Sie sind auf Seite 1von 14

CONSTRUCTION OF OFFICE BUILDING ON PLOT AT

GULISTAN BUNGALOW AT R C BUTT ROAD, ALKAPURI,


VADODARA

Design Basis Report


– Electrical Installation –

October 2013
47305000/EL/DBR/001 Rev – R0

CONSULTING ENGINEERING SERVICES (I) PVT. LTD.


NEW DELHI MUMBAI KOLKATA
Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

Table of Contents

1. INTRODUCTION 3

2. SCOPE OF WORK 3

3. PROJECT OBJECTIVES 3

4. MAIN POWER SYSTEM 4

4.1 Reference Documents, Codes & Standards 4


4.2 Site Condition 5
4.3 Utility Substation 5
4.4 Distribution System 5
4.5 UPS System 7
4.6 11 / 0.433 kV Transformer 7
4.7 Emergency Power Back up 7
4.8 Rising Mains 8
4.9 Power Factor Correction 8
5 CABLING SYSTEM 8

6 LIGHTING SYSTEM 10

7 EARTHING SYSTEM 12

8 LIGHTNING PROTECTION SYSTEM 12

9 LOAD ESTIMATE 13

Design Basis Report - Electrical Page : 2 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

ELECTRICAL DISTRIBUTION SYSTEM

1. INTRODUCTION

Bank of Baroda has proposed to construct Administrative office Building at Gulistan


Bungalow at R C Dutta Road, Alkapuri, Vadodara. The building is proposed with
Basement + Ground + 7 Storied. Built-up area of the Office Building will be approx
125,000 Sq. ft,

This report outlines the overall Design Scheme for the Electrical Distribution for the
proposed Office Building. Detailed Engineering of the Electrical System would be carried
out on approval of this Concept Design. Design Report is prepared based on the input
data assumed and overall electrical load estimate, sizing calculation of various
equipments.

2. SCOPE OF WORK

The objective of this report is to give an overview of services designed for the proposed
Office Building at Alkapuri, Vadodara. The design of Electrical Services undertaken
includes following:

 HVAC System
 External and Internal electrical distribution including substation.
 UPS Power
 Emergency DG set
 HT and LT cabling system
 LT Bus riser system
 Earthing system.
 Lightning protection

3. PROJECT OBJECTIVES

The project objectives include eco-friendly and energy efficient design, centralized
grouped location of services installation to ensure easy maintenance, state of the art
technology, fast track installation and compliance to all statutory regulations.

Design Basis Report - Electrical Page : 3 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

4. MAIN POWER SYSTEM

4.1 Reference Documents, Codes & Standards

Electrical Systems Design shall be carried out in accordance with following Codes and
Standards :
 Indian Electricity Act, 2003.
 Indian Electricity Rules, 1956.
 National Building Code of India – 2005.
 IS 7098 Cross linked polyethylene insulated PVC sheathed cables.
 IS 1646 : Code of Practice for the Fire Safety of Buildings - General Electrical
Installations.
 IS 1913 : General and Safety requirements for Luminaries.
 IS : 2026 / IEC 60076 : Transformers (Oil filled).
 IS 2309 : Lightning Protection System.
 IS 3043 : Grounding & Bonding.
 IS 3231 Electrical relays for Power Systems Protection
 IS 3427 : 1997 / IEC 298 A.C. Metal Enclosed Switchgear and Controlgear for
Rated Voltages Above 1 kV and Up to and Including 52 kV.
 IS - 3646 : Code of Practice for Interior Illumination.
 IS 10322 Specification for Luminaries
 IS 12063 Classification of degrees of protection provided by enclosures of electrical
equipment.
 IS 13340 & IS 13341 / IEC 60831 : Capacitors.
 IS 13947 / IEC 60947 : Specification for Low Voltage Switchgear & Controlgear.
 IEC 60034 for Rotating Electrical Machines.
 IEC 62271 High Voltage Switchgear and Controlgear – All parts.
 IEC 60364 : Requirements for Electrical installation
 IEC 62040 for Uninterruptible Power Supply.
 IEC 61439 (1&6) & IS (8623 (1&2) for Bus Trunking System
 IS 1255 for Cable laying

Design Basis Report - Electrical Page : 4 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

.
4.2 Site Condition

Altitude 35.5 above MSL


Ambient Temperature Design 45 deg. C
Maximum Temperature 43.3 deg. C
Minimum Temperature 10 deg.C
Humidity 68% RH during summer
Soil Resistivity 1.28 Ohm m
Rainfall 93 cm
Seismic Zone Zone III
Environment Normal

4.3 Utility Substation

Main power will be received at 11 kV from local power Supply Company. An 11 KV


Panel with one incomer and two outgoing panel will be installed at the proposed
substation building which will be located outside the building premises.

