A General
1 The itemised breakdown of the Lump Sum Tender Price as listed below shall form
only as an indication of the breakdown value for this contract works.
2 The descriptions stated in the breakdown of the Lump sum Tender Prices are not
comprehensive. The tenderer shall price the contract work in accordance with the
tender drawings and documents
1.1 Water tank accessories shall include inlet/outlet valves, overflow and drain, level
indicators, internal and external ladders, access panels and other associated ancillary
accessories as specified.
1.3 Pipework shall include valves, flow switches, fittings, support and other associated
ancillary accessories as specified.
1.4 Cabling work shall include cables, cable termination glands/lugs, cable support
system, testing, commissioning and other associated ancillary accessories as
specified.
1.6 Services and maintenance during defects liability or maintenance period shall include
the supply of all labour, materials, tools, transport and everything necessary to carry
out scheduled servicing and maintenance as specified.
Fire Protection Works
Lump Sum Tender Price Breakdown
Item Description
Hose reel tank complete with valves, fittings, supports and all necessary
1.1
accessories.
Hose reel pumps complete with pressure vessel and all necessary
1.2
accessories
LMCP for hose reel pumps complete with starters, protective devices, wiring,
1.3
cable support and containment system and all necessary accessories
Incoming water supply pipe from PUB water meter chamber to hose reel tank
1.4
complete with valves, fittings, support and all necessary accessories
Hose reel pipe work complete with valves, fittings, support and all necessary
1.5
accessories
Hose reels with steel cabinets complete with hoses, nozzles, hose guides and
1.7
all necessary accessories
Dry riser pipe work complete with valves, fittings, support and all necessary
2.1
accessories
Landing valves complete with standby hose, strap locks and all necessary
2.2
accessories
2.3 Fire Service breeching inlet connection complete with cabinet and earthing
3.1 Wet riser pumps and jockey pump complete with all necessary accessories
3.2 Wet riser transfer pumps complete with all necessary accessories
LMCP for wet riser pumps complete with starters, protective devices, wiring,
3.3
cable support and containment system and all necessary accessories
LMCP for wet riser transfer pumps complete with starters, protective devices,
3.4
wiring, cable support and containment system and all necessary accessories
Fire Service breeching inlet connection complete with cabinet, earthing and
3.5
piping to wet riser transfer water tank.
Incoming water supply pipe from PUB water meter chamber to transfer water
3.6 storage tank complete with valves, fittings, support and all necessary
accessories
Transfer water pipe from transfer tank to wet riser water storage tank
3.7
including valves, fittings, support and all necessary accessories
Wet riser water tank accessories including inlet/outlet valves, overflow and
3.9 drain, level indicators, internal and external ladders, access panels and all
necessary accessories
Wet riser pipe work complete with valves, fittings, support and all necessary
3.12
accessories
Landing valves complete with standby hose, strap locks and all necessary
3.13
accessories
External private hydrant pumps complete with pressure vessel and all
4.1
necessary accessories
LMCP for external private hydrant pumps complete with starters, protective
4.2 devices, wiring, cable support and containment system and all necessary
accessories
Incoming water supply pipe from PUB water meter chamber to hydrant water
4.3
tank complete with valves, fittings, support and all necessary accessories
Underground fire hydrant pipe work complete fittings, support and all
4.6
necessary accessories
Pillar hydrants complete with sluice valves, valve chambers, duck foot bends
4.7
and necessary accessories
Main Fire Alarm Panel complete with remote fire pumps/tanks status mimic
5.1
section and alarm functions and 24V battery charger and batteries
5.4 Detectors:
Wiring for connecting to all field devices complete with cable support and
5.5
containment system
Fire alarm signal complete with wiring, cable support and containment system
5.8
to the following
5.8.8.1 __________________________
5.8.8.2 __________________________
5.8.8.3 __________________________
DECAM Alarm transmission including all fees and charges payable during the
5.9
Defects Liability / Maintenance Period
Piping and nozzles complete with valves, fittings, support and all necessary
6.2
accessories
6.3 Gas control panel c/w 24V battery charger and nickel cadmium batteries
Smoke and/or heat detectors complete with wiring, cable support and
6.4
containment system and all necessary accessories
6.5 Evacuate', `Abort' and 'Gas Fired' signs and audible alarm
7.1 Sprinkler pumps and jockey pump complete with all necessary accessories
LMCP for sprinkler pumps and jockey pump complete with starters, protective
7.3 devices, wiring, cable support and containment system and all necessary
accessories
LMCP for sprinkler transfer pumps complete with starters, protective devices,
7.4
wiring, cable support and containment system and all necessary accessories
Fire Service breeching inlet connection complete with cabinet, earthing and
7.5
piping to sprinkler transfer water tank including earthing for breeching inlets
Incoming water supply pipe from PUB water meter chamber to transfer / water
7.6 storage tanks complete with valves, fittings, fire rated enclosure, support and
all necessary accessories
Transfer water pipe from transfer tank to roof water storage tank including
7.7
valves, fittings, fire rated enclosure, support and all necessary accessories
Water tank accessories including inlet/outlet valves, overflow and drain, level
7.9
indicators, internal and external ladders
7.10 Main riser pipes complete with valves, fittings, support and all accessories
Sprinkler distribution pipework complete with valves, fittings, support and all
7.11
necessary accessories
Sprinkler heads complete with dropper pipe work, guards and all necessary
7.14
accessories:
7.14.5.1 __________________________
7.14.5.2 __________________________
7.14.5.3 __________________________
Sub-Total for Very Early Smoke Detection and Alarm System (VESDA) S$
Master control firemen intercom panel in FCC room complete with standby
9.2 battery and charger, LED status and handsets, etc including controls wiring in
conduit/trunkings and all necessary accessories
Dry riser system - wet riser pumps, jockey pump, storage tank, transfer
10.2
pumps, transfer tank
Wet riser system - wet riser pumps, jockey pump, storage tank, transfer
10.3
pumps, transfer tank
10.4 External hydrant system - hydrant pumps, jockey pump, storage tank
Sub-Total for Comprehensive Maintenance and Warranty Concurrent with Defects Liability /
Maintenance Period S$
13 CONTINGENCY SUM
14 PROVISIONAL SUM
14.1.1
__________________________
14.1.2
__________________________
14.1.3
__________________________
15 PRELIMINARIES
15.3 Preparation and submission of hard copy and softcopy As-Built Drawings
15.4 Preparation and submission of hard copy and softcopy Operating Manuals
15.1.1 __________________________
15.1.2 __________________________
15.1.3 __________________________
Any other works which are necessary for the completion of the works or
16.1 included in the Drawings and/or Specifications but not included above (please
specify):
15.1.1 __________________________
15.1.2 __________________________
15.1.3 __________________________
13 Contingency Sum
14 Provisional Sum
15 Preliminaries
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
Lump Sum Tender Price Breakdown Fire Protection 18/23
ver.Jul2013
Amount ($)
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
Lump Sum Tender Price Breakdown Fire Protection 20/23
ver.Jul2013
Amount ($)
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………
…………………………