Electromagnetic accordance with EN50293:2000, section Road
traffic signal systems

pcs 1 1,607.45 1,607.45

TOTAL A: 1,607.45

B. WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total


Mounting and connecting traffic signs on canopy
B.1 pcs 1.00 2,000.02 2,000.02
Various materials for mounting, connecting and cabling
B.3 set 1.00 1,499.98 1,499.98

TOTAL B: 3,500.00

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 17
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

IIIb TRAFFIC INFORMATION SYSTEM

C. DOCUMENTATION AND COMMISSIONING


No ITEM DESCRIPTION Unit Qty Unit Price Total
Examination and commissioning of traffic signs including
fabrication of examination protocols and reports
C.1 set 1.00 2,000.02 2,000.02
Instalation of control PC with control software with examination
C.2 set 1.00 2,000.02 2,000.02
As-built documentation with details and instructions for managing
and maintaining.
C.4 set 1.00 999.98 999.98
Test documentation for built-in equipment
C.5 set 1.00 250.02 250.02

TOTAL C: 5,250.04

D. ELECTROINSTALATIONS

No ITEM DESCRIPTION Unit Qty Unit Price Total


Acquirement, delivery and cable laying of signal cable 3x2x0.6
D.1 mm2 in hollow tile for connecting opposite traffic signs. m 20.00 1.18 23.60
Acquirement, delivery and cable laying of power cable PP00 3x1,
5mm2 in hollow tile on canopy with inspection, for variable
message traffic sign powering, and cable conduit for blinker
powering and control. Cable connects OG boxes on canopy with
variable traffic signs and blinkers with blinker control unit.

D.3 m 20.00 1.12 22.40


Acquirement, delivery and mounting of hollow tile PK100 on
canopy and support pillars. Item includes mounting materials.
D.4 m 20.00 10.02 200.40
Acquirement, delivery and cable laying in hollow tile of cable PP/2
D.5 3x0,75 mm2 for LUX powering, with inspection. m 30.00 0.41 12.30
D.6 OG box - IP 65 pcs 1.00 7.00 7.00
Various consumable electrical materials
D.7 pcs 1.00 200.02 200.02

TOTAL C: 465.72

RECAPITULATION
IIIb. TRAFFIC INFORMATION SYSTEM
No ITEM DESCRIPTION Total EUR

A VARIABLE MESSAGINING TRAFFIC SIGN EQIPMENT 1,607.45

B DOCUMENTATION AND COMMISSIONING 3,500.00

C WORKS 5,250.04

D ELECTROINSTALATION 465.72

TOTAL IIIb: 10,823.21

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 18
PHASE IV
LOT 7: section POČITELJ - BIJAČA
IVa ARCHITECTURAL
Note: In cases where certain equipment is specifically named, it is only an indication of the technical features
the offered equipment would need to comply with.

ARCHITECTURAL PHASE IV
1. STRUCTURE 1.1 - THE CENTRAL CANOPY

A. EARTHWORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


GENERAL
Excavation of humus material and basic backfill are addressed by
Roads design, i.e. the entire TCMC plateau.
A basic backfill is designed for the plateau only, with no subbase
and asphalt, i.e. approx. 40 cm below finished pavement.
All the excavation is designed in semi-solid rock soils, where partial
explosive blasting is necessary, and the remaining excavation is
performed directly by machinery, “B” category soil.
Excavated material of compaction module Ms = 80 MN/m² shall be
used for backfill in layers after execution of all the foundations (to
the elevation specified).
All calculations of the excavation, backfill and removal of soil shall
be performed for compacted material.
The excavated material shall be disposed of at a distance of 25 m
because it shall be reused later for backfilling around the
foundations.
The excavation shall be performed 95 % by machinery and 5 % by
hand.
A1 Excavation of soil for canopy column footings 0.00
Excavation of “B” category soil for the central canopy column
footings.
Excavation depth up to 2.00 m.
The unit price includes loading, grading of the excavation pit
bottom to +/- 2cm cm accuracy, and removal of the excavated
material to a dump site approx. 25m away.
The excavation shall be performed 95% by machinery and 5% by
hand.
Calculation per bank m³ of soil. m³ 66.00 1.79 118.14
A2 Backfill of material around foundation heels 0.00
Backfilling material, spreading, compacting and levelling the
approx. 70cm deep backfilled layer around the foundation heels.
Use the excavated material for the backfilling.
Compacting shall be executed using the same compacting module
as applied at the plateau, i.e. Ms =80 to100 KN/m².
Levelling shall be performed to +/-2 cm accuracy.
Calculation per m³ of the compacted backfill executed. m³ 28.00 1.43 40.04
A3 Excavation of land for installation channel m³ 74.00 1.79 132.46

A4 Filling installation channels m³ 10.40 1.43 14.87


Coarse and fine planning excavation below the bottom of
A5 0.00
footings and installation channels
Coarse and fine grading of the bottom of the excavation with
simultaneous excavation of 0.03 m³ / m2.
The grading shall be performed to ± 1 cm accuracy.
Calculation per m² m2 72.00 0.51 36.72
Planning the bottom of the excavation and compaction of
A6 0.00
gravel below the rates foundation and installation channels

Supply, transportation, spreading, grading and compacting of


gravel 15 cm deep, serving as a subbase layer under the central
canopy footings.
Calculation per m³ m³ 10.00 10.74 107.40

19 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


A7 Disposal of excess material 0.00
The works include disposal of excess humus material, excess
excavated material and all waste material, transportation from the
excavation site to a disposal site, including loading, offloading,
spreading and grading.
The contractor is required to provide transport within the
construction site itself and on public transport routes.
Within the unit price, the contractor is responsible to find a disposal
site, provide a disposal site improvement plan with all required
approvals (of the supervising body, the design engineer and the
Client) and to improve the disposal site.
Calculation per bank m³ of the material removed. m³ 37.00 3.07 113.59
TOTAL A: 563.22
B. CONCRETE AND REINFORCED CONCRETE WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


B1 Blinding concrete under the footings C12/15 0.00
Casting of a weak blinding concrete base below the foundation
footings, C12/15 class compressive strength concrete, d = 5 cm
thick.
The item includes all required works, material and resources.
Calculation per m3 of concrete poured. m³ 19.00 76.69 1,457.11
B2 Supply and pouring of footings concrete C30/37 0.00
Concreting of the footings using C30/37 class compressive
strength concrete, in smooth formwork.
Calculation per m3 of concrete poured.
a) concrete m³ 186.00 94.59 17,593.74
B3 Concreting of reinforced concrete foundation heels C30/37 0.00
Concreting of reinforced concrete foundation heels using C30/37
class compressive strength concrete, 120 cm size, 90 cm tall.
a) concrete m³ 41.00 94.59 3,878.19
b) formwork m2 138.00 5.11 705.18
B4 Concreting of sewer drainage shaft C30/37 0.00
Supply and pouring of concrete into sewer drainage shafts, shafts
on the canopy footings.
Compressive strength of the concrete is C30/37.
Shaft wall thickness shall comply with the design.
Concrete shall conform to composition defined by the design.
Calculation per m3 of concrete poured.
a) concrete m³ 12.00 94.59 1,135.08
b) smooth formwork m² 154.00 5.11 786.94
TOTAL B: 25,556.24

C. REINFORCEMENT STEEL BENDING WORKS


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Reinforcing steel must be placed securely and professionally in
compliance with applicable regulations and professional rules.
Size, shape and position of the reinforcing steel are defined in
reinforcing steel plans, contained in the design.
The reinforcing steel bending, extending and installation works
must conform to applicable regulations.
C1 Supply, manufacturing and placing of the reinforcing steel
Supply, manufacturing and installation of concrete reinforcement in
compliance with the steel reinforcing design.
This item pertains to standard part of the structure only.
The unit price shall include straightening, cutting, bending, 100%
binding and placement in the structural elements.
The reinforcing steel must be clean of rust and any grease.
The reinforcing steel must conform to a quality control and
assurance programme, and the contractor is required to supply, not
only manufacturer certificates supplied
to the construction site with every batch delivered, but also to
submit samples for testing in compliance with the programme.

20 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


Calculation per kg of the reinforcing steel placed.
ribbed reinforcing steel RA 400/500 (B 500B) kg 26,290.00 0.69 18,140.10
TOTAL C: 18,140.10
D. MASONRY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

GENERAL:
The unit price includes all basic and binding material, anchors,
labour, tools, transport, various types of protection etc.
D1 Installation of steel columns
Installation of steel columns executed in ø 508/16mm and ø
406.4/10mm steel sections.
Calculation per piece of ø 508/16mm section installed. pcs 4.00 2259.91 9,039.64
Calculation per piece of ø 406.4/10mm section installed. pcs 4.00 1273.12 5,092.48
TOTAL D: 14,132.12
E. CARPENTRY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Concrete and reinforced concrete works related formwork is
included in the concrete and reinforced concrete works.
E1 Supply, manufacturing and removal of scaffolding 0.00
Supply, assembly and dismantling of the scaffolding after
completion of all the works, and removal of the steel and timber
scaffolding for masonry, carpentry, metal and painting works.
The scaffolding shall be approx. 9.00 m tall.
It pertains to the works carried out in high spaces.
Calculation per m2 of scaffolding installed. m2 2,556.00 2.05 5,239.80
Supply, manufacturing and removal of painting works
E2
scaffolding
All as item 5.1, except mobile scaffolding for execution of the
painting works.
Calculation per scaffolding piece. pcs 1.00 255.65 255.65

5,495.45

F. STEEL STRUCTURE
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
F1 Elements of the central canopy steel structure 0.00
The central canopy shall be executed above border customs and
police control area of Bijača Border Crossing (The main border
customs and police building, border customs and police building,
prefabricated booths for customs and police control, customs
inspection and vehicle scales).
Manufacturing, supply and installation of the central canopy.

The price includes: Procurement of the basic materials,


procurement of connecting materials, execution of a working
design and workshop documentation, workshop scaffolding, trial
assembling in the workshop and dismantling of the main trusses,
transportation, installation at the construction site,

corrosion protection, base coat and finish coat painting, execution


of auxiliary scaffolding and supply and transport of cranes to the
construction site, as well as control and supply of quality certificate
for the completed structure, welder certificates, all in compliance
with norms and national additional materials conforming to EC3.
Quality of the steel shall be S235 JR, while the welds shall be of
the 1st quality (I).

Elements of the central canopy steel structure are as follows:


- Cover girders POS 001 – UPN 80 rolled sections
- The secondary girders POS 002 – hot formed pipe □70/40/4
- The secondary girders POS 004 lo = 9.60 m (l = 12.00 m):
– upper chord Ø88.9/5 mm
– lower chord Ø88.9/4 mm
– lower diagonal members Ø88.9/4 mm

21 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


– side diagonal members Ø88.9/5 mm
– cover girder supports ≠80/80/6 and ≠200/80/6 mm
- The secondary girders POS 005 lo =16.60 m (l =19.00 m):
– upper chord Ø88.9/5 mm
– lower chord Ø88.9/4 mm
– lower diagonal members Ø88.9/4 mm
– side diagonal members Ø88.9/5 mm
– cover girder supports ≠80/80/6 and ≠200/80/6 mm
- Walkway girders POS 006 lo = 9.60 m (l = 12.00 m):
– walkway chord hot formed pipe □120/80/4 mm
– upper chords Ø88.9/5 mm
– crossbars and vertical elements Ø70/4 mm
– all diagonal members Ø51/4 mm
- Walkway girders POS 007 lo = 16.60 m (l = 19.00 m):
– walkway chord hot formed pipe □120/80/4 mm
– portal frames, hot formed pipe □120/80/4 mm
– upper chords Ø88.9/5 mm
– crossbars and vertical elements Ø70/4 mm
– all diagonal members Ø51/4 mm
- Walkway portal frames POS 008 lo =16.60 m (l =19.00 m):
– walkway chord hot formed pipe □120/80/4 mm
– portal frames, hot formed pipe □120/80/4 mm
– upper chords Ø88.9/5 mm
- Lateral siding girders POS 009:
– horizontal and vertical siding girders Ø51/4 mm
– all diagonal members Ø51/4 mm
- Main trusses POS 010 and POS 011:
– lower columns Ø508/16 mm
– upper columns Ø406.4/10 mm
– supporting inclined struts Ø88.9/5 mm
– all lower chord diagonal members and crossbars Ø51/5 mm
– supporting posts Ø88.9/4 mm
– fixed and sliding support plates ≠200/120/10 mm
- Anchoring plates and anchors:
– anchoring plates Ø720, Ø680 mm, 30 and 16 mm thick
– sheet metal anchor hoops ≠50/5 mm
– B500 Ø20 mm steel anchors, l = 1400 mm long
-Protective bird netting on the canopy soffit
The contractor is required to take measurement of the foundation
heels executed, prior to commencement of the works. Calculation
per kg of executed structure.
Connecting material (welds and assembling screws) – 5% of the
material
Total kg 27,000.00 1.85 49,950.00
TOTAL F: 49,950.00
G. ROOFING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
This group of works includes roofing works related to the central
canopy.
The unit price shall include supply of materials, manufacturing of all
the elements, finish processing, and all required substructure, fixing
and accessory material, all required seals, and transportation and
assembling to full functioning.

Standardized substructure of individual elements shall be fixed to


the substructure executed within the load bearing canopy structure.
The roof shall be executed as double-pitched at 8.5% grade.
The price includes: Taking measures in situ, supply of the basic
and the connecting materials, workshop manufacturing,
transportation and assembling at the construction site, working
scaffolding, elements connecting to the substructure and at areas
of contact with other materials.
G1 Trapezoid sheet metal roofing of the central canopy 0.00
Zinc coated trapezoid sheet steel, 53 mm tall, T53/162.5. The
sheet metal shall be 0.8 mm thick.
The cover shall be executed with required seals of the joints.

22 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


The metal sheets must be unbroken in direction of the roof pitch
grade, with no joints.
The unit price of the item includes all standardized flashing
elements.
All in compliance with the structural analysis and workshop
documentation. Finish processing using paint (coil coating) in
m2 5,948.00 13.05 77,621.40
colour selected by the design engineer.

G2 Roof ridge cover

Covering the ridge using metal sheet identical to the cover metal
sheet, 0.6 mm thick, except with flat sheet metal with no moulding.
Developed width of the sheet metal is 30 cm.
The unit price includes supply and insertion of bituminised rubber
foam seals into indentations of the cover sheet metal curvatures
and cutting the ridge sheet metal to fit the cover.
Calculation per m' of roof ridge covered m 65.00 8.59 558.35
TOTAL G: 78,179.75

H. SHEET METAL WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


GENERAL:
All sheet metal flashings, gutters and similar items are
manufactured in 0.55 mm thick zinc coated (hot-dipped) sheet
metal except downspouts and horizontal flashings which are
executed in the same sheet metal as the covering (flat, painted).

The unit price shall include supply of material, workshop


manufacturing, transport and site assembly, scaffolding, use of
cranes, gutter and downspout supports, connection of the
downspouts into
cast-iron piping, manufacture and installation of gable flashing
fixing elements, gutter and downspout connections.

Likewise, the unit price shall include supply and installation roofing
paper strip on all areas of contact of the zinc coated sheet metal
and concrete or other material, while in places of direct contact with
other types of metal, plastic soft band shall be inserted.

All executed in compliance with detailed drawings and details, and


in agreement with the supervising engineer and the design
engineer who shall determine colour of the sheet metal.
The unit price shall include all labour, tools, materials (basic and
fixtures), all transportation, complete scaffolding, special guides,
various forms of professional safety, execution of workshop
drawings, on site material storage etc.
All joints and transitions – breaks of slope of the sheet metal shall
be executed by insertion of “Z” or several similar capping and
transition sections included in the unit price.

H1 Horizontal box-section gutter of the main canopy 0.00


Stainless steel sheet, 0.6 thick, approx. 110 cm developed width.
The gutter shall be installed on the supports governing grade of the
gutter, at every 50 cm.
Includes netting at connections to the downspouts.
Details in compliance with standardized designs of the roofing
cover manufacturer.
Calculation per m'. m 384.00 14.27 5,479.68
H2 Roof drain connecting pipe 0.00
Pipe connecting the gutter and the downspout (running through the
steel columns).
Stainless steel sheet, 0.6 mm thick, 160 mm pipe diameter, total
length according to the design.
The item includes all elements of the connection between the
gutter and the drainage downspout steel pipe in the canopy column
(included in the steel structure). pcs 16.00 4.91 78.56

23 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


H3 Flashing sheet metal of eaves and gables cornice siding 0.00
Supply of materials and execution of two-sided flashing of the
siding.
The sheet metal shall be plastic coated, zinc coated, partially flat
and partially moulded (as indicated by the design).
The siding is 2.50m tall.
The sheet metal is 1.0 mm thick.
Quality of the sheet metal shall conform to the above description.
Self-adhesive bituminised strips designed to separate the sheet
metal and the steel shall be glued to the steel substructure.
The unit price shall include all of the specified, as well as all original
connecting and auxiliary material.
Calculation per m² of executed siding.
Waveform shape siding. m2 860.00 13.50 11,610.00
Flashing of intersection of the siding and the upper cover
H4 0.00
sheet metal
Supply of materials and execution of flashing at intersection of the
siding and the upper cover sheet metal on the steel canopy.
Developed width of the sheet metal is approx. 30 cm.
Use flat plastic coated and zinc coated sheet steel, matching the
cover in colour and thickness.
Calculation per m' of executed flashing. m 344.00 8.03 2,762.32
H5 Rooflight strip flashing 0.00
Manufacturing and installation of complete flashing executed in
plastic coated, zinc coated steel sheet around the rooflight strips.
External drip edge and flashing shall be executed.
They consist of a horizontal and a vertical band.
30 cm wide horizontal band and 20 cm wide vertical band shall be
executed in painted sheet metal like the cover sheet metal, except
flat and connected to the profiled cover sheet metal.
Developed width of the painted sheet metal in the horizontal line is
30 cm and in the vertical line it is 20 cm.
Calculation per m' of actually executed flashing. m 548.00 8.74 4,789.52
H6 Execution of snow guards
Manufacturing and installation of original snow guard on the
structure roof, TRIMO system or corresponding.
The snow guard has a pipe shape cross-section and is executed in
plastic coated, zinc coated 40mm diameter steel pipe, and its
colour matches the roof.
The snow guard shall be fixed to the roof using screws with special
caps fitting nosings on the sheet metal.
Length of the snow guard is equal to length of the structure.
Calculation per m' of actual installed snow guard. m 672.00 4.85 3,259.20
TOTAL H: 27,979.28
I. IRON METAL WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

GENERAL:
Iron metal works products consist of non-processed and cold
formed drawn sections.
All frames have anchoring claws, and all joints are welded.
Prior to installation, the metal products shall be cleaned of rust by
sandblasting and degreased, and two coats of epoxy-based paint
as corrosion protection shall be applied.
I1 Manufacturing and installation of walkway railing 0.00
Manufacturing, supply and installation of railing on the walkways.
The railing shall be executed in compliance with the design.
The unit price includes sealing of a 150 mm tall parapet using
aluminium sheet and connecting material as well as cleaning of
rust using sandblasting and double corrosion protection using
epoxy based paint.
Calculation per m' of executed railing. m 488.00 28.12 13,722.56
I2 Steel step irons in the drainage shafts 0.00
Manufacturing and supply to the construction site and installation of
steel step irons in the drainage shafts.

24 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


The step irons shall be executed in 16 mm diameter ribbed
concrete reinforcing, bent into “U” shape, 45 cm wide, set 16 cm
away from walls.
Loose ends shall be built into the shaft walls 15 cm deep.
The step irons shall be placed 30 cm apart.
After installation, double Resitol coat shall be applied to the step
irons.
All shall be executed conforming to the working design.
Calculation per piece of manufactured and installed step irons. pcs 64.00 7.67 490.88
I3 Step irons at the walkways 0.00
Supply and installation of steel step irons facilitating access to the
walkways.
Calculation per piece of step irons installed m2 2.00 23.01 46.02
TOTAL I: 14,259.46
J. ROOFLIGHT STRIP WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
J1 Rooflight strips around the roof ridge
Cover executed in transparent polycarbonate plates, two-sided,
using patented procedure, UV radiation protected, of exceptionally
high impact strength, corresponding to Lexan Exell D.

The price shall include measure taking in situ, supply of the basic
and connecting materials, workshop manufacturing, transportation
and installation at the construction site, working scaffolding,
elements connecting it to
the substructure and all other accessories required for installation
of flat polycarbonate plates.
Size and installation details shall be in compliance with the working
design.
Dry assembling using standardized metal sections, using sealing
strips or silicone sealants.
Installation of seals of ± 65 Shore hardness.
Design shall allow sufficient space for expansion of the plates
occurring due to thermal expansion, in order to avoid deformations.
Thermal expansion is approx. 3mm/m'.
The contractor is required to execute a protective cover in a
polyethylene or similar foil after installation and removal of the
protective foil, as a protection from paint and other coating spray.
Calculation per m². m2 133.00 76.69 10,199.77
TOTAL J: 10,199.77
K. PAINTING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
K1 Surcharge for painting of the steel structure
Surcharge for two coats of additional paint of the canopy steel
structure columns base using black paint, resistant to weather
effects, salt and fuel.
Executed approx. 50 cm high.
Calculation per m2 of painted surface. m2 26.00 13.29 345.54
TOTAL K: 345.54
L. OTHER
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
L1 Execution of technical documents set 1 511.29 511.29
TOTAL L: 511.29

RECAPITULATION
No ITEM DESCRIPTION Total EUR
A. EARTHWORKS 563.22
B. CONCRETE AND REINFORCED CONCRETE WORKS 25,556.24
C. REINFORCEMENT STEEL BENDING WORKS 18,140.10
D. MASONRY WORKS 14,132.12
E. CARPENTRY WORKS 5,495.45
F. STEEL STRUCTURE 49,950.00

25 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


G. ROOFING WORKS 78,179.75
H. SHEET METAL WORKS 27,979.28
I. IRON METAL WORKS 14,259.46
J. ROOFLIGHT STRIP WORKS 10,199.77
K. PAINTING WORKS 345.54
L. OTHER 511.29
TOTAL 1: 245,312.22

26 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


2. STRUCTURE 2.4. FREIGHT VEHICLE EXIT CONTROL, TYPE 3 - 4 identical structures in lot 4
A. SITE PREPARATION AND EARTHWORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Excavation of humus material and basic backfill are addressed by
Roads design, i.e. the entire BC plateau. A basic backfill is
designed for the plateau only, with no subbase and asphalt, i.e.
approx. 40 cm below finished pavement.
All the excavation is designed in semi-solid rock soils, where partial
explosive blasting is necessary, and the remaining excavation is
performed directly by machinery, “B” category soil.
Excavated material of compaction module Ms = 80 MN/m² shall be
used for backfill in layers after execution of all the foundations (to
the elevation specified).
All calculations of the excavation, backfill and removal of soil shall
be performed for compacted material. The excavated material shall
be disposed of 25 m away,
since it shall be reused for backfilling around the foundations.
The excavation shall be performed 95 % by machinery and 5 % by
hand.
A1 Staking out of the structure 0.00

The item comprises all works related to staking out of the structure
including installations; all design to site (and vice versa) data
transfer measurements; setup and maintenance of markers and

chainage markers on the site from commencement of the works


until acceptance of all the works by the Client and execution of an lump 1 15.34 15.34
as-built survey. sum
A2 Excavation up to 200 cm deep 0.00
Excavation for the booth concrete shaft in “B” category soil,
excavation depth up to 200 cm.
The excavation shall be performed 95 % by machinery and 5 % by
hand.
Calculation per bank m³ of the excavation. m³ 17.00 1.79 30.43
A3 Grading of the bottom of the excavation 0.00
Coarse and fine grading of the bottom of the excavation with
simultaneous excavation of 0.03 m3 / m2. The grading shall be
performed to ± 1 cm accuracy.
Calculation per m² of the material excavated. m2 11.00 0.51 5.61
A4 Crushed stone or gravel layer 0.00
Delivery and placement of crushed stone or gravel, and backfilling,
spreading and grading a 15 cm deep layer below the reinforced
concrete slab of the structure.
The grading shall be performed to +/- 2 cm accuracy.
Calculation per m³ of the compacted material placed. m³ 2.00 10.74 21.48
A5 Disposal of excess material
The works include disposal of excess material, excess excavated
material and all waste material, transportation from the excavation
site to a disposal site, including loading, offloading, spreading and
grading.
The contractor is required to provide transport within the
construction site itself and on public transport routes.
Within the unit price, the contractor is responsible to find a disposal
site, provide a disposal site improvement plan with all required
approvals (of the supervising body, the design engineer and the
Client) and to improve the disposal site.
Calculation per bank m³ of the material removed. m³ 17.00 3.07 52.19
TOTAL A: 125.05

27 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


B. CONCRETE AND REINFORCED CONCRETE WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Concrete strength is defined by design of the structure.
Each reinforced concrete element item is defined by structural
analysis, reinforcing plan and the bill of quantities’ items, and has
compressive strength class (C) assigned to it. Apart from the
concrete compressive strength marking, the design may present
special demands

During construction of the reinforced concrete structure it is


necessary to sample concrete and deliver the samples to an
authorized laboratory for certification. The samples collected in a
concrete plant are not relevant due to possibility of subsequent
Prior to concreting,
addition of water in timber
order toformwork should
reduce its be thoroughly
strength cleaned,
for transport.
moistened, while smooth formwork should be oiled. Also,
measurements and workmanship should be checked. The
formwork may be removed only after the concrete poured attains
B1 appropriate strength,
Blinding concrete after an
below theorder issued
booth shaftby the C12/15
floor supervising 0.00
engineer.
Casting of a blinding base concrete below the booth shaft floor,
C12/15 compressive strength class, d = 5 cm thick.
The item includes all required works, material and resources.
Calculation per m³ of concrete poured. m³ 0.55 76.69 42.24
B2 Concreting of the reinforced walls of the booth shaft C30/37 0.00

Supply and placement of concrete into the reinforced concrete


booth shaft, compressive strength class C30/37, in large surface
smooth formwork.

The concrete must conform to water impermeability, frost and salt


resistance criteria.
In order to protect the reinforcing steel from corrosion, including
colloid corrosion, MCI – 2005 type corrosion inhibitor (product
corresponding to LONGUS) shall be added
to the concrete during its preparation in quantity of approx. 0.6 l/m³
concrete.
The internal formwork should be accurately executed to avoid
further processing of the concrete.
The reinforcing steel is specified in a separate item.
Concrete shall conform to composition defined by the design.
Calculation per m³ of concrete poured. 0.00
a) concrete m³ 7.00 99.70 697.90
b) large area formwork m² 31.00 5.11 158.41
B3 Concreting of the reinforced walls of the booth shaft C30/37 0.00
Supply and pouring of concrete into the reinforced concrete booth
shaft foundation slab.
30/37 class strength concrete with water impermeability and
plasticizing admixtures.
In order to protect the reinforcing steel from corrosion, including
chloride corrosion, MCI – 2005 corrosion inhibitor should be added
to the concrete
(product corresponding to LONGUS) mixed into concrete during
preparation in quantity of approx. 0.6 l/m3 of concrete.
Concrete shall conform to composition defined by the design.
Calculation per m³ of concrete poured. m³ 3.00 99.70 299.10

28 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


B4 Reinforced concrete staircase flight C30/37

Supply and pouring of concrete into the reinforced concrete flight of


stairs facilitating access to the upper slab of the booth shaft.
30/37 class strength concrete with water impermeability and
plasticizing admixtures.
In order to protect the reinforcing steel from corrosion, including
chloride corrosion, MCI – 2005 corrosion inhibitor should be added
to the concrete
(product corresponding to LONGUS) mixed into concrete during
preparation in quantity of approx. 0.6 l/m3 of concrete.
Concrete shall conform to composition defined by the design.
Calculation per m³ of concrete poured. 0.00
a) concrete m³ 1.00 99.70 99.70
b) formwork m² 4.00 7.16 28.64
TOTAL B: 1,325.99
C. REINFORCEMENT STEEL BENDING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Reinforcing steel must be placed securely and professionally in
compliance with applicable regulations and professional rules.
Supply, manufacturing and installation of concrete reinforcement in
compliance with the steel reinforcing design.
The reinforcing steel bending, extending and installation works
must conform to applicable regulations.
C1 Concrete reinforcement

Supply, manufacturing and installation of concrete reinforcement in


compliance with the steel reinforcing design.
This item pertains to standard part of the structure only – without
the prefabricated reinforced concrete elements.
The unit price shall include straightening, cutting, bending, 100%
binding and placement in the structural elements.
The reinforcing steel must be clean of rust and any grease.
The reinforcing steel must conform to a quality control and
assurance programme, and the contractor is required to supply test
samples in compliance with the programme as well as
manufacturer certificates supplied to the site with each delivery.
Calculation per kg of the reinforcing steel placed.
a) ribbed reinforcing steel B 500B kg 1,320.00 0.69 910.80
TOTAL C: 910.80
D. PAINTING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Prior to performance of painting works, the surfaces must be
prepared for skimming, any uneven areas patched and ground,
and that shall be included in the item unit price.

D1 Protection of the concrete around the prefabricated booths


Protection of exposed part of the concrete around the prefabricated
booths.
The surface should be cleaned of uneven areas and dirt, the entire
area should be impregnated, more substantial uneven areas
treated and repair mortar applied to the surface.
Supply of the materials and painting of the concrete surface of the
protective blocks in signal paint with skimming executed in external
works skim coating grout.
The paint coat must be resistant to effects of salt, frost, crude and
oil.
Calculation per m² of actually painted surface. m² 11.00 11.25 123.75
TOTAL D: 123.75

29 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


E. IRON METAL WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Iron metal works products consist of non-processed and cold
formed drawn sections.
All frames have anchoring claws, and all joints are welded.
Prior to installation, the metal products shall be cleaned of rust by
sandblasting and degreased, and two coats of epoxy-based paint
as corrosion protection shall be applied.
These technical conditions shall be appended by descriptions of
individual bill of quantity items and by quality control and assurance
programme.
Calculation per piece, m' of executed and installed iron metal works
elements.
E1 Steel step irons
Manufacturing and supply to the construction site and installation of
the steel step irons facilitating access into the shaft.
The step irons are 40 cm wide, across a total height of
approximately 2.30 cm, placed at 27 cm intervals.
In order to facilitate installation on the wall, anchoring posts shall
be provided at approx. 80 cm intervals.
All shall be executed in 20 mm diameter smooth concrete
reinforcing.
The unit price shall include all connecting and fixtures, corrosion
protection with two coats of epoxy-based paint.
Charged per piece of actually executed step irons. pcs 1 43.46 43.46
E2 Staircase protective railing
Staircase protective railing (on both sides). Handrail and posts.
The railing shall be executed in 2” diameter steel pipes. Smooth 12
mm diameter iron is placed inside the posts at approx. 100-120 cm
spacing.
The railing is approximately 2.00 m' long.
The railing shall be welded to prepositioned anchoring plates.
It shall be protected against corrosion using two coats of epoxy
based coating.
Calculation per m'. m' 4 23.01 92.04
TOTAL E: 135.50

F. PREFABRICATED BOOTH
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
F1 Toll booth 235/230/310 cm
A booth is executed as a prefabricated kiosk in the workshop until
fully completed with anchoring screws embedded in the upper part
of the posts, to be lifted by a truck crane and positioned on its
foundation.
After the assembly, the anchoring screws are removed and holes
left over are closed using decorative studs.

Entire structure is executed as a combination of steel frame and


aluminium siding with sliding counter windows and entrance doors.

Solid panelling in form of composite sandwich panelling, with zinc


coated 1 mm thick sheet metal siding and 8 cm thick mineral wool
filling.
All movable parts, guides, bearings etc. must comprise the
maximum accuracy.
All connecting material (screws etc.) must be executed in corrosion
resistant material.

Roofing sandwich panelling, 14 cm thick overall, covered with zinc


coated 1 mm thick sheet metal, with filling consisting of 12 cm thick
mineral wool, 0.2 mm thick PE foil and 2 cm air gap.
Dropped ceiling shall be executed in PVC grille comprising the
maximum sieve size 15x15 mm (installation at the construction
site).
Connection of the siding and the roof shall be rounded.

30 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


Finish of all exposed metal elements shall be plastic coating, in
colour as selected by the design engineer, conforming to the RAL
palette.
Flooring sandwich panelling, 8 cm thick overall, covered with zinc
coated 1 mm thick sheet metal, with filling consisting of 8 cm thick
mineral wool.
2-3 mm PVC or linoleum finish, across water resistant plywood 24
mm thick, shall be executed at the construction site.
The air gap between the sandwich panelling and the timber flooring
shall be 8 cm.
Fixing of the toll booth to the foundation shall be in compliance with
the details provided by the toll booth contractor.

The toll collection windows (two-sash sliding window) – window


sashes executed in aluminium sections with a thermal break and
insulation glazing.
Includes a aluminium guide with brush and rollers.
Hinged door, door leaf executed in aluminium sections with thermal
break and insulation glazing.
The windows and the doors shall be equipped with seals and
appropriate fittings and handles executed in satinated stainless
steel.
Fixed glazed sections shall also be executed using insulation
glazing.
All the glazing shall be executed in insulation glazing comprising
external 6 mm thick tempered glass and internal 5 mm thick
window glass.
The contractor is required to execute working documentation
(workshop drawings) and submit them to the design engineer for
approval.

The unit price shall include supply of required materials, execution,


transportation, assembling and sealing to full completeness. .

Designed conforming to HRN ENV 1991-2-4 in proportion to


referent wind velocities.
The windows and doors are executed conforming to HRN 14351-
1:2006, water impermeability according to HRN EN 12208:2001,
thermal properties of the aluminium siding, the windows and the
doors conforming to HRN EN 1125/A1/AC:2005, and HRN EN ISO
10077-1:2002.

The entire structure of the inspection booth must comply, in terms


of physics, to all EUROPEAN NORMS and STANDARDS adopted
by Croatia (or Bosnia and Herzegovina) as compulsory.
- TYPE 2 booth pcs 1 5767.37 5,767.37
TOTAL F: 5,767.37
G. SUNLIGHT PROTECTION

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

G1 Movable aluminium laminas on the windows


Supply and installation of internal painted aluminium movable
laminas that may be drawn up or down.
The aluminium laminas are placed on the windows.
The unit price shall include all basic and fixing material, top
trimming and operating strings.
Type and colour of the movable aluminium laminas shall be
determined by the design engineer.
Calculation per m² of actually installed laminas. pcs 10 14.06 140.60
TOTAL G: 140.60

31 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


H. OTHER

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


H1 Execution of technical documents 0.00 0.00
Execution of technical documentation of as-built situation with
complete operating and maintenance instruction, submission to the
1 102.26 102.26
client (in 6 copies). The item pertains to the entire Traffic Control
and Maintenance Centre (TCMC). set
H2 Detailed final cleaning 0.00

Cleaning of the structure and its surrounding, removal of debris


and waste to a stockpile. Detailed final cleaning of floors, tiling etc.

To be executed immediately prior to acceptance of the structure.

Calculation per completely cleaned structure and its surroundings. 1 10.23 10.23
set
TOTAL H: 112.49

RECAPITULATION
No ITEM DESCRIPTION Total EUR
A. SITE PREPARATION AND EARTHWORKS 125.05
B. CONCRETE AND REINFORCED CONCRETE WORKS 1,325.99
C. REINFORCEMENT STEEL BENDING WORKS 910.80
D. PAINTING WORKS 123.75
E. IRON METAL WORKS 135.50
E. PREFABRICATED BOOTH 5,767.37
F. SUNLIGHT PROTECTION 140.60
G. OTHER 112.49
TOTAL 2: 8,641.55
NOTE: The bill of quantities for heading 2 is executed for one structure. Please note there are
four (4) identical structures in lot 4. Therefore, the total number of the structures is calculated
in the below "Total recapitulation (all buildings)", in the total for the respective heading.

3. STRUCTURE 2.7 - BORDER CUSTOMS AND POLICE BUILDING


A. SITE PREPARATION AND EARTHWORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Excavation of humus material and basic backfill are addressed by
Roads design, i.e. the entire TCMC plateau. A basic backfill is
designed for the plateau only, with no subbase and asphalt, i.e.
approx. 40 cm below finished pavement.
All the excavation is designed in semi-solid rock soils, where partial
explosive blasting is necessary, and the remaining excavation is
performed directly by machinery, “B” category soil.
Excavated material of compaction module Ms = 80 MN/m² shall be
used for backfill in layers after execution of all the foundations (to
the elevation specified).
All calculations of the excavation, backfill and removal of soil shall
be performed for compacted material. The excavated material shall
be disposed of 25 m away,
since it shall be reused for backfilling around the foundations.
The excavation shall be performed 95 % by machinery and 5 % by
hand.
A1 Staking out of the structure 0.00

The item comprises all works related to staking out of the structure
including installations; all design to site (and vice versa) data
transfer measurements; setup and maintenance of markers and

chainage markers on the site from commencement of the works


lump
until acceptance of all the works by the Client and execution of an 1.00 51.13 51.13
sum
as-built survey.

32 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

A2 Foundation strip excavation 0.00

Excavation of the strip foundation in “B” category soil, strip width 40


cm, excavation depth up to 200 cm.
The excavation shall be performed 95% by machinery and 5 % by
hand.
Calculation per m³ of the material excavated. m³ 11.00 1.79 19.69
A3 Grading of the bottom of the excavation 0.00
Coarse and fine grading of the bottom of the excavation with
simultaneous excavation of 0.03 m3 / m2. The grading shall be
performed to ± 1 cm accuracy.
Calculation per m² of the material excavated. m2 64.00 0.51 32.64
A4 Crushed stone or gravel layer 0.00

Delivery and placement of crushed stone or gravel, and backfilling,


spreading and grading a 15 cm deep layer below floor of the entire
structure, and in a 10 cm layer at the strip foundations.

The grading shall be performed to +/- 2 cm accuracy.