11 kV Power supply will be step down to 415 Volts LT supply through a suitable rated 11
/ 0.433 kV Transformer, which will be installed outside the substation premises. LT
supply from the transformer will be fed to an LT Panel to be housed in the Substation
building. Provision for installation of 2nd Transformer to be considered in the proposed
layout for future load growth and redundancy.

4.4 Distribution System

The cable for 11 kV supply will be 11 kV earthed grade, aluminum conductor, XLPE
insulated, semi conducting compound screened, the extruded inner sheathed, armored
and extruded outer sheathed.

The cables for LV power supply will be 1100 V grade aluminium conductor, XLPE
insulated; the cables for emergency services will be with additional FRLS properties.

Design Basis Report - Electrical Page : 5 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

The control cables will be FRLS except with stranded copper conductor. The cables
within the building will be routed through cable trays. The cables coming from Substation
will be run through the cable trenches. Fireproof sealing will be done at all the shafts at
each floor, wall entries and floor entries.

Power cables will be sized considering applicable derating factors. Bus duct will be
provided from the Transformer and DG sets upto Low voltage switchgears. From the low
voltage switchgear upto rising mains suitably rated cables will be provided.

Rising Mains are proposed to be used as the backbone for power distribution throughout
the building. Rising mains system of sandwiched type will be provided along the
electrical shaft to provide power supply to each floor for lighting and general power.
Cables from Main LT Panel will be terminated at End Feed Bos of the rising main at
basement. Power supply for each floor will be tapped from rising mains from plug in tap
of box through cables. Each floor will be provided dedicated LT distribution board for
power distribution.

Dedicated UPS and Battery system for each floor is proposed to cater office area
computer load, BMS load. While sizing UPS, a design margin of 10% considered in case
Client considered catering other load through UPS syste. Power supply to UPS syetm
will be received from dedicated LT distribution panel at each floor. UPS and Battery
room at each floor shall be air conditioned. Additionally adequate ventilation shall be
proved for Battery room for Hydrogen emmission.

Main LT Panel which will be located at Utility substation shall be free standing, floor
mounted, fully compartmentalized, cubicle type panel having separate enclosures for
bus bars, chambers & feeder breakers with associated cable terminations. Power supply
to Utility load at Terrace will be fed separately from Main LT Panel. Rising mains will
cater power supply for Power, lighting of each floor, Lifts, UPS, BMS, HVAC system of
each floor and Plumbing system. For Utility load at Terrace, a separate cable system will
run along a separate shaft from basement.

Design Basis Report - Electrical Page : 6 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

Sub panels and the subsequent distribution boards (DB) at different floor will receive
power from rising mains in Electrical shaft from tap off boxes as mentioned above. The
lighting/power DB would be provided with ELCB for protection as per IE Regulations. All
wiring for light and power points shall be with PVC conduits for concealed wiring and MS
conduits for surface wiring. Wiring shall be carried out with FRLS copper wires as per
the requirement. The full distribution network from the incoming feeders to each point of
usage is designed to be fuse-less system comprising of Molded Case Circuit Breakers
(MCCB), Miniature Circuit Breakers (MCB) and Earth Leakage Circuit Breakers (ELCB)
and therefore intrinsically fire-safe.

4.5 UPS System

Based on estimated office area load and BMS load, dedeicated UPS system for each
floor is sized considering an overall Diversity Factor (DF) of 90%. UPS system with N+N
is considered for the purpose. Battery backup for UPS will be designed to provide 30
minutes of back up time. UPS system shall be designed for limit the harmonic distortion
of input supply to maximum 3% THD. For UPS sizing refer Annexure 1

4.6 11 / 0.433 kV Transformer

1 No.11 / 0.433 kV, 1500 kVA Dry Type (Resin Cast), Dyn11 with Z = 6.25%, with off
Load Tap Changer (Tap+/- 5% in steps of 2.5%) outdoor type transformers. Transformer
capacity will be selected considering 90% maximum loading. For Transformer sizing
refer Annexure 1

4.7 Emergency Power Back up

Emergency power generation is planned to be provided through HSD fired DG set with
AMF provision capable of meeting entire lighting and power demand of the Building. In
order to meet the statutory regulation regarding noise and air pollution, DG set is housed
in acoustic and weather proof enclosures have been proposed. The sets would conform
to the latest enforced regulatory norms with regard to the noise and air pollution.

Design Basis Report - Electrical Page : 7 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

In the event of any failure of the mains grid, emergency backup power supply system
has been designed to come in to operation automatically to support 100% load to avoid
any down time in the proposed Office Building.

