CLIENT : CHAMBAL FERTILIZERS CHEMICALS LIMITED , GADEPAN PRELIMINARY SCHEDULE SHEET - 1 OF 2

WORK : MISC. MECHANICAL WORK IN 2019 ATR


PRE

Sr.
SHUTDOWN SHUTDOWN ACTIVITY
No.
DESCRIPTION ACTIVITY Remarks

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

A UREA STRIPPER 11 E-1 REVERSAL


Assemble of crane looad testing & placement of crane at location (300 MT.҉)
1 Dismantling of pipelines , valves, Instruments, Manhole top & bottom etc.
2 Remove the cross member structural beams of foundation bracket
3 Dismentling of equipement.
4 Reversal & erection equipement .
5 Fixing of foundation bracket cross member structural beams
6 Equipement eliment
7 Assemble of pipelines , valves, Instruments, Manhole top & bottom etc.
B AMM. RECEIVER (11V-01) & AMM. RECOVERY TOWER (11C-05) REPLACEMENT
Fixing of temporary structure ,tool & machinery
1 Dismantling of pipelines , valves, Instruments, recover tower top & bottom etc.
2 Dismantling of De-mounting 11-C-05 Lifting & hold in certain height
3 Shifting of equipment up to reached aprocht of crane
4 Lifting and remove of equipment help of crane and shifting and dismentling and 11-05
5 Erection and lift certain height of 11-E-05 recovery tower
6 lifting new equipment at temporary structures and shifting on foundation
7 Equipement eliment
8 Assemble of pipelines , valves, Instruments, Manhole top & bottom etc.

D MP CONSENSER 21 E-07 REPLACEMENT


1 Assemble of crane placement of crane at location
2 Dismantling of pipelines , valves, Instruments, Manhole top & bottom etc.
3 Dismantling of equipment
4 Erection new equipement .
5 Equipement eliment
6 Assemble of pipelines , valves, Instruments, Manhole top & bottom etc.
SHEET -2 OF 2

CLIENT : CHAMBAL FERTILIZERS CHEMICALS LIMITED , GADEPAN PRELIMINARY SCHEDULE


WORK : MISC. MECHANICAL WORK IN 2019 ATR
PRE

Sr.
SHUTDOWN SHUTDOWN ACTIVITY
No.
DESCRIPTION ACTIVITY Remarks

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

C CONDENSER (E-17) REMOVAL, PARTIAL RETUBING & REFIXING COVED 100 mt crane )
1 Dismantling of pipelines , valves, Instruments, Manhole top & bottom etc.
2 Dismantling of equipment and lay ground level
3 Removal of tubes and new tubes fitting and expenction 100 nos. Hydrotesting
4 Erection of equipment & eliment
5 Assemble of pipelines , valves, Instruments etc.

E 11/21 UREA STRIPPER VAPOR OUTLET LINE REPLCEMENT


1 Shop joint - 24 Nos.
2 Dismentlin of existing pipelines & Erection of new line joint - 10 Nos.