Calculation per m³ of the compacted material placed. m³ 9.00 10.74 96.66
A5 Disposal of excess material
The works include disposal of excess material, excess excavated
material and all waste material, transportation from the excavation
site to a disposal site, including loading, offloading, spreading and
grading.
The contractor is required to provide transport within the
construction site itself and on public transport routes.
Within the unit price, the contractor is responsible to find a disposal
site, provide a disposal site improvement plan with all required
approvals (of the supervising body, the design engineer and the
Client) and to improve the disposal site.
Calculation per bank m³ of the material removed. m³ 11.00 3.07 33.77
TOTAL A: 233.89
B. CONCRETE AND REINFORCED CONCRETE WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Concrete strength is defined by design of the structure.
Each reinforced concrete element item is defined by structural
analysis, reinforcing plan and the bill of quantities’ items, and has
compressive strength class (C) assigned to it. Apart from the
concrete compressive strength marking, the design may present
special demands

During construction of the reinforced concrete structure it is


necessary to sample concrete and deliver the samples to an
authorized laboratory for certification. The samples collected in a
concrete plant are not relevant due to possibility of subsequent
addition of water in order to reduce its strength for transport.

Prior to concreting, timber formwork should be thoroughly cleaned,


moistened, while smooth formwork should be oiled. Also,
measurements and workmanship should be checked. The
formwork may be removed only after the concrete poured attains
appropriate strength, after an order issued by the supervising
engineer.
Blinding concrete beneath the strip foundation and floors
B1 0.00
C12/15
Casting of a weak blinding concrete base below the strip
foundation and structure floors, C12/15 compressive strength
class, d = 5 cm thick.
The item includes all required labour, material and resources.
Calculation per m³ of concrete poured. m³ 3.00 76.69 230.07
Supply and pouring of concrete in concrete strip foundations
B2 0.00
C25/30
Supply and pouring of concrete in concrete strip foundations
beneath walls, C25/30 compressive strength class concrete.
The strip foundations comprise cross-section 40 x 80 cm.

33 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


Calculation per m³ of concrete poured. m³ 13.00 81.81 1,063.53

34 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


B3 Reinforced concrete floor slab C25/30 0.00
Supply and placement of concrete in reinforced concrete floor slab,
d = 12 cm thick, C25/30 class.
The concrete slab is divided by concreting joints or cutting within 48
hours after concreting into 6.0 x 6.0 m fields.
Upper surface of the concrete base is executed at a grade towards
drainage gratings.
The top surface must be completely level and smooth as it
supports waterproofing.
The concrete must be cured using a curing system. The unit price
shall include supply and placement of 0.2 mm thick PE foil.
Reinforcing steel of the concrete base shall be executed in
compliance with the working construction design.
Calculation per m³ of concrete poured. 0.00
a) concrete m3 7.00 81.81 572.67
b) surcharge for execution of the joints per m' m' 4.50 0.51 2.30
c) surcharge for the surface processing m2 64.00 2.56 163.84
Concreting of vertical reinforced concrete circular beams
B4 0.00
C25/30
Concreting of reinforced concrete vertical circular beams using C
25/30 compressive strength concrete
Calculation per m³ of concrete poured. 0.00
a) concrete m3 4.00 81.81 327.24
b) formwork m2 32.00 13.29 425.28
Concreting of horizontal reinforced concrete circular beams
B5 0.00
C25/30
Supply and pouring of concrete of the horizontal reinforced
concrete circular beams, C 25/30 compressive strength concrete
Calculation per m³ of concrete poured.
a) concrete m3 7.00 81.81 572.67
b) formwork m2 50.00 13.29 664.50
B6 Concreting of reinforced concrete roof cornice 0.00
Supply and placement of concrete in reinforced concrete roof
cornice, d = 17 cm thick, C25/30 class.
Calculation per m³ of concrete poured. 0.00
a) concrete m3 3.00 81.81 245.43
b) formwork m2 34.00 5.11 173.74
B7 Cement screed 0.00
Supply and placement of material, execution of cement screed with
light reinforcing, d = 5 cm thick.
Executed atop thermal insulation on the floor of the ground floor
and on the roof slab. The unit price shall include cleaning of the
surface, supply and placement of 0.02 mm thick PVC foil, supply
and placement of a reinforcing mesh,
execution of glazing to trowel finish, and maintenance of the
glazing.
The cement glazing reinforcing shall be O-131 mesh.
Calculation per m² of executed cement screed.
cement screed below ceramic finish d = 5 cm m2 111.00 8.03 891.33

35 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


B8 Floor structure (ceiling) 0.00

Supply of elements, installation and bracing of the semi-precast


floor structure, 16+5 cm, pouring of concrete and installation of
reinforcing steel into the compressive slab, using C 25/30
compressive strength concrete and B 500B reinforcing steel.
The price shall include manufacturing of bracing beams
perpendicular to the semi-precast structure beams.
Calculation per m² m2 50.00 30.93 1,546.50
Supply and pouring of concrete into reinforced concrete
B9
compressive slab C25/30
Supply and placement of concrete in reinforced concrete
compressive slab C25/30 concrete compressive strength. The
concrete is poured atop semi-precast floor structure. The semi-
precast floor structure must be cleaned and properly moistened
with water prior to concreting to prevent concrete thermal stress.
Reinforcing steel is the same.
Calculation per m³ of concrete poured. m³ 3.00 92.03 276.09
TOTAL B: 7,155.19

C. REINFORCEMENT STEEL BENDING WORKS


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Reinforcing steel must be placed securely and professionally in
compliance with applicable regulations and professional rules.
Size, shape and position of the reinforcing steel are defined in
reinforcing steel plans, contained in the design.
The reinforcing steel bending, extending and installation works
must conform to applicable regulations.
C1 Concrete reinforcement

Supply, manufacturing and installation of concrete reinforcement in


compliance with the steel reinforcing design.
This item pertains to standard part of the structure only – without
the prefabricated reinforced concrete elements.
The unit price shall include straightening, cutting, bending, 100%
binding and placement in the structural elements.
The reinforcing steel must be clean of rust and any grease.
The reinforcing steel must conform to a quality control and
assurance programme, and the contractor is required to supply test
samples in compliance with the programme as well as
manufacturer certificates supplied to the site with each delivery.
Calculation per kg of the reinforcing steel placed.
a) ribbed reinforcing steel B 500B kg 2,700.00 0.69 1,863.00
b) reinforcing steel mesh B 500B kg 668.00 0.69 460.92
TOTAL C: 2,323.92

36 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


D. MASONRY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:

The unit price includes all basic and binding material, anchors,
labour, tools, transport, scaffolding, various types of protection etc.

The unit price shall include anchoring of the outer walls using 8 mm
diameter concrete steel using 2 anchors in every second row.

Anchoring holes shall be drilled to 12 mm diameter at a 15° angle


for at least 150 mm.
The holes shall be dusted and moistened, filled with Tricosal
sealing mortar and an anchor shall be placed.
Overall length of the anchors is 55 cm.
Load bearing and partition wall also need be bound by brickwork
bonding.
Closing up performed after ducts and wires are laid (plastering
grooves, gutters etc.) shall not be charged separately.
D1 External wall construction 0.00
Supply of materials and construction of 30 cm thick outer walls
using POROTHERM type 30 S PLUS or corresponding brick,
brickwork height up to 4.50 m.
The works shall be performed using cement-lime mortar M-100.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works.
The walls shall be executed with 2 faces.
Calculation per m³ of executed wall. m³ 12.00 69.02 828.24
D2 Construction of internal walls 20 cm 0.00
Supply of materials and construction of 20 cm thick internal walls
using POROTHERM type 20-50 PROFI or corresponding brick,
brickwork height up to 4.00 m.
The works shall be performed using cement-lime mortar M-100.
Pertains to all internal walls.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works.
Calculation per m³ m³ 5.00 71.07 355.35
D3 Construction of internal walls 12 cm 0.00
Supply of materials and construction of 12 cm thick internal walls
using POROTHERM type 12-50 PROFI or corresponding brick,
brickwork height up to 4.00 m.
The works shall be performed using cement-lime mortar M-100.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works.
Calculation per m² m2 5.00 11.35 56.75

37 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


D4 Prefabricated lintels 0.00
Supply and installation of prefabricated door lintels (lintels
corresponding to POROTHERM).
Calculation per piece pcs 3.00 17.90 53.70
D5 Plastering of the internal walls 0.00
Coarse and fine plastering of the internal brick walls and also
partially of the concrete surfaces. Coarse plastering using cement-
lime M-5 class mortar, and fine plastering using lime plaster M-2.5
class with all required preparatory operations.
Calculation per m². m2 170.00 4.86 826.20
D6 Plastering ceilings 0.00
Coarse and fine plastering of ceilings. Coarse plastering using
cement-lime M-5 class mortar, and fine plastering using lime
plaster M-2.5 class with all required preparatory operations.
Calculation per m². m2 50.00 4.86 243.00
D7 Supply and installation of rubber studs 0.00
Cleaning of the structure and its surrounding, removal of debris
and waste to a stockpile.
Detailed final cleaning of floors, tiling, glazing, metal works, joinery
etc.
Calculation per piece pcs 3 2.56 7.68
D8 Supply and installation of aluminium sills 0.00
Supply and installation of aluminium sills executed in L 40 x 40 mm
angle profile in areas where there is a difference of flooring type or
elevation.
The unit price includes fixing of the aluminium angle section to a
timber or aluminium door frame.
Calculation per piece of installed sill.
a) sill up to 1 m long pcs 3 7.16 21.48
D9 Cleaning of the structure 0.00
Cleaning of the structure, removal of rubble and other dirt 3 times
during construction of the structure.
Calculation per m² of gross area m2 66.00 0.51 33.66
D10 Final cleaning of the structure

Final cleaning of the structure prior to the technical inspection


(washing of all glazed surfaces, detailed cleaning of floors,
ceramics, sanitary facilities etc. after completion of all the works).

Calculation per m² of net area m2 50.00 0.51 25.50


TOTAL D: 2,451.56

38 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


E. INSULATION WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
E1 Horizontal waterproofing of the floors 0.00
Execution of horizontal waterproofing of the ground floor floors and
socle.
The waterproofing consists of a cold bituminous coat and two
layers of 4 mm thick welded bituminous paper, with welded
overlaps of 10 cm.
On the inside, the strips must remain wider to accommodate the
required overlap and bond to vertical wall waterproofing.
The waterproofing strips must be 100 % welded to the base and to
each other.
The unit price shall include cleaning of any impurities from the
concrete base, application of a primer (Resitol) coat and welding of
the first and the second strip.
The second strip must have the overlaps offset by 50 % relative to
the first one.
The lower base must be dry in compliance with regulations, as
evidenced by a measurement of relative humidity on the concrete
surface.
Calculation per m² of executed waterproofing. m2 134.00 11.15 1,494.10
E2 Supply and placement of plastic foil 0.00
Supply and installation of plastic foil corresponding to Tervol
STOPAIR d = 0.25 mm thick, across extruded polystyrene foam
(XPS) and extruded polystyrene (EPS).
Select foil type chemically compatible with thermal insulation in
place.
Calculation per m² of executed foil, measured in plan view. m2 118.00 0.82 96.76
Supply and placement of thermal insulation in floor/socle
E3 0.00
layers
Supply and installation of EXTRUDED POLYSTYRENE FOAM
(XPS) with overall thickness of d= 4.0 cm
Thermal insulation covers the waterproofing in the ground floor
floors, and on the inside part of the socle towards facade walls, all
in compliance with the working design.
Calculation per m² of thermal insulation placed. m2 52.00 5.01 260.52
E4 Supply and installation of roof thermal insulation 0.00
Supply and installation of extruded polystyrene (EPS) of overall
thickness of d = 8.0 cm.
The thermal insulation covers the ceiling semi-precast floor slab
waterproofing.
Calculation per m² of thermal insulation placed. m2 56.00 4.04 226.24
E5 Thermal insulation of horizontal box-section gutter
Procurement, supply of material required and installation of
extruded polystyrene d = 5 cm in the horizontal gutter.
Calculation per m². m2 5.00 3.73 18.65
TOTAL F: 2,096.27

39 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


F. CARPENTRY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Concrete and reinforced concrete works related formwork is
included in the concrete and reinforced concrete works.

F1 Supply and placement of boards and laths in the gutter 0.00


Supply and installation of class II softwood boards and laths,
manufacture and placement of a timber channel in the horizontal
roof drainage gutter.
Clearance of the channel shall be 16 x 20 cm.
Bottom of the channel shall be executed at 1% grade towards
outlets.
The boards and the laths should be impregnated to protect them
from rot and pests.
Calculation per m' of installed boards and laths. m' 24.00 6.03 144.72
F2 Supply and installation of timber 0.00
Supply and installation of 12x14 cm and 5x5 cm timber, as shims
between the semi-precast floor slab and the roofing structure.

The beam should be impregnated to protect them from rot and


pests.
Calculation per m³ and m' of timber elements installed. 0.00
a) 12x14cm – wall plates m³ 1.00 332.34 332.34
b) 12x14cm - rafters m³ 1.00 332.34 332.34
c) 5x5cm – battens m' 71.00 1.18 83.78
F3 Mobile steel and timber scaffolding 0.00
Supply, transportation and moving, assembly and dismantling of
the scaffolding after completion of all the works, and removal of the
steel and timber scaffolding for masonry and painting works.
The scaffolding shall be up to 4.0 m tall.
It pertains to the works carried out in high spaces. pcs 1 28.12 28.12
F4 Prefabricated facade scaffolding
Execution of a prefabricated facade scaffolding with flooring and
railings at each floor level.
The unit price shall include delivery, assembly, dismantling and
removal of the facade scaffolding elements.
The scaffolding is used for execution of all the facade works
(bricklaying, rendering and plastering).
The scaffolding shall be up to 4.0 m tall.
Calculation per m² of vertical projection of the scaffolding. m2 177.00 2.05 362.85
TOTAL F: 1,284.15

40 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


G. SHEET METAL WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
All sheet metal flashings, gutters and similar items are
manufactured in 0.55 mm thick zinc coated (hot-dipped) sheet
metal except downspouts and horizontal flashings which are
executed in the same sheet metal as the covering (flat, painted).
The unit price shall include supply of material, workshop
manufacturing, transport and site assembly, scaffolding, use of
cranes, gutter and downspout supports, connection of the
downspouts into
cast-iron piping, manufacture and installation of gable flashing
fixing elements, gutter and downspout connections.

Likewise, the unit price shall include supply and installation roofing
paper strip on all areas of contact of the zinc coated sheet metal
and concrete or other material, while in places of direct contact with
other types of metal, plastic soft band shall be inserted.

G1 Horizontal box-shaped gutter 0.00


Manufacture and installation of horizontal box-section gutters š =
26 cm wide of variable height, achieving gutter grade of approx.
0.5% toward its outlets.

A drip edge shall be executed along with the gutter, around the
reinforced concrete channel, in sheet metal, as well as the top
cover, while zinc coated sheet metal shall be slipped 50 cm deep.

Total developed width of the sheet metal is 160 cm.


The unit price shall include execution of a 10 x 10 cm size, 40 cm
long side channel.
Calculation per m' of actually executed gutter and side channel. 0.00
a) zinc coated gutter m' 24.00 15.08 361.92
b) side channel pcs 2 2.97 5.94
G2 Deaerating tank 0.00
Manufacture and installation of deaerating tanks atop the
downspouts, size 30x30x20cm.
Calculation per piece. pcs 2 3.02 6.04
G3 Vertical roof drainage downspout 0.00
Manufacture and installation of 10x10 cm vertical downspout.
The vertical downspouts are designed in 2 locations.
The unit price shall include execution of connections to cast-iron
piping below, i.e. manufacture of seals, and manufacture of swan-
necks and connections to the gutter side channel.
Developed length of the swan-neck is 50 cm.
All shall be executed in flat painted sheet metal as structure cover.
Wall mounting clamps shall be placed at every 1m' of height.
Calculation per m' of actually executed downspout and swan-neck
0.00
and the lower seal piece.
a) vertical downspout m' 8.00 9.51 76.08
b) swan-neck pcs 2 9.82 19.64
c) lower seal pcs 2 5.88 11.76
G4 Drip edge

Manufacture and installation of painted sheet metal drip edge and


flashing, quality corresponding to Kalzip, at facade elements.
Horizontal drip edge is approx. 50 cm wide, executed in painted
sheet metal matching facade colour, except flat and connected via
zinc coated steel hooks onto reinforced concrete roof cornice.
The sheet metal shall be 0.8 mm thick.
The unit price shall comprise manufacturing and installation of the
steel hooks at every 50 to 60 cm, supply of the self-adhesive
bituminised strip and its adhesive attachment, proper intertwining of
all the connections, welding the sheet metal and all accessories
and auxiliary material
Calculation per m' of actually executed drip edge. m' 35.00 9.92 347.20
TOTAL G: 828.58

41 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


H. ROOFING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Fire resistant panels corresponding to Trimoterm SNV, consisting of
two moulded, bilaterally zinc coated (275 g/m²) and painted steel
sheets (of 0.6 mm standard thickness) with an insulation filling
consisting of non-flammable laminated mineral wool.
All the layers comprise a compact sandwich element providing
required load bearing capacity, impermeability and compactibility.
The mineral wool core of the panel provides excellent thermal and
sound insulation of the panel as well as high fire resistance.
The panels are up to 14 m long.
H1 Covering of the entire structure roof 0.00
Covering of the entire structure roof using roofing panels
corresponding to Trimoterm SNV 120.
The panel consists of two bilaterally zinc coated painted steel
sheets, 0.6 mm thick, one with shallow profile and another with
deep (trapezoidal) profile.
The sheet metal is glued to the panel core comprising non-
flammable laminated mineral wool, class A1 (DIN 4102).
It comprises polyester based corrosion protection (standard
protection).
Colour of the sheet metal matches RAL palette, and is selected by
the design engineer.
All three layers comprise a compact 120 mm thick panel, providing
required load bearing capacity, impermeability and assembling
properties.
The roof shall be executed as double-pitched roof, with 6% grade
to both sides.
Calculation per m² of the roof area. m2 52.00 35.48 1,844.96
H2 Roof ridge cover 0.00
Covering the ridge using metal sheet identical to the cover metal
sheet, 0.6 mm thick, just with flat sheet metal with no moulding.
Developed width of the sheet metal is 100 cm.
The unit price includes supply and insertion of bituminised rubber
foam seals into indentations of the cover sheet metal curvatures
and cutting the ridge sheet metal to fit the cover.
Calculation per m' of roof ridge covered m' 12.00 11.71 140.52
H3 Adjustment of the cover to the cornice flashing
Surcharge for adjustment of the metal sheet cover of the cornice
flashing.
Pertains to possible bending of edges of the sheet metal
"UPWARDS"
Calculation per m' of metal sheet gable flashing. m' 9 0.56 5.04
TOTAL H: 1,990.52

42 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


I. JOINERY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
The 1st class oak veneer shall be used to manufacture doors,
since the doors shall be painted preserving growth rings visible.
The 1st class fir-spruce timber without growth rings shall be used to
manufacture door frames, since the door frames shall be painted
after installation.
Width of the door jamb equals thickness of the wall.
The door jambs must be delivered to the site impregnated, with a
moisture repellent coating applied to their outsides.
The unit price shall include supply of basic material and fixtures,
measure taking in situ, workshop manufacturing, delivery to the
site, fitting and adjustment at location of
installation and after the installation, supply and installation of
metal fittings selected by the design engineer, including cylinder
locks, keys and a doorstop.
Everything else according to joinery schematic layout and
directions of the supervising engineer and the design engineer.
Apart from the aforementioned elements, the unit price shall
include manufacturing and installation of two-sided trim selected by
the design engineer.
A ventilation grille shall be installed in the lower part of all toilet
doors.
4 mm thick OPTIFLOAT glass shall be used for glazing of the fixed
fanlight.
Glazing putty or permanently elastic sealant shall be used for
installation of glazing.
Joinery colour (leafs and door frame) shall be agreed upon with
the Client.
Everything is to be made according to joinery schematics.
Calculation per piece of manufactured and installed doors,
including fittings, locks, glazing, seals, fixing accessories and all
other labour, material and resources required for installation of the
joinery until it is fully functioning.
I1 Partition wall with doors 0.00
Partition wall is executed in multilayered HPL laminate 14 mm
thick, with rounded edges and corners.
The doors are equipped with shock absorbers and plastic scratch
guards and self-closing fixtures.
Elliptical stainless steel lock shall be built into the doors with no
parts projecting outside, and it shall have an occupied/free
indicator and an emergency opening system.
An anodized aluminium profile shall be installed along the upper
outside wall in order to bind together the entire structure.
The partition wall is attached to the wall using aluminium fixtures
allowing fine adjustments.
The partition modules shall be raised from the floor by 150 mm
using aluminium posts with a plastic base.
On the bottom of the posts there shall be a screw used to adjust
stainless steel fixtures attaching it to the floor.
Colour shall be selected by the design engineer.
Partition wall with door, size 188/225cm Position 1 pcs 1 529.70 529.70

43 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


I2 Partition wall
Partition wall is executed in multilayered HPL laminate 14 mm
thick, with rounded edges and corners.
The partition is equipped with shock absorbers and plastic scratch
guards and self-closing fixtures.
An anodized aluminium profile shall be installed along the upper
outside wall in order to bind together the entire structure.
The partition walls are attached to the wall using aluminium fixtures
allowing fine adjustments.
The partition modules shall be raised from the floor by 150 mm
using aluminium posts with a plastic base.
On the bottom of the posts there shall be a screw used to adjust
stainless steel fixtures attaching it to the wall.
Partition wall size 90/225cm. Position 2 pcs 1 255.65 255.65
TOTAL I: 785.35
J. IRON METAL WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Iron metal works products consist of non-processed and cold
formed drawn sections. All frames have anchoring claws, and all
joints are welded.
Prior to installation, the metal products shall be cleaned of rust by
sandblasting and degreased, and two coats of epoxy-based paint
as corrosion protection shall be applied.

J1 Frame and “coconut” doormat


Supply of material (stainless steel), manufacturing and installation
of the frame and the doormat.
The doormat frame size is 120 x 60 cm and it is executed in “L”
sections 30 x 30 x 3 mm with anchoring claws.
The doormat is “COCONUT” type and included in the unit price.
Calculation per piece of installed frame with the doormat. pcs 2 71.58 143.16
TOTAL J: 143.16

K. NONFERROUS METAL WORKS


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
All the works must be performed skilfully and properly, with
appropriate quality material which must conform to existing
regulations and norms.
Prior to commencement of the works related to manufacturing on
nonferrous metal works, the contractor is required to inspect the
construction works completed, and if shortcomings which may
present an impediment are observed, that must be communicated
to the construction works contractor
in order to have the latter remove them.
All aluminium sections and products must be executed in high
quality and properly.
Contractor of these works is required to protect the works
performed by other contractors to prevent any damage occurring
due to performance of the works.
The contractor is also required to protect all the works from dirt,
and after completion of the works, the contractor is required to
remove all excess material and waste from the construction site.
Aluminium sections with a thermal break corresponding to
SCHUECO INTERNATIONAL type shall be used to execute the
nonferrous metal works.
The aluminium sections shall be executed in aluminium alloy Al Mg
Si 0.5, F220 strength up to 260 N/mm2.

The minimum thickness of the protective layer shall be 18 to 25


microns, and must comply with HRN.C.T7.234, 236, 226 and 228.

The unit price shall include supply of basic material and fixtures,
measure taking in situ, workshop manufacturing,

44 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


delivery to the site, fitting and adjustments in situ and after
installation, supply and installation of metal fittings as selected by
the design engineer with cylinder locks and keys and all the
trimmings.

45 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


Everything else according to metal works schematic layout and
directions of the supervising engineer and the design engineer.
Apart from the aforementioned, the unit price shall include
execution of workshop documents and submission of the
documents for review and approval of the design engineer.
Steel sections used for anchoring the aluminium partitions have at
least two coats of paint for protection.
Apart from the aforementioned, the unit price shall include
execution of workshop documents and submission of the
documents for review and approval of the design engineer.
Steel sections used for anchoring the aluminium partitions have at
least two coats of paint for protection.
Aluminium sheet and section fixing anchors shall be executed in
stainless steel.
Screws and other fixing material shall be executed in stainless
steel, aluminium or other anticorrosive material.
Corner pieces must be executed impeccably.
Areas which are especially sensitive to loss of impermeability must
be sealed using two-component putty of appropriate quality.
Doors and those windows that open must have rubber seals at the
edges.
All external doors must have built-in closers.
THERMOPLUS and OPTIFLOAT glass 4+16+4 mm insulation
glazing must be used for window glazing so that the thermal
conductivity coefficient is 1.6 W/m2K, while door glazing shall be
LAMISTAL 3+3+12+ LAMISTAL 3+3 insulation glazing.
Proper plastic elements shall be used to install the insulation
glazing.
Colour of the plastic coated aluminium metal works shall be
determined by the design engineer in agreement with the client.
Unit prices of all doors shall also include a rubber floor mounted
doorstop.
These technical conditions shall be appended by descriptions of
individual bill of quantity items and by quality control and assurance
programme.
The contractor must present certificate to prove that the aluminium
sections and the glazing comply with the conditions set, especially
in terms of thermal conductivity.
All shall be executed in compliance with nonferrous metal works
schematics, bill of quantities descriptions and detailed drawings.

Calculation shall be per piece of manufactured and installed


nonferrous metal works product, complete with all accessories,
fittings, locks, glazing, seals, fixtures and other items required for
installation of nonferrous metal works to their full functioning.

46 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
K1 Two-leaf glazed external door 160/255 cm 0.00
One-leaf external door 160 cm wide and 255 cm tall, executed in
plastic coated aluminium sections with a thermal beak,
corresponding to SCHUECO INTERNATIONAL type, and
LAMISTAL 3+3+12+LAMISTAL 3+3 insulation glazing.
The metal fittings shall be selected by the design engineer, and
include cylinder locks, handles and keys (corresponding to “WINK
HAUS” or “KABA”), and a floor mounted doorstop.
The door leafs shall have built-in closers corresponding to “GEZZE”
type.
Colour of the steel and metal works and design of the handles shall
be selected by the design engineer.
Calculation per piece. Position 1 pcs 2 820.62 1,641.24
K2 Single-leaf internal door 90/210+90cm 0.00
One-leaf internal door 90cm wide and 210cm tall with a fixed
fanlight measuring 90x90cm.
The door is executed in plastic coated aluminium sections with a
thermal break, corresponding to SCHUECO INTERNATIONAL
type, with 2 cm thick thermo panels.
The metal fittings shall be selected by the design engineer, and
include cylinder locks, handles and keys (corresponding to “WINK
HAUS” or “KABA”), and a floor mounted doorstop.
The door leafs shall have built-in closers corresponding to “GEZZE”
type.
4mm thick OPTIFLOAT glass shall be used for glazing of the fixed
fanlight.
Colour of the steel and metal works and design of the handles shall
be selected by the design engineer.
Calculation per piece. Position 6 0.00
a) left hand door pcs 2 493.40 986.80
b) right hand door pcs 1 493.40 493.40
K3 Window 120+120/120+60cm size 0.00
The windows are executed in plastic coated aluminium sections
with a thermal break, corresponding to SCHUECO
INTERNATIONAL type, with 4+16+4 mm insulating glazing.
Size 120+120/120+60cm.
The item includes window jambs, sashes, all the fittings and
insulation glazing.
Both of the sashes tilt inwards or rotate around their respective
vertical axes to open, while the fanlights tilt inwards to open, and
Ventus mechanisms shall be provided for the purpose.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 2 pcs 4 414.15 1,656.60
K4 Window 120/120+60cm size 0.00
The windows are executed in plastic coated aluminium sections
with a thermal break, corresponding to SCHUECO
INTERNATIONAL type, with 4+16+4 mm insulating glazing.
Size 120/120+60cm.
The item includes window jambs, sashes, all the fittings and
insulation glazing.
Both of the sashes tilt inwards and rotate around their respective
vertical axes to open, while the fanlights tilt inwards to open, and
Ventus mechanisms shall be provided for the purpose.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 3 pcs 4 414.15 1,656.60

47 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
K5 Window 120/60+60cm size 0.00
The windows are executed in plastic coated aluminium sections
with a thermal break, corresponding to SCHUECO
INTERNATIONAL type, with 4+16+4 mm insulating glazing.
Size 120/60+60cm.
The item includes window jambs, sashes, all the fittings and
insulation glazing.
Both of the sashes tilt inwards and rotate around their respective
vertical axes to open, while the fanlights tilt inwards to open, and
Ventus mechanisms shall be provided for the purpose.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 4 pcs 3 363.02 1,089.06
K6 Window 120/60cm
The windows are executed in plastic coated aluminium sections
with a thermal break, corresponding to SCHUECO
INTERNATIONAL type, with 4+16+4 mm insulating glazing.
Their size is 120x60cm.
The item includes window jambs, sashes, all the fittings and
insulation glazing.
The sashes tilt inward to open, and are operated via a Ventus
opening mechanism.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 5 pcs 1 204.52 204.52
TOTAL K: 7,728.22

L. STONEWORK
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
L1 External and internal window sills
Supply and installation artificial or natural stone window sills using
cement mortar.

The sills are 15 cm (external) and 25 cm wide (internal). The sill


must extend beyond the final facade layer by at least 3 to 3.5 cm.

The minimum length of the sill is width of the window plus 2 cm, i.e.
at least 62cm and 122cm.
The sills must be placed strictly horizontally viewed along their
length, with a transversal grade of 10 %.
Undersides of the sills must have a groove along the length to
prevent backflow of water.
After installation, the sills contact to the nonferrous metal works
need be cleaned and sealed with two-component permanently
elastic putty for exterior works.
The unit price shall include supply of the window sill with the drip
edge and polished exposed

surfaces, cement mortar and preparation of the surface it is applied


to, cleaning and sealing of the NF metal works joints, protection of
the sill and all other operations required for installation.

Calculation per piece of installed sills. 0.00


a) external window sills l = 120 cm pcs 12 21.63 259.56
b) internal window sills l = 120 cm pcs 12 36.81 441.72
TOTAL L: 701.28

48 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


M. FLOOR AND WALL TILING
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
All floor and wall tiling are designed to be executed in the 1st class
ceramic tiles, 30 x 30 or 20 x 20 cm size, ground or rough top
surface in colour to be determined by the design engineer in
agreement with the client.
At joints of tiled floors and plastered walls a 10 cm tall socle shall
be executed in the same ceramic tiles.
Wall ceramic tiles shall be placed using appropriate adhesive onto
lime-cement mortar plastered walls.
In smaller premises (sanitary facilities etc.) 20 x 20 cm tiles shall
be used for floors and walls (of same quality, colour and production
lot).
Tiling system shall always be joint to joint, while the joint width shall
be agreed with the design engineer.
Floor ceramic tiles are laid in cement mortar or glued onto prepared
cement glazing using construction adhesive.
The unit price shall include supply of the basic and binding
material, laying and tuck pointing of the ceramic tiles using ready-
made mixture as selected by the design engineer, supply and
installation
of PVC, Al, brass or chrome plated angle and cap trimming,
cleaning of the floors and the walls and all transportation.
The structure is divided into 7 zones according to drawing 02-03
and 02-04 ground floor plan. The zones are assigned colours which
apply to the ceramic tiles, all in agreement with the design engineer
or the client.
M1 Floor and wall tiling
Tiling of the sanitary facilities premises’ floors, baby care premises’
floors and corridor floors using the 1st class safety tread non-skid
ceramic tiles comparable to FLOOR GRES cheramiche BASIC,
ceramic tile size 20 x 20 cm. (R9)
The ceramic tiles shall be placed in a single or two colour pattern in
compliance with tiling scheme for individual premises.
The ceramic tiles must be grinded, polished and skid safe (R9
safety tread rating), in colour selected by the design engineer.
Tiling with joints no wider than 2 to 3 mm.
The tiles shall be placed in construction adhesive in compliance
with recommendations of manufacturer of the tiles.
The ceramic tiles shall be at least 8 mm thick.
Tiling system shall be joint to joint.
The unit price shall include supply of the basic and the binding
material, taking measurements in situ, installation, tuck pointing,
trimming and protection after the tiles are laid.
The item includes supply and installation of fitting tiles for the 15
cm tall socle, possessing the same properties as the tiles specified
above.
The item also includes tiling of walls to a height of 300 cm (of the
same quality, colour and production lot) around sanitary facilities’ 0.00
elements.
a) floor tiles m² 50.00 16.36 818.00
b) wall tiles m² 30.00 16.36 490.80
c) socle m' 62.00 3.32 205.84
TOTAL M: 1,514.64

49 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


N. PAINTING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
N1 Skimming and painting the walls and the ceilings 0.00
Painting of the walls and the ceilings in all the premises where no
tiles are placed.
Painting shall be performed using factory ready-made lime based
paint corresponding to “POLIFLOR” conforming to the following
formula:
1) repair of minor uneven patches, 2) skimming all areas using a
special mixture corresponding to “POLIFIX”, 3) triple coat of paint
corresponding to “POLIFLOR”.
Paint hue shall be agreed with the design engineer and the client.
The unit price shall include all material, labour, tools, scaffolding,
transport, safety measures etc.
Calculation per m² of actually painted surface. m2 173.00 2.25 389.25
N2 Iron metal works painting 0.00

Painting of iron metal works using epoxy based paint.


The unit price shall include cleaning of surfaces previously
protected against corrosion, one base coat of epoxy based paint,
application of putty and grinding of any uneven areas.
double coat of epoxy based paint, protection of other surfaces from
contamination, protection of finished paint from damage following
completion of painting and other auxiliary material.
The works shall be performed in compliance with regulation on
corrosion protection of steel structures.
Thickness of the coat shall be inspected by the supervising
engineer.
Paint colour shall be defined by the user in agreement with the
design engineer, using RAL colour chart only.
Calculation per m² of painted surface. m2 1.00 9.71 9.71
N3 Painting of entire joinery
Painting of entire joinery with doorjamb and leafs/sashes.

Prior to painting, the doorjambs shall be protected using protective


vapour permeable paint onto which putty shall be applied.

The surfaces should be ground after the putty dries up, and the first
coat of paint should be applied.
After the first coat of paint dries up, repeat application of putty over
any remaining uneven areas.
Subsequently, repeat grinding process and then apply the second
coat of paint.
The last coat of paint shall be executed in glossy paint, while the
paint colour shall be determined by the design engineer.
Leafs/sashes shall be sprayed using paint (Neolin) outlining growth
rings after the protective permeable nitro paint is applied.
The price includes all required auxiliary material.
Calculation per m² of painted joinery. m2 13.00 6.65 86.45
TOTAL N: 485.41

50 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


O. EXTERNAL PLASTERING WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


O1 Supply and placement of plastic foil 0.00
Supply and installation of plastic water vapour permeable foil
corresponding to Tervol STOPAIR d = 0.25 mm thick, across
extruded polystyrene foam (EPS). (Facade siding d = 6 cm.)
Select foil type chemically compatible with thermal insulation in
place.
Calculation per m² of foil installed. m2 132.00 1.28 168.96
O2 Supply and installation of facade thermal insulation 0.00
Supply and installation of EXTRUDED POLYSTYRENE (EPS).
(Facade siding d = 6 cm.)
Calculation per m² of thermal insulation placed. m2 132.00 5.37 708.84
Supply and installation of ventilated facade executed in MAX
O3 0.00
Compact NT siding
Supply of materials and execution of ventilated facade siding in
MAX Compact NT plates.
Substructure:
Executed in absolutely anti-corrosive material – aluminium,
corresponding to MAX-EURO FOX system.
The substructure system facilitates distancing of the siding away
from the thermal insulation and thereby an air gap of 30 - 50 mm,
required for airflow and ideal straightening of the facade, as well as
relief protrusions.
Siding:
Executed in MAX COMPAT NT siding, based on high pressure
laminate, 6 mm thick, in colour and pattern as selected by the
design engineer.

Centre of the siding executed in high quality cellulose papers


enhanced using phenol resin. The external and the internal
decorative layers protected by acrylic resins and special NT-
technology protecting the siding with its diamond structure from the
worst effects – UV radiation.
The siding shall be fixed to an appropriate substructure with
invisible joints – adhesively (SIKA TACK PANEL PU – adhesives)
Installed using open horizontal and vertical joints, 6 mm minimum
width, 10 mm maximum width.
The facade pattern, size and layout and all other technical details
in compliance with technical instructions of the siding element
manufacturer and systems designed to use the siding most
efficiently, and authorization of the design engineer.
The decorative pattern shall be selected by the client.
A perforated aluminium net shall be placed on the lower edges of
the facade.
Calculation per m² of facade installed. m2 132.00 109.93 14,510.76
O4 Supply and installation of reveal of the windows and the walls

Supply and installation of decorative reveal of the windows and the


walls. Reveal, approx. 180 mm in MAX COMPACT siding executed
on standardized aluminium substructure.
Calculation per m'. m' 37.00 28.12 1,040.44
TOTAL O: 16,429.00

51 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


P. SUNLIGHT PROTECTION
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
P4 Aluminium laminas
Supply and installation of internal painted aluminium movable
laminas that may be drawn up or down.
The aluminium laminas are placed on the windows.
The unit price shall include all basic and fixing material, top
trimming and operating strings.
Type and colour of movable aluminium laminas shall be determined
by the design engineer.
Calculation per piece of actually installed laminas. 0.00
a) 120+120/120+60cm size window Position 2 pcs 4 23.06 92.24
b) 12/120+60cm size window Position 3 pcs 4 31.50 126.00
c) 120/60+60cm size window Position 4 pcs 3 28.12 84.36
c) 120/60cm size window. Position 5 pcs 1 14.06 14.06
TOTAL P: 316.66
R. OTHER
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
R1 Execution of technical documents 0.00
Execution of technical documentation of as-built situation with
complete operating and maintenance instruction, submission to the set 1 255.65 255.65
client (in 6 copies). The item pertains to the entire TCMC.

R2 Detailed final cleaning 0.00

Cleaning of the structure and its surrounding, removal of debris


and waste to a stockpile. Detailed final cleaning of floors, tiling etc.

To be executed immediately prior to acceptance of the structure.