DG set is proposed outside the Utility building shall be mounted inside individual
acoustic enclosure in order to minimize disturbance to occupants. The ambient noise
level from DG set shall not exceed 75 dB (A) at 1 m distance, during day time and 70 dB
(A) during night time. For DG sizing refer Annexure 1

4.8 Rising Mains

The complete prefabricated bus way distribution system shall be for 433 Volts 3-phase 4
wire with integral grounding bar. The neutral bar shall be 100% cross sectional area of
phase conductors. The bus way system shall be of the low impedance type and totally
enclosed for protection against mechanical damage and dust accumulation.

Fire stops or barriers shall be included as an integral part of each feeder bus way length
& fitting. Degree of protection shall be IP-65 for outdoor and IP-54 for indoor application.
Rising Mains will be provided with End Feed Box at basement and End cover at terrace
level. Tap of box will be provided at each floor.

4.9 Power Factor Correction

Power factor correction unit shall be of Active harmonics / PF filter design. The final size
of the power factor correction units to be designed during the detailed engineering.
Power factor shall be maintained at 0.95 or higher through APFC panel. APFC Panel will
be installed mear Main LT Panel at Substation.

5 CABLING SYSTEM

All high-tension cables shall be laid and jointed in accordance with IS: 1255. A minimum
separation of one cable diameter will be maintained between any two horizontal cables.
Accordingly derating factor will be considered. To reduce the total width required, the
two circuits will be vertically separated by 200 mm edge to edge.

Design Basis Report - Electrical Page : 8 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

A separating distance between parallel runs of Instrument and Electrical cables shall be
as follows, except in substation:

For 11 kV Cables – 1000 mm


For 415 V Cables – 600 mm
For 240, 110 V Cables – 300 mm

Above ground cables shall be supported by cable racks or trays. Power cables shall
generally be laid on racks or trays in a single layer. Cables trays shall be secured at
required intervals.

Power (and associated control) and instrumentation / telecommunication cables shall


be run in different racks.

GI ladder type cable trays are proposed for laying cables in preformed trenches, laying
cables for various equipments along the shaft, in plant room etc. and perforated cable
trays for cables from panels to distribution boards etc.

The enclosure degree of protection for various electrical equipment shall be as per the
requirements below as a minimum:

HT Switchgear : IP 4X
Distribution Transformers : IP 55
Cable Box : IP 55
i) Kiosks and Marshalling Box : IP 55
ii) Bus Duct (Indoor) / (Outdoor) : IP 54 / IP-55
(Indoor) / (Outdoor)
iii) 415 V PCC / MCC / DBs : IP 42
iv) Pushbutton Station and any other Kiosk /
Box / Panel / Enclosure Indoor / Outdoor : IP 55
v) Junction Boxes for Cables / Wires : IP 55
vi) Outdoor Lighting Fixtures : IP 55
vii) Battery Charger Panel : IP 42

Design Basis Report - Electrical Page : 9 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

6 LIGHTING SYSTEM

Lighting arrangement for the Office Building is proposed with the use of high efficiency,
mirror optic light fixtures equipped with very low loss electronic ballasts and high
efficacy tri-phosphate coated T-5 tubes. The average lighting level is proposed to be
500 lux. Since 100% of lighting is backed-up with inverter floor wise, in the event of any
failure of mains power, all the lights would be re-energized after a break of about 15
seconds. Further to provide continuity of lighting to facilitate safe evacuation in extreme
situation, emergency lights including EXIT signage lights fed from a separate inverter
would be provided at strategic locations in and around the Office Building.

The illumination levels considered for calculation for various areas will be as follows:

Sl.
Area Lux level
No.
1 Office Area / Cabin / Secretary 300
2 Server Room 300
3 Corridors 100
4 Conference Room 300
5 Reception / Lounge 150
6 Toilet / Locker Room 150
7 Library 200
8 Electrical Room 200
9 Chiller Area 100
10 Storage Area 100
11 DG Room 200
12 Car Park 100
13 Xerox / Fax / EPABX Room 150
14 Documentation Room 150

The luminaries will be selected to suit architectural, functional & aesthetic requirement,
for office areas in general & for other areas, energy saving fluorescent lamps and high
efficiency lamps will be used. Common areas will be provided with 1 x 11 or 1 - x 18 w
CFL lamps. Reflector shall be made out of high purity aluminum scientifically designed

Design Basis Report - Electrical Page : 10 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

for high optical performance. All conference rooms and auditorium lighting shall be
dimmer controlled.

