Beruflich Dokumente
Kultur Dokumente
2. EARTHWORKS
2.1 Excavation
a. Footing excavation shall be dug to the exact width
and depth and levels as indicated in the drawings.
b. Whenever water is encountered in the excavation
process, it shall be removed by bailing or pumping.
c. No excavation or foundation work shall be filled in
or covered up before the inspection and approval of the Project
Engineer.
2.2 Backfill
a. The work shall consist of filling for construction
of embankment and include furnishing, placing, compacting and
shaping materials obtained in accordance to lines, levels,
grades and dimensions shown on the drawings.
b. Backfill and fills shall be placed in layers not
exceeding 150mm in thickness, and each layer shall be thoroughly
compacted by wetting, tamping and rolling.
2.3 Gravel Base
A bed of 4” screened gravel, use a straight edge or
line level to make sure that gravel base is flat.
3. CONCRETE WORKS
3.1 Storage
a. Cement bags should be placed closely together in
the stack to reduce circulation of air as much as possible.
b. All cement shall be stored on platforms and
protected from weather.
c. All concrete works shall be done in accordance with
the standard specifications for plain and reinforced
concrete as adopted by the Government.
3.2 Cement
Cement, to be used shall be Republic Portland Plus or
any other equivalent brands more readily available in the
locality. which must meet the requirements of Portland
cements.
3.3 Mixture
a. The following proportions of concrete mixtures
shall be used for the various parts of the building:
Columns and footings - Class A (1:2:4)
Concrete Hollow Block Footings - Class B (1:2-1/2:5)
Reinf. Conc. Beams and Slabs - Class A (1:2:4)
Concrete slab foot on fill - Class C (1:3:6)
3.4 Placement
a. For pouring of concrete for columns, the Contractor
shall use drop chute with a maximum drop height of 1.50
meters or less.
b. For pouring of concrete for slab, the Contractor
shall execute the placing direction with backward movement.
c. Concrete slab on fill with 100 mm thick shall be
poured on gravel bed and shall be placed with the 10mm
diameter Reinforcement Steel Bar (RSB) spaced at 400mm both
ways.
d. When placing on a nearly horizontal surface,
placing shall start at the lower end of the surface to
avoid decompaction of concrete.
e. Concrete shall not be placed during rain. However, in
dry weather, covers shall be provided for all fresh
concrete surfaces, which are not being worked on. Water
shall not be added to concrete for any reason.
3.5 Compaction
Concrete shall be fully compacted throughout the full
extent of the placed layer. It shall be thoroughly worked
against the formwork and around any reinforcement and other
embedded item, without displacing them. Care shall be taken
at arises or other confined spaces. Successive layers of
the same pour shall be thoroughly worked together.
3.6 Curing
The contractor shall provide a suitable form of shading to
prevent the direct rays of the sun reaching the concrete
surfaces for at least the first four days of the curing
period. Curing shall be continued for as long as may be
necessary to achieve the above objectives but not less than
7 days until the concrete is covered by successive
construction whichever is the shortest period.
4. STEELWORKS
4.2 Storage
Store bars of different classes, sizes and lengths
separately to facilitate issues in such sizes and lengths
so as to minimize wastage in cutting from standard lengths.
If reinforcement bars have to be stored for a long period,
then stack it above ground level by at least 150 mm to
avoid distortions.
4.3 Bending
The minimum bending of bars for 10mm to 25 mm is bend
plus 5 times the bar diameter, for 180 degrees bend and
bend plus 6 times the bar diameter, and for 90 degrees bend
extended up to 12 times bar diameter. For stirrups and tie
hooks, the minimum bending of bars is bend plus 10 times
the bar diameter.
4.4 Fixing Reinforcement
The minimum concrete cover to protect all
reinforcements for each different structure is as follows:
1. Footing, footing tie beams – 75 mm
2. Beams and columns (to stirrups & ties) – 40 mm
3. Suspended slab -- 20 mm
5. MASONRY WORKS
6.TILEWORKS
6.1 The toilet and bathroom floors shall be finished
with 200mm x 200mm ceramic tiles The walls of the toilets,
bathrooms, top of kitchen cabinets, and laundry tub, and
their adjacent walls shall be wainscoted with 200mm x 200mm
ceramic tiles.
6.2 Before the tiles and mouldings are laid in place,
they shall be thoroughlysoaked in water if recommended by
the manufacturer. Mortar to be used in settingthe tiles and
moldings shall be a mixture of 1 part cement and 2 parts
sand by volume.
6.3 After the tiles have been adherent on the surface,
the surface should be fulfilled. After fulfilling the
surface, no shaking or knock before the material has been
connected. With the surface in the open air, and the
joining material is mortar, the method of covering to
prevent raining will be done at least from 1 to 3 days. If
the tiling surface is in the open air and not being
indicated in the drawing, the width of gap compensation
joint will be 2cm and being inserted with elastoplastic
material.
7. CEILING
9. PAINTING
9.1 All painting materials shall be delivered on site
intact in the original drums or tins and shall be mixed and
applied strictly in accordance with the manufacturer’s
instructions and to the approval of the Engineer. All latex
and enamel paints shall be applied by brush.
9.2 All painting work for this project, except has
herein after specifed, shall be done with the use of Davies
paint products. The painting contractor shall supply all
labor, paint materials, tools staging and equipment
necessary, and shall perform all painting and finishing
works as for this project.
9.3 The painting contractor shall store his materials
in one place in the building to be kept neat and clean. Any
damage thereto, or its surrounding shall be made good care,
care being taken storage of paints, oil, etc. Oily rags shall
be kept in metal containers and shall be removed from
building everyday upon the stopping of works.
9.4 Before painting is done, all surfaces shall be
cleaned, smooth and freed from dust. dirt, grease, mortar,
rust and other foreign substances and all paint shall be
spread evenly and carefully.
9.5 No painting shall be done on outside work on cold
or damp weather.
10. HARDWARES
10.1 All loose pin hinges, all bronze fnished shall be
used for all doors. Provide three hinges on each door
concealed hinges shall be used for kitchen, cabinet and
closet. All cabinet doors shall be provided with catches,
cabinets with pullers and hook.
10.2 Hardwares and fittings for louver windows shall
be galvanized-plated steel with rotor-operators.
12. ROOFING
12.1 The contractor shall provide all items, articles
materials operation, or method listed, mentioned all
schedules on the drawings and/or herein, including all
labor, materials, equipment and incidental necessary as
required for their completion.
12.2 Roofing shall be pre-painted GA 26 sheet approved
by the contractor. Roofing accessories shall be made of
material as per installation procedures specified by the
manufacturer.
12.3 Ridge rolls, hip rolls and valleys to be used
shall be pre-pointed long-span roofing sheets. They shall
lap the roofing sheets at least 250mm. The ridge rolls, hip
rolls and valleys shall be riveted to the roofing sheets,
in addition to the rivets engaging the GI straps in
securing theroofing sheets to the purlins. All roofing
sheets adjacent to concrete hollow block and other masonry
wallssuch as at property line firewalls, shall be provided
w3ith Gauge No. 26 plain GI flashing to extend up to the
top and over to the other side of the wall.
11.4 All rivets shall be placed at the top of the
corrugations of the roofing sheets to prevent water from
standing around the rivets