Calculation per completely cleaned structure and its surroundings. set 1 51.13 51.13

TOTAL R: 306.78

RECAPITULATION
No ITEM DESCRIPTION Total EUR
A. SITE PREPARATION AND EARTHWORKS 233.89
B. CONCRETE AND REINFORCED CONCRETE WORKS 7,155.19
C. REINFORCEMENT STEEL BENDING WORKS 2,323.92
D. MASONRY WORKS 2,451.56
E. INSULATION WORKS 2,096.27
F. CARPENTRY WORKS 1,284.15
G. SHEET METAL WORKS 828.58
H. ROOFING WORKS 1,990.52
I. JOINERY WORKS 785.35
J. IRON METAL WORKS 143.16
K. NONFERROUS METAL WORKS 7,728.22
L. STONEWORK 701.28
M. FLOOR AND WALL TILING 1,514.64
N. PAINTING WORKS 485.41
O. EXTERNAL PLASTERING WORKS 16,429.00
P. SUNLIGHT PROTECTION 316.66
R. OTHER 306.78
TOTAL 3: 46,774.58

52 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


4. STRUCTURE 2.8. SANITARY AND WATER FACILITIES FOR MEN & WOMEN
A. SITE PREPARATION AND EARTHWORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Excavation of humus material and basic backfill are addressed by
Roads design, i.e. the entire BC plateau. A basic backfill is
designed for the plateau only, with no subbase and asphalt, i.e.
approx. 40 cm below finished pavement.
All the excavation is designed in semi-solid rock soils, where partial
explosive blasting is necessary, and the remaining excavation is
performed directly by machinery, “B” category soil.
Excavated material of compaction module Ms = 80 MN/m² shall be
used for backfill in layers after execution of all the foundations (to
the elevation specified).
All calculations of the excavation, backfill and removal of soil shall
be performed for compacted material. The excavated material shall
be disposed of 25 m away,
since it shall be reused for backfilling around the foundations.
The excavation shall be performed 95 % by machinery and 5 % by
hand.
A1 Staking out of the structure 0.00
The item comprises all works related to staking out of the structure
including installations; all design to site (and vice versa) data
transfer measurements; setup and maintenance of markers and
1.00 51.13 51.13
chainage markers on the site from commencement of the works
until acceptance of all the works by the Client and execution of an lump
as-built survey. sum
A2 Foundation strip excavation
Excavation of the strip foundation in “B” category soil, strip width 40
cm, excavation depth up to 200 cm.
The excavation shall be performed 95 % by machinery and 5 % by
hand.
Calculation per bank m³ of the excavation. m³ 18.00 1.79 32.22
A3 Grading of the bottom of the excavation 0.00
Coarse and fine grading of the bottom of the excavation with
simultaneous excavation of 0.03 m3 / m2. The grading shall be
performed to ± 1 cm accuracy.
Calculation per m² of the material excavated. m2 26.00 0.51 13.26
A4 Backfilling the material below the ground floor 0.00
Backfilling material, spreading, compacting and levelling the 10 cm
deep backfilled layer to below the ground floor.
Use the excavated material for the backfilling.
Backfilling shall be performed to the layer specified in item A5.
Compacting shall be executed using the same compacting module
as applied at the plateau, i.e. Ms =80 to 100 kN/m².
Levelling shall be performed to +/-2 cm accuracy.
Calculation per m³ of the compacted backfill executed. m³ 7.00 1.43 10.01
A5 Crushed stone or gravel layer 0.00

Delivery and placement of crushed stone or gravel, and backfilling,


spreading and grading a 15 cm deep layer below floor of the entire
structure, and in a 10 cm layer at the strip foundations.

The grading shall be performed to +/- 2 cm accuracy.


Calculation per m³ of the compacted material placed. m³ 13.00 10.74 139.62
A6 Disposal of excess material 0.00
The works include disposal of excess material, excess excavated
material and all waste material, transportation from the excavation
site to a disposal site, including loading, offloading, spreading and
grading.
The contractor is required to provide transport within the
construction site itself and on public transport routes.
Within the unit price, the contractor is responsible to find a disposal
site, provide a disposal site improvement plan with all required
approvals (of the supervising body, the design engineer and the
Client) and to improve the disposal site.
Calculation per bank m³ of the material removed. m³ 11.00 3.07 33.77

53 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


TOTAL A: 280.01

54 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


B. CONCRETE AND REINFORCED CONCRETE WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Concrete strength is defined by design of the structure.
Each reinforced concrete element item is defined by structural
analysis, reinforcing plan and the bill of quantities’ items, and has
compressive strength class (C) assigned to it. Apart from the
concrete compressive strength the design also provides special
requirements for other concrete properties (wearing resistance,
water impermeability, frost resistance etc.).

During construction of the reinforced concrete structure it is


necessary to sample concrete and deliver the samples to an
authorized laboratory for certification. The samples collected in a
concrete plant are not relevant due to possibility of subsequent
addition of water in order to reduce its strength for transport.

Prior to concreting, timber formwork should be thoroughly cleaned,


moistened, while smooth formwork should be oiled. Also,
measurements and workmanship should be checked. The
formwork may be removed only after the concrete poured attains
appropriate strength, after an order issued by the supervising
engineer.
B1 Blinding concrete beneath the strip foundation C12/15
Casting of a weak blinding concrete base below the strip
foundation, C12/15 class compressive strength, d = 5 cm thick.
The item includes all required works, material and resources.
Calculation per m³ of concrete poured. m³ 1.00 76.69 76.69
B2 Blinding concrete below all ground floor premises C12/15
All as item 2.1, except below all ground floor premises.
The concrete is 5cm thick.
Calculation per m³ of concrete poured. m³ 3.00 76.69 230.07
Supply and pouring of concrete in concrete strip foundations
B3 0.00
C25/30
Supply and pouring of concrete in concrete strip foundations
beneath walls, C25/30 compressive strength class concrete.
The strip foundations comprise cross-section 40 x 80 cm.
Calculation per m³ of concrete poured. m³ 21.00 81.81 1,718.01
B4 Reinforced concrete floor slab C25/30
Supply and placement of concrete in reinforced concrete floor slab,
d = 12 cm thick, C25/30 class.
The concrete slab is divided by concreting joints or cutting within 48
hours after concreting into 6.0 x 6.0 m fields.
Upper surface of the concrete base is executed at a grade towards
drainage gratings.
The top surface must be completely level and smooth as it
supports waterproofing.
The concrete must be cured using a curing system. The unit price
shall include supply and placement of 0.2 mm thick PE foil.
Reinforcing steel of the concrete base shall be executed in
compliance with the working construction design.
Calculation per m³ of concrete poured. m³ 11.00 81.81 899.91
b) surcharge for execution of the joints per m' m' 19.00 0.51 9.69
c) surcharge for the surface processing m² 93.00 2.56 238.08
Concreting of vertical reinforced concrete circular beams
B5 0.00
C25/30
Concreting of reinforced concrete vertical circular beams using C
25/30 compressive strength concrete
Calculation per m³ of concrete poured. 0.00
a) concrete m³ 3.00 81.81 245.43
b) formwork m² 18.00 14.32 257.76

55 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Concreting of horizontal reinforced concrete circular beams
B6 0.00
C25/30
Supply and pouring of concrete of the horizontal reinforced
concrete circular beams, C 25/30 compressive strength concrete
Calculation per m³ of concrete poured.
a) concrete m³ 5.00 81.81 409.05
b) formwork m² 18.00 13.29 239.22
B7 Concreting of the reinforced concrete roof slab 0.00
Supply and placement of concrete in reinforced concrete floor slab
(cantilever), d = 12 cm thick, C25/30 class.
Calculation per m³ of concrete poured. 0.00
a) concrete m³ 4.00 81.81 327.24
b) formwork m² 30.00 7.16 214.80
B8 Concreting of reinforced concrete roof cornice 0.00
Supply and placement of concrete in reinforced concrete roof
cornice, d = 12 cm thick, C25/30 class.
Calculation per m³ of concrete poured. 0.00
a) concrete m³ 5.00 81.81 409.05
b) formwork m² 71.00 5.11 362.81
B9 Cement screed 0.00
Supply and placement of material, execution of cement screed with
light reinforcing, 4 to 6 cm thick.
Executed atop thermal insulation on the floor of the ground floor.
The unit price shall include cleaning of the surface, supply and
placement of 0.02 mm thick PVC foil, supply and placement of a
reinforcing mesh,
execution of glazing to trowel finish, and maintenance of the
glazing.
The cement glazing reinforcing shall be O-131 mesh.
Calculation per m² of executed cement screed.
a) cement screed below ceramic finish d = 5 cm m² 64.00 8.03 513.92
a) cement screed below ceramic finish d = 6 cm m² 11.00 8.69 95.59
B10 Floor structure (ceiling) 0.00
Supply of elements, installation and bracing of the semi-precast
floor structure, 16+5 cm, pouring of concrete and installation of
reinforcing steel into the compressive slab, using C 25/30
compressive strength concrete and B 500B reinforcing steel. The
price shall include manufacturing of bracing beams perpendicular
to the semi-precast structure beams.
Calculation per m² m² 73.00 30.93 2,257.89
Supply and pouring of concrete into reinforced concrete
B11 0.00
compressive slab C25/30
Supply and placement of concrete in reinforced concrete
compressive slab C25/30 concrete compressive strength. The
concrete is poured atop semi-precast floor structure. The semi-
precast floor structure must be cleaned and properly moistened
with water prior to concreting to prevent concrete thermal stress.
Reinforcing steel is the same.
Calculation per m3 of concrete poured. m³ 2.00 92.03 184.06
B12 Concreting sidewalks around the structure 0.00
Concreting of the sidewalk using C25/30 compressive strength
concrete 12 cm thick and simultaneous execution of concrete
screed and gravel subbase d = 10 cm. Expansion joints shall be
executed in the concrete at every 2m². The sidewalk shall be
executed at a grade sloping away from the structure.
Calculation in m². m² 50.00 10.74 537.00
TOTAL B: 9,226.27

56 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


C. REINFORCEMENT STEEL BENDING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Reinforcing steel must be placed securely and professionally in
compliance with applicable regulations and professional rules.
Size, shape and position of the reinforcing steel are defined in
reinforcing steel plans, contained in the design.
The reinforcing steel bending, extending and installation works
must conform to applicable regulations.
C1 Concrete reinforcement 0.00
Supply, manufacturing and installation of concrete reinforcement in
compliance with the steel reinforcing design.
This item pertains to standard part of the structure only – without
the prefabricated reinforced concrete elements.
The unit price shall include straightening, cutting, bending, 100%
binding and placement in the structural elements.
The reinforcing steel must be clean of rust and any grease.
The reinforcing steel must conform to a quality control and
assurance programme, and the contractor is required to supply test
0.00
samples in compliance with the programme as well as
manufacturer certificates supplied to the site with each delivery.
Calculation per kg of the reinforcing steel placed.
a) ribbed reinforcing steel B 500B kg 3,800.00 0.69 2,622.00
b) reinforcing steel mesh B 500B kg 963.00 0.69 664.47
TOTAL C: 3,286.47

D. MASONRY WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


GENERAL:

The unit price includes all basic and binding material, anchors,
labour, tools, transport, scaffolding, various types of protection etc.

The unit price shall include anchoring of the outer and inner walls
using 8 mm diameter concrete steel using 2 anchors in every
second row.
Anchoring holes shall be drilled to 12 mm diameter at a 15° angle
for at least 150 mm.
The holes shall be dusted and moistened, filled with Tricosal
sealing mortar and an anchor shall be placed.
Overall length of the anchors is 55 cm.
Load bearing and partition wall also need be bound by brickwork
bonding.
Closing up performed after ducts and wires are laid (plastering
grooves, gutters etc.) shall not be charged separately.
D1 External wall construction 0.00
Supply of materials and construction of 30 cm thick outer walls
using POROTHERM type 30 S PLUS or corresponding brick,
brickwork height up to 4.50 m.
The works shall be performed using cement-lime mortar M-100.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works.
The walls shall be executed with 2 faces.
Calculation per m³ m³ 43.00 69.02 2,967.86
D2 Construction of internal walls 0.00
Supply of materials and construction of 20 cm thick internal walls
using POROTHERM type 20-50 PROFI or corresponding brick,
brickwork height up to 4.00 m.
The works shall be performed using cement-lime mortar M-100.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works. 0.00
Calculation per m³ m³ 5.00 71.07 355.35

57 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

D3 Construction of partition walls 0.00


Supply of materials and construction of partition walls using
POROTHERM type 10 PROFI or corresponding brick, brickwork
height up to 4.00 m.
The works shall be performed using cement-lime mortar M-100.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works.
Calculation per m² m² 23.00 9.82 225.86
D4 Prefabricated lintels 0.00
Supply and installation of prefabricated door lintels (lintels
corresponding to POROTHERM).
Calculation per piece pcs 5 17.90 89.50
D5 External wall plastering 0.00
Plastering of the outer walls with coarse and fine cement-lime
mortar, lime plaster or gypsum plaster with spraying
of all the surfaces using cement slurry, chiselling away minor
uneven areas, filling in minor damages in the wall etc.
The scaffolding is included in a separate item.
Calculation per m² of plastered wall. m² 170.00 5.11 868.70
D6 Plastering of the internal walls 0.00
Coarse and fine plastering of the internal brick walls and also
partially of the concrete surfaces. Coarse plastering using cement-
lime M-5 class mortar, and fine plastering using lime plaster M-2.5
class with all required preparatory operations.
Calculation per m². m² 243.00 4.86 1,180.98
D7 Plastering ceilings 0.00
Coarse and fine plastering of ceilings. Coarse plastering using
cement-lime M-5 class mortar, and fine plastering using lime
plaster M-2.5 class with all required preparatory operations.
Calculation per m². m² 75.00 4.86 364.50
D8 Supply and installation of rubber studs 0.00
Supply and installation of floor mounted rubber studs acting as
doorstops.
Calculation per piece pcs 6.00 2.56 15.36
D9 Supply and installation of aluminium sills 0.00
Supply and installation of aluminium sills executed in L 40 x 40 mm
angle profile in areas where there is a difference of flooring type or
elevation.
The unit price includes fixing of the aluminium angle section to a
timber or aluminium door frame.
Calculation per piece of installed sill.
a) sill up to 1 m long pcs 2 7.16 14.32
b) sill between 1 and 1.5 m long pcs 1 10.74 10.74
D11 Cleaning of the structure 0.00
Cleaning of the structure, removal of rubble and other dirt 3 times
during construction of the structure.
Calculation per m² of net area m² 96.00 0.51 48.96
D12 Final cleaning of the structure m² 75.00 0.51 38.25

Final cleaning of the structure prior to the technical inspection


(washing of all glazed surfaces, detailed cleaning of floors, 0.00
ceramics, sanitary facilities etc. after completion of all the works).

TOTAL D: 6,180.38

58 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


E. INSULATION WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
E1 Horizontal and vertical waterproofing of the floors/socle
Execution of horizontal and vertical waterproofing of the ground 0.00
floor floors and socle.
The waterproofing consists of a cold bituminous coat and two
layers of 4 mm thick welded bituminous paper, with welded
overlaps of 10 cm.
The waterproofing strips must be 100 % welded to the base and to
each other.
The unit price shall include cleaning of any impurities from the
concrete base, application of a primer (Resitol) coat and welding of
the first and the second strip. The second strip must have the
overlaps offset by 50 % relative to the first one.
The lower base must be dry in compliance with regulations, as
evidenced by a measurement of relative humidity on the concrete
surface.
Calculation per m² of executed waterproofing.
a) horizontal waterproofing m² 96.00 11.15 1,070.40
b) vertical waterproofing m² 5.00 11.96 59.80
E2 Supply and placement of plastic foil 0.00
Supply and installation of plastic foil corresponding to Tervol
STOPAIR d = 0.25 mm thick, across extruded polystyrene foam
(XPS) and extruded polystyrene (EPS).
Select foil type chemically compatible with thermal insulation in
place.
Calculation per m² of executed foil, measured in plan view. m² 207.00 0.82 169.74
Supply and placement of thermal insulation in floor/socle
E3 0.00
layers
Supply and installation of EXTRUDED POLYSTYRENE FOAM
(XPS) with overall thickness of d= 4.0 cm
Thermal insulation covers the waterproofing in the ground floor
floors, and on the inside part of the socle towards facade walls, all
in compliance with the working design.
Calculation per m² of thermal insulation placed. m² 64.00 5.01 320.64
E4 Supply and installation of roof thermal insulation 0.00
Supply and installation of EXTRUDED POLYSTYRENE (EPS) of
overall thickness of d = 10.0 cm.
The thermal insulation covers the ceiling semi-precast floor slab
waterproofing.
Calculation per m² of thermal insulation placed. m² 118.00 4.86 573.48
E5 Thermal insulation of horizontal box-section gutter 0.00
Procurement, supply of material required and installation of
extruded polystyrene d = 5 cm in the horizontal gutter.
Calculation per m². m² 7.00 3.73 26.11
TOTAL E: 2,220.17

59 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


F. CARPENTRY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Concrete and reinforced concrete works related formwork is
included in the concrete and reinforced concrete works.
F1 Supply and placement of boards and laths in the gutter 0.00
Supply and installation of class II softwood boards and laths,
manufacture and placement of a timber channel in the horizontal
roof drainage gutter.
Clearance of the channel shall be 16x20cm.
Bottom of the channel shall be executed at 1% grade towards
outlets.
The boards and the laths should be impregnated to protect them
from rot and pests.
Calculation per m' of installed boards and laths. m' 37.00 6.03 223.11
F2 Supply and installation of timber 0.00
Supply and installation of 12x14 cm and 5x5 cm timber, as shims
between the semi-precast floor slab and the roofing structure.

The timber should be impregnated to protect it from rot and pests.

Calculation per m³ and m' of timber elements installed.

a) 12x14cm – wall plates m³ 1.00 332.34 332.34


b) 12x14cm - rafters m³ 2.00 332.34 664.68
c) 5x5cm – battens m' 146.00 1.18 172.28
F3 Mobile steel and timber scaffolding 0.00
Supply, transportation and moving, assembly and dismantling of
the scaffolding after completion of all the works, and removal of the
steel and timber scaffolding for masonry and painting works.
The scaffolding shall be up to 3.00 m tall.
It pertains to the works carried out in high spaces. pcs 1 28.12 28.12
F4 Prefabricated facade scaffolding 0.00
Execution of a prefabricated facade scaffolding with flooring and
railings at each floor level.
The unit price shall include delivery, assembly, dismantling and
removal of the facade scaffolding elements.
The scaffolding is used for execution of all the facade works
(bricklaying, rendering and plastering).
The scaffolding shall be up to 5.50 m tall.
Calculation per m² of vertical projection of the scaffolding. m² 276.00 2.05 565.80
TOTAL F: 1,986.33
G. SHEET METAL WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
All sheet metal flashings, gutters and similar items are
manufactured in 0.80 mm thick aluminium sheet except
downspouts and horizontal flashings which are executed in the
same sheet metal as the covering (flat, painted).
The unit price shall include supply of material, workshop
manufacturing, transport and site assembly, scaffolding, use of
cranes, gutter and downspout supports, connection of the
downspouts into
cast-iron piping, manufacture and installation of gable flashing
fixing elements, gutter and downspout connections.
Likewise, the unit price shall include supply and installation roofing
paper strip on all areas of contact of the zinc coated sheet metal
and concrete or other material, while in places of direct contact with
other types of metal, elastic soft band shall be inserted.

60 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


G1 Horizontal box-shaped gutter
Manufacture and installation of horizontal box-section gutters š =
26 cm wide of variable height, achieving gutter grade of approx.
0.5% toward its outlets.
A drip edge shall be executed along with the gutter, around the
reinforced concrete channel, in sheet metal, as well as the top
cover, while aluminium sheet shall be slipped 50 cm deep.
Total developed width of the sheet metal is 160 cm.
The unit price shall include execution of a 10 x 10 cm size, 40 cm
long side channel.
Calculation per m' of actually executed gutter and side channel.
a) zinc coated gutter m' 37.00 15.08 557.96
b) side channel pcs 2 4.91 9.82
G2 Deaerating tank 0.00
Manufacture and installation of deaerating tanks atop the
downspouts, size 30x30x20cm.
Calculation per piece. pcs 2 3.02 6.04
G3 Vertical roof drainage downspout 0.00
Manufacture and installation of 10x10 cm vertical downspout.
The vertical downspouts are designed in 2 locations.
The unit price shall include execution of connections to cast-iron
piping below, i.e. manufacture of seals, and manufacture of swan-
necks and connections to the gutter side channel.
Developed length of the swan-neck is 50 cm.
All shall be executed in flat painted sheet metal as structure cover.

Calculation per m' of actually executed downspout and swan-neck


and the lower seal piece.
a) vertical downspout m' 6.00 9.51 57.06
b) swan-neck pcs 4 4.70 18.80
c) lower seal pcs 4 5.88 23.52
G4 Drip edge and flashing 0.00
Manufacture and installation of painted sheet metal drip edge and
flashing, quality corresponding to Kalzip, at facade elements.
Drip edge and flashing of roofing inner side substructure shall be
executed.
Horizontal drip edge is approx. 50 cm wide, executed in painted
sheet metal matching facade colour, except flat and connected via
zinc coated steel hooks onto reinforced concrete roof cornice.
Developed width of the painted sheet metal flashing on one end is
approx. 40 cm, and approx. 70 cm at the other end.
The sheet metal shall be 0.8 mm thick.
Prior to installation of the sheet metal, self-adhesive foam band
shall be placed onto the substructure.
The unit price shall comprise manufacturing and installation of the
steel hooks at every 50 to 60 cm, supply of the self-adhesive
bituminised strip and its adhesive attachment, proper intertwining of
all the connections, welding the sheet metal and all accessories
and auxiliary material

Calculation per m' of actually executed drip edge. m' 50.00 9.82 491.00
Calculation per m' of actually executed flashing. m' 47.00 9.66 454.02
TOTAL G: 1,618.22

61 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


H. ROOFING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Fire resistant panels corresponding to Trimoterm SNV, consisting of
two moulded, bilaterally zinc coated (275 g/m²) and painted steel
sheets (of 0.6 mm standard thickness) with an insulation filling
consisting of non-flammable laminated mineral wool.
All the layers comprise a compact sandwich element providing
required load bearing capacity, impermeability and compactibility.
The mineral wool core of the panel provides excellent thermal and
sound insulation of the panel as well as high fire resistance.
The panels are up to 14m long.
H1 Covering of the entire structure roof 0.00
Covering of the entire structure roof using roofing panels
corresponding to Trimoterm SNV 120.
The panel consists of two bilaterally zinc coated painted steel
sheets, 0.6 mm thick, one with shallow profile and another with
deep (trapezoidal) profile.
The sheet metal is glued to the panel core comprising non-
flammable laminated mineral wool, class A1 (DIN 4102).
It comprises polyester based corrosion protection (standard
protection).
Colour of the sheet metal matches RAL palette, and is selected by
the design engineer.
All three layers comprise a compact 120 mm thick panel, providing
required load bearing capacity, impermeability and assembling
properties.
The roof shall be executed as double-pitched roof, with 6% grade
to both sides.
Calculation per m² of the roof area. m² 117.00 35.38 4,139.46
H2 Covering the roof ridge with sheet metal 0.00
Covering the ridge using metal sheet identical to the cover metal
sheet, 0.6 mm thick, just with flat sheet metal with no moulding.
Developed width of the sheet metal is 100 cm.
The unit price includes supply and insertion of bituminised rubber
foam seals into indentations of the cover sheet metal curvatures
and cutting the ridge sheet metal to fit the cover.
Calculation per m' of roof ridge covered m' 18.00 11.71 210.78
H3 Adjustment of the cover to the cornice flashing 0.00
Surcharge for adjustment of the metal sheet cover of the cornice
flashing.
Pertains to possible bending of edges of the sheet metal
"UPWARDS"
Calculation per m' of sheet metal cornice flashing. m' 51.00 0.56 28.56
TOTAL H: 4,378.80

62 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


I. JOINERY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
The 1st class oak veneer shall be used to manufacture doors,
since the doors shall be painted preserving growth rings visible.
The 1st class fir-spruce timber without growth rings shall be used to
manufacture door frames, since the door frames shall be painted
after installation.
Width of the door frame equals thickness of the wall.
The door frames must be delivered to the site impregnated, with a
moisture repellent coating applied to their outsides.
The unit price shall include supply of basic material and fixtures,
measure taking in situ, workshop manufacturing, delivery to the
site, fitting and adjustment at location of
installation and after the installation, supply and installation of
metal fittings selected by the design engineer, including cylinder
locks, keys and a doorstop.
Everything else according to joinery schematic layout and
directions of the supervising engineer and the design engineer.
Apart from the aforementioned elements, the unit price shall
include manufacturing and installation of two-sided trim selected by
the design engineer.
A ventilation grille shall be installed in the lower part of all toilet
doors.
4 mm thick OPTIFLOAT glass shall be used for glazing of the fixed
fanlight.
Glazing putty or permanently elastic sealant shall be used for
installation of glazing.
Joinery colour (leafs and door frame) shall be agreed upon with
the Client.
Everything is to be made according to joinery schematics.
Calculation per piece of manufactured and installed doors,
including fittings, locks, glazing, seals, fixing accessories and all
other labour, material and resources required for installation of the
joinery until it is fully functioning.

I1 Partition wall 0.00


Partition walls are executed in multilayered HPL laminate 14 mm
thick, with rounded edges and corners.
The partition is equipped with shock absorbers and plastic scratch
guards and self-closing fixtures.
An anodized aluminium profile shall be installed along the upper
outside wall in order to bind together the entire structure.
The partition walls are attached to the wall using aluminium fixtures
allowing fine adjustments.
The partition modules shall be raised from the floor by 150 mm
using aluminium posts with a plastic base.
On the bottom of the posts there shall be a screw used to adjust
stainless steel fixtures attaching it to the wall.
Partition wall size 40/225cm. Position g pcs 5 114.32 571.60

63 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
I2 Partition walls with doors
Partition walls are executed in multilayered HPL laminate 14 mm
thick, with rounded edges and corners.
The doors are equipped with shock absorbers and plastic scratch
guards and self-closing fixtures.
Elliptical stainless steel lock shall be built into the doors with no
parts projecting outside, and it shall have an occupied/free
indicator and an emergency opening system.
An anodized aluminium profile shall be installed along the upper
outside wall in order to bind together the entire structure.
The partition walls are attached to the wall using aluminium fixtures
allowing fine adjustments.
The partition modules shall be raised from the floor by 150 mm
using aluminium posts with a plastic base.
On the bottom of the posts there shall be a screw used to adjust
stainless steel fixtures attaching it to the floor.
Colour shall be selected by the design engineer.
Partition wall with door, size 107+165/225cm. Position a pcs 2 497.18 994.36
Partition wall with door, size 106/225cm Position b pcs 1 298.49 298.49
Partition wall with door, size 112+165/225cm. Position c pcs 1 510.99 510.99
Partition wall with door, size 110/225cm Position d pcs 1 309.79 309.79
Partition wall with door, size 114+165/225cm. Position e pcs 2 529.70 1,059.40
Partition wall with door, size 112/225cm Position f pcs 1 315.42 315.42
TOTAL I: 4,060.05
J. IRON METAL WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Iron metal works products consist of non-processed and cold
formed drawn sections. All frames have anchoring claws, and all
joints are welded.
Prior to installation, the metal products shall be cleaned of rust by
sandblasting and degreased, and two coats of epoxy-based paint
as corrosion protection shall be applied.
J1 Flashing supports
Procurement, supply of required material, manufacture and
installation of steel supports (girders) for installation of the flashing.

The supports shall be fixed by welding onto prepared steel plates


on the reinforced concrete roof cornice.
The supports are executed in 50x30x3mm cold formed sections.
The price includes procurement, supply and installation of required
materials, scaffolding, base paint coat 2x.
Calculated per m' of the supports installed. m' 100.00 7.87 787.00
J2 Frame and “coconut” doormat
Supply of material (stainless steel), manufacturing and installation
of the frame and the doormat.
The doormat frame size is 120 x 60 cm and it is executed in “L”
sections 30 x 30 x 3 mm with anchoring claws.
The doormat is “COCONUT” type and included in the unit price.
Calculation per piece of installed frame with the doormat. pcs 2 71.58 143.16
TOTAL J: 930.16

64 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


K. NONFERROUS METAL WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


GENERAL:
All the works must be performed skilfully and properly, with
appropriate quality material which must conform to existing
regulations and norms.
Prior to commencement of the works related to manufacturing on
nonferrous metal works, the contractor is required to inspect the
construction works completed, and if shortcomings which may
present an impediment are observed, that must be communicated
to the construction works contractor
in order to have the latter remove them.
All aluminium sections and products must be executed in high
quality and properly.
Contractor of these works is required to protect the works
performed by other contractors to prevent any damage occurring
due to performance of the works.
The contractor is also required to protect all the works from dirt,
and after completion of the works, the contractor is required to
remove all excess material and waste from the construction site.
Aluminium sections with a thermal break corresponding to
SCHUECO INTERNATIONAL type shall be used to execute the
nonferrous metal works.
The aluminium sections shall be executed in aluminium alloy Al Mg
Si 0.5, F220 strength up to 260 N/mm2.
The minimum thickness of the protective layer shall be 18 to 25
microns, and must comply with HRN.C.T7.234, 236, 226 and 228.

The unit price shall include supply of basic material and fixtures,
measure taking in situ, workshop manufacturing,
delivery to the site, fitting and adjustments in situ and after
installation, supply and installation of metal fittings as selected by
the design engineer with cylinder locks and keys and all the
trimmings.
Everything else according to metal works schematic layout and
directions of the supervising engineer and the design engineer.
Apart from the aforementioned, the unit price shall include
execution of workshop documents and submission of the
documents for review and approval of the design engineer.
Steel sections used for anchoring the aluminium partitions have at
least two coats of paint for protection.
Apart from the aforementioned, the unit price shall include
execution of workshop documents and submission of the
documents for review and approval of the design engineer.
Steel sections used for anchoring the aluminium partitions have at
least two coats of paint for protection.
Aluminium sheet and section fixing anchors shall be executed in
stainless steel.
Screws and other fixing material shall be executed in stainless
steel, aluminium or other anticorrosive material.
Corner pieces must be executed impeccably.
Areas which are especially sensitive to loss of impermeability must
be sealed using two-component putty of appropriate quality.
Doors and those windows that open must have rubber seals at the
edges.
All external doors must have built-in closers.
THERMOPLUS and OPTIFLOAT glass 4+16+4 mm insulation
glazing must be used for window glazing so that the thermal
conductivity coefficient is 1.6 W/m2K, while door glazing shall be
LAMISTAL 3+3+12+ LAMISTAL 3+3 insulation glazing.

Proper plastic elements shall be used to install the insulation


glazing.
Colour of the plastic coated aluminium metal works shall be
determined by the design engineer in agreement with the client.

65 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


Unit prices of all doors shall also include a rubber floor mounted
doorstop.
These technical conditions shall be appended by descriptions of
individual bill of quantity items and by quality control and assurance
programme.
The contractor must present certificate to prove that the aluminium
sections and the glazing comply with the conditions set, especially
in terms of thermal conductivity.
All shall be executed in compliance with nonferrous metal works
schematics, bill of quantities descriptions and detailed drawings.
Calculation shall be per piece of manufactured and installed
nonferrous metal works product, complete with all accessories,
No fittings, locks, glazing, seals, fixtures and other items required for
ITEM DESCRIPTION Unit Qty Unit Price Total EUR
installation of nonferrous metal works to their full functioning.
K1 One-leaf external door 100/210cm 0.00
One-leaf external door 100 cm wide and 210 cm tall, executed in
plastic coated aluminium sections with a thermal beak,
corresponding to SCHUECO INTERNATIONAL type.
The metal fittings shall be selected by the design engineer, and
include cylinder locks, handles and keys (corresponding to “WINK
HAUS” or “KABA”), and a floor mounted doorstop.
The door leafs shall have built-in closers corresponding to “GEZZE”
type.
Colour of the steel and metal works and design of the handles shall
be selected by the design engineer.
Calculation per piece. Position 1
a) right hand door pcs 2 403.92 807.84
b) left hand door pcs 1 403.92 403.92
K2 One-leaf external door 110/210cm 0.00
The door is executed in plastic coated aluminium sections with a
thermal break, corresponding to SCHUECO INTERNATIONAL
type, with 2 cm thick thermo panels.
The metal fittings shall be selected by the design engineer, and
include cylinder locks, handles and keys (corresponding to “WINK
HAUS” or “KABA”), and a floor mounted doorstop.
The door leafs shall have built-in closers corresponding to “GEZZE”
type.
Colour of the steel and metal works and design of the handles shall
be selected by the design engineer.
Calculation per piece. Position 1a
a) left hand door pcs 1 429.49 429.49
K3 Window 120/60cm 0.00
The windows are executed in plastic coated aluminium sections
with a thermal break, corresponding to SCHUECO
INTERNATIONAL type, with 4+16+4 mm insulating glazing.
Their size is 120x60cm.
The item includes window jambs, sashes, all the fittings and
insulation glazing.
The sashes tilt inward to open, and are operated via a Ventus
opening mechanism.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 2 pcs 15 189.18 2,837.70
K4 Window 60/60cm 0.00
The windows are executed in plastic coated aluminium sections
with a thermal break, corresponding to SCHUECO
INTERNATIONAL type, with 4+16+4 mm insulating glazing.
Their size is 60x60cm.
The item includes window jambs, sashes, all the fittings and
insulation glazing.
The sashes tilt inward to open, and are operated via a Ventus
opening mechanism.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 3 pcs 4 148.27 593.08

66 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
K5 Single-leaf internal door 90/210cm 0.00
One-leaf internal door 90 cm wide and 210 cm tall, executed in
plastic coated aluminium sections with a thermal beak,
corresponding to SCHUECO INTERNATIONAL type.
The metal fittings shall be selected by the design engineer, and
include cylinder locks, handles and keys (corresponding to “WINK
HAUS” or “KABA”), and a floor mounted doorstop.
The door leafs shall have built-in closers corresponding to “GEZZE”
type.
Colour of the steel and metal works and design of the handles shall
be selected by the design engineer.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 4
a) right hand door pcs 1 414.15 414.15
K6 Single-leaf internal door 70/210cm 0.00
One-leaf internal door 70 cm wide and 210 cm tall, executed in
plastic coated aluminium sections with a thermal beak,
corresponding to SCHUECO INTERNATIONAL type.
The metal fittings shall be selected by the design engineer, and
include cylinder locks, handles and keys (corresponding to “WINK
HAUS” or “KABA”), and a floor mounted doorstop.
The door leafs shall have built-in closers corresponding to “GEZZE”
type.
Colour of the steel and metal works and design of the handles shall
be selected by the design engineer.
Calculation per piece. Position 5
a) right hand door pcs 1 383.47 383.47
TOTAL K: 5,869.65
L. STONEWORK
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
L1 External window sills
Supply and installation artificial or natural stone window sills using
cement mortar.
The sills are 15 cm (external) and 25 cm wide (internal). The sill
must extend beyond the final facade layer by at least 3 to 3.5 cm.

The minimum length of the sill is width of the window plus 2 cm, i.e.
at least 62cm and 122cm.
The sills must be placed strictly horizontally viewed along their
length, with a transversal grade of 10 %.
Undersides of the sills must have a groove along the length to
prevent backflow of water.
After installation, the sills contact to the nonferrous metal works
need be cleaned and sealed with two-component permanently
elastic putty for exterior works.
The unit price shall include supply of the window sill with the drip
edge and polished exposed
surfaces, cement mortar and preparation of the surface it is applied
to, cleaning and sealing of the NF metal works joints, protection of
the sill and all other operations required for installation.

Calculation per piece of installed sills.


a) external window sills l = 60 cm pcs 4.00 10.84 43.36
external window sills l = 120 cm pcs 15.00 21.63 324.45
b) internal window sills l = 60 cm pcs 4.00 18.41 73.64
internal window sills l = 120 cm pcs 15.00 36.81 552.15
TOTAL L: 993.60

67 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


M. FLOOR AND WALL TILING
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
All floor and wall tiling are designed to be executed in the 1st class
ceramic tiles, 30 x 30 or 20 x 20 cm size, ground or rough top
surface in colour to be determined by the design engineer in
agreement with the client.
At joints of tiled floors and plastered walls a 10 cm tall socle shall
be executed in the same ceramic tiles.
Wall ceramic tiles shall be placed using appropriate adhesive onto
lime-cement mortar plastered walls.
In smaller premises (sanitary facilities etc.) 20 x 20 cm tiles shall
be used for floors and walls (of same quality, colour and production
lot).
Tiling system shall always be joint to joint, while the joint width shall
be agreed with the design engineer.
Floor ceramic tiles are laid in cement mortar or glued onto prepared
cement glazing using construction adhesive.
The unit price shall include supply of the basic and binding
material, laying and tuck pointing of the ceramic tiles using ready-
made
of PVC, mixture as selected
Al, brass by the
or chrome design
plated angle engineer,
and capsupply and
trimming,
installation
cleaning of the floors and the walls and all transportation.
The structure is divided into 7 zones according to drawing 02-03
and 02-04 ground floor plan. The zones are assigned colours which
apply to the ceramic tiles, all in agreement with the design engineer
or the client.

