1
Why do we Use CRs?
• Without CRs we are never sure if a • A Change Request makes the
change is official. decision official and creates a
• For example, a manager asks a workflow to update everyone on the
worker what would it take to change change.
the scope?
– The worker misunderstands this to be an
order to change the scope
– Other workers don’t even know that a
change is being considered since they
weren’t part of the conversation.
2
Examples
• Would you use a CR for the
following changes:
1. Shipping costs come in at 10% above
estimates?
– No. Shipping costs would not normally be
a big part of a project’s cost and so 10%
would normally be absorbed by the
contingency.
However, if shipping was a big part and
there was no contingency left, then a CR
might be required.
Examples Examples
2. 5 people come down with the flu? 3. The client wants to add 10 more
– No. Normally, the project should have servers to the list of servers migrating
enough contingency to handle these to a new Operating System?
events. – Yes, this is a change in scope.
However, if these people are all working on
activities on the Critical Path and their
illness will delay Deliverables on the
Deliverable list, then a CR is used.
Examples Examples
4. Shipping delays will add a month to the 5. Client wants to change an already
project’s end date? signed-off document?
– Yes. The end-date or final deliverable is on – Yes. A signed-off document is part of the
the deliverable list. project baseline.
Changing a signed-off document usually
means “re-work”. People will have to go
back and change things they’ve already
done. This can add to the scope, time, and
budget
3
Examples Steps in a Change Request
6. Total project cost looks to be 30% 1. The Project Manager identifies and
more than estimated? analyzes the change. He/she needs
– Yes. 30% is more than most contingency to explain the change to the client
reserves will allow. The project budget and why it occurred/needs to occur.
needs to be changed.
2. The Project Manager meets with
stakeholders to discuss the change
and option for change.
• Stakeholders are anybody involved in
the project: team, client, vendors,
customers, partners, etc.
Exercise:
(Disaster Recovery Project)