Sie sind auf Seite 1von 3

You as an energy planning engineer wants to plan to replace an existing 10 tonR chiller of SEER value 8 

with an equal size unit of SEER value 12. The air‐conditioner is expected to operate for 5000 hr / yr. How 
much less energy will new unit consume if the incremental cost of new unit is Rs 350,000. If you want to 
recover this money in 10 years at a discount rate of 10% per year, what will be the cost of conserved 
energy? What will be the feasibility of this project if the electricity tariff is Rs 12 / kWh? 
Solution
Cooling capacity  10 10 12,000 120,000 /  
Operating hours  ∆ 5000 /  
Discount rate = r = 10% 
Number of years = n = 10 
 
SEER 12 A/C: Cost of Conserved Energy (CCE)

∆ 120,000 5000
 

600 10 /
0.1627 350,000
⇒    
25,000 /
600 10
5 10   1.19 /  
12
5 10    
  Comment
SEER 8 A/C Since, CCE < electricity tariff, therefore this 
project is feasible to install. 
600 10   
7.5 10  
8
 
 
 
Annual energy saved  
7.5 10 5 10    
25,000 /    
 
 
Savings in Bill  
12 / 25,000 /    
300,000 /    
   
Capital Recovery Factor (CRF)  
1  
   
1 1
 
0.1 1 .01  
 
1 0.1 1  
 
0.1627 
 
   
To save electricity on air‐conditioning in an office building located in Karachi, four energy efficiency 
measures are under consideration. The details of the projects are given in the table below. 
 
Energy Efficiency Measures  Cost ($)  Energy Conserved (kWh/year) 
Roof insulation  1500  3200 
Wall insulation  1800  3500 
Efficient windows  1600  1100 
Heat recovery from vent windows  1200  1800 
 
If the office building is open for 12 hr/day, five days per week and cooling season is 8 months long, then 
estimate the cost of conserved energy for each energy efficiency measure. Also draw energy 
conservation supply curve and select the projects for implementation. Take project life as 25 years and 
discount rate of 12% per year. Grid electricity rate is 10 cents/kWh. 
Solution

Calculating CRF

1
  0.1274 1600
1 1  
1100
0.12 1.12
  $ 0.1853 
1.12 1
¢ 18.53 /  
0.1274 
CCE for 4th Project (Heat Recovery)
CCE for 1st Project (Roof Insulation)



0.1274 1200
0.1274 1500  
1800
3200
$ 0.0849 
$ 0.0597 /
¢ 8.49 /  
¢ 5.97 /
 
CCE for 2nd Project (Wall Insulation)


0.1274 1800
3500
$ 0.0655
¢ 6.55 /

CCE for 3rd Project (Windows)


 
  The high temperature for a particular day was 
  90⁰F and low temperature was 66⁰F. Find 
  heating/cooling degree days (HDD/CDD). 
   
   
  Find the annual heating bill of a house located 
  in northern area. The heat transfer coefficient 
  for the house is 315 W/K. the heating degree 
  days for the area is 352 ⁰C‐day. Internal heat 
  generated is 830 W. Find out the seasonal 
  heating load of this building. 
   
   
  Two air‐conditioning systems are under 
  consideration for installation in an office 
  building. The total air‐conditioning load of office 
  building is 45 tonR. One system is traditional 
   chiller with CAV system. The other system is 
  chilled beam and dehumidification system 
  based on enthalpy wheel. The cost of CAV 
  system is Rs 35000 per tonR and the cost of 
  chilled beam system consisting of vapor 
  compression chiller and dehumidification unit is 
  twice the cost of CAV system. The COP of CAV 
  system is 3 and COP of chilled beam system is 
  3.5. the total cooling load of office building is 
  composed of 60% sensible load and 40% latent 
  load. The CAV system will have a 1 kW blower 
  to supply air to different areas of office using 
Calculate the heat transfer coefficient for the  ceiling ducts. The chilled beam system will have 
following building.  reduced size of air flow that will require a 
Roof and wall have same insulation in the  blower of 1/5th the size of CAV system. The 
building with k = 0.06 W/m. K, roof insulation  dehumidification system will consume another 
thickness is 250 mm, wall insulation thickness is  200 W for operating 2 fans. The operation hours 
150 mm, conductance of glazing is 3 W/m2. K.  for air‐conditioning system for cooling are 5800 
Area of window is 20% of the area of wall. For  hours/year. The electricity rate for the office 
simplicity, consider only the thermal resistance  building is Rs 18 per kWh. Determine the best 
of insulation and neglect the brick insulation,  system for this office building from the point of 
indoor and outdoor film coefficients. Infiltration  view of energy savings and bill savings.   
is half of the volume of room.    
 
 

Das könnte Ihnen auch gefallen