M1 External floor tiling 0.00


Tiling of the external floors using the 1st class exterior, safety tread
non-skid ceramic tiles comparable to FLOOR GRES cheramiche
BASIC, ceramic tile size 30 x 30 cm.
Safety tread ceramic tiles with special embossed structure and
safety tread rating R13, 30 x 30 cm size.
The tiles are placed in all main entrances where the design
provides that they shall be resistant to weather effects occurring in
climate characteristic to the construction area.
The item includes supply and installation of fitting tiles for the 15
cm tall socle, possessing the same properties as the tiles specified
above.
The item also includes procurement, supply and placement of self-
adhesive anti-slip strip on external entrance stairs.
The strip shall be placed in two parallel lines.
a) floor tiles m² 11.00 17.90 196.90
b) socle m' 11.00 3.32 36.52
c) anti-slip strip m' 8.00 2.05 16.40

68 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
M2 Floor and wall tiling
Tiling of the sanitary facilities premises’ floors, baby care premises’
floors and corridor floors using the 1st class safety tread non-skid
ceramic tiles comparable to FLOOR GRES cheramiche BASIC,
ceramic tile size 20 x 20 cm. (R9)
The ceramic tiles shall be placed in a single or two colour pattern in
compliance with tiling scheme for individual premises.
The ceramic tiles must be grinded, polished and skid safe (R9
safety tread rating), in colour selected by the design engineer.
Tiling with shall
The tiles jointsbe
no placed
wider than 2 to 3 mm. adhesive in compliance
in construction
with recommendations of manufacturer of the tiles.
The ceramic tiles shall be at least 8 mm thick.
Tiling system shall be joint to joint.
The unit price shall include supply of the basic and the binding
material, taking measurements in situ, installation, tuck pointing,
trimming and protection after the tiles are laid.
The item includes supply and installation of fitting tiles for the 15
cm tall socle, possessing the same properties as the tiles specified
above.
The item also includes tiling of walls to a height of 300 cm (of the
same quality, colour and production lot) around sanitary facilities’
elements.
a) floor tiles m² 64.00 16.36 1,047.04
b) wall tiles m² 210.00 16.36 3,435.60
c) socle m' 14.00 3.32 46.48
TOTAL M: 4,778.94

69 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


N. PAINTING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
N1 Skimming and painting the walls and the ceilings 0.00
Painting of the walls and the ceilings in all the premises where no
tiles are placed.
Painting shall be performed using factory ready-made lime based
paint corresponding to “POLIFLOR” conforming to the following
formula:
1) repair of minor uneven patches, 2) skimming all areas using a
special mixture corresponding to “POLIFIX”, 3) triple coat of paint
corresponding to “POLIFLOR”.
Paint hue shall be agreed with the design engineer and the client.
The unit price shall include all material, labour, tools, scaffolding,
transport, safety measures etc.
Calculation per m² of painted joinery. m² 124.00 2.25 279.00
N2 Iron metal works painting
Painting of iron metal works using epoxy based paint.
The unit price shall include cleaning of surfaces previously
protected against corrosion, one base coat of epoxy based paint,
application of putty and grinding of any uneven areas.
double coat of epoxy based paint, protection of other surfaces from
contamination, protection of finished paint from damage following
completion of painting and other auxiliary material.
The works shall be performed in compliance with regulation on
corrosion protection of steel structures.
Thickness of the coat shall be inspected by the supervising
engineer.
Paint colour shall be defined by the user in agreement with the
design engineer, using RAL colour chart only.
Calculation per m² of painted surface. m² 2.00 9.71 19.42
N3 Painting of entire joinery
Painting of entire joinery with frames and leafs/sashes.
Prior to painting, the doorframes shall be protected using protective
vapour permeable paint onto which putty shall be applied.

The surfaces should be ground after the putty dries up, and the first
coat of paint should be applied.
After the first coat of paint dries up, repeat application of putty over
any remaining uneven areas.
Subsequently, repeat grinding process and then apply the second
coat of paint.
The last coat of paint shall be executed in glossy paint, while the
paint colour shall be determined by the design engineer.
Leafs/sashes shall be sprayed using paint (Neolin) outlining growth
rings after the protective permeable nitro paint is applied.
The price includes all required auxiliary material.
Calculation per m² of painted joinery. m² 80.00 6.65 532.00
TOTAL N: 830.42

70 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


O. EXTERNAL PLASTERING WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

O1 Thermally insulated exterior wall facade


Procurement, supply of required material and execution of
thermally insulated facade corresponding to Demit facade, on the
main external walls of the structure, adhesively fixing 6cm thick m² 170.00 16.36 2,781.20
polystyrene to masonry block wall, along with double netting and
adhesive and a finish corresponding to BAUMIT Edelputz.
O2 Roof cornice finish 0.00
Roof cornice finish shall be acrylate protective-decorative plaster of
trowelled (rice) texture corresponding to “TERA-KRILA Z”.
Prior to execution of the external wall finish, all surfaces must be
clean, sound, dry, not frozen, free of formwork oils, at least 21 day
old.
Maximum departure of the wall from a straight in 4 m length ± 0.5
cm.
Prior to execution of the works it is wise to protect joinery, glazing,
metal.
All surfaces shall be impregnated using appropriate
MINERALKVARC GRUND (white or coloured) a day prior to
application of the final layer.
Calculation per m² of plastered cornice. m² 71.00 8.69 616.99
TOTAL O: 3,398.19

P. SUNLIGHT PROTECTION
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
P1 Aluminium laminas 0.00
Supply and installation of internal painted aluminium movable
laminas that may be drawn up or down.
Aluminium lamellas shall be executed at all sanitary facilities
premises windows.
The unit price shall include all basic and fixing material, top
trimming and operating strings.
Type and colour of movable aluminium laminas shall be determined
by the design engineer.
Calculation per piece of actually installed laminas.
a) 120x60cm size window. Position 2 pcs 15 14.06 210.90
b) 60x60cm size window. Position 3 pcs 4 14.06 56.24
TOTAL P: 267.14

R. OTHER
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
R1 Execution of technical documents set 1 255.65 255.65
Execution of technical documentation of as-built situation with
complete operating and maintenance instruction, submission to the
client (in 6 copies). The item pertains to the entire TCMC.
R2 Detailed final cleaning 0.00
Cleaning of the structure and its surrounding, removal of debris
and waste to a stockpile. Detailed final cleaning of floors, tiling etc.

To be executed immediately prior to acceptance of the structure.


Calculation per completely cleaned structure and its surroundings.
51.13
set 1.00 51.13
TOTAL R: 306.78

71 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


RECAPITULATION
No ITEM DESCRIPTION Total EUR
A. SITE PREPARATION AND EARTHWORKS 280.01
B. CONCRETE AND REINFORCED CONCRETE WORKS 9,226.27
C. REINFORCEMENT STEEL BENDING WORKS 0.00 0.00 3,286.47
D. MASONRY WORKS 0.00 0.00 6,180.38
E. INSULATION WORKS 0.00 0.00 2,220.17
F. CARPENTRY WORKS 0.00 0.00 1,986.33
G. SHEET METAL WORKS 0.00 0.00 1,618.22
H. ROOFING WORKS 0.00 0.00 4,378.80
I. JOINERY WORKS 0.00 0.00 4,060.05
J. IRON METAL WORKS 0.00 0.00 930.16
K. NONFERROUS METAL WORKS 0.00 0.00 5,869.65
L. STONEWORK 993.60
M. FLOOR AND WALL TILING 0.00 0.00 4,778.94
N. PAINTING WORKS 0.00 0.00 830.42
O. EXTERNAL PLASTERING WORKS 0.00 0.00 3,398.19
P. SUNLIGHT PROTECTION 0.00 0.00 267.14
R. OTHER 0.00 0.00 306.78
TOTAL 4: 50,611.58

72 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


5. STRUCTURE 2.9. SANITARY AND WATER FACILITIES FOR MEN & JANITOR
A. SITE PREPARATION AND EARTHWORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Excavation of humus material and basic backfill are addressed by
Roads design, i.e. the entire TCMC plateau. A basic backfill is
designed for the plateau only, with no subbase and asphalt, i.e.
approx. 40cm below finished pavement.
All the excavation is designed in semi-solid rock soils, where partial
explosive blasting is necessary, and the remaining excavation is
performed directly by machinery, “B” category soil.
Excavated material of compaction module Ms = 80 MN/m² shall be
used for backfill in layers after execution of all the foundations (to
the elevation specified).
All calculations of the excavation, backfill and removal of soil shall
be performed for compacted material. The excavated material shall
be disposed of 25 m away,
since it shall be reused for backfilling around the foundations.
The excavation shall be performed 95 % by machinery and 5 % by
hand.
A1 Staking out of the structure 0.00
The item comprises all works related to staking out of the structure
including installations; all design to site (and vice versa) data
transfer measurements; setup and maintenance of markers and
1.00 51.13 51.13
chainage markers on the site from commencement of the works
until acceptance of all the works by the Client and execution of an lump
as-built survey. sum
A2 Foundation strip excavation 0.00
Excavation of the strip foundation in “B” category soil, strip width 40
cm, excavation depth up to 200 cm.The excavation shall be
performed 95% by machinery and 5 % by hand.
Calculation per bank m³ of the excavation. m³ 15.00 1.79 26.85
A3 Grading of the bottom of the excavation 0.00
Coarse and fine grading of the bottom of the excavation with
simultaneous excavation of 0.03 m³ / m². The grading shall be
performed to ± 1 cm accuracy.
Calculation per m² of the material excavated. m2 21.00 0.51 10.71
A4 Backfilling the material below the ground floor 0.00
Backfilling material, spreading, compacting and levelling the 10 cm
deep backfilled layer to below the ground floor.
Use the excavated material for the backfilling.
Backfilling shall be performed to the layer specified in item 1.5.
Compacting shall be executed using the same compacting module
as applied at the plateau, i.e. Ms =80 to 100 KN/m².
Levelling shall be performed to +/-2 cm accuracy.
Calculation per m³ of the compacted backfill executed. m³ 6.00 1.43 8.58
A5 Crushed stone or gravel layer 0.00

Delivery and placement of crushed stone or gravel, and backfilling,


spreading and grading a 15 cm deep layer below floor of the entire
structure, and in a 10 cm layer at the strip foundations.

The grading shall be performed to +/- 2 cm accuracy.


Calculation per m³ of the compacted material placed. m³ 11.00 10.74 118.14
A6 Disposal of excess material
The works include disposal of excess humus material, excess
excavated material and all waste material, transportation from the
excavation site to a disposal site, including loading, offloading,
spreading and grading.
The contractor is required to provide transport within the
construction site itself and on public transport routes.
Within the unit price, the contractor is responsible to find a disposal
site, provide a disposal site improvement plan with all required
approvals (of the supervising body, the design engineer and the
Client) and to improve the disposal site.
Calculation per bank m³ of the material removed. m³ 9.00 3.07 27.63
TOTAL A: 243.04

73 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


B. CONCRETE AND REINFORCED CONCRETE WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Concrete strength is defined by design of the structure.
Each reinforced concrete element item is defined by structural
analysis, reinforcing plan and the bill of quantities’ items, and has
compressive strength class (C) assigned to it. Apart from the
concrete compressive strength marking, the design may present
special demands

During construction of the reinforced concrete structure it is


necessary to sample concrete and deliver the samples to an
authorized laboratory for certification. The samples collected in a
concrete plant are not relevant due to possibility of subsequent
addition of water in order to reduce its strength for transport.

Prior to concreting, timber formwork should be thoroughly cleaned,


moistened, while smooth formwork should be oiled. Also,
measurements and workmanship should be checked. The
formwork may be removed only after the concrete poured attains
appropriate strength, after an order issued by the supervising
engineer.
B1 Blinding concrete beneath the strip foundation C12/15 0.00
Casting of a weak blinding concrete base below the strip
foundation, C12/15 class compressive strength, d = 5 cm thick.
The item includes all required works, material and resources.
Calculation per m³ of concrete poured. m³ 1.00 76.69 76.69
B2 Blinding concrete below all ground floor premises C12/15 0.00
All as item 2.1, except below the strip foundations and the
foundation beams.
Blinding concrete is 5 cm deep.
Calculation per m³ of concrete poured. m³ 3.00 76.69 230.07
Supply and pouring of concrete in concrete strip foundations
B3 0.00
C25/30
Supply and pouring of concrete in concrete strip foundations
beneath walls, C25/30 compressive strength class concrete.
The strip foundations comprise cross-section 40 x 80 cm.
Calculation per m³ of concrete poured. m³ 17.00 81.81 1,390.77
B4 Reinforced concrete floor slab C25/30 0.00
Supply and placement of concrete in reinforced concrete floor slab,
d = 12 cm thick, C25/30 class.
The concrete slab is divided by concreting joints or cutting within 48
hours after concreting into 6.0 x 6.0 m fields.
Upper surface of the concrete base is executed at a grade towards
drainage gratings.
The top surface must be completely level and smooth as it
supports waterproofing.
The concrete must be cured using a curing system. The unit price
shall include supply and placement of 0.2 mm thick PE foil.
Reinforcing steel of the concrete base shall be executed in
compliance with the working construction design.
Calculation per m³ of concrete poured.
a) concrete m3 9.00 81.81 736.29
b) surcharge for execution of the joints per m' m' 9.00 4.60 41.40
c) surcharge for the surface processing m² 79.00 2.56 202.24
Concreting of vertical reinforced concrete circular beams
B5 0.00
C25/30
Concreting of reinforced concrete vertical circular beams using C
25/30 compressive strength concrete
Calculation per m³ of concrete poured.
a) concrete m3 3.00 81.81 245.43
b) formwork m² 18.00 14.32 257.76

74 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Concreting of horizontal reinforced concrete circular beams
B6 0.00
C25/30
Supply and pouring of concrete of the horizontal reinforced
concrete circular beams, C 25/30 compressive strength concrete
Calculation per m³ of concrete poured.
a) concrete m3 4.00 81.81 327.24
b) formwork m² 12.00 13.29 159.48
B7 Concreting of the reinforced concrete roof slab 0.00
Supply and placement of concrete in reinforced concrete floor slab
(cantilever), d = 12 cm thick, C25/30 class.
Concreting of the heels is tied to concreting of the foundation
beams and the strip foundations.
Calculation per m³ of concrete poured.
a) concrete m3 3.00 81.81 245.43
b) formwork m² 26.00 7.16 186.16
B8 Concreting of reinforced concrete roof cornice 0.00
Supply and placement of concrete in reinforced concrete roof
cornice, d = 12 cm thick, C25/30 class.
Calculation per m³ of concrete poured.
a) concrete m3 4.00 81.81 327.24
b) formwork m² 62.00 5.11 316.82
B9 Cement screed 0.00
Supply and placement of material, execution of cement screed with
light reinforcing, d = 4 to 7 cm thick.
Executed atop thermal insulation on the floor of the ground floor.
The unit price shall include cleaning of the surface, supply and
placement of 0.02 mm thick PVC foil, supply and placement of a
reinforcing mesh,
execution of glazing to trowel finish, and maintenance of the
glazing.
The cement glazing reinforcing shall be O-131 mesh.
Calculation per m² of executed cement screed.
a) cement screed below ceramic finish d = 5 cm m² 56.00 8.03 449.68
a) cement screed below ceramic finish d = 6 cm m² 6.00 8.69 52.14
B10 Floor structure (ceiling) 0.00
Supply of elements, installation and bracing of the semi-precast
floor structure, 16+5 cm, pouring of concrete and installation of
reinforcing steel into the compressive slab, using C 25/30
compressive strength concrete and B 500B reinforcing steel. The
price shall include manufacturing of bracing beams perpendicular
to the semi-precast structure beams.

Calculation per m² m² 62.00 30.93 1,917.66


Supply and pouring of concrete into reinforced concrete
B11 0.00
compressive slab C25/30
Supply and placement of concrete in reinforced concrete
compressive slab C25/30 concrete compressive strength. The
concrete is poured atop semi-precast floor structure. The semi-
precast floor structure must be cleaned and properly moistened
with water prior to concreting to prevent concrete thermal stress.
Reinforcing steel is the same.
Calculation per m3 of concrete poured. m³ 2.00 92.03 184.06
B12 Concreting sidewalks around the structure
Concreting of the sidewalk using C25/30 compressive strength
concrete 12 cm thick and simultaneous execution of concrete
screed and gravel subbase d = 10 cm. Expansion joints shall be
executed in the concrete at every 2m². The sidewalk shall be
executed at a grade sloping away from the structure.
Calculation in m². m² 44.00 10.74 472.56
TOTAL B: 7,819.12

75 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


C. REINFORCEMENT STEEL BENDING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Reinforcing steel must be placed securely and professionally in
compliance with applicable regulations and professional rules.
Size, shape and position of the reinforcing steel are defined in
reinforcing steel plans, contained in the design.
The reinforcing steel bending, extending and installation works
must conform to applicable regulations.
C1 Concrete reinforcement 0.00
Supply, manufacturing and installation of concrete reinforcement in
compliance with the steel reinforcing design.
This item pertains to standard part of the structure only – without
the prefabricated reinforced concrete elements.
The unit price shall include straightening, cutting, bending, 100%
binding and placement in the structural elements.
The reinforcing steel must be clean of rust and any grease.
The reinforcing steel must conform to a quality control and
assurance programme, and the contractor is required to supply test
samples in compliance with the programme as well as
manufacturer certificates supplied to the site with each delivery.
Calculation per kg of the reinforcing steel placed.
a) ribbed reinforcing steel B 500B kg 3,100.00 0.69 2,139.00
b) reinforcing steel mesh B 500B kg 818.00 0.69 564.42
TOTAL C: 2,703.42
D. MASONRY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:

The unit price includes all basic and binding material, anchors,
labour, tools, transport, scaffolding, various types of protection etc.

The unit price shall include anchoring of the outer walls using 8 mm
diameter concrete steel using 2 anchors in every second row.

Anchoring holes shall be drilled to 12 mm diameter at a 15° angle


for at least 150 mm.
The holes shall be dusted and moistened, filled with Tricosal
sealing mortar and an anchor shall be placed.
Overall length of the anchors is 55 cm.
Load bearing and partition wall also need be bound by brickwork
bonding.
D1 External wall construction 0.00
Supply of materials and construction of 30 cm thick outer walls
using POROTHERM type 30 S PLUS or corresponding brick,
brickwork height up to 4.50 m.
The works shall be performed using cement-lime mortar
M-100.
Pertains to all outer walls.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
The working scaffolding is calculated within a separate carpentry
works item.
The walls shall be executed with 2 faces.
Calculation per m³ of executed wall. m³ 38.00 69.02 2,622.76
D2 Construction of internal walls 0.00
Supply of materials and construction of 20 cm thick internal walls
using POROTHERM type 20-50 PROFI or corresponding brick,
brickwork height up to 4.00 m.
The works shall be performed using cement-lime mortar M-100.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works.
Calculation per m³ m³ 5.00 71.07 355.35

76 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
D3 Construction of internal walls 0.00
Supply of materials and construction of 12 cm thick internal walls
using POROTHERM type 12-50 PROFI or corresponding brick,
brickwork height up to 4.00 m.
The works shall be performed using cement-lime mortar M-100.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works.
Calculation per m² m² 9.00 11.35 102.15
D4 Construction of internal partition walls 0.00
Supply of materials and construction of 10 cm thick internal
partition walls using POROTHERM type 10 PROFI or
corresponding brick, brickwork height up to 4.00 m.
The works shall be performed using cement-lime mortar M-100.
The unit price shall include supply of the bricks, bricklaying with
100% sealed with mortar, preparation of the mortar, all internal
transports, curing during and after the works.
Bricklaying scaffolding is included in carpentry works.
Calculation per m² m² 6.00 9.82 58.92
D5 Prefabricated lintels 0.00
Supply and installation of prefabricated door lintels (lintels
corresponding to POROTHERM).
Calculation per piece pcs 4 17.90 71.60
D6 External wall plastering 0.00
Plastering of the outer walls with coarse and fine cement-lime
mortar, lime plaster or gypsum plaster with spraying
of all the surfaces using cement slurry, chiselling away minor
uneven areas, filling in minor damages in the wall etc.
The scaffolding is included in a separate item.
Calculation per m² of plastered wall. m² 146.00 5.11 746.06
D7 Plastering of the internal walls 0.00
Coarse and fine plastering of the internal brick walls and also
partially of the concrete surfaces. Coarse plastering using cement-
lime M-5 class mortar, and fine plastering using lime plaster M-2.5
class with all required preparatory operations.
Calculation per m². m² 182.00 4.86 884.52
D8 Plastering ceilings 0.00
Coarse and fine plastering of ceilings. Coarse plastering using
cement-lime M-5 class mortar, and fine plastering using lime
plaster M-2.5 class with all required preparatory operations.
Calculation per m². m² 61 4.86 296.46
D9 Supply and installation of rubber studs 0.00
Supply and installation of floor mounted rubber studs acting as
doorstops.
Calculation per piece pcs 3 2.56 7.68
D10 Supply and installation of aluminium sills 0.00
Supply and installation of aluminium sills executed in L 40 x 40 mm
angle profile in areas where there is a difference of flooring type or
elevation.
The unit price includes fixing of the aluminium angle section to a
timber or aluminium door frame.
Calculation per piece of installed sill. 0.00
a) sill up to 1 m long pcs 2 7.16 14.32
D12 Cleaning of the structure 0.00
Cleaning of the structure, removal of rubble and other dirt 3 times
during construction of the structure.
Calculation per m² of gross area m² 79 0.51 40.29
D13 Final cleaning of the structure 0.00

Final cleaning of the structure prior to the technical inspection


(washing of all glazed surfaces, detailed cleaning of floors,
ceramics, sanitary facilities etc. after completion of all the works).

Calculation per m² of net area m² 61.00 0.51 31.11


TOTAL D: 5,231.22

77 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


E. INSULATION WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
E1 Horizontal and vertical waterproofing of the floors/socle
Execution of horizontal and vertical waterproofing of floors below
the outer walls executed as in item E1.
The waterproofing is executed on the top surface of the socle, and
consists of a cold bituminous coat and two layers of 4 mm thick
welded bituminous paper, with welded overlaps 10 cm wide.
On the inside, the strips must remain wider to accommodate the
required overlap and bond to vertical wall waterproofing.
The waterproofing strips must be 100 % welded to the base and to
each other.
The unit price shall include cleaning of any impurities from the
concrete base, application of a primer (Resitol) coat and welding of
the first and the second strip.
The second strip must have the overlaps offset by 50 % relative to
the first one.
The lower base must be dry in compliance with regulations, as
evidenced by a measurement of relative humidity on the concrete
surface.
Calculation per m² of executed waterproofing.
a) horizontal waterproofing m² 79.00 11.15 880.85
b) vertical waterproofing m² 4.00 11.96 47.84
E2 Supply and placement of plastic foil 0.00
Supply and installation of plastic foil corresponding to Tervol
STOPAIR d = 0.25 mm thick, across extruded polystyrene foam
(XPS) and extruded polystyrene (EPS).
Select foil type chemically compatible with thermal insulation in
place.
Calculation per m² of executed foil, measured in plan view. m² 180.00 0.82 147.60
Supply and placement of thermal insulation in floor/socle
E3 0.00
layers
Supply and installation of EXTRUDED POLYSTYRENE FOAM
(XPS) with overall thickness of d= 4.0 cm
Thermal insulation covers the waterproofing in the ground floor
floors, and on the inside part of the socle towards facade walls, all
in compliance with the working design.
Calculation per m² of thermal insulation placed. m² 56.00 5.01 280.56
E4 Supply and installation of roof thermal insulation 0.00
Supply and installation of EXTRUDED POLYSTYRENE (EPS) of
overall thickness of d = 10.0 cm.
The thermal insulation covers the ceiling semi-precast floor slab
waterproofing.
Calculation per m² of thermal insulation placed. m² 101.00 4.86 490.86
E5 Thermal insulation of horizontal box-section gutter 0.00
Procurement, supply of material required and installation of
extruded polystyrene d = 5 cm in the horizontal gutter.
Calculation per m². m² 6.00 3.73 22.38
TOTAL E: 1,870.09

78 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


F. CARPENTRY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Formwork of the prefabricated reinforced concrete structures is
included in the reinforced concrete assembly works.
Formwork of the remaining concrete and reinforced concrete
elements is included in unit prices of those items and comprised
within the concrete and reinforced concrete works.
F1 Supply and placement of boards and laths in the gutter 0.00
Supply and installation of class II softwood boards and laths,
manufacture and placement of a timber channel in the horizontal
roof drainage gutter.
Clearance of the channel shall be 24 x 20 cm.

Bottom of the channel shall be executed at 1% grade towards


outlets.
The boards and the laths should be impregnated to protect them
from rot and pests.
Calculation per m' of installed boards and laths. m' 30.00 6.03 180.90
F2 Supply and installation of timber 0.00
Supply and installation of 12x14 cm and 5x5 cm timber, as shims
between the semi-precast floor slab and the roofing structure.

The timber should be impregnated to protect it from rot and pests.

Calculation per m³ and m' of timber elements installed.


a) 12x14cm – wall plates m³ 1.00 332.34 332.34
b) 12x14cm - rafters m³ 1.00 332.34 332.34
c) 5x5cm – battens m' 121.00 1.18 142.78
F3 Mobile steel and timber scaffolding 0.00
Supply, transportation and moving, assembly and dismantling of
the scaffolding after completion of all the works, and removal of the
steel and timber scaffolding for masonry and painting works.
The scaffolding shall be up to 3.0 m tall.
It pertains to the works carried out in high spaces. pcs 1 28.12 28.12
F4 Prefabricated facade scaffolding 0.00
Execution of a prefabricated facade scaffolding with flooring and
railings at each floor level.
The unit price shall include delivery, assembly, dismantling and
removal of the facade scaffolding elements.
The scaffolding is used for execution of all the facade works
(bricklaying, rendering and plastering).
The scaffolding shall be up to 5.5 m tall.
Calculation per m² of vertical projection of the scaffolding. m² 267.00 2.05 547.35
TOTAL F: 1,563.83

79 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


G. SHEET METAL WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
All sheet metal flashings, gutters and similar items are
manufactured in 0.55 mm thick zinc coated (hot-dipped) sheet
metal except downspouts and horizontal flashings which are
executed in the same sheet metal as the covering (flat, painted).
The unit price shall include supply of material, workshop
manufacturing, transport and site assembly, scaffolding, use of
cranes, supports of gutters and downspouts, connection of the
downspouts to cast-iron piping, manufacturing and installation of
gable flashing fixing elements, gutter and downspout connections.

Likewise, the unit price shall include supply and installation roofing
paper strip on all areas of contact of the zinc coated sheet metal
and concrete or other material, while in places of direct contact with
other types of metal, plastic soft band shall be inserted.

G1 Horizontal box-shaped gutter 0.00


Manufacture and installation of zinc coated sheet metal horizontal
box-section gutters š = 26 cm wide of variable height, achieving
gutter grade of approx. 1% toward its outlets.
A drip edge shall be executed along with the gutter, around the
reinforced concrete channel, in sheet metal, as well as the top
cover, while zinc coated sheet metal shall be slipped 50 cm deep.

Total developed width of the sheet metal is 160 cm.


The unit price shall include execution of a 12.5 cm diameter and 30
cm long side channel at the bottom.
Calculation per m' of actually executed gutter and side channel.
a) zinc coated gutter m' 30.00 15.08 452.40
b) side channel pcs 2 2.86 5.72
G2 Deaerating tank
Manufacture and installation of deaerating tanks atop the
downspouts, size 30x30x20cm.
Calculation per piece. pcs 2.00 3.02 6.04
G3 Vertical roof drainage downspout 0.00
Manufacturing and installation of water drainage downspout, 12.5
cm in diameter.
The downspouts are designed at 6 locations, i.e. 3 locations at
each side of the structure.
The unit price shall include execution of connections to cast-iron
piping below, i.e. manufacture of seals, and manufacture of swan-
necks and connections to the gutter side channel.
Developed length of the swan-neck is 50 cm.
All shall be executed in flat painted sheet metal as structure cover.

Wall mounting clamps shall be placed at every 1m' of height.


Calculation per m' of actually executed downspout and swan-neck
and the lower seal piece.
a) vertical downspout m' 20.00 9.51 190.20
b) swan-neck pcs 4 4.70 18.80
c) lower seal pcs 4 5.88 23.52

80 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
G4 Drip edge and flashing 0.00
Manufacture and installation of painted sheet metal drip edge and
flashing, quality corresponding to Kalzip, at facade elements.
Drip edge and flashing of roofing inner side substructure shall be
executed.
Horizontal drip edge is approx. 50 cm wide, executed in painted
sheet metal matching facade colour, except flat and connected via
zinc coated steel hooks onto reinforced concrete roof cornice.
Developed width of the painted sheet metal flashing on one end is
approx. 35 cm, and approx. 65 cm at the other end.
Developed width of the painted sheet metal in the horizontal line is
25 cm and in the vertical line it is 60 cm.
The sheet metal shall be 0.8 mm thick.
Prior to installation of the sheet metal, self-adhesive foam band
shall be placed onto the substructure.
The unit price shall comprise manufacturing and installation of the
steel hooks at every 50 to 60 cm, supply of the self-adhesive
bituminised strip and its adhesive attachment, proper intertwining of
all the connections, welding the sheet metal and all accessories
and auxiliary material
Calculation per m' of actually executed drip edge. m' 45.00 9.92 446.40
Calculation per m' of actually executed flashing. m' 41.00 9.41 385.81
TOTAL G: 1,528.89

81 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


H. ROOFING WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Fire resistant panels corresponding to Trimoterm SNV, consisting of
two moulded, bilaterally zinc coated (275 g/m²) and painted steel
sheets (of 0.6 mm standard thickness) with an insulation filling
consisting of non-flammable laminated mineral wool.
All the layers comprise a compact sandwich element providing
required load bearing capacity, impermeability and compactibility.
The mineral wool core of the panel provides excellent thermal and
sound insulation of the panel as well as high fire resistance.
The panels are up to 14 m long.
H1 Covering of the entire structure roof 0.00
Covering of the entire structure roof using roofing panels
corresponding to Trimoterm SNV 120.
The panel consists of two bilaterally zinc coated painted steel
sheets, 0.6 mm thick, one with shallow profile and another with
deep (trapezoidal) profile.
The sheet metal is glued to the panel core comprising non-
flammable laminated mineral wool, class A1 (DIN 4102).
It comprises polyester based corrosion protection (standard
protection).
Colour of the sheet metal matches RAL palette, and is selected by
the design engineer.
All three layers comprise a compact 120 mm thick panel, providing
required load bearing capacity, impermeability and assembling
properties.
The roof shall be executed as double-pitched roof, with 6% grade
to both sides.
Calculation per m² of the roof area. m² 97.00 35.48 3,441.56
H2 Covering the roof ridge with sheet metal 0.00
Covering the ridge using metal sheet identical to the cover metal
sheet, 0.6 mm thick, just with flat sheet metal with no moulding.
Developed width of the sheet metal is 100 cm.
The unit price includes supply and insertion of bituminised rubber
foam seals into indentations of the cover sheet metal curvatures
and cutting the ridge sheet metal to fit the cover.
Calculation per m' of roof ridge covered m' 15.00 11.71 175.65
H3 Adjustment of the cover to the cornice flashing 0.00
Surcharge for adjustment of the metal sheet cover of the cornice
flashing.
Pertains to possible bending of edges of the sheet metal
"UPWARDS"
Calculation per m' of sheet metal cornice flashing. m' 45.00 0.56 25.20
TOTAL H: 3,642.41

82 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


I. JOINERY WORKS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
The 1st class oak veneer shall be used to manufacture doors,
since the doors shall be painted preserving growth rings visible.
The 1st class fir-spruce timber without growth rings shall be used to
manufacture door frames, since the door frames shall be painted
after installation.
Width of the door frame equals thickness of the wall.
The door frames must be delivered to the site impregnated, with a
moisture repellent coating applied to their outsides.
The unit price shall include supply of basic material and fixtures,
measure taking in situ, workshop manufacturing, delivery to the
site, fitting and adjustment at location of
installation and after the installation, supply and installation of
metal fittings selected by the design engineer, including cylinder
locks, keys and a doorstop.
Everything else according to joinery schematic layout and
directions of the supervising engineer and the design engineer.
Apart from the aforementioned elements, the unit price shall
include manufacturing and installation of two-sided trim selected by
the design engineer.
A ventilation grille shall be installed in the lower part of all toilet
doors.
4 mm thick OPTIFLOAT glass shall be used for glazing of the fixed
fanlight.
Glazing putty or permanently elastic sealant shall be used for
installation of glazing.
Joinery colour (leafs and door frame) shall be agreed upon with the
Client.
Everything is to be made according to joinery schematics.
Calculation per piece of manufactured and installed doors,
including fittings, locks, glazing, seals, fixing accessories and all
other labour, material and resources required for installation of the
joinery until it is fully functioning.
I1 Partition wall 0.00
Partition walls are executed in multilayered HPL laminate 14 mm
thick, with rounded edges and corners.
The partition is equipped with shock absorbers and plastic scratch
guards and self-closing fixtures.
An anodized aluminium profile shall be installed along the upper
outside wall in order to bind together the entire structure.
The partition walls are attached to the wall using aluminium fixtures
allowing fine adjustments.
The partition modules shall be raised from the floor by 150 mm
using aluminium posts with a plastic base.
On the bottom of the posts there shall be a screw used to adjust
stainless steel fixtures attaching it to the wall.
Partition wall size 40/225cm. Position g pcs 5 114.32 571.60

83 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
I2 Partition walls with doors 0.00
Partition walls are executed in multilayered HPL laminate 14 mm
thick, with rounded edges and corners.
The doors are equipped with shock absorbers and plastic scratch
guards and self-closing fixtures.
Elliptical stainless steel lock shall be built into the doors with no
parts projecting outside, and it shall have an occupied/free
indicator and an emergency opening system.
An anodized aluminium profile shall be installed along the upper
outside wall in order to bind together the entire structure.
The partition walls are attached to the wall using aluminium fixtures
allowing fine adjustments.
The partition modules shall be raised from the floor by 150 mm
using aluminium posts with a plastic base.
On the bottom of the posts there shall be a screw used to adjust
stainless steel fixtures attaching it to the floor.
Colour shall be selected by the design engineer.
Partition wall with door, size 92+165/225cm. Position a pcs 2 419.72 839.44
Partition wall with door, size 90/225cm Position b pcs 1 253.45 253.45
Partition wall with door, size 114+165/225cm. Position c pcs 2 529.70 1,059.40
Partition wall with door, size 112/225cm Position d pcs 1 315.42 315.42
Partition wall with door, size 114+165/225cm. Position e pcs 2 510.99 1,021.98
Partition wall with door, size 112/225cm Position f pcs 1 315.42 315.42
TOTAL I: 4,376.71

J. IRON METAL WORKS


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
GENERAL:
Iron metal works products consist of non-processed and cold
formed drawn sections. All frames have anchoring claws, and all
joints are welded.
Prior to installation, the metal products shall be cleaned of rust by
sandblasting and degreased, and two coats of epoxy-based paint
as corrosion protection shall be applied.
J1 Flashing supports 0.00

Procurement, supply of required material, manufacture and


installation of steel supports (girders) for installation of the flashing.

The supports shall be fixed by welding onto prepared steel plates


on the reinforced concrete roof cornice.
The supports are executed in 50x30x3mm cold formed sections.
The price includes procurement, supply and installation of required
materials, scaffolding, base paint coat 2x.
Calculated per m' of the supports installed. m' 87.00 7.87 684.69
J2 Frame and “coconut” doormat
Supply of material (stainless steel), manufacturing and installation
of the frame and the doormat.
The doormat frame size is 120 x 60 cm and it is executed in “L”
sections 30 x 30 x 3 mm with anchoring claws.
The doormat is “COCONUT” type and included in the unit price.
Calculation per piece of installed frame with the doormat. pcs 1 71.58 71.58
TOTAL J: 756.27

84 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


K. NONFERROUS METAL WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

GENERAL:
All the works must be performed skilfully and properly, with
appropriate quality material which must conform to existing
regulations and norms.
Prior to commencement of the works related to manufacturing on
nonferrous metal works, the contractor is required to inspect the
construction works completed, and if shortcomings which may
present an impediment are observed, that must be communicated
to the construction works contractor
in order to have the latter remove them.
All aluminium sections and products must be executed in high
quality and properly.
Contractor of these works is required to protect the works
performed by other contractors to prevent any damage occurring
due to performance of the works.
The contractor is also required to protect all the works from dirt,
and after completion of the works, the contractor is required to
remove all excess material and waste from the construction site.
Aluminium sections with a thermal break corresponding to
SCHUECO INTERNATIONAL type shall be used to execute the
nonferrous metal works.
The aluminium sections shall be executed in aluminium alloy Al Mg
Si 0.5, F220 strength up to 260 N/mm2.
The minimum thickness of the protective layer shall be 18 to 25
microns, and must comply with HRN.C.T7.234, 236, 226 and 228.

The unit price shall include supply of basic material and fixtures,
measure taking in situ, workshop manufacturing,
delivery to the site, fitting and adjustments in situ and after
installation, supply and installation of metal fittings as selected by
the design engineer with cylinder locks and keys and all the
trimmings.
Everything else according to metal works schematic layout and
directions of the supervising engineer and the design engineer.
Apart from the aforementioned, the unit price shall include
execution of workshop documents and submission of the
documents for review and approval of the design engineer.
Steel sections used for anchoring the aluminium partitions have at
least two coats of paint for protection.
Apart from the aforementioned, the unit price shall include
execution of workshop documents and submission of the
documents for review and approval of the design engineer.
Steel sections used for anchoring the aluminium partitions have at
least two coats of paint for protection.
Aluminium sheet and section fixing anchors shall be executed in
stainless steel.
Screws and other fixing material shall be executed in stainless
steel, aluminium or other anticorrosive material.
Corner pieces must be executed impeccably.
Areas which are especially sensitive to loss of impermeability must
be sealed using two-component putty of appropriate quality.
Doors and those windows that open must have rubber seals at the
edges.
All external doors must have built-in closers.
THERMOPLUS and OPTIFLOAT glass 4+16+4 mm insulation
glazing must be used for window glazing so that the thermal
conductivity coefficient is 1.6 W/m2K, while door glazing shall be
LAMISTAL 3+3+12+ LAMISTAL 3+3 insulation glazing.
Proper plastic elements shall be used to install the insulation
glazing.

85 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


Colour of the plastic coated aluminium metal works shall be
determined by the design engineer in agreement with the client.
Unit prices of all doors shall also include a rubber floor mounted
doorstop.
These technical conditions shall be appended by descriptions of
individual bill of quantity items and by quality control and assurance
programme.
The contractor must present certificate to prove that the aluminium
sections and the glazing comply with the conditions set, especially
in terms of thermal conductivity.
All shall be executed in compliance with nonferrous metal works
schematics, bill of quantities descriptions and detailed drawings.
Calculation shall be per piece of manufactured and installed
nonferrous metal works product, complete with all accessories,
fittings, locks, glazing, seals, fixtures and other items required for
installation of nonferrous metal works to their full functioning.