The wiring will be done with copper wires in using 3 cores 2.5 sqmm cables for point
wiring and looping and 2.5 sq.mm copper multistrand FRLS for circuit mains wiring.
HDPE conduits shall be used for concealed wiring and Galvanized conduits for surface
wiring. The lighting panels will be 3-phase type with outgoing MCB circuits. Third core
for earthing the lighting fittings, plug points, exhaust fans, etc. The lighting circuits for
the car park and common areas will be contactor controlled so that the illumination level
can be controlled during off peak periods by remote control from building automation
system. Similarly the circuits / feeders for outdoor lighting will be contactor controlled for
remote controlling purposes.

Each workstation shall have 2 nos. 6/16A switched & sockets. Cabins & secretary area
will have 2 nos. 6/16A switched sockets and 1 no. Extra-switched socket shall be
provided for laptop. 1 no. Additional switched 6/16A socket shall be provided in
secretary space for printer.

Internal Distribution

Light fittings & socket outlets for raw power in common areas will be fed from MCBDBs
in the respective areas. Emergency lighting for specified areas will be provided by
essential MCB DB’s.

For concealed and surface wiring rigid MS conduits will be used. For wiring FRLS PVC
sheathed 2.5 sq.mm copper wire shall be used. FRLS wires shall be provided for all
systems.

The lighting fixtures will get power supply from lighting distribution boards fed from
lighting panel through wiring. All the lighting fixtures are of with electronic ballast and
power factor improvement capacitors. Each lighting fixture will be provided with the
earthing terminal. All metal will be bonded to earth. Switch controlling light point will be
connected the phase wire of the circuit and not more than the 10 lights will be
connected on one circuit. The load of each circuit will be not more than 800Watt.The
minimum size of wiring for lighting will be 2.5 Sq.mm. Power sockets of 6A, 16A & 20A

Design Basis Report - Electrical Page : 11 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

will be getting supply from power distribution boards through the wiring. All sockets
switches and other receptacle will be rust proof and will be 2 mm thick mild steel with
HOT dipped galvanized having smooth external and internal surface to true finish. Wall
socket will be three-pin type. All 16A sockets will be connected to the independent
circuit. An earth wire will be provided along with the circuit wires and will be connected
to the earthing screw in side the box. All sockets will be shutter type.

For lighting and raw power one essential as well as nonessential lighting and raw power
panels will also be provided. These will feed to the emergency as well as normal
lighting and power load through suitable distribution boards.

7 EARTHING SYSTEM

There would be two separate grounding systems for the Office Building; one catering to
the safety requirement of the entire electrical distribution system and the other (known
as Dedicated Earthing) catering to the sensitive servers with in the Office Building. The
two systems would be bonded together with equi-potential bond as per the requirement
of IEEE code of practice. The dedicated earthing system would be laid out separately
using green-yellow PVC insulated copper cables terminated on a purpose built Earth
Bus which in turn would be connected to two separate earth pits specially created for
the purpose. Isolated Ground (IG) for the entire computer power supply is designed and
executed as per IEEE Standard- 1100 (Emerald Book).

8 LIGHTNING PROTECTION SYSTEM

Lightning protection system with early streamer is proposed. This system is an


controlled streamer Emission based lightning protection suitable for protecting of
buildings against direct lightning strike and has controlled streamer emission (CSE)
lightning conductor air terminal held in position at the highest point of building with
supporting mast and accessories comprising of the insulated FRP pipe mast & high
grade aluminium of required height as per vendor design, U bolts etc to withstand wind
velocities of 100 kmph. This system intercepts lightning discharges at a preferred point
earlier than conventional lightning protection system.

Design Basis Report - Electrical Page : 12 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

Earthing is done using minimum 4 nos of copper bonded steel earth rods of 250
microns with minimum 4 feet length and half inch dia joined with 25 mm x 3 mm copper
strip and the surrounding space is treated with ground enhancement material (GEM) to
reduce the overall impedance offered by earth. Lightning counter is also proposed
which gives the no. of lightning strokes captured by the each area.

9 LOAD ESTIMATE

The estimated connected electrical load for the entire Office Building comprising of
HVAC system, Lifts, Lighting, Computers, UPS etc. works out to 1206 KW considering
design margin of 10%, whereas operating load is 1098 KW. For detail load list and
sizing calculation of Transformer, UPS system and DG, refer Annexure 1

Design Basis Report - Electrical Page : 13 of 14


Project : Construction of Office Building on Plot at Gulistan Bungalow at October, 2013
R C Dutta Road, Alkapuri, Vadodara
Client : Bank of Baroda Revision : R0
Document : 47305000/DBR/EL/Rep-04

ANNEXURE 1

Design Basis Report - Electrical Page : 14 of 14

Das könnte Ihnen auch gefallen