K1 One-leaf glazed external door 100/210cm 0.00

One-leaf external door 100 wide and 210 cm tall, executed in


plastic coated aluminium sections with a thermal beak,
corresponding to SCHUECO INTERNATIONAL type, and
LAMISTAL 3+3+12+LAMISTAL 3+3 insulation glazing.

The metal fittings shall be selected by the design engineer, and


include cylinder locks, handles and keys (corresponding to “WINK
HAUS” or “KABA”), and a floor mounted doorstop.
The door leafs shall have built-in closers corresponding to “GEZZE”
type.
Colour of the steel and metal works and design of the handles shall
be selected by the design engineer.
Calculation per piece. Position 1 pcs 3 414.15 1,242.45
K2 Window 120/60cm
The windows are executed in plastic coated aluminium sections
with a thermal break, corresponding to SCHUECO
INTERNATIONAL type, with 4+16+4 mm insulating glazing.
Their size is 120x60cm.
The item includes window jambs, sashes, all the fittings and
insulation glazing.
The sashes tilt inward to open, and are operated via a Ventus
opening mechanism.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 2 pcs 11 214.74 2,362.14
K3 Window 60/60cm
The windows are executed in plastic coated aluminium sections
with a thermal break, corresponding to SCHUECO
INTERNATIONAL type, with 4+16+4 mm insulating glazing.
Their size is 60x60cm.
The item includes window jambs, sashes, all the fittings and
insulation glazing.
The sashes tilt inward to open, and are operated via a Ventus
opening mechanism.
Colour of the steel and metal works shall be selected by the design
engineer.
Calculation per piece. Position 3 pcs 7 148.27 1,037.89
TOTAL K: 4,642.48

86 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


L. STONEWORK

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


L1 External window sills 0.00
Supply and installation artificial or natural stone window sills using
cement mortar.
The sills are 15 cm (external) and 25 cm wide (internal). The sill
must extend beyond the final facade layer by at least 3 to 3.5cm.
The minimum length of the sill is width of the window plus 2 cm, i.e.
at least 62cm and 122cm.
The sills must be placed strictly horizontally viewed along their
length, with a transversal grade of 10 %.
Undersides of the sills must have a groove along the length to
prevent backflow of water.
After installation, the sills contact to the nonferrous metal works
need be cleaned and sealed with two-component permanently
elastic putty for exterior works.
The unit price shall include supply of the window sill with the drip
edge and polished exposed

surfaces, cement mortar and preparation of the surface it is applied


to, cleaning and sealing of the NF metal works joints, protection of
the sill and all other operations required for installation.

Calculation per piece of installed sills. 0.00


a) external window sills l = 60 cm pcs 7 10.84 75.88
external window sills l = 120 cm pcs 11 21.63 237.93
b) internal window sills l = 60 cm pcs 7 18.41 128.87
internal window sills l = 120 cm pcs 11 36.81 404.91
TOTAL L: 847.59

M. FLOOR AND WALL TILING

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

GENERAL:
All floor and wall tiling are designed to be executed in the 1st class
ceramic tiles, 30 x 30 or 20 x 20 cm size, ground or rough top
surface in colour to be determined by the design engineer in
agreement with the client.
At joints of tiled floors and plastered walls a 10 cm tall socle shall
be executed in the same ceramic tiles.
Wall ceramic tiles shall be placed using appropriate adhesive onto
lime-cement mortar plastered walls.
In smaller premises (sanitary facilities etc.) 20 x 20 cm tiles shall
be used for floors and walls (of same quality, colour and production
lot).
Tiling system shall always be joint to joint, while the joint width shall
be agreed with the design engineer.
Floor ceramic tiles are laid in cement mortar or glued onto prepared
cement glazing using construction adhesive.
The unit price shall include supply of the basic and binding
material, laying and tuck pointing of the ceramic tiles using ready-
made mixture as selected by the design engineer, supply and
installation
of PVC, Al, brass or chrome plated angle and cap trimming,
cleaning of the floors and the walls and all transportation.
The structure is divided into 7 zones according to drawing 02-03
and 02-04 ground floor plan. The zones are assigned colours which
apply to the ceramic tiles, all in agreement with the design engineer
or the client.

87 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

M1 External floor tiling 0.00


Tiling of the external floors using the 1st class exterior, safety tread
non-skid ceramic tiles comparable to FLOOR GRES cheramiche
BASIC, ceramic tile size 30 x 30 cm.
Safety tread ceramic tiles with special embossed structure and
safety tread rating R13, 30 x 30 cm size.
The tiles are placed in all main entrances where the design
provides that they shall be resistant to weather effects occurring in
climate characteristic to the construction area.
The item includes supply and installation of fitting tiles for the 15
cm tall socle, possessing the same properties as the tiles specified
above.
The item also includes procurement, supply and placement of self-
adhesive anti-slip strip on external entrance stairs.
The strip shall be placed in two parallel lines. 0.00
a) floor tiles m² 6.00 17.90 107.40
b) socle m' 8.00 3.32 26.56
c) anti-slip strip m' 4.00 2.05 8.20
M2 Floor and wall tiling 0.00
Tiling of the sanitary facilities premises’ floors, baby care premises’
floors and corridor floors using the 1st class safety tread non-skid
ceramic tiles comparable to FLOOR GRES cheramiche BASIC,
ceramic tile size 20 x 20 cm. (R9)
The ceramic tiles shall be placed in a single or two colour pattern in
compliance with tiling scheme for individual premises.
The ceramic tiles must be grinded, polished and skid safe (R9
safety tread rating), in colour selected by the design engineer.
Tiling with joints no wider than 2 to 3 mm.
The tiles shall be placed in construction adhesive in compliance
with recommendations of manufacturer of the tiles.
The ceramic tiles shall be at least 8 mm thick.
Tiling system shall be joint to joint.
The unit price shall include supply of the basic and the binding
material, taking measurements in situ, installation, tuck pointing,
trimming and protection after the tiles are laid.
The item includes supply and installation of fitting tiles for the 15
cm tall socle, possessing the same properties as the tiles specified
above.
The item also includes tiling of walls to a height of 300 cm (of the
same quality, colour and production lot) around sanitary facilities’ 0.00
elements.
a) floor tiles m² 56.00 16.36 916.16
b) wall tiles m² 194.00 16.36 3,173.84
TOTAL M: 4,232.16

88 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


N. PAINTING WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

N1 Iron metal works painting 0.00


Painting of iron metal works using epoxy based paint.
The unit price shall include cleaning of surfaces previously
protected against corrosion, one base coat of epoxy based paint,
application of putty and grinding of any uneven areas.
double coat of epoxy based paint, protection of other surfaces from
contamination, protection of finished paint from damage following
completion of painting and other auxiliary material.
The works shall be performed in compliance with regulation on
corrosion protection of steel structures.
Thickness of the coat shall be inspected by the supervising
engineer.
Paint colour shall be defined by the user in agreement with the
design engineer, using RAL colour chart only.
Calculation per m² of painted surface. m² 1.00 9.71 9.71
N2 Painting of entire joinery
Painting of entire joinery with frames and leafs/sashes.

Prior to painting, the doorframes shall be protected using protective


vapour permeable paint onto which putty shall be applied.

The surfaces should be ground after the putty dries up, and the first
coat of paint should be applied.
After the first coat of paint dries up, repeat application of putty over
any remaining uneven areas.
Subsequently, repeat grinding process and then apply the second
coat of paint.
The last coat of paint shall be executed in glossy paint, while the
paint colour shall be determined by the design engineer.
Leafs/sashes shall be sprayed using paint (Neolin) outlining growth
rings after the protective permeable nitro paint is applied.
The price includes all required auxiliary material.
Calculation per m² of painted joinery. m² 90.00 6.65 598.50
TOTAL N: 608.21

O. EXTERNAL PLASTERING WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

O1 Thermally insulated exterior wall facade 0.00

Procurement, supply of required material and execution of


thermally insulated facade corresponding to Demit facade, on the
main external walls of the structure, adhesively fixing 6cm thick m² 147.00 16.36 2,404.92
polystyrene to masonry block wall, along with double netting and
adhesive and a finish corresponding to BAUMIT Edelputz.

O2 Roof cornice finish


Roof cornice finish shall be acrylate protective-decorative plaster of
trowelled (rice) texture corresponding to “TERA-KRILA Z”.
Prior to execution of the external wall finish, all surfaces must be
clean, sound, dry, not frozen, free of formwork oils, at least 21 day
old.
Maximum departure of the wall from a straight in 4 m length ± 0.5
cm.
Prior to execution of the works it is wise to protect joinery, glazing,
metal.
All surfaces shall be impregnated using appropriate
MINERALKVARC GRUND (white or coloured) a day prior to
application of the final layer.
Calculation per m² of plastered cornice. m² 62.00 8.69 538.78
TOTAL O: 2,943.70

89 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


P. SUNLIGHT PROTECTION

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

P1 Aluminium laminas 0.00


Supply and installation of internal painted aluminium movable
laminas that may be drawn up or down.
Aluminium lamellas shall be executed at all sanitary facilities
premises windows.
The unit price shall include all basic and fixing material, top
trimming and operating strings.
Type and colour of movable aluminium laminas shall be determined
by the design engineer.
Calculation per piece of actually installed laminas.
a) 120x60cm size window. Position 2 pcs 11 14.06 154.66
b) 60x60cm size window. Position 3 pcs 7 14.06 98.42
TOTAL P: 253.08

R. OTHER

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

R1 Execution of technical documents


Execution of technical documentation of as-built situation with
complete operating and maintenance instruction, submission to the set 1.00 255.65 255.65
client (in 6 copies). The item pertains to the entire TCMC.
R2 Detailed final cleaning

Cleaning of the structure and its surrounding, removal of debris


and waste to a stockpile. Detailed final cleaning of floors, tiling etc.
To be executed immediately prior to acceptance of the structure.

Calculation per completely cleaned structure and its surroundings. 1.00 51.13 51.13
set
TOTAL R: 306.78

RECAPITULATION
No ITEM DESCRIPTION Total EUR
A. SITE PREPARATION AND EARTHWORKS 243.04
B. CONCRETE AND REINFORCED CONCRETE WORKS 7,819.12
C. REINFORCEMENT STEEL BENDING WORKS 2,703.42
D. MASONRY WORKS 5,231.22
E. INSULATION WORKS 1,870.09
F. CARPENTRY WORKS 1,563.83
G. SHEET METAL WORKS 1,528.89
H. ROOFING WORKS 3,642.41
I. JOINERY WORKS 4,376.71
J. IRON METAL WORKS 756.27
K. NONFERROUS METAL WORKS 4,642.48
L. STONEWORK 847.59
M. FLOOR AND WALL TILING 4,232.16
N. PAINTING WORKS 608.21
O. EXTERNAL PLASTERING WORKS 2,943.70
P. SUNLIGHT PROTECTION 253.08
R. OTHER 306.78
TOTAL 5: 43,569.00
TOTAL RECAPITULATION (BUILDINGS 1.1, 2.4,Type 3, 2.7, 2.8 & 2.9)
No ITEM DESCRIPTION Total EUR
1. STRUCTURE 1.1 - THE CENTRAL CANOPY 245,312.22
2. STRUCTURE 2.4. FREIGHT VEHICLE EXIT CONTROL, TYPE 3 34,566.19
3. STRUCTURE 2.7 - BORDER CUSTOMS AND POLICE BUILDING 46,774.58
4. STRUCTURE 2.8. SANITARY AND WATER FACILITIES FOR MEN & WOMEN 50,611.58
5. STRUCTURE 2.9. SANITARY AND WATER FACILITIES FOR MEN & JANITOR 43,569.00
TOTAL IVa: 420,833.57

90 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


Totals for headings 2 includes in its calculation the necessary number of the respective units (i.e. heading 2: 4 units
calculated).

91 of 153 Construction of the BCP Bijaca, LOT III, PHASE IV


Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

IVb ELECTRICAL INSTALLATIONS PHASE


Note: In cases where certain equipment is specifically named, it is only an indication of the technical
features the offered equipment would need to comply with.
1. EARTH WORKS; CABLE CONDUIT
Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
NOTE:For all items, where fot the purpose of defining technical characteristics and minimal tehnical
requirements of the items being the subject of supply, is mentioned type and manufacturer /as the type...,
manufacturer) another type of the same of corresponding characteristics may be offered.

NOTE: The price for each item of this bill of rates has to comprise supply, installation,connecting and putting the
item into the condition of full function. The price has comprise the cost of all connecting, installation supporting
and other material reqired for teh full function of particular item. During the preparation of the offer, the latest
valid regulations for the particular installations should be followed. For all potential remarks related to the
execution of works, bill of quantities, submission of bid Designer should be contacted. Controlor has to bear the
cost of transport, installation and equipment errection together with complete building/construction assistence,
and a offer all works in unit price of this bill.

A. EARTH WORKS FOR LOW TENSION CONDUITS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

Geodetic works: Setting out of cable route, position of cable


shaft, placing and maintaining of marks from the beginning
of works up to the handing over to the Client, all
measurements related to the transfer of data from the
A1 m 130.00 1.00 130.00
design onto the construction site and the preparation of
drawings (3 copies) of conduits as actually laid. The
drawings to be certified by relevant land registry.
Accounting per m1 of set route.

Excavation of the trench for cable conduits dimensions


(width) 0.4m (depth) 0.9m in the "c" soil type ( excavated
A2 amount for invoicing is based on compacted soil condition). m 82.00 3.00 246.00
The price should comprise all necessary items and
activities for the excavation up to the depth of 0.9 m:

Trench bottom clearing and planing


Filling and compaction of the sand in the layer of 10 cm at the
bottom of the trench
Covering of laid conducts or cables with sand up to the height of
10 cm above pipes with manual compacting
Placing of PVC marking strip
Backfilling of the remaining part of trench with fine grained
excavated soil, with compacting, in layers of 20 cm
Planing the surface of filled up trench with transporting away the
surplus soil to the dump site

Excavation of the trench for laying down of the FeZn strip,


dimensions (width) 0.4 (depth) 0.8 in the "c" soil type
A3 (excavated amount for invoicing is based on compacted soil m 45.00 5.00 225.00
condition). The price should comprise all necessary items
and activities for the excavation up to the depth of 0.8 m:

Trench bottom clearing and planing


Backfilling of the remaining part of trench with fine grained
excavated soil, with compacting, in layers of 20 cm
Planing the surface of filled up trench with transporting away the
surplus soil to the dump site.

Excavation of the pit (for building in the cable shaft MZ D1).


A4 pcs 1.00 30.00 30.00
dimensions 78x108x101 cm (1.4m3) in the "C" soil type.

excavation of the pit (for building in the cable shaft MZ D1).


dimensions 78x108x101 cm (1.4m3) in the "C" soil type.
Preparation of bedding for the cable shaft, compacted sand 10
cm thick (0.2 m3).
Backfilling of placed cable shaft with excavated material.
Transporting away of the surplus excavated material to the
dump site.

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 92 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

TOTAL A: 631.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 93 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

B. EARTH WORKS FOR TC CONDUITS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

Geodetic works: Setting out of cable route, position of cable


shaft, placing and maintaining of marks from the beginning
of works up to the handing over to the Client, all
measurements related to the transfer of data from the
B1 m 160.00 1.00 160.00
design onto the construction site and the preparation of
drawings (3 copies) of conduits as actually laid. The
drawings to be certified by relevant land registry.
Accounting per m1 of set route.

Excavation of the trench for cable conduits dimensions


(width) 0.4m (depth) 0.9m in the "c" soil type ( excavated
B2 amount for invoicing is based on compacted soil condition). m 160.00 3.00 480.00
The price should comprise all necessary items and
activities for the excavation up to the depth of 0.9 m:

Trench bottom clearing and planing


Filling and compaction of the sand in the layer of 10 cm at the
bottom of the trench
Covering of laid conducits or cables with sand up to the height
of 10 cm above pipes with manual compacting
Placing of PVC marking strip
Backfilling of the remaining part of trench with fine grained
excavated soil, with compacting, in layers of 20 cm
Planing the surface of filled up trench with transporting away the
surplus soil to the dump site

Excavating of the pit for building in the cable shaft


(excavation is calculated on the shaft unit basis):
excavation of the pit (for building in the cable shaft MZ D1).
B5 dimensions 78x108x101 cm (1.4m3) in the "C" soil type.
Preparation of bedding for the cable shaft, compacted sand 10
cm thick (0.3 m3).
Backfilling of placed cable shaft with excavated material.
Transporting away of the surplus excavated material to the dump
pcs 4.00 30.00 120.00
site.
TOTAL B: 760.00
C. LOW TENSION CABLES CONDUTS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Preparation of cable conducts which comprises of supply,
transport of pipes, required accessories and instalation of
them according to the design into previously prepared cable
C1 trenches.
PEHD Ø50 mm m 120 2.00 240.00
PEHD Ø110 mm m 130 3.00 390.00
PEHD Ø160 mm m 160 6.00 960.00
Standardised installation shaft MZ D1 (such as made by
Samoborka) outside dimensions approx. 78x108x101 cm
and building in onto prepared sand base, according to
designed measures and conditions, for the loading of up to
400 kN.
The item comprises supply, transport and placing of
C2 prefabricated instalation shaft into construction pit, together pcs 1.00 566.00 566.00
with all required work and connecting material for the
complete building in of the shaft (shaft to be placed by
mobile crane). The unit price comprises the shaft's cover
and works at pipe inlets and sealing of unused pipes.
Accounting according to the number of installed shaft's.

Punching of inlet plate of the shaft and subsequent makng


C3
up of inlet upon the inserting of pipes.
MZ D1 pcs 2 35.00 70.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 94 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


C4 Supply and placing of PVC plugs at the ends of spare
pipes.
Ø50 mm pcs 5.00 3.00 15.00
Ø110 mm pcs 7.00 4.00 28.00
Ø160 mm pcs 5.00 6.00 30.00
Supply and construction of protection for pipes laid under
the road:
C5 RC (reinforced concrete) slab C25/30 pcs 2.00 99.70 199.40
Wire mesh reinforcment Q-335 pcs 1.00 53.69 53.69
gravel pcs 2.00 10.74 21.48
Supply to the construction site and instal spacing rakes
C6 for parallel lying of pipes Ø110 in trench pcs 70.00 2.00 140.00
for parallel lying of pipes Ø160 in tench pcs 20.00 3.00 60.00
Measuring of passability of cable conduits with preparation
C7 set 1.00 300.00 300.00
of measuring minutes
Supply and laying down of the warning strip into the cable
C8 trench, reading "ATTENTION! ELECTRICITY SUPPLY m 130.00 0.10 13.00
CABLE"
Supply and placing of plastic cable cover into the cable
C9 m 130.00 0.50 65.00
trench
TOTAL C: 3,151.57

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 95 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

D. TC (TELECOMMUNICATION) CABLE CONDUITS


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Preparation of cable conduits to protectect
telecommunication cable, which compress supply transport
of pipes and the installation of the same, according to
design into already prepared cable trench.
D1 PEHD Ø50 mm m 500.00 3.00 1,500.00
PEHD Ø110 mm m 150.00 4.00 600.00
note:The cable conduits Ø160 in the cable trench between
control booths are dealt with in the Chapter: Low tension
cable conduits
Standardised installation shaft MZ D1 (such as made by
Samoborka) outside dimensions approx. 78x108x101 cm
and building in onto prepared sand base, according to
D2 pcs 4.00 566.00 2,264.00
designed measures and conditions, for the loading of up to
150 kN.
The item comprises supply,
Punching of inlet plate of the shaft and subsequent making
of inlet upon the inserting of pipes
MZ D1 pcs 10 35.00 350.00
D3
MZ D2 pcs 5 55.00 275.00
MZ D3 pcs 8 65.00 520.00
MZ D4 pcs 1 80.00 80.00
Supply and placing of PVC plugs at the ends of spare
pipes.
D4
Ø50 mm pcs 15.00 3.00 45.00
Ø110 mm pcs 4.00 4.00 16.00
Supply and construction of protection for pipes laid under
the road:
D5 RC (reinforced concrete) slab C25/30 pcs 2.00 99.70 199.40
Wire mesh reinforcment Q-335 pcs 1.00 53.69 53.69
gravel pcs 1.00 10.74 10.74
Supply to the construction site and instal spacing rakes
D6
for parallel lying of pipes Ø50 in tench pcs 20.00 2.00 40.00
Supply and laying down of the warning strip into the cable
D7 trench, reading "ATTENTION! ELECTRICITY SUPPLY m 160.00 0.10 16.00
CABLE"
Supply and placing of plastic cable cover into the cable
D8 m 160.00 0.50 80.00
trench
Measuring of passability of cable conduits with preparation
D9 set 1.00 250.00 250.00
of measuring minutes
TOTAL D: 6,299.83

RECAPITULATION
1. EARTH WORKS; CABLE CONDUIT
No ITEM DESCRIPTION Total EUR
A EARTH WORKS: CABLE CONDUIT 631.00
B EARTH WORKS FOR TC CONDUITS 760.00
C LOW TENSION CABLES CONDUTS 3,151.57
D TC (TELECOMMUNICATION) CABLE CONDUITS 6,299.83
TOTAL 1: 10,842.40

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 96 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

2. THE MAIN BUILDING OF BORDER POLICE AND CUSTOM


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply and laying of power cables from GR(1.7) to
distributor in the main building of border and customs
police, and under the main shed together with laying of
cables under plaster, and placing them in protective cable
ducts, and cable trays, complete with making cable endings
and connections, with all necessary assembling and
connecting accessory,connecting material, insertion tubes
and sealing elements for the laying the cable through the
A1
foundation. The price comprises all required works and
material.

from GR(1.7) to distributors R1, R4, R3B, R(2.7) m 130 8.00 1,040.00
PP00-Y 5x16mm2
from GR(1.7) to distributors R1B, R2B, RB(2.7)
m 130 5.50 715.00
PP00-Y 5x10mm2
Supply, mounting, building into the wall and connecting wall
plastic cabinet R(2.7) with nontransparant doors type
Pragma, 2 rows x 24 modules, complete with all required
mounting and connecting accessory comprising the
following (pcs 1)
MICRO SWITCH C60N 3P 32A C (pcs 1)
VOLTAGE TRIGGER MX-OF 220-240V 50Hz (pcs1)
MICRO SWITCH C60N 1P 6A C (pcs 1)
MICRO SWITCH C60N 1P 10A C (pcs 3)
MICRO SWITCH C60N 1P 16A C (pcs 10)
A2 set 1 750.00 750.00
DIFFERENTIAL PROTECTIVE SWITCH ID 4P 25A
30mA KL. AC (pcs 1)
All complete with line clips, bus bars, cable insertion pieces,
connecting conduits P/F corresponding cross section of
corresponding cross section and insulation colour, name
plates and warning plates, other small items and connecting
accessory. Accessible parts under voltage to be covered by
insulation plate. Documentation folder to be attached. The
price comprises all required works and material.

Supply, mounting, building into the wall and connecting wall


plastic cabinet R(2.7) with nontransparant doors type
Pragma, 1 row x 12 modules, complete with all required
mounting and connecting accessory comprising the
following (pcs 1)
MICRO SWITCH C60N 3P 20A C (pcs 1)
VOLTAGE TRIGGER MX-OF 220-240V 50Hz (pcs1)
MICRO SWITCH C60N 1P 6A C (pcs 1)
A3 MICRO SWITCH C60N 1P 16A C (pcs 7) set 1 450.00 450.00
All complete with line clips, bus bars, cable insertion pieces,
connecting conduits P/F corresponding cross section of
corresponding cross section and insulation colour, name
plates and warning plates, other small items and connecting
accessory. Accessible parts under voltage to be covered by
insulation plate. Documentation folder to be attached. The
price comprises all required works and material.

Supply and laying of cables under plaster parapet ducts or


protective installation pipes, complete with preparation of
cable endings and connecting:
A4 PP-Y 3x1.5mm2 m 80 0.80 64.00
PP-Y 4x1.5mm2 m 40 0.90 36.00
PP-Y 3x2.5mm2 m 150 1.10 165.00
Delivery and installation above working posts of parapet
plastic duct type as the Legrand DLP, complete with
A5 corners, covers and fittings: m 10 17.00 170.00
DLP 65x150 with partition to install high and low current

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 97 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Delivery and laying plastic self-extinguishing installation


protective pipes:
A6 CSS pipe Φ32mm m 10 1.00 10.00
CSS pipe Φ25mm m 180 0.70 126.00
CSS pipe Φ16 mm m 80 0.60 48.00
Supply and installation of required distribution boxes in lump
A7 1 2.00 2.00
undeplaster construction, complete with lids sum
Drilling of walls to enable cable passing with subseaquent lump
A8 1 25.00 25.00
makeup sum
Repairing of walls after chiselling and building in of lump
A9 1 25.00 25.00
installation equippment and accessory sum
Supply and instalation in/on ceiling and wall and connecting
of lighting sets, complete with corresponding installation
accessory and bulbs
A10
Comfit M 5LF51B72FS, 2xFDH 49 W pcs 2 50.00 100.00
Comfit M 5LF51B72RS, 2xFDH 35 W pcs 6 61.00 366.00
Europlex TC 5LS23472TR, 2xFSD 18 W pcs 4 95.00 380.00
Supply and installation in/on the cealing and wall
emergency (anti-panic illumination) complete with
A11 corresponding instalation accessory, bulbs and pictograms pcs 2 45.00 90.00
to indicate evacuation directions and exits:
safety lamp, top mounting E-LINE DIN, 1h, 1x8 W
Supply, installation and connecting of LEGRAND switch,
mozaic series, under plaster construction, complete with
installation box, support and decorative frame of white
A12 colour:
plain 10A, 250V~ pcs 1 4.00 4.00
serial 10A, 250V~ pcs 2 4.00 8.00
alternating 10A, 250V~ pcs 2 4.00 8.00

Supply, installation and connecting of sockets LEGRAND


series Mozaic, in underplaster construction, in the wall and
parapet canals, complete with instalation box, support and
A13 decorative frame in white colour (exceptionally red):
plain 2P+E, 16A, 230V, 50Hz pcs 8 4.00 32.00
plain with lid 2P+E, 16A, 230V, 50Hz pcs 1 5.00 5.00
double, 2P+E, 16A, 230V, 50Hz pcs 6 8.00 48.00
double(red colour), 2P+E, 16A, 230V, 50Hz pcs 6 10.00 60.00
Supply, installation and connecting of emergrncy cut-out
A14 push-button to (outdoor instalattion, equipped with one pcs 1 45.00 45.00
spare and operating contact)
Connecting of the following cooling system parts (DO NOT
PUT UNDER VOLTAGE WITHOUT THE PRESENCE OF
AUTHORISED SERVICE PERSON!):
A15 pcs 2 5.11 10.22
outer cooling system unit
inner cooling system unit pcs 2 5.11 10.22
room regulating device pcs 2 2.56 5.12
Connecting of bus bar into KDO with cable PP-Y 3x2,5 mm².
A16 pcs 1 5.00 5.00

Unspecified minor assembly and installation material lump


A17 1 100.00 100.00
sum
TOTAL A: 4,902.56

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 98 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

B. TELEPHONE AND COMPUTER INSTALATION


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, assembling and connecting of the main
comunication-distribution cabinet, for police and custom
(building) KDO 3. The item comprises all passive
equipment (communication distribution cabinet and
universal structural cabling). Active equipment will be
installed subsequently according to the demands and
requirements. KDO is anticipated as wall steel sheet pcs 1 0.00
cabinet with support, with glass door, with lock and key,
capacity 42U, dimensions:
(height)2000x(width)800x(lenght)1000 mm, as type RITTAL
or corresponding, in which the following equipment is
installed:

cable insertion for ceiling or bottom (brush) pcs 1 0.00


RJ 45patch pannel with 24 moduls, 6th kategory, height
pcs 1 0.00
1U
ISDN patch pannel with 25 moduls, 3rd, height 1U pcs 1 0.00
cabinet ventilation unit and thermostat pcs 1 0.00
supply bar, 9x grounded socket 230V, with surface surge
pcs 1 0.00
protection and switch
cable ducts, height 1U pcs 3 0.00
optical patch pannel for the instalation of 4 SC duplex
B1 singlemode re-router:
for instalation into 19" distributor, height 1U
optical cable box with lid
set 1 0.00
equipped with 4 SC duplex singlemode re-routers
cable insertions, plastic ties, and other required
equipment
with marking elements
document keeping drawer pcs 1 0.00
fixed rack pcs 1 0.00
lamp 35W in IP20 protection pcs 1 0.00
patch cable 1 m, 2 x RJ45 Western pcs 12 0.00
patch cable 2 m, 2 x RJ45 Western pcs 12 0.00
re-routing telephone 0,5 m pcs 10 0.00
re-routing telephone 1 m pcs 15 0.00
optical re-routing duplex cable 2 m:
singlemode cable, 9/125 µm pcs 2 0.00
connectors Duplex SC/Duplex SC
grounding of the cabinet by conduit P/FY 1x10 mm2
complete with material and work set 1 0.00
unspecified small assembling connecting accessory set 1 0.00
TOTAL B1 set 1 2,250.00 2,250.00
Supply, building into the wall of the sanitary facilities M+W,
B2 M+cleaning lady and connecting of telephone inlet cabinet pcs 4 75.00 300.00
type RTK 30 with lock, complete with 1 LSA disconnecting
reglettes
Supply and instalation of pipes (in the floor, wall, ceiling),
together with small connecting matterial and accessory
CSS16 m 10 0.60 6.00
B3
CSS25 m 20 0.70 14.00
CSS32 m 30 1.00 30.00
CSS50 m 6 3.00 18.00
Supply and assembling of cable racks on previously
mounted hanging and assembling elements, complete with
B4 connecting accessory
PK 100 (in ceiling) m 10 9.00 90.00
PK 50 (in ceiling) m 15 7.00 105.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 99 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


Supply and laying in the main building and in the building
for the boundary police and custom and from these toward
other buildings, along allready prepaired routs or layout
elements in the building and through TC cable ducts and
cable connecting:
STP 4x2x0,6mm2, 6th cathegory, indoor m 430 3.00 1,290.00
STP 4x2x0,6mm2, 6th cathegory, outdoor m 3000 3.00 9,000.00
Optical cabel, singlemode, 4 threads 9/125 µm, OS1, for
laying into pipes and into cable ducts with protection m 1500 2.00 3,000.00
against rodents and allowed tensile strenght of 1500 N,
B5 outdoor

Optical cable, singlemode, 8 threads 9/125 µm, OS1, for


laying into pipes and into cable ducts with protection
against rodents and allowed tensile strenght of 1500 N,
outdoor
TK 59 3x4x0,6mm2 m 900 1.50 1,350.00
TK 59 5x4x0,6 mm2 m 430 1.80 774.00
TK 59 6x4x0,6mm2 m 600 2.20 1,320.00
TK 59 10x4x0,6 mm2 m 160 4.00 640.00
TK 59 25x4x0,6 mm2 m 280 6.00 1,680.00
Supply, instalation and connecting of communication outlet
typa Legrand Mosaic for wall mounting, parapet duct,
interior equipment, consisting of underplaster box, frame
B6 with support and RJ45 module, 6th cathegory, type
Legrand Mosaic, white colour:
1xRJ45 pcs 3 10.00 30.00
4xRJ 45 pcs 6 35.00 210.00

Supply of required markings and labeling items to mark all


B7 elements of the comunication system according to the block set 4 25.00 100.00
diagram
Connecting of telecommunication cable directly to the
B8 pcs 4 25.00 100.00
device VDC-01 and CO1.
Testing according to valid standards and regulations with
corresponding documentation stating the results of testing,
for one media
B9 STP cable, RJ45 cat. 6 pairs 199 3.00 597.00
optical cable threads 164 3.00 492.00
multipair cable pairs 238 3.00 714.00
TOTAL B: 24,110.00
C. FIRE ALARM INSTALATION
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

Supply and laying trough previously installed pipes together


with small and other connecting material and accessory:
Instrumentation cable - marking RE-2X(St) H-PiMF
m 600 1.00 600.00
C1 4x2x0,75
Fire alarm cable, solid conduits 2x1 mm2, marking J-
H(St)-H 1x2x1mm2
- red colour, selfextinguishing PVC insulation m 400 1.00 400.00
- halogen-free, smokeless
Supply and laying mainly into lowered ceiling and under the
plaster, together with ellobow clips, bolts and other
connecting material and accessory:
PNT-16 m 55 1.00 55.00
C2
PNT-23 m 5 1.20 6.00
PNT-29 m 6 1.50 9.00
CS 20 m 5 0.60 3.00
CS 32 m 10 1.00 10.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 100 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


C3 Supply of the following equipment:
Analogue adressable optical communication fire detector
- compulsory automatic addressing from central unit
- compulsory possibility for manual addressing from the
central unit
- compulsory sensitivity regulation from the central unit,
separately for day and separately for night, operation
mode - the pcs 8 35.00 280.00
colour of detector according to clients specification
MANUFACTORER: Inim
AS TYPE: V100

support for addressable detectors


- lowprofile
- for under plaster cable connection
- compulsory instalation of double loop insulator pcs 8 4.00 32.00
MANUFACTORER: Inim
AS TYPE: VB100

Analogue addressable manual fire alarm


- mechanical visual activation inidcation
- with possible resetting by the key
- threecoloured lighting LED signalization to pcs 2 58.00 116.00
indicate condition
MANUFACTORER: Inim
AS TYPE: VCP100

Addressable firefighting sirene, to be instaled at the base pcs 1 43.00 43.00


of
Inlet detector
modul (detector
to connecttoclassic
be mounted
zone onon addressabile
sirene) loop pcs 1 79.00 79.00
-MANUFACTORER:
programmabile Inim
Fire
-AS alarm
controled sirene
by for outdoor
detector instalation pcs 1 85.00 85.00
TYPE:
-MANUFACTORER:
red S-VMCZ100
colour,
Power supplyIP65
24V / INIM
1.4A
--AS24V
with possibility
TYPE: two batteries 6,5Ah
VBS-100
MANUFACTORER: Cooper
- in metal housing (dimensions 325x325x80)
AS TYPE: FULL ROLP/R/D/3 pcs 1 80.00 80.00
MANUFACTORER: Inim
AS TYPE: S-BPS24040

Fire alarm sirene for outdoor instalation


- red colour, IP65 pcs 1 65.00 65.00
- 24V
instalation of outdoor sirene
MANUFACTORER: Cooper
C4 - attaching
AS TYPE: ofFULL
sireneROLP/R/D/3
fo facade at minimaly 4 points pcs 1 25.00 25.00
- connecting of sirene
- testing of activation

C5 U-VA-KOR DOK set 1 25.00 25.00


Preparation of the user's documentation
C6 Instalation and connection of indoor power alarm sirene pcs 1 7.00 7.00
Instalation and connecting of manual fire alarm and
C7 pcs 2 7.00 14.00
addressing
Instalation of support and connecting of support of fire
C8 pcs 8 7.00 56.00
alarm detectore on line
Instalation of fire alarm detector to support and detector
C9 pcs 8 7.00 56.00
addressing
C10 Testing of fire alarm detector, comunicator or module pcs 15 1.00 15.00
TOTAL C: 2,061.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 101 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

D. LIGHTNING PROTECTION INSTALATION AND POTENTIAL EQUALIZATION


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, laying and building into the foundatinon of the main
shed before concreting (narrow side perpendicular to the
layer of 10cm of base concrete; the strip to be connected to
reinforcement by clip) with the following lightning accessory:
D1
strip FeZn P30x4 m 40 3.00 120.00
cross-connector KON 01, FeZn, P pcs 15 3.00 45.00
cross-connector for reinforcement KON 09 P30x4 pcs 20 2.50 50.00
Laying of outlets of average 3m (for the connection to the
metal mass, preparation of the measuring connection,
distributor, control cabin, scales...) and connecting to the
D2 lightning strip in the foundation or trench by cross-connector pcs 11 5.00 55.00
KON 01, FeZn, P. The price comprises all required material
and work.

Supply, concreting into the concrete posts and instalation


of the following lightning accessory:
strip FeZn P25x4 m 20 2.00 40.00
measuring connection KON01, Rf, for P30x4 pcs 4 3.00 12.00
D3 box for the measuring connection ZON05 pcs 4 20.00 80.00
clip for downpipe KON10A, Rf-V, ∅(downpipe) for P30x4 pcs 4 3.00 12.00
clamp for downpipe KON06, Rf, for ∅8 pcs 4 3.20 12.80
connecting clip KON02, Rf, for P30x4 on ∅8 pcs 4 3.20 12.80
Supply, laying and instalation on the roof of the following
lightning accessory:
round conductor RH3, Rf, Ф8 m 40 3.00 120.00
roof support for steel sheat roofing or similar SON 16, Rf,
D4 pcs 35 2.50 87.50
for Ф8 complete with sealing and bolt
connecting clip KON04, Rf, for Ф8 pcs 10 2.50 25.00
contact joint between round conductors and metal masses
pcs 4 1.50 6.00
KON05, Rf, for Ф8
Supply and instalation of cables into cable racks and under
plaster complete with all required pipes and distribution
boxes, equipped with corresponding clips:
D5 P/F-Y 1x6 mm2 m 30 0.70 21.00
P/F-Y 1x10 mm2 m 15 1.00 15.00
P/F-Y 1x16 mm2 m 10 1.80 18.00
Connecting of all metal masses (fence, metal stairs, doors,
windows, distributor, gas instalation, KDO...), to the
D6 grounding and potential equalization system, complete with pcs 10 5.00 50.00
all required connecting material and accessory.

Supply and assemble the instalation for potential


equalization in sanitary facilities and heating substations by
conduit P/F 6mm2. All metal masses (water supply pipes,
etc.) to be connected to the bus bar for the additional
D7 pcs 1 7.00 7.00
potential equalization DIP and connect by conduite P/F
10mm2 bus bar to the the main potential equalization GIP

TOTAL D: 789.10

RECAPITULATION
2. THE MAIN BUILDING OF BORDER POLICE AND CUSTOM
No ITEM DESCRIPTION Total EUR
A ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS 4,902.56
B TELEPHONE AND COMPUTER INSTALATION 24,110.00
C FIRE ALARM INSTALATION 2,061.00
D LIGHTNING PROTECTION INSTALATION AND POTENTIAL EQUALIZATION 789.10
TOTAL 2: 31,862.66

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 102 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

3. MAIN SHED
Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply and laying of power cables from Rcn1/RcnB1 i
Rcn2 in previously layed pipes in cable trench and along
cable racks, complete with making cable endings and
connections, with all necessary assembling and connecting
accessory,connecting material, insertion tubes and sealing
elements for the laying the cable through the foundation.
A1 The price comprises all required works and material.

PP00-Y 5x6mm2 m 200 3.50 700.00


PP00-Y 3x6mm2 m 200 2.50 500.00
PP-Y 5x2.5 mm2 m 150 1.40 210.00
PP00-Y 3x2.5 mm2 m 20 1.10 22.00
Supply and brackets mounting on steel angle supports of
steel metal racks (protected by hot zinc plating), complete
A2 with angle sections, lids and connecting accessory for the
following types:
PK 200/50 m 60 14.00 840.00
Supply, assembling, and connecting of protective instalation
pipes above plaster mounting, complete with clips and
A4 assembling and connecting accessory:
PNT pipe Φ32mm m 5 1.50 7.50
PNT pipe Φ25mm m 60 1.20 72.00
Supply and instalation of required imperbeable distribution lump
A5 boxes such as Legrand series Plexo, IP55, with direct inlet 1 3.00 3.00
sum
membrane insertions
Supply and installation to the shed construction and
connecting lighting sets, complete with corresponding
mounting accessory and bulbs:
A6 Kompakt-Reflektorleuchte 5NX76721N, 1xMT 250 W pcs 8 188.00 1,504.00
Kompakt-Reflektorleuchte 5NX76721N + E27 with timer,
pcs 3 325.00 975.00
1xMT 250 W
Unspecified minor assembly and installation material lupm
A7 1 100.00 100.00
sum
TOTAL A: 4,933.50

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 103 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

B. LIGHTNING PROTECTION INSTALATION AND POTENTIAL EQUALIZATION


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, laying and building into the foundatinon of the main
shed before concreting (narrow side perpendicular to the
layer of 10cm of base concrete; the strip to be connected to
reinforcement by clip) with the following lightning accessory:
B1
strip FeZn P30x4 m 400 3.00 1,200.00
cross-connector KON 01, FeZn, P pcs 110 3.00 330.00
cross-connector for reinforcement KON 09 P30x4 pcs 210 2.50 525.00
Laying of outlets of average 3m (for the connection to the
metal mass, preparation of the measuring connection,
distributor, control cabin, scales...) and connecting to the
B2 lightning strip in the foundation or trench by cross-connector pcs 70 5.00 350.00
KON 01, FeZn, P. The price comprises all required material
and work.

Supply and instalation of cables into PEHD pipes and cable


canals in pits under control cabins, complete with all
required distribution boxes, equipped with corresponding 5.00
clips:
B3
P/F-Y 1x6 mm2 m 30 0.70 21.00
P/F-Y 1x10 mm2 m 100 1.00 100.00
P/F-Y 1x16 mm2 m 30 1.80 54.00
Connecting of all metal masses (fence, metal stairs, doors,
windows, distributor, gas instalation, KDO...), to the
B4 grounding and potential equalization system, complete with pcs 60 5.00 300.00
all required connecting material and accessory.

TOTAL B: 2,880.00

RECAPITULATION
3. MAIN SHED
No ITEM DESCRIPTION Total EUR
A ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS 4,933.50
B LIGHTNING PROTECTION INSTALATION AND POTENTIAL EQUALIZATION 2,880.00
TOTAL 3: 7,813.50

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 104 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

4. CONTROL CABIN TYPE 3


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, mounting, building on the wall bellow the working
plate and connecting wall plastic cabinet Rmk_n , cabinet
A1 for modular equippment type Kaedra 2 rows x 24 modulses,
complete with all required mounting and connecting
accessory comprising the following:
MICRO SWITCH C60N 3P 25A C (pcs 1)
VOLTAGE TRIGGER MX-OF 220-240V 50Hz (pcs 1)
MICRO SWITCH C60N 1P 6A C (pcs 2)
MICRO SWITCH C60N 1P 10A C (pcs 2)
MICRO SWITCH C60N 1P 16A C (pcs 6)
DIFERENTIAL PROTECTIVE SWITCH ID 2P 25A 30mA
KL. AC (pcs 2)
DIFERENTIAL PROTECTIVE SWITCH ID 2P 25A 300mA
KL. AC (pcs 1)
All complete with line clips, bus bars, cable insertion pieces,
connecting conduits P/F corresponding cross section of
corresponding cross section and insulation colour, name
plates and warning plates, other small items and connecting
accessory. Accessible parts under voltage to be covered by
insulation plate. Documentation folder to be attached. The
price comprises all required works and material.

Supply, mounting, building on the wall bellow the working


plate and connecting wall plastic cabinet RBmk_n , cabinet
A2 for modular equippment type Kaedra 1 rows x 12 moduls,
complete with all required mounting and connecting
accessory comprising the following:
MICRO SWITCH C60N 1P 20A C (pcs 1)
VOLTAGE TRIGGER MX-OF 220-240V 50Hz (pcs 1)
MICRO SWITCH C60N 1P 6A C (pcs 1)
MICRO SWITCH C60N 1P 16A C (pcs 4)
DIFERENTIAL PROTECTIVE SWITCHID 2P 25A 30mA
KL. AC (pcs 1)
DIFERENTIAL PROTECTIVE SWITCH ID 2P 25A 300mA
KL. AC (pcs 1)
All complete with line clips, bus bars, cable insertion pieces,
connecting conduits P/F corresponding cross section of
corresponding cross section and insulation colour, name
plates and warning plates, other small items and connecting
accessory. Accessible parts under voltage to be covered by
insulation plate. Documentation folder to be attached. The
price comprises all required works and material.

Supply and laying of cables into parapet ducts or protective


instalation pipes, complete with preparation of cable
A3 endings and connectig:

PP-Y 3x1.5mm2 (m 20) set 4 2250.00 9,000.00


PP-Y 4x1.5mm2 (m 5)
PP-Y 3x2.5mm2 (m 50)
Supply and laying under work posts of plastic parapet duct
A4 as type Legrand DLP, complete with angle sections, lids
and
DLPconnecting
65x150withaccessory:
partition for the installation of strong and
weak current (m 8) (pcs 1)
Supply, installation and connecting of protective installation
A5 pipes for above plaster mounting, complete with clips and
mounting and connecting accessory:
PNT pipe Φ25mm (m 5) (pcs 1)
PNT pipe Φ16mm (m 10) (pcs 1)
Supply and installation of reqired impermeabile distribution
A6 boxes as LEGRAND series Plexo, IP55, with direct inlet
membrane insertions (lump sum)

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 105 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Supply, installation in/on ceiling and wall and connecting of


A7 lighting sets, complete with corresponding instalation
accessory and bulbs :
Monsun 5LS41272F, 2xFDH 49 W (pcs 1)
Supply, mounting in/on ceiling and wall and connecting of
A8 the lamp for anti panic lighting, complete with
corresponding with instalation accessory, bulbs and
pictograms to mark evacuation direction and exits:
safety lamp, top mounting E-LINE DIN, 1h, 1x8 W (pcs 1)

A9 Supply, installation and connecting of switch Legrand series


Plexo, IP 55 on the plaster mounting construction:
plain 10A, 250V~ (pcs 1)

Supply, installation and connecting of sockets LEGRAND


A10 series Mozaic, of underplaster construction, into parapet
ducts, complete with installation box, support and
decorative frame of white colour (exceptionaly red):
double, 2P+E, 16A, 230V, 50Hz (pcs 1)
double(red colour), 2P+E, 16A, 230V, 50Hz (pcs 1)
Supply, installation and connecting of push button for
A11 emergency cut out (for outdoor installation, equipped with
two operating contacts) (pcs 1)
Connecting of the following part of cooling system (DO NOT PUT
A12 UNDER THE VOLTAGE WITHOUT THE PRESENCE OF
AUTHORISED SERVICE PERSON):
cooling system unit, outer (pcs 1)
cooling system unit, inner (pcs 1)
room regulator (pcs 1)
Conecting of current boom by KDO cable PP-Y 3x2,5 mm².
A13
(pcs 1)
Unspecified small assemblyng and instalation material
A14
(lump sum)
TOTAL A: 9,000.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 106 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

B. TELEPHONE AND COMPUTER INSTALATION


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, assembling and connecting of the main
comunication-distribution cabinet, for border police and
custom (building) KDO 5.n. The item comprises all passive
equipment (communication distribution cabinet and
universal structural cabling). Active equipment will be
installed subsequently according to the demands and
requirements. KDO is anticipated as wall, steel sheet
cabinet with support, with glass door, with lock and key,
capacity 9U, dimensions
(height)500x(width)600x(lenght)400 mm, as type RITTAL
or corresponding, in which the following equipment is
installed:

cable insertion for ceiling or bottom (brush) (psc 1)


RJ 45patch pannel with 24 moduls, 6th kategory, height
1U (psc 1)
cabinet ventilation unit and thermostat (psc 1)
supply bar, 9x grounded socket 230V, with surface surge
protection and switch (psc 1)
B1 cable ducts, height 1U (psc 2)
optical patch pannel for the instalation of 2 SC duplex
singlemode re-router: (set 1)
for instalation into 19" distributor, height 1U
optical cable box with lid
equiped with 2 SC duplex singlemode re-routers
cable insertions, plastic ties, and other required
equipment
with marking elements
document keeping drawer (psc 1)
patch cable 1 m, 2 x RJ45 Western (psc 4)
re-routing telephone cable 1 m (psc 4) set 4 1450.00 5,800.00
optical re-routing duplex cable 2 m (psc 2)
singlemode cable, 9/125 µm
connectors Duplex SC/Duplex SC
grounding of the cabinet by conduit P/FY 1x10 mm2
complete with material and work (set 1)
unspecified small assembling connecting accessory (set
1)
Supply and instalation of pipes (in the floor), together with
small connecting matterial and accessory:
B2
CSS32 (m 5)
CSS25 (m 2)
Supply and assembling of cable racks on previously
mounted hanging and assembling elements, complete with
B3 connecting accessory
PK 200 (in floor) (m 3)
Supply and laying, along allready prepaired routes or layout
B4 elements, and connecting of the cables:
STP 4x2x0,6mm2, cat. 6, indoor (m 18)
Supply, instalation and connecting of communication outlet
typa Legrand Mosaic for wall mounting, parapet duct,
B5 interior equippment, consisting of underplaster box, frame
with support and RJ45 module, 6th cathegory, type
Legrand Mosaic, white colour:
4xRJ 45 (pcs 1)
Supply of required markings and labeling items to mark all
B6 elements of the comunication system according to the block
diagram (setSTP
Testing of 1) cable according to valid standards and
regulations with corresponding documentation stating the
B7
results of testing, for one media (psc 4)
TOTAL B: 5,800.00

RECAPITULATION
4. CONTROL CABIN TYPE 3

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 107 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Total EUR


A ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS 9,000.00
B TELEPHONE AND COMPUTER INSTALATION 5,800.00
TOTAL 4: 14,800.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 108 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

5. SANITARY FACILITIES M+W


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, installation, wallmounting and connection of wall
plastic cabinet RS(2.8/3.6) with nontransparent door, type
Pragma, 3 rows x 36 modules, complete with all required
assembling and connecting accessory, comprising the
following (pcs 1)

MICRO SWITCH NG125N 3P 25A C (pcs 1)


VOLTAGE TRIGGER MX-OF 220-240V 50Hz (pcs1)
MICRO SWITCH C60N 1P 6A C (pcs 1)
MICRO SWITCH C60N 1P 10A C (pcs 5)
MICRO SWITCH C60N 1P 16A C (pcs 11)
A1 set 1.00 550.00 550.00
DIF.PROTECTIVE SWITCH ID 4P 40A 30mA KL. AC (pcs
1)
All complete with line clips, bus bars, cable insertion pieces,
connecting conduits P/F corresponding cross section of
corresponding cross section and insulation colour, name
plates and warning plates, other small items and connecting
accessory. Accessible parts under voltage to be covered by
insulation plate. Documentation folder to be attached. The
price comprises all required works and material.

Supply and lying of cables under plaster or in protective


plastic pipes complete with the preparation of cable endings
A2 and connecting:
PP-Y 3x1.5mm2 m 100 0.80 80.00
PP-Y 3x2.5mm2 m 100 0.90 90.00
Supply and laying of plastic self-extinguishing instalation
protective pipes:
A3 CSS pipe Φ32mm m 5 1.00 5.00
CSS pipe Φ25mm m 100 0.70 70.00
CSS pipe Φ16 mm m 100 0.60 60.00
Supply and installation of required distribution boxes of lump
A4 1 3.00 3.00
under plaster construction, complete with lids sum
Chiselling of walls for cable passages with subseaquent lump
A5 1 25.00 25.00
repair sum
Repairing the walls after chiselling and building in of lump
A6 1 25.00 25.00
installation equippment and accessory sum
Supply, mounting in/on the ceiling and wall and connecting
of lighting sets, complete with corresponding assembling
A7 accessory and bulbs
Europlex TC 5LS23472TR, 2xFSD 18 W pcs 13 95.00 1,235.00
Europlex TC 5LS23471TR, 1xFDH 55 W pcs 19 125.00 2,375.00

Supply, mountend in/on the ceiling and wall and connecting


A8 the lamp for the lighting against panic, complete with
corresponding assembling accessory, bulbs and pictograms
to mark evacuation directions and exits:
Safety lamp with lowered pannel to indicate evacuation
pcs 1 45.00 45.00
direction S.1 LED, 1h, 1x8 W
Supply, installation and connecting of switch Legrand series
safety
Mozaic, lamp, top mounting
under plaster E-LINE DIN, 1h, 1x8
construction, W
complete with pcs 3 35.00 105.00
installation box, support and decorative frame of white
A10 colour: pcs 3 4.00 12.00
plain 10A, 250V~
Supply, installation and connecting of sockets Legrand
series Mozaic in underplaster construction, into the wall and
A11 parapet ducts, complete with installation box, support and pcs 9 4.00 36.00
decorative frame of white colour(exceptionally red)
plain with lid 2P+E, 16A, 230V, 50Hz

Supply, installation and connecting of movement detector


A12 360°, 8m, master, 2300W/10A, 250V~,1-30 min, 5-2000lux, pcs 4 55.00 220.00
ceiling

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 109 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Supply, installation and connecting of movement detector


A13 360°, 8m, slave, ceiling pcs 5 55.00 275.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 110 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


Supply, installation and connecting :
pulling switch in toilette for disabled persons
mushroom push button NC to be turned for reset of SOS
A14 set 1 55.00 55.00
calls within the toilette
el. Bell with transformer 230V/8V(for SOS calls, sound
signal in corridor)
Supply, installation and connecting of emergency cut-out
A15 (outdoor installation, equipped with one steaddy and one pcs 1 45.00 45.00
opperating contact)
Conecting of the following items of the heating system (DO
NOT PUT UNDER VOLTAGE WITHOUT THE PRESENCE
OF AUTHORIZED SERVICE PERSON!):
A16 Wiring for el. equippment (circulation pumps, three-way
valves, thermostates, outer thermostat, boiler regulation ) set 1 51.13 51.13

gass fired water heater pcs 1 25.56 25.56


Connecting of el.water heater, for the preparation of hot
A17 pcs 1 5.00 5.00
water by cable PP-Y 3x2,5 mm².
Unspecified small mounting and installation material lump
A18 1 100.00 100.00
sum
TOTAL A: 5,492.69
B. FIRE ALARM INSTALATION
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

Supply and laying trough previously installed pipes together


with small and other connecting material and accessory:
Fire alarm cable, solid conduits 2x0,8 mm2, marking J-
B1 H(St)-H 1x2x0,8 m 20 1.00 20.00
- red colour
- selfextinguishing PVC isolation
- halogen free, smokeless
Supply and under plaster instalation together with small and
other connecting material and accessory:
B2 m 15 0.60 9.00
CS 20
CS 32 m 5 1.00 5.00
Supply of the following equippment pcs
Classical optical fire alarm detector
2 35.00 70.00
MANUFACTORER: Inim pcs
AS TYPE: S-S100
Support for classic INIM detectores
- with 390 ohm resistor
MANUFACTORER: Inim pcs 2 45.00 90.00
B3 AS TYPE: S-UBR100-390
Analogue addressable manual fire alarm
- mechanical visual activation inidcation
- with possible resetting by the key
- threecoloured lighting LED signalization to pcs 1 35.00 35.00
indicate condition
MANUFACTORER: Inim
AS TYPE: VCP100

The first testing of the system by authorized company -


B4 the price based on specific test unit - pcs 3 10.00 30.00
comprises issuing of certificate
Instalation and connecting of manual fire alarm and
B5 pcs 1 25.00 25.00
adressing
Instalation of support and connecting of support of fire
B6 pcs 2 7.00 14.00
alarm detectore on line
Instalation of the fire alarm comunicator on the support and
B7 pcs 2 5.00 10.00
addressing of detector.
B8 Testing of fire alarm detector, comunicator or module pcs 3 1.00 3.00
TOTAL B: 311.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 111 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

C. LIGHTNING PROTECTION INSTALATION AND POTENTIAL EQUALIZATION


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, laying and building into the foundatinon of the main
shed before concreting (narrow side perpendicular to the
layer of 10cm of base concrete; the strip to be connected to
reinforcement by clip) with the following lightning accessory:
C1
strip FeZn P30x4 m 50 3.00 150.00
cross-connector KON 01, FeZn, P pcs 10 3.00 30.00
cross-connector for reinforcement KON 09 P30x4 pcs 20 2.50 50.00
Laying of outlets of average 3m (for the connection to the
metal mass, preparation of the measuring connection,
distributor, control cabin, scales...) and connecting to the
C2 lightning strip in the foundation or trench by cross-connector pcs 10 5.00 50.00
KON 01, FeZn, P. The price comprises all required material
and work.

Supply, concreting into the concrete posts and instalation


of the following lightning accessory:
strip FeZn P25x4 m 15 2.00 30.00
measuring connection KON01, Rf, for P30x4 pcs 4 3.00 12.00
C3 box for the measuring connection ZON05 pcs 4 20.00 80.00
clip for downpipe KON10A, Rf-V, ∅(downpipe) for P30x4 pcs 4 3.00 12.00
clamp for downpipe KON06, Rf, for ∅8 pcs 4 3.20 12.80
connecting clip KON02, Rf, for P30x4 on ∅8 pcs 4 3.20 12.80
Supply, laying and instalation on the roof of the following
lightning accessory:
round conductor RH3, Rf, Ф8 m 50 3.00 150.00
roof support for steel sheat roofing or similar SON 16, Rf,
C4 pcs 40 2.50 100.00
for Ф8 complete with sealing and bolt
connecting clip KON04, Rf, for Ф8 pcs 8 2.50 20.00
contact joint between round conductors and metal masses
pcs 4 1.50 6.00
KON05, Rf, for Ф8
Supply and instalation of cables into cable racks and under
plaster complete with all required pipes and distribution
boxes, equipped with corresponding clips:
C5 m 50 0.70 35.00
P/F-Y 1x6 mm2
P/F-Y 1x10 mm2 m 20 1.00 20.00
P/F-Y 1x16 mm2 m 5 1.80 9.00
Connecting of all metal masses (fence, metal stairs, doors,
windows, distributor, gas instalation, KDO...), to the
C6 grounding and potential equalization system, complete with pcs 10 5.00 50.00
all required connecting material and accessory.

Supply and assemble the instalation for potential


equalization in sanitary facilities and heating substations by
conduit P/F 6mm2. All metal masses (water supply pipes,
etc.) to be connected to the bus bar for the additional
C7 pcs 4 7.00 28.00
potential equalization DIP and connect by conduit P/F
10mm2 bus bar to the the main potential equalization GIP

TOTAL C: 857.60
RECAPITULATION
5. SANITARY FACILITIES M+W
No ITEM DESCRIPTION Total EUR
A ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS 5,492.69
B FIRE ALARM INSTALATION 311.00
C LIGHTNING PROTECTION INSTALATION AND POTENTIAL EQUALIZATION 857.60
TOTAL 5: 6,661.29

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 112 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

6. SANITARY FACILITIES M+ CLEANING LADY


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS
No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, mounting, building into the wall and connecting of
wall plastic cabinet RS(2.9/3.7) with nontransparent door,
type Pragma, 3 rows x 36 modules, complete with all
required assembling and connecting accessory, comprising
the following (pcs 1)
MICRO SWITCH NG125N 3P 25A C (pcs 1)
VOLTAGE TRIGGER MX-OF 220-240V 50Hz (pcs 1)
MICRO SWITCH C60N 1P 6A C (pcs 1)
MICRO SWITCH C60N 1P 10A C (pcs 4)
MICRO SWITCH C60N 1P 16A C (pcs 8)
A1 set 1 450.00 450.00
DIF. PROTECTIVE SWITCH ID 4P 40A 30mA KL. AC
(pcs 1)
All complete with line clips, bus bars, cable insertion pieces,
connecting conduits P/F corresponding cross section of
corresponding cross section and insulation colour,cable
ducts, name plates and warning plates, other small items
and connecting accessory. Accessible parts under voltage
to be covered by insulation plate. Documentation folder to
be attached. The price comprises all required works and
material.

Supply and laying under plaster or/in protective instalation


pipes complete of preparation of cable endings and
A2 connecting:
PP-Y 3x1.5mm2 m 100 0.80 80.00
PP-Y 3x2.5mm2 m 80 0.90 72.00
Supply and laying of plastic self-extinguishing installation
protective pipes
A3 CSS pipe Φ32mm m 5 1.00 5.00
CSS pipe Φ25mm m 80 0.70 56.00
CSS pipe Φ16 mm m 100 0.60 60.00
Supply and instalation of required distribution boxes of lump
A4 1.00 3.00 3.00
underplaster construction, complete with lids sum
Chiselling of walls for cable passages, with subseaquent lump
A5 1.00 25.00 25.00
repair sum
Repairing of walls after chiselling and building in of lump
A6 1.00 25.00 25.00
installation equippment and accessory sum
Supply, mounting in/on the ceiling and wall and connecting
of lighting sets, complete with corresponding assembling
A7 accessory and bulbs
Europlex TC 5LS23472TR, 2xFSD 18 W pcs 9 95.00 855.00
Europlex TC 5LS23471TR, 1xFDH 55 W pcs 18 125.00 2,250.00

Supply, mounting in/on the ceiling and wall and connecting


the lamp for the lighting against panic, complete with
A8 corresponding assembling accessory, bulbs and pictograms
to mark lamp
Safety evacuation directionspannel
with lowered and exits:
to indicate evacuation
direction S.1 LED, 1h, 1x8 W pcs 1 45.00 45.00
safety lamp, top mounting E-LINE DIN, 1h, 1x8 W pcs 2 35.00 70.00
Supply, installation and connecting of switch Legrand series
A9 Mozaic, under plaster construction, complete with pcs 2 4.00 8.00
installation box, support and decorative frame of white
colour: plain 10A, 250V~
Supply, installation and connecting of sockets Legrand
series Mozaic in underplaster construction, into the wall and
A10 parapet ducts, complete with installation box, support and pcs 7 4.00 28.00
decorative frame of white colour(exceptionally red)
plain with lid 2P+E, 16A, 230V, 50Hz

Supply, instalation and connecting of movement detector


A11 360°, 8m, master, 2300W/10A, 250V~,1-30 min, 5-2000lux, pcs 1 55.00 55.00
ceiling
Supply, installation and connecting of movement detector
A12 pcs 2 55.00 110.00
360°, 8m, slave, ceiling

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 113 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


Supply, installation and connecting of emergency cut-out
A13 (outdoor instalation, equipped with one steady and one pcs 1 45.00 45.00
operating contact)
Conecting of the following items of the heating system (DO
NOT PUT UNDER VOLTAGE WITHOUT THE PRESENCE
OF AUTHORIZED SERVICE PERSON!):
A14
Wiring for el. equippment (circulation pumps, three-way
set 1 25.00 25.00
valves, thermostates, outer thermostat, boiler regulation )
gas fired water heater pcs 1 25.00 25.00
Unspecified small mounting and installation material lump
A15 1 100.00 100.00
sum
TOTAL A: 4,392.00

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 114 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

B. FIRE ALARM INSTALATION

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR

Supply and laying trough previously installed pipes together


with small and other connecting material and accessory:
Fire alarm cable, solid conduits 2x0,8 mm2, marking J-
B1 m 20 1.00 20.00
H(St)-H 1x2x0,8
- red colour
- selfextinguishing PVC isolation
- halogen free, smokeless
Supply and under plaster instalation together with small and
other connecting material and accessory:
B2
CS 20 m 15 0.70 10.50
CS 32 m 5 1.00 5.00
Supply of the following equipment
Classical optical fire alarm detector
MANUFACTORER: Inim pcs 1 35.00 35.00
AS TYPE: S-S100
Support for classic INIM detectores
- with 390 ohm resistor
MANUFACTORER: Inim pcs 1 45.00 45.00
B3 AS TYPE: S-UBR100-390
Analog addressable manual fire alarm
- mechanical visual activation inidcation
- with possible resetting by the key
- threecoloured lighting LED signalization pcs 1 35.00 35.00
to indicate condition
MANUFACTORER: Inim
AS TYPE: VCP100

The first testing of the system by authorized company -


B4 the price based on specific test unit pcs 2 10.00 20.00
-comprises issuing of certificate
Instalation and connecting of manual fire alarm and
B5 pcs 1 7.00 7.00
adressing
Instalation of support and connecting of support of fire
B6 pcs 1 7.00 7.00
alarm detector on line
Instalation of fire detector on the support and addressing of
B7 pcs 1 7.00 7.00
detector
B8 Testing of fire alarm detector, comunicator or module pcs 2 1.00 2.00
TOTAL B: 193.50

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 115 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

C. LIGHTNING PROTECTION INSTALATION AND POTENTIAL EQUALIZATION


No ITEM DESCRIPTION Unit Qty Unit Price Total EUR
Supply, laying and building into the foundation of the main
shed before concreting (narrow side perpendicular to the
layer of 10cm of base concrete; the strip to be connected to
reinforcement by clip) with the following lightning accessory:
C1
strip FeZn P30x4 m 50 3.00 150.00
cross-connector KON 01, FeZn, P pcs 10 3.00 30.00
cross-connector for reinforcement KON 09 P30x4 pcs 20 2.50 50.00
Laying of outlets of average 3m (for the connection to the
metal mass, preparation of the measuring connection,
distributor, control cabin, scales...) and connecting to the
C2 lightning strip in the foundation or trench by cross-connector pcs 7 5.00 35.00
KON 01, FeZn, P. The price comprises all required material
and work.

Supply, concreting into the concrete posts and instalation


of the following lightning accessory:
strip FeZn P25x4 m 15 2.00 30.00
measuring connection KON01, Rf, for P30x4 pcs 4 3.00 12.00
C3 box for the measuring connection ZON05 pcs 4 20.00 80.00
clip for downpipe KON10A, Rf-V, ∅(downpipe) for P30x4 pcs 2 3.00 6.00
clamp for downpipe KON06, Rf, for ∅8 pcs 2 3.20 6.40
connecting clip KON02, Rf, for P30x4 on ∅8 pcs 4 3.20 12.80
Supply, laying and instalation on the roof of the following
lightning accessory:
round conductor RH3, Rf, Ф8 m 45 3.00 135.00
roof support for steel sheat roofing or similar SON 16, Rf,
C4 pcs 40 2.50 100.00
for Ф8 complete with sealing and bolt
connecting clip KON04, Rf, for Ф8 pcs 8 2.20 17.60
contact joint between round conductors and metal masses
pcs 4 1.50 6.00
KON05, Rf, for Ф8
Supply and instalation of cables into cable racks and under
plaster complete with all required pipes and distribution
boxes, equipped with corresponding clips:
C5 m 50 0.70 35.00
P/F-Y 1x6 mm2
P/F-Y 1x10 mm2 m 20 1.00 20.00
P/F-Y 1x16 mm2 m 5 1.70 8.50
Connecting of all metal masses (fence, metal stairs, doors,
windows, distributor, gas instalation, KDO...), to the
C6 grounding and potential equalization system, complete with pcs 10 5.00 50.00
all required connecting material and accessory.

Supply and assemble the instalation for potential


equalization in sanitary facilities and heating substations by
conduit P/F 6mm2. All metal masses (water supply pipesi,
etc.) to be connected to the bus bar for the additional
C7 pcs 3 7.00 21.00
potential equalization DIP and connect by conduit P/F
10mm2 bus bar to the the main potential equalization GIP

TOTAL C: 805.30
RECAPITULATION
6. SANITARY FACILITIES M+ CLEANING LADY
No ITEM DESCRIPTION Total EUR
A ELECTRICAL WIRING FOR LIGHTING, SOCKET AND OTHER CONSUMERS 4,392.00
B FIRE ALARM INSTALATION 193.50
C LIGHTNING PROTECTION INSTALATION AND POTENTIAL EQUALIZATION 805.30
TOTAL 6: 5,390.80

7. LOW TENSION CONNECTION AND ELECTRIC POWER WIRING; GRO, RKo, KPO
DISTRIBUTORS
Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 116 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

A. LOW TENSION CONNECTION AND ELECTRIC POWER WIRING

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


Supply and laying of power cables into already excavated
trench and inserting into laid pipes, complete with
preparation of corresponding cable endings, conecting
material cable ducts and sealing elements at points of
insertion through foundations. The price includes all
auxiliary works, handling and transport, all material and
work:
A1
from GRO to distributers RKo, KPO1, KPO2, GR(3.12),
GR(1.7), GR(3.13), EVAPORATOR
PP00 4x16 mm2 m 150 7.00 1,050.00
from KPO1 i KPO2 to the distributors RS(2.8/3.6) and
RS(2.9/3.7)
PP00-Y 5x10 mm2 m 95 5.50 522.50
TOTAL A: 1,572.50

B. GRO, RKo, KPO DISTRIBUTORS

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


Supply, mounting and connecting of self standing cable
cabinet KPO1, type PLA mannufactured in IP65, with single
door, complete with insulation panel and all instalation and
connecting accessory,consisting of the following switching
and instalation items
MICRO SWITCH C60N 1P 10A C (pcs 1)
MICRO SWITCH C60N 1P 16A C (pcs 1)
SHIP LAMP WITH 60W BULB (pcs 1)
EARTHED POWER OUTLET 2P+E 10/16A (pcs 1)
ISFT160 SWITCH FUSE CUTOUT (pcs 1)
B1 ISFT100 SWITCH FUSE CUTOUT (pcs 3) set 1 550.00 550.00
ENCLOSED FUSE NVO RATING 00 35A (pcs 3)
ENCLOSED FUSE NVO RATING 00 25A (pcs 6)
All completeted with clips, copper bus bars 30x5 mm, cable
inserton ducts connecting conducts P/F of corresponding
cross section and insulation colour, cable ducts,
nameplates and warning plates together with other small
items and connecting accessory. Accessible parts under
voltage to be covered by insulation plate. A folder for
documentation to be provided. The price comprises the
value of all required works and material. (lump sum)

TOTAL B: 550.00

RECAPITULATION
7. LOW TENSION CONNECTION AND ELECTRIC POWER WIRING; GRO, RKo, KPO
DISTRIBUTORS
No ITEM DESCRIPTION Total EUR
A LOW TENSION CONNECTION AND ELECTRIC POWER WIRING 1,572.50
B GRO, RKo, KPO DISTRIBUTORS 550.00
TOTAL 7: 2,122.50

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 117 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

8. TESTING AND MEASURING:


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. GENERAL

No ITEM DESCRIPTION Unit Qty Unit Price Total EUR


Testing, measuring, check, trial operation, inspections,
issuing of measuring protocols and similar, in accordance
with quallity programs (measuring and issuing of the
certificate on measured mean illumination of rooms,
measuring of insulation resistance of particular el. circuits
and supply lines, with certificate issuing, the issuing of
certificate of protection efficacy against indirect contact,
issuing of the certificate of measured transient resistance of
protective earthing of equpment, functional testing of
emergency power cut-out, functional testing of emergency
A1 lighting, testing of the function of connections, putting into set 1 1,500.00 1,500.00
the full opperation, trial run and the preparation of the
revision log of lightning instalation)

The testing and measuring applies to all distributors,


lighting and outlet's instalation, telephone-computer
instalation, instalation of public adressing system, lightning
instalation, fire alarm instalation, generator, i.e. all other
items comprised by the bill of rates items 1, 2, 3, 4, 7 and 8

TOTAL A: 1,500.00

8. TESTING AND MEASURING


No ITEM DESCRIPTION Total EUR
A GENERAL 1,500.00
TOTAL 8: 1,500.00

RECAPITULATION

IVb /ELECTRICAL INSTALLATIONS PHASE


No ITEM DESCRIPTION Total
1 EARTH WORKS; CABLE CONDUIT 10,842.40
2 THE MAIN BUILDING OF BORDER POLICE AND CUSTOM 31,862.66
3 MAIN SHED 7,813.50
5 CONTROL CABIN TYPE 3 14,800.00
6 SANITARY FACILITIES M+W 6,661.29
7 SANITARY FACILITIES M+ CLEANING LADY 5,390.80
LOW TENSION CONNECTION AND ELECTRIC POWER WIRING; GRO, RKo,
8 2,122.50
KPO DISTRIBUTORS
9 TESTING AND MEASURING 1,500.00
TOTAL IVb: 80,993.15

BOSNIA I HERZEGOVINA
"CORRIDOR Vc MOTORWAY PROJECT" Page 118 Construction of the BCP Bijaca, LOT III, PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

IVc HVAC
Note: In cases where certain equipment is specifically named, it is only an indication of the technical
features the offered equipment would need to comply with.
1. LPG INSTALLATION
Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
Each point in this cost estimate must include the supply, assembly, connecting, balancing and calibration, and
delivery of the item in a fully functional state, by being put into operation by the contractor or licensed
maintenance company, depending on the type of equipment. The item has to include the estimate of all
connecting, assembly, retaining and other material required for full functioning of the respective item, drilling of
openings in the wall and floor and their subsequent rehabilitation. When preparing the tender, the valid
regulations for certain types of installations have to be taken into account. The contractor shall bear the costs of
all transport, installation and assembly of the equipment, including all construction assistance and providing of
materials, and all the works in the cost estimate shall be quoted per unit prices.

A. LPG INSTALLATION
Supply, transport and installation of the following
equipment and material:
Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Gas connection for the objects: 2.8, 2.9.
connection pipe, PEHD in compliance with the standard
ISO 4437, SDR 11; d63x5,8
PEHD electro-fusion reducer d63/d32
bushing PEHD/steel d32/DN25 (Ø33,7x3,25) - 1 piece
steel pipe NO25 (Ø33,7x3,25)-2m
casing pipe NO50x3,65-1.5m
pipe elbow 90° NO25
A.1 reducer DN25/NO20 set 2.00 336.94 673.88
gas ball valve with threaded connection DN20 PN4
coupling DN20
dirt trap DN20; PN4
detachable joint DN20
sheet metal cabinet 400x 600x 200
warning labels: prohibited use of sparking tools, fire
hazard, smoking prohibited
Calculation for the set
PEHD pipes

Pipes made from high density polyethylene (PE 100)


fabricated in accordance with the ISO 4437, SDR 11; (S5)
PN 6 standard
Included: Pipe fittings, bushing members PEHD/steel and
A.2 couplings made from high density polyethylene for
electrofusion welding, the

Calculation per metre


d32 x 3,0 m 10.00 2.56 25.60
d63 x 5,8 m 200.00 7.16 1,432.00
Reducer PE 100 SDR 11 (ISO S-5)
A.3
d63/d32 pcs. 2.00 14.32 28.64
T-piece 90° PE 100 SDR 11 (ISO S-5)
A.4
d63 / d63 pcs. 1.00 26.59 26.59
Elbow 90° PE 100 SDR 11 (ISO S-5)
A.5
d63 x 5,8 pcs. 3.00 19.94 59.82
Casing pipe for the gas pipeline installation passing below a
road, road channels, electrical and PTT cables, fabricated
A.6
by cutting according to the lengths measured on site - made
of steel, sandblasted, surface protection
Calculation per metre
PE Ø90 X 5,4 m 115.00 22.50 2,587.50

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 119
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Yellow PVC strip for marking the gas pipeline with the sign
A.7 "POZOR PLIN", also containing the copper detection m 200.00 0.26 52.00
conductor for installation above the gas pipeline
Steel pipes
Supply and installation of the steel seamless pipes made of
Č.12.12, DIN 2441, with ends to be welded on site,
mechanical cleaning and corrosion protection.
Steel elbows, T-pieces, reducers and similar, with the ends
A.8 prepared for welding, which have been
Calculation per metre.
DN 15 , Ø21,3 X 2,65 m 6.00 14.83 88.98
DN 20 , Ø26,9 X 2,65 m 3.00 15.85 47.55
DN 25 , Ø33,7 X 3,25 m 6.00 17.90 107.40
Gas ball valve
Gas ball valve, in compliance with DIN 3357/1 and DIN
A.9
3230/2, PN4, with a union fitting and gaskets
dimension DN 15 pcs. 2.00 18.41 36.82
TOTAL for LPG INSTALLATIONS: 5,166.78

B. PRELIMINARY WORKS AND EARTHWORKS


Supply, transport and installation of the following
works, equipment and material:
Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Marking the excavation route for placement of the gas
B.1 m 200.00 0.51 102.00
pipeline installation

It includes all the work on staking out of all objects,


together with the installations; all measurements related
to the transfer of the design data on the site and vice
versa, placement and maintenance of the stakeout marks
and boards with chainage marks on the site, from the
commencement of the works until the delivery of all
works to the investor, and as-built survey.

B.2 Trench excavation in the ground m3 140.00 1.53 214.20

Excavation of the trench in the ground to place the pipes


from the evaporator station to the object, with the
following dimensions (width= 0,7m, depth =1m, total
length=50m)

B.3 Trench bottom levelling m2 140.00 0.41 57.40


B.4 Sand supply and sand spreading m3 20.00 12.78 255.60
Supply of and sand spreading up to 5-10 cm thick, and
after the placement of the pipe backfilling with sand
above the pipe up to the height of 10 cm.
B.5 Backfilling of the trench after pipe installation m3 120.00 1.64 196.80

Backfilling of the trench after the pipe is assembled and


pressure test carried out, in layers up to 30cm thick, with
compacting and wetting. Loading, disposal and unloading
of excess material at the landfill chosen by the
contractor.

All the costs of disposal of the material are included in the


item: obtaining the approval from the competent
authority to dispose of the material, disposal of material
in compliance with the requirements of the competent
authority etc.

B.6 Spreading and levelling of excess soil m3 20.00 1.43 28.60


TOTAL for PRELIMINARY WORKS AND EARTHWORKS: 854.60

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 120
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

RECAPITULATION
1. LPG INSTALLATION
No. DESCRIPTION Total
A LPG INSTALLATION 5,166.78
B PRELIMINARY WORKS AND EARTHWORKS 854.60
TOTAL 1: 6,021.38

2. OBJECTS 2.7. ( BORDER CUSTOMS AND POLICE BUILDING), and 2.4. (CONTROL BOOTHS)
Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. HEATING, AIR-CONDITIONING AND VENTILATION
Supply, transport and installation of the following
equipment and material:
Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Panel radiators

Steel plate flat radiator, with central connections on the


bottom. The radiator is standard-supplied with the
radiator valve, bleed valve, drain plug and blind plug. The
item includes all support accessories for mounting on the
A.1 wall, and angle tie for connecting to the pipes in the wall.

Type such as Vogel&Noot T6


VN T6 21 VM-S/600/520 set 1.00 86.92 86.92
VN T6 22 VM/600/920 set 1.00 133.45 133.45
VN T6 22 VM/600/1000 set 4.00 140.61 562.44
Thermostatic control head for mounting on the radiator
valve to control temperature in the room (ambient
A.2 temperature) pcs. 6.00 7.67 46.02
Type such as: Danfoss RA 2000
Manifold for radiator circuits
Material: brass in compliance with DIN EN 12164; DIN EN
12165

It consists of: flow (supply)/return manifold for the


alternating connection, external thread G1" with flat
sealing, connection joint with REHAU Euro cone G3/4" for
A.3
the REHAU union fitting, integrated bleed valve, ball
valves G1" with the nut and seal, closing plug G1 with a
seal, all mounted on galvanised brackets with sound
insulation. Type such as:

Type such as REHAU HLV:


HLV 6 (6 circuits) set 1.00 145.21 145.21
Distribution cabinet - wall-mounted
Wall-mounted distribution cabinet, made of galvanised steel
A.4 plate, depth 80 mm
Type such as:
REHAU UP 80-3 (874 x 708 x 80) pcs. 1.00 101.75 101.75

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 121
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Fan coil unit with mixing air streams

Ceiling mounted fan coil unit, for operation with


circulating and fresh air, for the two-pipe heating system
(hot water) and with a direct cooling evaporator. The
supplied item includes a replaceable filter, condensate
tray, facing, intake grille, toes, 3-way modulating heating
valve, mixing section with fresh air connection from above
(through the ceiling), protection from freezing,
microprocessor, 3-speed fan. Together with the fan coil,
an external 3,5kW cooling power unit is supplied, in a set
A.5 with the expansion valve and 12V transformer which is set 4.00 4,549.48 18,197.92
installed in the convector as part of the service. The
entire system is controlled by Matrix 4000

Type such as: GEA Flex-Geko Comfort


External unit: Qh=3,5kW
Control Matrix 4000: OP44C
Fan coil unit: GF61.MDW4.M80A2

Steel plate for fresh air intake (per cabin): 20kg

Calculation for the set.


Pressure relief damper
Pressure relief damper for mounting on the inspection
A.6
booth
Type such as: Klimaoprema PŽ-T 200*390 pcs. 4.00 32.21 128.84
Steel seamless pipes

Installation of steel seamless pipes for hot water


distribution, flat, in compliance with DIN 2448, with
support and connection material for insulated pipes, with
prior mechanical cleaning of rust, coated with a primer
A.7 and two coats of varnish resistant to the temperature up
to 150°C, with 30 or 40 mm thick mineral wool insulation,
in aluminium casing 0,6mm thick

Calculation per metre.


DN 20 (Ø26,9x2,65), insulation s=30mm m 80.00 15.85 1,268.00
DN 25 (Ø33,7x3,25), insulation s=30mm m 20.00 17.90 358.00
Pre-insulated pipes for underfloor distribution from the
distribution cabinets to the radiators

Round, factory pre-insulated PE-X/Al/PE pipes from cross-


linked high-pressure polyethylene with a protective
diffusion coat, for underfloor distribution of hot water to
A.8 the radiators. Insulation PE foam with PE foil, resistant to
wear, corrosion, impervious to moisture. Supplied in a
coil.

Type such as REHAU RAUTITAN stabil


Ø16,2x2,6 m 60.00 4.09 245.40
Automatic air vent
A.9 pcs. 2.00 6.14 12.28
Automatic air bleeder, dimensions 1/2".
Ethylene glycol for charging the installation, to prevent
A.10 l 25.00 3.07 76.75
freezing during the winter period
Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 122
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Mono SPLIT air conditioner for air-conditioning of the


Police office in object 2.7., with the inverter and
compulsory installed auto-restart option, with the
accompanying wired remote controller and installation
material
Cooling effect: Qh=2,5 kW
Heating effect: Qg=3,4 kW
Interior unit:
Dimensions (l*h*w): 800*295*215 mm
Mass: 9 kg

A.11 Type such as: Daikin FTXS25G pcs. 1 set 1.00 898.34 898.34
External unit:
Electrical connection: ~230/1/50
Dimensions (l*h*w): 765*550*285 mm
Mass: 34 kg
Type such as: Daikin RXS25G pcs. 1

Wired remote controller: Type such as BRC944 pcs. 1

Total pipe length for R-410A refrigerant: m 5


Calculation for the set
Mono SPLIT air conditioner for air-conditioning of
Customs' offices in object 2.7., with the inverter and
installed auto-restart option, with the accompanying wired
remote controller and installation material
Cooling effect: Qh=3,5 kW
Heating effect: Qg=4,0 kW
Interior unit:
Dimensions (l*h*w): 840*840*204 mm
Mass: 19 kg
Type such as: Daikin FCQ35C pcs. 1
A.12 set 1.00 1,348.28 1,348.28
External unit:
Electrical connection: ~230/1/50
Dimensions (l*h*w): 765*550*285 mm
Mass: 34 kg
Type such as: Daikin RXS35G pcs. 1

Wired remote controller: Type such as BRC944 pcs. 1

Total length of pipes for R-410A refrigerant: m 5


Calculation for the set
PVC draining pipes for the condensate - hard
Hard PVC pipes for condensate draining, flat, with all
accompanying connecting and support accessories,
A.13 including pipe fittings
Calculation per metre
Ø 32 m 10.00 2.56 25.60
TOTAL for HEATING, AIR-CONDITIONING AND VENTILATION: 23,635.20

RECAPITULATION
2. OBJECTS 2.7. ( BORDER CUSTOMS AND POLICE BUILDING), and 2.4. (CONTROL BOOTHS)
No. DESCRIPTION Total
A HEATING; DHW; AIR-CONDITIONING AND VENTILATION 23,635.20
TOTAL 2: 23,635.20

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 123
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

3. OBJECT 2.8. (SANITARY FACILITY)


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. HEATING AND DHW
Supply, transport and installation of the following
equipment and material:
Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Wall mounted gas-fired condensing unit
Wall mounted condensing circular boiler made of ingot steel
with the Matrix burner and closed combustion chamber,
safety valve and own programmable control unit
Nominal thermal effect: 4,8-19,0 kW (at 50/30°C)
Nominal thermal effect: 4,3-17,2 kW (at 80/60°C)
Nominal heat load: 4,5-17,9 kW
LPG connection pressure: 50 mbar
A.1 Electrical connection: ~1/230/50 set 1.00 2,359.10 2,359.10
Flue/Air intake connection: Ø60/100 mm
Gas connection: 1/2"

Type of unit: such as Viessmann Vitodens 200-W, tip WB2B

Installed temperature control of the supply line controlled by


ambient conditions, Type such as: Vitotronic 200 - H01
Type: such as Viessmann Vitotronic 200, tip H01
Calculation for the set.
Flue-air intake set
A set of flue-air intake system for fitting through the roof
AZ - routed through the roof Ø60/100mm
A.2 Universal roof clamp D=100mm set 1.00 279.17 279.17
AZ - inspection piece flat Ø60/100mm
AZ - slip coupling Ø60/100mm
Calculation for the set.
Standing tank for domestic hot water
DHW steel standing tank, with Caraprotect glazing, internal
heating, insulated. 300 litres volume, with flange opening.
The tank is equipped with connecting joints for the tank
temperature sensor and a thermometer

A.3 The tank has the following characteristics: set 1.00 775.63 775.63
Tank volume: V (litres): 160
Permanent effect at 70/50°C: Q (kW): 25
Type such as: Viessmann Vitocell 100-W (CVA)
Dimensions: Ø581mm, H=1189mm
Calculation for the set.
DHW expansion vessel
Membrane flow ("flowfresh") expansion vessel, volume 12
litres, maximum permissible pressure 10 bars. All metal
parts in contact with the water are made of stainless steel,
A.4 with butyl bellows in compliance with protočna DIN 4807 set 1.00 115.04 115.04
T3
Connections: 2 x R 1/2"
Type such as: Pneumatex Aquapresso ADF. 12.10
Calculation for the set.
Safety group for DHW, in compliance with DIN 1988,
consisting of a block valve, check valve, diaphragm safety
valve and connection for the pressure gauge, for tanks up
A.5 to 200 litres capcaity, DN15/R3/4", 10 bars set 1.00 119.64 119.64
Type such as: Viessmann
Calculation for the set.

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 124
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
DHW circulation pump

Domestic hot water circulation pump for fitting in the


recirculation DHW circuit, with return flow blocking valve,
impeller suitable for drinking water, integrated timer,
temperature control and routine for the recognition and
support for startup of thermal disinfection of the boiler
A.6 set 1.00 155.43 155.43

Medium: drinking water


Pipe connection threaded 1/2"
El. connection V/Ph/Hz = ~230/1/50
Type such as: WILO Star-Z 15 TT
Calculation for the set.
Panel radiators

Steel plate flat radiator, with central connections on the


bottom. The radiator is standard-supplied with the
radiator valve, bleed valve, drain plug and blind plug. The
item includes all support accessories for mounting on the
wall, and angular kit for connecting to the pipes in the
A.7
wall.

Type such as Vogel&Noot T6


VN T6 21 VM-S/600/720 set 1.00 102.77 102.77
VN T6 22 VM/600/1120 set 3.00 149.81 449.43
VN T6 22 VM/600/1400 set 1.00 173.84 173.84
Thermostatic control head for mounting on the radiator
valve to control temperature in the room (ambient
A.8 temperature) pcs. 5.00 7.67 38.35
Type such as: Danfoss RA 2000
Manifolds for radiator circuits
Material: brass in compliance with DIN EN 12164; DIN EN
12165

It consists of: flow (supply)/return manifold for the


alternating connection, external thread G1" with flat
sealing, connection joint with REHAU Euro cone G3/4" for
A.9 the REHAU union fitting, integrated bleed valve, ball
valves G1" with the nut and seal, closing plug G1 with a
seal, all mounted on galvanised brackets with sound
insulation. Type such as:

Type such as REHAU HLV:


HLV 5 (5 circuits) set 1.00 137.54 137.54
Distribution cabinet - wall-mounted
Wall-mounted distribution cabinet, made of galvanised steel
A.10
plate, depth 80 mm
Type such as: REHAU UP 80-2 (574 x 708 x 80) pcs. 1.00 80.27 80.27
Copper pipes for the distribution of heating

Hard copper pipes, for hot water distribution from the


heating station to the wall-mounted distribution cabinets,
flat, in compliance with DIN 1786, with all fixing and support
A.11 accessories, various fittings such as bends, T-pieces,
reducers and similar,
Calculation per metre
Ø 28 x 1,5 mm m 12.00 10.74 128.88

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 125
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Pre-insulated pipes for underfloor distribution from the
distribution cabinets to the radiators

Round, factory pre-insulated PE-X/Al/PE pipes from cross-


linked high-pressure polyethylene with a protective
diffusion coat, for underfloor distribution of hot water to
A.12 the radiators. Insulation PE foam with PE foil, resistant to
wear, corrosion, impervious to moisture. Supplied in a
coil.

Type such as REHAU RAUTITAN stabil


Ø16,2x2,6 m 100.00 4.09 409.00
Heating system valves
Pipe valves for hot water with the accompanying elements
for installation in the pipeline
Ball valve
DN 15, NP 10 - threaded pcs. 4.00 6.14 24.56
DN 20, NP 10 - threaded pcs. 4.00 7.67 30.68
A.13 DN 25, NP 10 - threaded pcs. 4.00 9.20 36.80
Dirt trap
DN 25, NP 10 - threaded pcs. 1.00 12.78 12.78
Check valve
DN 15, NP 10 - threaded pcs. 1.00 5.11 5.11
DN 25, NP 10 - threaded pcs. 3.00 8.18 24.54
Round pressure gauge
Round pressure gauge with bourdon tube Ø100, 0-6 bars,
A.14 set 1.00 22.50 22.50
with a tap and seal
Calculation for the set.
Thermometer, glass in metal housing, flat, with the
A.15 accompanying sleeve coupling for installation in the set 1.00 17.38 17.38
relevant pipeline 0-130°C
Water outlet tap
A.16 pcs. 2.00 6.14 12.28
Inlet /outlet tap R1/2˝
PVC draining pipes for the condensate - hard
Hard PVC pipes for condensate draining, flat, with all
accompanying connecting and support accessories,
A.17 including pipe fittings
Calculation per metre
Ø 32 m 3.00 2.56 7.68
TOTAL for HEATING AND DHW: 5,518.40

RECAPITULATION
3. OBJECT 2.8. (SANITARY FACILITY)
No. DESCRIPTION Total
A HEATING AND DHW 5,518.40
TOTAL 3: 5,518.40

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 126
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

4. OBJECT 2.9. (SANITARY FACILITY)


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. HEATING AND DHW
Supply, transport and installation of the following
equipment and material:
Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Wall mounted gas-fired condensing unit
Wall mounted condensing circular boiler made of ingot steel
with the Matrix burner and closed combustion chamber,
safety valve and own programmable control unit
Nominal thermal effect: 4,8-19,0 kW (pri 50/30°C)
Nominal thermal effect: 4,3-17,2 kW (pri 80/60°C)
Nominal heat load: 4,5-17,9 kW
LPG connection pressure: 50 mbar
A.1 Electrical connection: ~1/230/50 set 1.00 2,359.10 2,359.10
Flue/Air intake connection: Ø60/100 mm
Gas connection: 1/2"

Type of unit: such as Viessmann Vitodens 200-W, tip WB2B

Installed temperature control of the supply line controlled by


ambient conditions, Type such as: Vitotronic 200 - H01

Tip: kao Viessmann Vitotronic 200, tip H01


Calculation for the set .
Flue-air intake set
A set of flue-air intake system for fitting through the roof
AZ - routed through the roof Ø60/100mm
A.2 Universal roof clamp D=100mm set 1.00 279.17 279.17
AZ - inspection piece flat Ø60/100mm
AZ - slip coupling Ø60/100mm
Calculation for the set .
Standing tank for domestic hot water
DHW steel vertical tank, with Caraprotect glazing, internal
heating, insulated. 300 litres volume, with flange opening.
The tank is equipped with connecting joints for the tank
temperature sensor and a thermometer

A.3 The tank has the following characteristics: : set 1.00 794.55 794.55
Tank volume: V (litres): 200
Permanent effect at 70/50°C: Q (kW): 25
Type such as: Viessmann Vitocell 100-W (CVA)
Dimensions: Ø581mm, H=1409mm
Calculation for the set .
DHW expansion vessel
Membrane flow ("flowfresh") expansion vessel, volume 12
litres, maximum permissible pressure 10 bars. All metal
parts in contact with the water are made of stainless steel,
A.4 with butyl bellows in compliance with DIN 4807 T3 set 1.00 115.04 115.04

Connections: 2 x R 1/2"
Type such as: Pneumatex Aquapresso ADF. 12.10
Calculation for the set .

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 127
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Safety group for DHW, in compliance with DIN 1988,
consisting of a block valve, check valve, diaphragm safety
valve and connection for the pressure gauge, for tanks up
A.5 to 200 litres capacity, DN15/R3/4", 10 bars set 1.00 119.64 119.64
Type such as: Viessmann
Calculation for the set .
DHW circulation pump

Domestic hot water circulation pump for fitting in the


recirculation DHW circuit, with return flow blocking valve,
impeller suitable for drinking water, integrated timer,
temperature control and routine for the recognition and
support for start-up of thermal disinfection of the boiler
A.6 set 1.00 155.43 155.43
Medium: drinking water
Pipe connection threaded 1/2"
El. connection V/Ph/Hz = ~230/1/50
Type such as: WILO Star-Z 15 TT
Calculation for the set.
Panel radiators
Steel plate flat radiator, with central connections on the
bottom. The radiator is standard-supplied with the radiator
valve, bleed valve, drain plug and blind plug. The item
includes all support accessories for mounting on the wall,
and angular kit for connecting to the pipes in the wall.
A.7 Type such as Vogel&Noot T6
VN T6 11 VM/600/400 set 1.00 65.45 65.45
VN T6 21 VM-S/600/800 set 1.00 84.36 84.36
VN T6 21 VM-S/600/1120 set 1.00 124.76 124.76
VN T6 22 VM/600/1000 set 1.00 140.61 140.61
VN T6 22 VM/600/1120 set 2.00 149.81 299.62
Thermostatic control head for mounting on the radiator
valve to control temperature in the room (ambient
A.8 temperature) pcs. 6.00 7.67 46.02
Type such as: Danfoss RA 2000
Manifold for radiator circuits
Material: brass in compliance with DIN EN 12164; DIN EN
12165
It consists of: flow (supply)/return manifold for the
alternating connection, external thread G1" with flat sealing,
connection joint with REHAU Euro cone G3/4" for the
A.9 REHAU union fitting, integrated bleed valve, ball valves G1"
with the nut and seal, closing plug G1 with a seal, all
mounted on galvanised brackets with sound insulation.
Type such as:
Type such as: REHAU HLV:
HLV 6 (6 circuits) set 1.00 145.21 145.21
Distribution cabinet - wall-mounted
Wall-mounted distribution cabinet, made of galvanised steel
A.10 plate, depth 80 mm
Type such as:
REHAU UP 80-3 (874 x 708 x 80) pcs. 1.00 100.72 100.72
Copper pipes for the distribution of heating

Hard copper pipes, for hot water distribution from the


heating station to the wall-mounted distribution cabinets,
flat, in compliance with DIN 1786, with all fixing and
A.11 support accessories, various fittings such as bends, T-
pieces, reducers and similar,

Calculation per meter.


Ø 28 x 1,5 mm m 12.00 10.74 128.88

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 128
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Unit Price
No. DESCRIPTION Unit Quantity Total EURO
EURO
Pre-insulated pipes for underfloor distribution from the
distribution cabinets to the radiators

Round, factory pre-insulated PE-X/Al/PE pipes from cross-


linked high-pressure polyethylene with a protective
diffusion coat, for underfloor distribution of hot water to
A.12 the radiators. Insulation PE foam with PE foil, resistant to
wear, corrosion, impervious to moisture. Supplied in a
coil.

Type such as: REHAU RAUTITAN stabil


Ø16,2x2,6 m 70.00 4.09 286.30
Heating system valves
Pipe valves for hot water with the accompanying elements
for installation in the pipeline
Ball valve
DN 15, NP 10 - threaded pcs. 4.00 6.14 24.56
DN 20, NP 10 - threaded pcs. 4.00 9.20 36.80
A.13 DN 25, NP 10 - threaded pcs. 4.00 12.27 49.08
Strainer
DN 25, NP 10 - threaded pcs. 1.00 12.78 12.78
Check valve
DN 15, NP 10 - threaded pcs. 1.00 5.11 5.11
DN 25, NP 10 - threaded pcs. 3.00 8.18 24.54
Round pressure gauge with bourdon tube Ø100, 0-6 bars,
A.16 set 1.00 22.50 22.50
with a tap and seal
Thermometer, glass in metal housing, flat, with the
A.15 accompanying sleeve coupling and mounting bushing in set 1.00 17.38 17.38
the relevant pipeline 0-130°C
Water outlet tap
A.16 pcs. 2.00 6.14 12.28
Inlet/outlet tap R1/2˝
PVC draining pipes for the condensate - hard
Hard PVC pipes for condensate draining, flat, with all
accompanying connecting and support accessories,
A.17 including pipe fittings
Calculation per meter.
Ø 32 m 3.00 2.56 7.68
TOTAL for HEATING AND DHW: 5,457.57

RECAPITULATION
4. OBJECT 2.9. (SANITARY FACILITY)
No. DESCRIPTION Total
A HEATING AND DHW 5,457.57
TOTAL 4: 5,457.57

HVAC (PHASE IV)


No. DESCRIPTION Total
1 LPG INSTALLATION 6,021.38
2 OBJECTS 2.7., and 2.4. (CONTROL BOOTHS) 23,635.20
3 OBJECT 2.8. (SANITARY FACILITY) 5,518.40
4 OBJECT 2.9. (SANITARY FACILITY) 5,457.57
TOTAL IVc: 40,632.55

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 129
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

IV/ WATER SUPPLY PHASE


Note: In cases where certain equipment is specifically named, it is only an indication of the technical
features the offered equipment would need to comply with.

IV a/ INTERIOR WATER SUPPLY AND DRAINAGE


Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
The specification includes works pertaining to execution of the installations within buildings, “up to 1 m” outside
each of the building engineering structures, as follows:
- sanitary water installation
- sanitary-faecal water drainage installation
2.7. BORDER CUSTOMS AND POLICE BUILDING
A. WATER SUPPLY INSTALLATIONS

Unit Price
No. Item Description Unit Qty Total Euro
Euro
A1 Polyethylene PE-100 water supply pipes.
Supply and installation of PE-100 polyethylene water supply pipes
of 10 bar operating pressure, for execution of water supply network.
The pipes should conform to EN 12201, ISO 4437, DIN 8074/75
requirements.

The pipeline shall be connected using electric welding. The item


includes complete labour required for installation of the pipes with
all connecting and sealing material.
d=20 mm m' 6.00 3.58 21.48
The price for m1 finished work.
A2 PP-R 80 water supply pipes
Supply and installation of composite PP-R 80 SDR 7.4 water supply
pipes for execution of internal water supply installation of hot and
cold water, as well as circulation main, including all parts required
for connections of the pipes
(such as: couplings, tees, reductions, elbows, electric couplings and
similar), required insulation (the pipes shall be placed within the
sanitary facilities, in the floor and walls), and accessories required
for execution of suspension and fixing of the pipeline, etc.

Pipe quality conforming to DIN 8077, 8078 and 16962.


All the mains placed unobstructed, shall be lined with PLAMAFLEKS
or a similar thermal insulation system.
The installations placed in wall gutters shall have insulation
executed in wrapped felt bands.
ø 20 mm m' 5.00 4.55 22.75
The price for m1 finished work.
A3 PE/PP-R transition fitting
Supply and installation of transition fittings between the PE and PP-
R water supply pipes.
ø 20 mm pcs 1.00 5.11 5.11
The price for 1 piece finished work.
A4 Walled in valve with nickel plated cap
Supply and installation of walled in valves with nickel plated caps.

DN 20 pcs 1.00 14.32 14.32


The price for 1 piece finished work.
Fire extinguisher
Supply and installation of fire extinguishers designed for initial fire
fighting. Place a “location of a fire extinguisher” label above the fire
A5 extinguishers.

fire extinguisher type S-9 pcs 2.00 43.97 87.94


The price for 1 piece finished work.
Water supply grid testing
Testing of completed water supply grid at 10 bar pressure during at
A6 least 6 hours or until all joints have been inspected.
The price for m1 finished work. m' 11.00 0.51 5.61

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 130
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Flushing and disinfecting the pipeline


Flushing and disinfecting the installed pipeline using chlorine. After
a successfully performed pressure test and installation of fittings,
the entire pipeline shall be disinfected using water solution of
chlorine, with concentration of 10 g Cl/m3 of water in the
installation,
A7 with a previous and a subsequent flushing of the installation using
water flow equal to fivefold volume of water in the installation. The
pipeline shall be disinfected and flushed until satisfactory results are
achieved in terms of acceptable properties of potable water.

The price for m1 finished work. m' 11.00 0.51 5.61

TOTAL A 162.82
B. DRAINAGE INSTALLATIONS
Unit Price
No. Item Description Unit Qty Total Euro
Euro
B1 Internal sewer PVC pipes
Procurement, supply and installation of internal sewer PVC pipes
and fittings with couplings. The sewer pipes shall be sealed using
rubber ring seals.
The fittings shall be calculated as a linear metre of the sewer pipe,
with all required accessories, and completely in compliance with
HRN G.C6.512.
The price for m1 finished work.
DN 110 m' 4.00 8.69 34.76
DN 50 m' 9.00 4.09 36.81
PVC ventilation cap
Supply and installation of a PVC ventilation cap to be installed onto
B2 the vertical vent.
DN 50 pcs 1.00 29.65 29.65
The price for 1 piece finished work.
Water impermeability testing
Testing of the entire sewer installation in terms of water
B3 impermeability using 500 mbar static overpressure applied during
30 minutes, all in compliance with EN 1610

The price for m1 finished work. m' 13.00 0.51 6.63


TOTAL B 107.85
C. PLUMBING FIXTURES
Unit Price
No. Item Description Unit Qty Total Euro
Euro
Wash basin
Supply and installation of a wash basin executed in the 1st class
majolica (vitreous china), white, 600/490 mm size, completely
functionally executed with a single handle upright mixer water
C1
faucet corresponding to ARMAL, and a drain fixture (siphon), and all
required accessories and installation material.

The price for 1 piece finished work. pcs 1.00 118.11 118.11

Toilet bowl
Supply and installation of a toilet bowl executed in the 1st class
C2 majolica (vitreous china), white, entirely functional with a solid
plastic lid and seat, toilet cistern (low mounted) connecting to an
angle valve and a floor drain.
The price for 1 piece finished work. pcs 1.00 93.06 93.06
Urinal
Supply and installation of the 1st class majolica (vitreous china)
urinal, white, completely functional execution with a flush valve and
C3 a nickel plated Ø32 mm siphon; sealing and fixing accessories; Ø15
mm cold water supply fixtures.

Calculation per piece of installed urinal. pcs 1.00 125.27 125.27

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 131
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Tankless electric water heater


Procurement, supply and installation of a tankless electric water
heater, complete with all connecting equipment required, installed
C4 below the wash basin in the sanitary facilities.

V=5 l (supplying one fixture) psc 1.00 61.36 61.36


Calculation per piece of installed water heater.

Unit Price
No. Item Description Unit Qty Total Euro
Euro
Wall mirror
Procurement, supply and installation of a wall mirror, 600 x 400 mm
C5 size, 4 mm thick, with grinded edges and all fixing accessories.

Calculation per piece of installed mirror. pcs 1.00 19.43 19.43


Toilet paper roll plastic box

C6 Procurement, supply and installation of plastic boxes for toilet paper


rolls.
Calculation per piece of installed box. pcs 1.00 10.23 10.23
Paper towel roll holder

C7 Procurement, supply and installation of paper towel roll holders at


the wash basins.
Calculation per piece of installed holder. pcs 1.00 15.85 15.85
Liquid soap vessel
Procurement, supply and installation of a 0.3 to 0.5 litre capacity
C8 liquid soap vessel at each of the wash basins.
Calculation per piece of installed vessel. pcs 1.00 9.20 9.20
Toilet bowl cleaning brush
Procurement, supply and installation of a toilet bowl cleaning brush.
C9
Calculation per piece of installed toilet brush. pcs 1.00 10.74 10.74

TOTAL C 463.25

RECAPITULATION
2.7. BORDER CUSTOMS AND POLICE BUILDING

No. ITEM DESCRIPTION Total Euro

A WATER SUPPLY INSTALLATIONS 162.82

B DRAINAGE INSTALLATIONS 107.85


C PLUMBING FIXTURES 463.25
TOTAL 2.7: 733.92

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 132
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

2.8. SANITARY AND WATER FACILITIES FOR MEN AND WOMEN


A. WATER SUPPLY INSTALLATIONS
Unit Price
No. Item Description Unit Qty Total Euro
Euro
Polyethylene PE-100 water supply pipes.
Supply and installation of PE-100 polyethylene water supply pipes
of 10 bar operating pressure, for execution of water supply network.
The pipes should conform to EN 12201, ISO 4437, DIN 8074/75
requirements.
A1
The pipeline shall be connected using electric welding. The item
includes complete labour required for installation of the pipes with
all connecting and sealing material.
d=32 mm m' 4.00 4.55 18.20
The price for m1 finished work.
PP-R 80 water supply pipes
Supply and installation of composite PP-R 80 SDR 7.4 water supply
pipes for execution of internal water supply installation of hot and
cold water, as well as circulation main, including all parts required
for connections of the pipes

(such as: couplings, tees, reductions, elbows, electric couplings and


similar), required insulation (the pipes shall be placed within the
sanitary facilities, in the floor and walls), and accessories required
for execution of suspension and fixing of the pipeline, etc.

A2
Pipe quality conforming to DIN 8077, 8078 and 16962.
All the mains placed unobstructed, shall be lined with
PLAMAFLEKS or a similar thermal insulation system.
The installations placed in wall gutters shall have insulation
executed in wrapped felt bands.
ø 32 mm m' 4.00 7.57 30.28
ø 25 mm m' 32.00 6.24 199.68
ø 20 mm m' 53.00 4.55 241.15
The price for m1 finished work.
PE/PP-R transition fitting
A3 Supply and installation of transition fittings between the PE and PP- pcs 1.00 5.11 5.11
R water supply pipes.
The price for 1 piece finished work.
Walled in valve with nickel plated cap
Supply and installation of walled in valves with nickel plated caps.

A4 DN 32 pcs 2.00 23.01 46.02


DN 25 pcs 1.00 14.32 14.32
DN 20 pcs 1.00 14.32 14.32
The price for 1 piece finished work.
Fire extinguisher
Supply and installation of fire extinguishers designed for initial fire
fighting. Place a “location of a fire extinguisher” label above the fire
A5 extinguishers.

fire extinguisher type S-9 pcs 1.00 43.97 43.97


The price for 1 piece finished work.
Water supply grid testing
Testing of completed water supply grid at 10 bar pressure during at
A6 least 6 hours or until all joints have been inspected.
The price for m1 finished work. m' 93.00 0.51 47.43
Flushing and disinfecting the pipeline
Flushing and disinfecting the installed pipeline using chlorine. After
a successfully performed pressure test and installation of fittings,
the entire pipeline shall be disinfected using water solution of
chlorine, with concentration of 10 g Cl/m3 of water in the installation,

A7 with a previous and a subsequent flushing of the installation using


water flow equal to fivefold volume of water in the installation. The
pipeline shall be disinfected and flushed until satisfactory results are
achieved in terms of acceptable properties of potable water.

The price for m1 finished work. m' 93.00 0.51 47.43

TOTAL A 707.91

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 133
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

B. DRAINAGE INSTALLATIONS

Unit Price
No. Item Description Unit Qty Total Euro
Euro
Polyethylene PE-100 water supply pipes.
Procurement, supply and installation of internal sewer PVC pipes
and fittings with couplings. The sewer pipes shall be sealed using
rubber ring seals.
The fittings shall be calculated as a linear metre of the sewer pipe,
with all required accessories, and completely in compliance with
HRN G.C6.512.

DN 50 m' 30.00 4.09 122.70


B1
DN 75 m' 5.00 5.62 28.10

DN 110 m' 25.00 8.69 217.25

DN 125 m' 4.00 10.23 40.92


DN 160 m' 4.00 14.32 57.28

The price for m finished work.


1

PVC ventilation cap


Supply and installation of a PVC ventilation cap to be installed onto
the vertical vent.
B2 DN 50 pcs 1.00 29.65 29.65
DN 110 pcs 1.00 26.59 26.59
The price for 1 piece finished work.
Water impermeability testing
Testing of the entire sewer installation in terms of water
B3 impermeability using 500 mbar static overpressure applied during
30 minutes, all in compliance with EN 1610

The price for m1 finished work. m' 68.00 0.51 34.68

TOTAL B 557.17

C. PLUMBING FIXTURES
Unit Price
No. Item Description Unit Qty Total Euro
Euro
Wash basin
Supply and installation of a wash basin executed in the 1st class
majolica (vitreous china), white, 600/490 mm size, completely
functionally executed with a single handle upright mixer water faucet
C1 corresponding to ARMAL, and a drain fixture (siphon), and all
required accessories and installation material.

The price for 1 piece finished work. pcs 12.00 118.11 1,417.32
Toilet bowl
Supply and installation of a toilet bowl executed in the 1st class
majolica (vitreous china), white, entirely functional with a solid
C2 plastic lid and seat, toilet cistern (low mounted) connecting to an
angle valve and a floor drain.

The price for 1 piece finished work. pcs 8.00 93.06 744.48

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 134
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Unit Price
No. Item Description Unit Qty Total Euro
Euro
Disabled toilet
Supply and installation of a complete, disabled toilet in unisex
sanitary facilities (shape and size selected by the interior design
engineer), consisting of:
- cantilevered ceramic toilet bowl (1st class), 6 litre flushing
capacity, raised at least 6 cm above the floor, with a removable seat
and lid to facilitate cleaning;
- prefabricated installation element for toilet bowls of 112 cm
installation height, with low-noise in-wall cistern (corresponding to
Geberit Duofix). Self-supporting installation element for use in dry
C3 assembly walls or partition wall structures covered with gypsum-
cardboard tiles, complete with integrated water supply 1/2" angle
valve, low-noise intake valve, drain elbow 110/ mm with a
soundproof seal, a toilet bowl coupling with seals and soundproofing
set, sanitary ware fixing screws and all other accessories required
to complete the installation according to the manufacturer's
instructions.

- in-wall cistern with a push-button manually activating flushing.

The price for 1 piece finished work. pcs 1.00 419.26 419.26
Urinal
Supply and installation of the 1st class majolica (vitreous china)
urinal, white, completely functional execution with a flush valve and
C4 a nickel plated Ø32 mm siphon; sealing and fixing accessories; Ø15
mm cold water supply fixtures.

The price for 1 piece finished work. pcs 6.00 125.27 751.62
Tankless electric water heater
Procurement, supply and installation of a tankless electric water
heater, complete with all connecting equipment required, installed
C5 below the wash basin in the sanitary facilities.

V=5 l (supplying one fixture) pcs 1.00 61.36 61.36


The price for 1 piece finished work.
Wall mirror
Procurement, supply and installation of a wall mirror, 600 x 400 mm
C6 size, 4 mm thick, with grinded edges and all fixing accessories.

The price for 1 piece finished work. pcs 12.00 19.43 233.16
Toilet paper roll plastic box
Procurement, supply and installation of plastic boxes for toilet paper
C7 rolls.

The price for 1 piece finished work. pcs 8.00 10.23 81.84
Paper towel roll holder
Procurement, supply and installation of paper towel roll holders at
C8 the wash basins.

The price for 1 piece finished work. pcs 12.00 15.85 190.20
Liquid soap vessel
Procurement, supply and installation of a 0.3 to 0.5 litre capacity
C9 liquid soap vessel at each of the wash basins.

The price for 1 piece finished work. pcs 12.00 9.20 110.40
Toilet bowl cleaning brush
Procurement, supply and installation of a toilet bowl cleaning brush.
C10

The price for 1 piece finished work. pcs 8.00 10.74 85.92
TOTAL C 4,095.56
RECAPITULATION
2.8. SANITARY AND WATER FACILITIES FOR MEN AND WOMEN
No. ITEM DESCRIPTION Total Euro
A WATER SUPPLY INSTALLATIONS 707.91
B DRAINAGE INSTALLATIONS 557.17
C PLUMBING FIXTURES 4,095.56
TOTAL 2.8: 5,360.64

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 135
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

2.9. SANITARY AND WATER FACILITIES FOR MEN AND JANITOR


A. WATER SUPPLY INSTALLATIONS

Unit Price
No. Item Description Unit Qty Total Euro
Euro
Polyethylene PE-100 water supply pipes.
Supply and installation of PE-100 polyethylene water supply pipes
of 10 bar operating pressure, for execution of water supply network.
The pipes should conform to EN 12201, ISO 4437, DIN 8074/75
requirements.
A1 The pipeline shall be connected using electric welding. The item
includes complete labour required for installation of the pipes with
all connecting and sealing material.

d=32 mm m' 4.00 4.55 18.20


The price for m1 finished work.
PP-R 80 water supply pipes
Supply and installation of composite PP-R 80 SDR 7.4 water supply
pipes for execution of internal water supply installation of hot and
cold water, as well as circulation main, including all parts required
for connections of the pipes
(such as: couplings, tees, reductions, elbows, electric couplings and
similar), required insulation (the pipes shall be placed within the
sanitary facilities, in the floor and walls), and accessories required
for execution of suspension and fixing of the pipeline, etc.
A2
Pipe quality conforming to DIN 8077, 8078 and 16962.
All the mains placed unobstructed, shall be lined with
PLAMAFLEKS
The installationsorplaced
a similar thermal
in wall insulation
gutters system.
shall have insulation
executed in wrapped felt bands.
ø 32 mm m' 11.00 7.59 83.49
ø 25 mm m' 28.00 6.24 174.72
ø 20 mm m' 36.00 4.55 163.80
The price for m1 finished work.
PE/PP-R transition fitting
Supply and installation of transition fittings between the PE and PP-
A3 PCs 1.00 5.11 5.11
R water supply pipes.
The price for 1 piece finished work.
Walled in valve with nickel plated cap
Supply and installation of walled in valves with nickel plated caps.

A4 DN 32 pcs 2.00 23.01 46.02


DN 25 pcs 1.00 14.32 14.32
DN 20 pcs 1.00 14.32 14.32
The price for 1 piece finished work.
Fire extinguisher
Supply and installation of fire extinguishers designed for initial fire
fighting. Place a “location of a fire extinguisher” label above the fire
A5 extinguishers.
fire extinguisher type S-9 pcs 2.00 43.97 87.94
The price for 1 piece finished work.
Water supply grid testing
A6 Testing of completed water supply grid at 10 bar pressure during at
least 6 hours
The price forormuntil
1 all joints
finished have been inspected.
work. m' 79.00 0.51 40.29
Flushing and disinfecting the pipeline
Flushing and disinfecting the installed pipeline using chlorine. After
a successfully performed pressure test and installation of fittings,
the entire pipeline shall be disinfected using water solution of
chlorine, with concentration of 10 g Cl/m3 of water in the installation,

A7
with a previous and a subsequent flushing of the installation using
water flow equal to fivefold volume of water in the installation. The
pipeline shall be disinfected and flushed until satisfactory results are
achieved in terms of acceptable properties of potable water.

The price for m1 finished work. m' 79.00 0.51 40.29


TOTAL A 688.50

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 136
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

B. DRAINAGE INSTALLATIONS
Unit Price
No. Item Description Unit Qty Total Euro
Euro
Polyethylene PE-100 water supply pipes.
Procurement, supply and installation of internal sewer PVC pipes
and fittings with couplings. The sewer pipes shall be sealed using
rubber ring seals.

The fittings shall be calculated as a linear metre of the sewer pipe,


with all required accessories, and completely in compliance with
HRN G.C6.512.
B1 DN 50 m' 34.00 4.09 139.06
DN 75 m' 6.00 5.62 33.72
DN 110 m' 15.00 8.69 130.35
DN 125 m' 5.00 10.23 51.15
DN 160 m' 2.00 14.32 28.64

The price for m finished work.


1

Floor siphon

B2 Procurement, supply and installation of a 150 x 150 mm floor siphon


with a 50 mm diameter horizontal sewer drain.
The price for 1 piece finished work. pcs 3.00 13.80 41.40
PVC ventilation cap
Supply and installation of a PVC ventilation cap to be installed onto
the vertical vent.
B3
DN 50 pcs 2.00 29.65 59.30
The price for 1 piece finished work.
Water impermeability testing
Testing of the entire sewer installation in terms of water
B4 impermeability using 500 mbar static overpressure applied during
30 minutes, all in compliance with EN 1610

The price for m1 finished work. m' 62.00 0.51 31.62


TOTAL B 515.24
C. PLUMBING FIXTURES
Unit Price
No. Item Description Unit Qty Total Euro
Euro
Wash basin
Supply and installation of a wash basin executed in the 1st class
majolica (vitreous china), white, 600/490 mm size, completely
functionally executed with a single handle upright mixer water faucet
C1 corresponding to ARMAL, and a drain fixture (siphon), and all
required accessories and installation material.

The price for 1 piece finished work. pcs 10.00 118.11 1,181.10
Toilet bowl
Supply and installation of a toilet bowl executed in the 1st class
majolica (vitreous china), white, entirely functional with a solid
C2 plastic lid and seat, toilet cistern (low mounted) connecting to an
angle valve and a floor drain.

The price for 1 piece finished work. pcs 6.00 93.06 558.36
Urinal
Supply and installation of the 1st class majolica (vitreous china)
urinal, white, completely functional execution with a flush valve and
C3 a nickel plated Ø32 mm siphon; sealing and fixing accessories; Ø15
mm cold water supply fixtures.

The price for 1 piece finished work. pcs 6.00 125.27 751.62
Unit Price
No. Item Description Unit Qty Total Euro
Euro
Shower bath
Supply and installation of a PVC shower bath, 90/90 cm size,
complete with a single handed mixer faucet of ARMAL type and a
C4 movable showerhead on a vertical guide, and accompanying drain
elements – release valve, nickel plated siphon and overflow, plug
and chain

The price for 1 piece finished work. pcs 3.00 366.60 1,099.80
Paper towel roll holder
Procurement, supply and installation of paper towel roll holders at
C5
the wash basins.
The price for 1 piece finished work. pcs 10.00 15.85 158.50

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 137
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Wall mirror
Procurement, supply and installation of a wall mirror, 600 x 400 mm
C6 size, 4 mm thick, with grinded edges and all fixing accessories.

The price for 1 piece finished work. pcs 10.00 19.43 194.30
Toilet paper roll plastic box
Procurement, supply and installation of plastic boxes for toilet paper
C7 rolls.
The price for 1 piece finished work. pcs 6.00 10.23 61.38
Liquid soap vessel
Procurement, supply and installation of a 0.3 to 0.5 litre capacity
C8 liquid soap vessel at each of the wash basins and the shower baths.

The price for 1 piece finished work. pcs 13.00 9.20 119.60
Toilet bowl cleaning brush
Procurement, supply and installation of a toilet bowl cleaning brush.
C9

The price for 1 piece finished work. pcs 6.00 10.74 64.44
Towel bar
Procurement, supply and installation of towel bars at each of the
C10 shower baths.
The price for 1 piece finished work. pcs 3.00 10.23 30.69
TOTAL C 4,219.79
RECAPITULATION
2.9. SANITARY AND WATER FACILITIES FOR MEN AND JANITOR
No. ITEM DESCRIPTION Total Euro
A WATER SUPPLY INSTALLATIONS 688.50
B DRAINAGE INSTALLATIONS 515.24
C PLUMBING FIXTURES 4,219.79
TOTAL 2.9: 5,423.53

RECAPITULATION
IV d/ INTERIOR WATER SUPPLY AND DRAINAGE
No. DESCRIPTION Total
1 2.7. BORDER CUSTOMS AND POLICE BUILDING 733.92
2 2.8. SANITARY AND WATER FACILITIES FOR MEN AND WOMEN 5,360.64
3 2.9. SANITARY AND WATER FACILITIES FOR MEN AND JANITOR 5,423.53
TOTAL IVd: 11,518.09

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 138
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

V ROAD LIGHTNING
Note: In cases where certain equipment is specifically named, it is only an indication of the technical
features the offered equipment would need to comply with.
Each activity considers: purchase, delivery and installation of inputs, components and materials, and the
requested quality controls, unless clearly stipulated differently.
A. PREPARATORY WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total

A2 Staking out the position of columns pcs 2.00 25.00 50.00

TOTAL A: 50.00

D. CABLES

No ITEM DESCRIPTION Unit Qty Unit Price Total

D3 Cable PPOO-Y 3x1,5 mm2,(1kV,Cu) m 240.00 0.90 216.00


D12 Bracket for 2 cables in the pole (as MMB01/2) pcs 6.00 25.00 150.00
Making and connecting of cable endings Cable PP00 3 x
D15 pcs 12.00 4.00 48.00
1,5 mm2,1kV, Cu
TOTAL D: 414.00

E. STEEL CONSTRUCTION OF LIGHTING POLES

No ITEM DESCRIPTION Unit Qty Unit Price Total

Workshop documentation of pole type SUN 16Z-3,


manufacturing of steel construction in workshop, material
supply and preparation are includedu (constructio steel
E1 pcs 2.00 925.00 1,850.00
S355JR). Anchor bolts, anchor bolts scheme for installation,
test assembly, hot galvanizing, transportation on buildig site
and assembly are included in price.

TOTAL E: 1,850.00

G. LUMINAIRES

Materials and mounting of luminaires, materials and


installation of lamps in luminaires

No ITEM DESCRIPTION Unit Qty Unit Price Total


Simmetrical floodlight in IP-65 ingress protection degree for
HPS-T 400W lamp with built-in control gears without
compensating capacitors and ballast (installed in ORE),
with anti-glare louvre, for mounting on 16m high floodlight
poles (as type LVT-11S-14.
G3 set 8.00 150.00 1,200.00
High pressure sodium lamp NAV-T 400W
SUPER.

Accessories for mounting of floodlights on 16m floodlight


poles (as type P2)
Asimmetrical floodlight in IP-65 ingress protection degree
for HPS-T 400W lamp with built-in control gears without
compensating capacitors and ballast (installed in ORE),
with anti-glare louvre, for mounting on 16m high floodlight
G4 poles (as type LVT-11A-1. set 4.00 165.00 660.00
High pressure sodium lamp NAV-T
400W SUPER.
Accessories for mounting of floodlights on 16m floodlight
poles (as type P2)

TOTAL F: 1,860.00

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca,LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 139
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

H. OTHER WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total

H7 Trial run 0,1*2631,58 pcs 1.00 250.00 250.00

H8 Landscaping 0,1*2631,58 pcs 1.00 500.00 500.00

H10 Measurement of illumination pcs 4.00 50.00 200.00

TOTAL H: 950.00

RECAPITULATION

ROAD LIGHTNING

No ITEM DESCRIPTION Total EUR

A PREPARATORY WORKS 50.00

D CABLES 414.00

E STEEL CONSTRUCTION OF LIGHTING POLES 1,850.00

G LUMINAIRES 1,860.00

H OTHER WORKS 950.00

TOTAL V: 5,124.00

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca,LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 140
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

VI VIDEO CONTROL
Note: In cases where certain equipment is specifically named, it is only an indication of the technical
features the offered equipment would need to comply with.

A CONSTRUCTION WORKS OF ELECTRICAL INSTALLATION


No ITEM DESCRIPTION Unit Qty Unit Price Total
A1 Stake out track m 150 0.83 124.50
Stake out of power and signal cables and other elements
shown in the layout in the design.
A2 Excavation of trench for laying of power and signal cables m³ 48 1.79 85.92
Excavation of trench for laying of power cables and cable
ducts in the category IV/V soil at least 40 cm wide and at
least 80 cm deep.
The trench is used for laying of power and signal cables of
power supply of video system. The trench is used also for
laying galvanized earthing strip Fe-Zn.
A4 Excavation of the duct for instalallation of prefabricated man pcs 1 37.27 37.27
Excavation of the duct for instalallation of prefabricated
manhole type Hidroex Ø800 - V4 with dimensions 1 x 1 x
1,1 m (length x width x height). The duct must exceed the
specified manhole dimensions by 1 to 2 cm to provide air
area.

Supply and delivery of the duct for instalallation of


A5 prefabricated PEHD manhole pcs 1 696.60 696.60

Supply, delivery and mount of the duct for instalallation of


prefabricated PEHD manhole type Hidroex Ø800 - V4 into
the prepared ducts. The mounting and backfilling of
manhole and set cables into ducting are included.
A6 Sand for the subgrade m³ 12 13.30 159.60
Supply, delivery and backfilling of sand for the subgrade, 10
cm thick in excavated ditches and subsequent backfilling
with an additional 10 cm layer.
A9 Pipe PEHD 50mm m 300 3.00 900.00
Supply, delivery and laying of the pipes type PEHD Ø50
mm to the sand foundation in the excavationed crossing
trenches. Item includes pipe packing.
A11 Plastic shields m 165 0.50 82.50
Supply, delivery and laying the 1 m long plastic shields
type V-Š/12 into the trench. The shields are layed with
10cm overlaps.
A12 PVC red warning tape for power cable m 66 0.10 6.60
Supply, delivery and laying red PVC warning tape with
warning labels for power cables into trench.
A13 PVC yellow warning tape for communication cable m 116 0.10 11.55
Supply, delivery and laying red PVC warning tape with
warning labels for communication cables into trench.
A14 Backfill trench m 150 4.00 600.00
Backfill trenches with pounded soil from trench excavation
in layers, compact, lay down FeZn strip 40x4mm for
earthing, lay down PVC shields and warning tape. It
includes alignment shipping and transportation excess soil
to landfill.
A15 Transportation excess soil set 1 110.00 110.00
Plan and transportation excess soil to landfill.

TOTAL A: 2,814.54

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 141
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

B. POWER SUPPLY INSTALLATION WORKS AND MATERIAL

No ITEM DESCRIPTION Unit Qty Unit Price Total


B1 Review and preparation of the route m 150 5.00 750.00
Inspect ducting and clean the pipe before installation and
set cables into ducting.
B2 Galvanized earthing strip m 165 3.00 495.00
Supply, delivery and lay down galvanized earthing strip Fe-
Zn 30x4 mm into excavationed trench.
B3 Connection of galvanized earthing strips pcs 30 7.00 210.00

Make connection between grounding and earthing strips in


the cable trench using cross connectors 80 x 80 mm and
make connection to poles. It includes supply and delivery
crossing couplings and protection contacts in the earth or
trench with bitumen.

B4 Earthing conductor Ø6mm2 kmpl 100 3.00 300.00

Supply, delivery and lay down conductor P/F-Y 6mm , 2

length cca 3m, for earthing of metal parts dividers and other
closed metal boxes. Item includes cable lugs, screws, nuts,
washers and thermo pipes for installation isolation.

B5 Connections of earthing conductor pcs 100 7.00 700.00


Execution of the connection between earthing strip and
P/F-Y conductor in the cable trench using cross connectors
80 x 80 mm. It includes supply and delivery the cross
connectors 80 x 80 mm and connection protection in the
soil or duct with bitumen.

B6 Cable PP/L (HO3VV-F) 2x0,75 mm² m 1,000 0.60 600.00


Supply, delivery and lay down power cable PP/L (HO3VV-F)
2x0,75 mm² into ducting or onto cable trays.
B7 Cable PP (YM) 3x1,5 mm² m 600 0.80 480.00
Supply, delivery and lay down power cable PP (YM) 3x1,5
mm² into ducting or onto cable trays.
B8 Cable PP (YM) 3x2,5 mm² m 400 0.90 360.00
Supply, delivery and lay down power cable PP (YM) 3x2,5
mm² into ducting or onto cable trays.

B9 Cable NYY (PP00) 5x6 mm² m 60 3.50 210.00


Supply, delivery and lay down power cable NYY (PP00) 5x6
mm² into ducting or onto cable trays.
B10 Multimode optical cable UDQ (ZN) BN - 4G50 m 900 2.00 1,800.00
Supply, delivery and put a signal 4-clues multimode optical
cable into ducting. It uses for connection and transmission
data between central control unit and equipment and also
for transmission data between camera system video control
and video dividers.
B11 Multimode optical cable UDQ (ZN) BN - 8G50 m 800 3.00 2,400.00
Supply, delivery and put a signal 8-clues multimode optical
cable into ducting. It uses for connection and transmission
data between central control unit and equipment and also
for transmission data between camera system video control
and video dividers.
B12 Multimode optical cable UDQ (ZN) BN - 12G50 m 300 3.50 1,050.00
Supply, delivery and put a signal 12-clues multimode optical
cable into ducting. It uses for connection and transmission
data between central control unit and equipment and also
for transmission data between camera system video control
and video dividers.
B13 Multimode optical cable UDQ (ZN) BN - 24G50 m 200 4.00 800.00
Supply, delivery and put a signal 24-clues multimode optical
cable into ducting. It uses for connection and transmission
data between central control unit and equipment and also
for transmission data between camera system video control
and video dividers.

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 142
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


B14 Supply and lay down cable RG59B/U LSF m 4,500 0.60 2,700.00

Supply and lay down cable YSLY (HO5VV5-F) 2x0,75 mm²


B15 m 2,500 0.60 1,500.00
Supply, transport and construction of cable branching rack
B16 (Type as Legrand) pcs 2 0.00

B17 Voltage surge protection pcs 22 25.00 550.00


Supply, delivery and installation of cabinet with transparent
door with IP65 protection and voltage surge protection, like
OBO Bettermann - VF 230-AC/DC) for protecting power
supply of the traffic information system and data transfer
protection 130V, VG-C/DC-PH

Combination from fuse and residual current circuit breaker


B18 3/2/0,03A (type as Legrand) pcs 95 5.00 475.00
Combination from fuse and residual current circuit breaker
B19 6/2/0,03A (type as Legrand) pcs 53 6.00 318.00

B20 Cable tray PK 100 m 350 9.00 3,150.00


Supply, delivery and mounting cable tray PK 100 on
construction marquee, including fixing accessories

Cable tray PK 100 with cover


B21 m 50 9.00 450.00
Supply, delivery and mounting cable tray PK 100 with cover
on construction marquee or walls, including fixing
accessories
B22 Cable tray PK 200 m 900 14.00 12,600.00
Supply, delivery and mounting cable tray PK 200 on ceiling
construction, including fixing accessories
B23 Steel pipe Ø 1" m 100 5.50 550.00
Supply, delivery and mounting of steel pipe Ø 1" on
construction marquee

B24 Transportation costs of materials set 1 200.00 200.00


Transportation costs of materials and removal of
excess/waste material to dump

TOTAL B: 32,648.00

C. INFORMATION EQUIPMENT
No ITEM DESCRIPTION Unit Qty Unit Price Total
C1 Software for video monitoring and charge system set 1 48,350.00 48,350.00

Software for video monitoring in accordance to


technological solution and with possibility of the
identification driver control and cargo at border crossing.
The system could be expanded.
Possibility of the subsystem connection with:
- changeable traffic signalisation equipment, information
panel and gates
- video monitoring and video detection equipment
- circuits for power supply

C2 Gates pcs 6 992.50 5,955.00


Supply and mounting gate for camera control with arm
length 3m. Networking through IP protocol.
C3 Cameras with lens pcs 21 950.00 19,950.00
Supply and mounting the high resolution camera (5 Mega
pixel) with external input and output and RS-485 interface.
Networking through IP protocol. It includes the set with
shelf, suited unit for the stake mounting.

C4 Cameras for the vehicle registration recognition with lens pcs 36 1,180.00 42,480.00
Supply and mounting the camera for the vehicle registration
recognition (1 Mega pixel), 24V DC, external input and
output and RS-485 interface. Networking through IP
protocol.

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 143
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total

C5 Movable (rotation) camera pcs 8 2,547.00 20,376.00

Supply, delivery and mounting the movable (rotation)


camera fixed on stake, 22x zoom objectiv with autoiris. The
zoom possibility is 22x optical and 10x digital, programming
alarm with priority selection, digital processing channel,
horizontal angle 48°, remote control through keyboard,
resolution 470 TV lines, rotation 360°, working temperature
from -25° to 50°C, auto white balance. It i suitable for traffic
control. Remote control through PC, functional testing of
processing unit. Sensibility min. 0,01 lx. Networking through
IP protocol. It includes the set with shelf, suited unit for the
stake mounting, voltage surge protection and optical
converter RS 232C-RS 485, min. IP66 protection.

C6 External unmovable camera pcs 18 683.00 12,294.00


Supply, delivery and mounting the unmovable camera fixed
on overhang. It includes the set with shelf, suited unit for
the stake mounting, voltage surge protection and optical
converter RS 232C-RS 485, min. IP66 protection.
C7 Internal unmovable camera pcs 75 498.00 37,350.00

Supply, delivery and mounting the unmovable camera fixed


in buildings. It includes the set with shelf, suited unit for the
stake mounting, voltage surge protection and optical
converter RS 232C-RS 485.
C8 Video rack for rotation camera pcs 1 1,175.00 1,175.00

Supply, delivery and mounting the video rack for setting of


the video equipment and the equipment for data transfer of
rotation camera. It includes supply, delivery and:
- mounting rack on stake
- mounting voltage surge protection 275V, 20kA in the rack
- put into and connect cables
- mounting cable inlets
- mounting terminal blocks 4 mm2 (9 pieces)
- voltage surge protection for coaxial cable 275V, 8kA
- cassette for the optic acceptance and distribution
- rectifier 230V/(6/12/24)V
- networking through TCP-IP protocol
- remote control with RS485 input, zoom control, video
camera rotation with output for cable TK59 6x2x0,6mm
- converter: 1 video input, 1 multimode optical cable output

C9 Video rack for unmovable camera pcs 17 875.00 14,875.00

Supply, delivery and mounting the video rack for setting of


the video equipment and the equipment for data transfer of
rotation camera. It includes supply, delivery and :
- mounting rack on stake
- mounting voltage surge protection 275V, 20kA in the rack
- put into and connect cables
- mounting cable inlets
- mounting terminal blocks 4 mm2 (9 pieces)
- cassette for the optic acceptance and distribution
- rectifier 230V/(6/12/24)V
- networking through TCP-IP protocol
- remote control with RS485 input, zoom control, video
camera rotation with output for cable TK59 6x2x0,6mm
- converter: 1 video input, 1 multimode optical cable output

C10 Uninterruptible power supply set 1 3,425.00 3,425.00


Uninterruptible power supply, 3kW, 1h
Supply, transportation and mounting communication rack
C11 (type as Legrand) set 1 1,694.00 1,694.00

Supply, delivery and construction of communication cabinet


and equipment:
- Cabinet 42U,2108x800x800
- Earthing
- Plate (brush) for top part for 600 mm of cabinet, for bottom
part 600 i 800 cabinet mm - 4 pcs
- For width 800 mm, 3 ventilators
- Thermostat 12 to 250 V~ - 10A max
- Lighting kit
- Set 4 casters, 210 kg
- Document holder, 310x200x18 mm
- Wire cable tray for 42 U cabinets 1800x50x200
- Cable supports for wire cable trays
- Power supply unit, 9 sockets
- Fixed shelf, depth 800 mm (4 holders)
- Optical drawer, 19 ", capacity 24 connectors - 5 pcs
- Fibre optic unit with 2 SC duplex connectors - 30 pcs
- SC connector (crimping) - 120 pcs
- SC/SC cable, 50/125µm,1m - 30 pcs
- SC/SC cable, 50/125µm,2 m - 30 pcs
- Horizontal management panel (plastic), 2U - 4 pcs
- Fibre optic management panel - 5 PCS

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 144
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


Supply, transportation and mounting communication rack
C12 (type as Legrand) set 1 1,060.00 1,060.00

Supply, delivery and construction of communication cabinet


and equipment:
- Cabinet 42U,2108x800x800
- Earthing
- Plate (brush) for top part for 600 mm of cabinet, for bottom
part 600 i 800 cabinet mm - 4 pcs
- For width 800 mm, 3 ventilators
- Thermostat 12 to 250 V~ - 10A max
- Lighting kit
- Set 4 casters, 210 kg
- Document holder, 310x200x18 mm
- Wire cable tray for 42 U cabinets 1800x50x200
- Cable supports for wire cable trays
- Power supply unit, 9 sockets
- Fixed shelf, depth 800 mm (4 holders)
- Optical drawer, 19 ", capacity 24 connectors - 5 pcs
- Fibre optic unit with 2 SC duplex connectors - 12 pcs
- SC connector (crimping) - 48 pcs
- SC/SC cable, 50/125µm,1m - 12 pcs
- SC/SC cable, 50/125µm,2 m - 12 pcs
- Horizontal management panel (plastic), 2U - 4 pcs
- Fibre optic management panel - 5 pcs

Supply, transportation and mounting communication rack


C13 (type as Legrand) set 1 506.00 506.00

Supply, delivery and construction of communication cabinet


and equipment:
- Cabinet 21U,1000x600x600, wall mounting, pivoting
- Earthing
- Wire-guide ring 56x89 mm
- Cable supports (for pivoting cabinets)
- Cable entry plate (with brush)
- Fan with 2,5 m cable
- Thermostat 12 to 250 V~ - 10A max
- Power supply unit, 9 sockets
- Fixed shelf, depth 300 mm
- Optical drawer, 19 ", capacity 24 connectors
- Fibre optic unit with 2 SC duplex connectors
- SC connector (crimping)
- SC/SC cable, 50/125µm,1m - 12 pcs
- Horizontal management panel (plastic), 2U
- Fibre optic management panel
- Blanking plate

Supply, transportation and mounting communication rack


C14 (type as Legrand) set 3 420.00 1,260.00

Supply, delivery and construction of communication cabinet


and equipment:
- Cabinet 16U,800x600x600, wall mounting, pivoting
- Earthing
- Wire-guide ring 56x89 mm
- Cable supports (for pivoting cabinets)
- Cable entry plate (with brush)
- Fan with 2,5 m cable
- Thermostat 12 to 250 V~ - 10A max
- Power supply unit, 9 sockets
- Fixed shelf, depth 300 mm
- Optical drawer, 19 ", capacity 24 connectors
- Fibre optic unit with 2 SC duplex connectors
- SC connector (crimping)
- SC/SC cable, 50/125µm,1m
- Horizontal management panel (plastic), 2U

Supply, transportation and mounting communication rack


C15 (type as Legrand) set 2 601.00 1,202.00

Supply, delivery and construction of communication cabinet


and equipment:
- Cabinet 21U,1000x600x600, wall mounting, pivoting
- Earthing
- Wire-guide ring 56x89 mm
- Cable supports (for pivoting cabinets)
- Cable entry plate (with brush)
- Fan with 2,5 m cable
- Thermostat 12 to 250 V~ - 10A max
- Power supply unit, 9 sockets
- Fixed shelf, depth 300 mm
- Optical drawer, 19 ", capacity 24 connectors
- Fibre optic unit with 2 SC duplex connectors
- SC connector (crimping)
- SC/SC cable, 50/125µm,1m - 12 pcs
- Horizontal management panel (plastic), 2U

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 145
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


Supply, transportation and mounting communication rack
C16 (type as Legrand) set 2 601.00 1,202.00

Supply, delivery and construction of communication cabinet


and equipment:
- Cabinet 21U,1000x600x600, wall mounting, pivoting
- Earthing
- Wire-guide ring 56x89 mm
- Cable supports (for pivoting cabinets)
- Cable entry plate (with brush)
- Fan with 2,5 m cable
- Thermostat 12 to 250 V~ - 10A max
- Power supply unit, 9 sockets
- Fixed shelf, depth 300 mm
- Optical drawer, 19 ", capacity 24 connectors
- Fibre optic unit with 2 SC duplex connectors
- SC connector (crimping)
- SC/SC cable, 50/125µm,1m - 12 pcs
- Horizontal management panel (plastic), 2U

Supply, transportation and mounting communication rack


C17 (type as Legrand) set 1 506.00 506.00

Supply, delivery and construction of communication cabinet


and equipment:
- Cabinet 21U,1000x600x600, wall mounting, pivoting
- Earthing
- Wire-guide ring 56x89 mm
- Cable supports (for pivoting cabinets)
- Cable entry plate (with brush)
- Fan with 2,5 m cable
- Thermostat 12 to 250 V~ - 10A max
- Power supply unit, 9 sockets
- Fixed shelf, depth 300 mm
- Optical drawer, 19 ", capacity 24 connectors
- Fibre optic unit with 2 SC duplex connectors
- SC connector (crimping)
- SC/SC cable, 50/125µm,1m - 12 pcs
- Horizontal management panel (plastic), 2U
- Fibre optic management panel
- Blanking plate
TOTAL C: 213,660.00
D DOCUMENTATION, FINAL WORKS AND TESTING

No ITEM DESCRIPTION Unit Qty Unit Price Total


D1 Geodetic record pcs 1 500.00 500.00
Geodetic record of power and signal layed cables before
cable backfilling

D2 Executive project set 1 1,950.00 1,950.00


Make the executive project of the video monitoring and
charge system
D3 Earthing testing set. 1 475.00 475.00
Measure the resistance of the earthing protection and make
the documentation of earthing installation because of
annual audit in accordance with the manuals and law
regulation.
D4 Power cable testing pcs 1 1,250.00
1,250.00

Testing the complete road lighting installations (loop


resistance, insulation resistance), commissioning and trial
operation.
- measuring the insulation resistance of cable and
preparation of respective documentation,
- measuring the voltage drop and preparation of respective
documentation,
- testing the safety and protection efficiency and preparation
of documentation on testing,
- preparation of measurement protocol,
-preparation of attestation for the completed
measurements,
- trial operation,
- establishment of complete operation.
Calculated per circuit
D5 Functional testing and commissioning set 1 1,425.00 1,425.00
Functional testing and commissioning
Report on functional testing with proof that the equipment is
operational , and commissioning of the system
D6 Implementation project set 1 1,750.00 1,750.00

Preparation of „As-done“ documentation with details of


work execution and connecting schemes and diagrams.
The documents shall include description of work of
individual systems, instructions for preventive and
corrective maintenance.
D7 Designer inspection hour 24 15.00 360.00
TOTAL D: 7,710.00

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 146
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

RECAPITULATION
VI. VIDEO CONTROL
No ITEM DESCRIPTION Total EUR
A CONSTRUCTION WORKS OF ELECTRICAL INSTALLATION 2,814.54
B POWER SUPPLY INSTALLATION WORKS AND MATERIAL 32,648.00
C INFORMATION EQUIPMENT 213,660.00
D DOCUMENTATION, FINAL WORKS AND TESTING 7,710.00
TOTAL VI: 256,832.54

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 147
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

VII Landscape
A. PREPARATORY WORKS

No ITEM DESCRIPTION Unit Qty Unit Price Total

Geodetic Works in staking out all elements of landscaping,


including all measurements related data from the project in
court and otherwise, setting up and maintaining good visible
staked out marks on the ground since the start of works to
the surrender papers investor and making the recording as
built. Distances to be staked plants under the management
A1
and design to individual trees, shrubs and hedges and by
groups. Stakes for marking must be painted white, height
30 to 40 cm, in order to be visible in the tall grass. Remain
in the soil after planting until the plant reaches its full height,
so the seedlings would not be damaged during
maintenance work.

Calculation lump sum. lump sum 1 511.29 511.29

TOTAL A: 511.29

B. WORKS WITH PLANT MATERIAL

No ITEM DESCRIPTION Unit Qty Unit Price Total


B1 Spreading garden soil
Spreading of fertile soil in a layer of 30 cm. This item
includes shipping, handling, unloading, spreading, fine
planning, and all other work and funding for installation of
the layer at a height given elevation. Material provided by
the investor.
Calculation per m² surface spread of the soil. m² 17,000 1.28 21,760.00
B2 Grassing flat surfaces - hand-seeding
Protection of flat grass surface cover-hand planted 5
grams / m². Category includes Seedbed (weed removal,
milling, fertilizer fertilizers, 5 grams / m²), hand drills with
rolling and watering with 20 liters of water per square meter,
the emergence of grass.
Lolium perena calibra 45%
Festuca rubra echo 15%
Festuca pratensis laura 15%
Festuca arundinacea finelawn 12%
Poa pratensis balin 5%
Vicia sativa jaga 8%
The calculation is done per sq m area of grown grass. m² 17,000 0.51 8,670.00
B3 Mowing grass
Mowing grass 2 times before putting the highway in traffic,
at a height of 5 cm with mulching cuts.
Calculation per m² total of mowed grass. m² 34,000 0.05 1,700.00

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 148
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


B4 Supply of trees

Supply and delivery of trees. All plants must have a clearly


defined straight trunk and well-developed crown with a
minimum of three primary branches, minimum 3 × trained
trees, a minimum height of 3 m. All plants must have a well
developed root system, and in case of a ball root seedlings
tied with wired mesh. Use only container root seedlings first
class and good condition (must pass min. one year from the
moment of removing seedlings from the field and container
root until the beginning of planting). As an exception to
allow planting of seedlings root ball with the reduction of the
agreed unit price by 25%, but only if the planting is done in
a favorable time for planting (from the moment of falling leaf
until the beginning of vegetation).

Calculation per seedlings.


Albizia julibrissin, range 14-16 cm pcs 45 109.93 4,946.85
Acer campestre, range 12-14 cm pcs 6 65.96 395.76
Celtis australis, range 16-18 cm pcs 103 92.03 9,479.09
Fraxinus ornus, range 16-18 cm pcs 15 112.48 1,687.20
Cercis siliquastrum, range 12-14 cm pcs 2 99.70 199.40
Pinus halepensis, h 200-250 cm pcs 24 44.48 1,067.52
B5 Planting of trees

Planting of trees, including digging holes for planting trees,


diameter 0.80 m, 0.80 m depth with a 50% change of
materials from site with fertile soil (exchanges material from
deeper layers). Pruning of branches damaged during
transport. Loosening the bottom of the pit, planting
seedlings, poles and three generations by cuttings of
deciduous trees and tying an elastic rope. Fertilizing
manure of prolonged action (Osmocote exact or equivalent)
according to manufacturer's instructions depending on the
size of seedlings. Creating soil saucer. A single irrigation
with 50 liters of water per seedling. Per tree, provided 3
poles turned diameter of 6 cm, height 250cm. For each pole
is projected 1 m of synthetic rope for tying. The item
includes supplying, transport and works related to planting,
fertile land, fertilizer, stakes, binders, water.

Calculation per planted tree. pcs 195 12.78 2,492.10


B6 Supply of shrubs

Supply and delivery shrub grown in a horticultural way of


quality, all plants must have containered root (must pass
min. one year from the moment of removing seedlings from
the soil and containing root until the beginning of planting).
Planting is done in a triangle. Minimum 3 bursts. Provided
for the plants:

COTINUS COGGYRIA, h 40-60 cm, CLT 3 pcs 4 25.05 100.20


NERIUM OLEANDER, h 60-80 cm, CLT3 pcs 39 8.69 338.91
PITTOSPORUM TOBIRA, h 60-80 cm, CLT3 pcs 51 7.93 404.43
VIBURNUM TINUS, h 60-80 cm, CLT 3 pcs 40 18.41 736.40

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 149
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


B7 Planting of shrubs

Pruning of branches damaged during transport. Digging


holes for planting, diameter 0.40 m, 0.40 m depth with a
50% change of materials from site with fertile soil
(exchange material from deeper layers). Fertilizing with
organic fertilizer depending on the size of seedlings.
Watering with 20 liters of water per seedling. Mulching of
the shrub surrounding (mulching should cover 40 cm
diameter area around a single shrub, and the whole area
around shrub cluster) with shredded tree bark in a 5 cm
thick layer. Staking out of a shrub cluster should be done
with colored stakes (for increased visibility during mowing)
The paragraph includes procurement, transport and works
related to planting, fertile soil, fertilizer, stakes, binders,
mulch and irrigation water, and all other necessary work,
materials and tools for planting, including the loading and
disposal of surplus soil. Staking out the shrubs is calculated
in paragraph Geodetic works.

Calculation per planted shrub. pcs 134 9.20 1,232.80

TOTAL B: 55,210.66

C. NOURISHING
Nourishing two years

Nourishing the entire surface of the two years following the completion of construction, ie from the moment of
commissioning / handover and / based on the construction and building log books, writing and approved
changes. Care includes all works and materials in accordance with the rules of the trade exchange-dried plant
material, seeding grassland that has not sprout, control and eradication of diseases and pests, and control
bindings and renewal, renewal of mulch. This work is included in the price and does not charge a separate item.

About the cultivation of land, the contractor is still obligated to maintain the building and the log book, and carry
out the orders entered in the log construction of the Supervisor.

No ITEM DESCRIPTION Unit Qty Unit Price Total


C1 Mowing grass
Mowing grass 4x per year and more if needed, at a height
of 5 cm with mulching cuts.
Calculation per m² mowed grass. m² 136,000 0.05 6,800.00
C2 Watering plants
Watering plants in the period from 01.06 to 15.09. At least
once a week (depending on climatic conditions) according
to the rules of the profession or order of the Supervisor.
Calculation per m³ of water consumed.
Tree 50 lit./plant x 26 weeks m³ 507 0.77 390.39
Shrub 20 lit./plant x 26 weeks m³ 69.68 0.77 53.65
C3 Pruning trees
Formal pruning deciduous trees forming a canopy; includes
gathering and disposal of brush, 1x / at the end of the
warranty period/.
Calculation per cut tree. pcs 195 7.67 1,495.65
C4 Hoeing trees
Hoeing trees 1 x per year of the first 2 years, including the
gathering and transportation of sticks.
Calculation per hoed tree. pcs 390 5.11 1,992.90
C5 Pruning shrubs
Pruning shrubs 1x / at the end of warranty period /; includes
gathering and disposal of branches.
Calculation per pruned seedlings. pcs 134 5.11 684.74
C6 Hoeing, weeding and mulching renewal shrubs
Hoeing, weeding and mulching shrubs 4x per year for the
first 2 year. Includes collection and disposal of sticks.
Calculation per seedling. pcs 1,072 3.58 3,837.76

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 150
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

No ITEM DESCRIPTION Unit Qty Unit Price Total


C7 Fertilization
Fertilization of plant material according to regulations and
the manufacturer's instructions depending on the size and
type of plant material.
Calculation lump sum. lump sum 1 255.65 255.65

TOTAL C: 15,510.74

RECAPITULATION
LANDSCAPE

No ITEM DESCRIPTION Total EUR

A. PREPARATORY WORK 511.29

B. WORKS WITH PLANT MATERIAL TOTAL 55,210.66

C. NOURISHING 15,510.74

TOTAL VII: 71,232.69

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca, LOT III,
"CORRIDOR Vc MOTORWAY PROJECT" Page 151
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Design Number: A-0857/12
Modification of detailed design
Common designation: GP Vc - LOT 7 - MGP

Construction of the BCP Bijaca - LOT III, PHASE IV

RECAPITULATION

OVERALL RECAPITULATION OF BILL OF QUANTITIES

No ITEM DESCRIPTION Total EUR


I PAVEMENT 297,614.32
II INTERNAL DRAINAGE 24,214.11
III TRAFFIC
IIIa TRAFFIC 631,946.61
IIIb TRAFFIC INFORMATION SYSTEM 10,823.21
IV STRUCTRES
IVa ARCHITECTUAL 420,833.57
IVb ELECTRICAL INSTALLATION 80,993.15
IVc HVAC 40,632.55
IVd INTERIOR WATER SUPPLY AND DRAINAGE 11,518.09
V ROAD LIGHTNING 5,124.00
VI VIDEO CONTROL 256,832.54
VI LANDSCAPE 71,232.69
TOTAL WORKS PHASE IV - Bijača Crossing Point : 1,851,764.84

BOSNIA I HERZEGOVINA
Construction of the BCP Bijaca , LOT III
"CORRIDOR Vc MOTORWAY PROJECT" Page 152
PHASE IV
LOT 7: section POČITELJ - BIJAČA
Construction of the BCP Bijaca - LOT III, Phases III and IV
OVERALL RECAPITULATION OF BILL OF QUANTITIES

No Total EUR
I Phase III 3,022,101.46
II Phase IV 1,851,764.84
A TOTAL WORKS - LOT III (Phases III + IV) 4,873,866.30
B CONTINGENCIES (10 % OF TOTAL WORKS) 487,386.63
C TOTAL CONTRACT PRICE (A+B) 5,361,252.93
DISCOUNT 8% 428,900.23
4,932,352.69