Project Code : RTL

S.No. Code of Account WBS Sub Products


1 RTL-1 Renovation of Tv lounge
2 RTL-1.1 Floor Restoration
3 RTL-1.1.1 Floor Repair
Floor
4 RTL-1.1.2 Floor Cleaning
5 RTL-1.1.3 Floor Polish
6 RTL-1.2 Walls Restoration
7 RTL-1.1.1 Deciding Theme
8 RTL-1.1.2 Fixing Damage Areas Walls
9 RTL-1.1.3 Remove linings
10 RTL-1.1.4 Painting
11 RTL-1.3 Carpet
12 RTL-1.3.1 Carpet Selection and Order
Carpet
13 RTL-1.3.2 Carpet Installation
14 RTL-1.1.3 Carpet Trimming
15 RTL-1.4 Ceiling and Lighting
16 RTL-1.3.1 Lighting Selection and ordering
17 RTL-1.3.2 Lighting Installation Lights
18 RTL-1.3.3 Deciding type of ceiling and ordering
19 RTL-1.3.4 Ceiling installation
20 RTL-1.4 Video Equipment
21 RTL-1.4.1 Tv screen selection and order Screen
22 RTL-1.4.2 Deciding Location of Tv and Installation

23 RTL-1.5 Sound System


Sound System
24 RTL-1.5.1 Speakers selection and order
25 RTL-1.5.2 Deciding Location of Speakers and Installation
26 RTL-1.6 Repair Electrical works
27 RTL-1.6.1 Wiring
28 RTL-1.6.2 Cable Connection
29 RTL-1.7 Sitting Arrangement
Sitting
30 RTL-1.7.1 Selection and ordering of seating and sofa Arragement
31 RTL-1.7.2 Placing seating and sofa

32 RTL-1.8 Decorating
Features Resource Type

High light reflectivity Labour


Easy to clean Mason
More Resistant to retain shine Contractor/Supervisor

Labour
1.Paint Resistant to moisture Mason
transmission Contractor/Supervisor
Long life of Paint Painter

Light weight
Stain protection Contractor/Supervisor
Easy to clean Labour

LED Lights Contractor/Supervisor


Longer life-cycle Electrician
Less usage of electricity

40" - 1920 x 1080 - Full HD Contractor/Supervisor


More vibrant colours Tv Installation expert
HDMI x 2, USB x 2
2.0 Ch 100W Sound
Slim Design Contractor/Supervisor
Bluetooth™ Sound system Installation
Remote App expert

Heat stable Electrician


withstand high load variation

Contractor/Supervisor
Sustanibility and Long Lasting Labour

Contractor/Supervisor
Labour
Project Code: COH
S.No Code of Accounts Activity Time Average Time Calculation
days Max Time Mid time
1 COH-1 Construction of House
2 COH-1.1 Planning 18 30 25
3 COH-1.1.1 Design 30 40 28
4 COH-1.1.1.1 Layout 5 7 6
5 COH-1.2 Foundation 25 27 24
6 COH-1.2.1 Excavation 5 7 6
7 COH-1.2.2 Lean Concrete
8 COH-1.2.3 Reinforcement of Bed 2 5 4
9 COH-1.2.4 Formwork of Bed 6 8 6
10 COH-1.2.5 Concreting of Bed 5 7 6
11 COH-1.3 Steel Erection 8 10 5
12 COH-1.3.1 Steel Columns 5 4 3
13 COH-1.3.2 Beams 2 4 3
14 COH-1.3 Building of wall and structure 120 150 130
15 COH-1.4 Electrical work 10 8 6
16 COH-1.4.1 Install and terminate 5 7 6
17 COH-1.4.2 HVAC Equipment 4 6 5
18 COH-1.5 Piping works 5 4 3
19 COH-1.5.1 Drains 10 8 6
20 COH-1.6 Masonary work 22 26 25
21 COH-1.6.1 Lay masoonary 10 8 6
22 COH-1.6.2 Flooring 13 9 6
23 COH-1.7 Tilling 5 7 6
24 COH-1.7.1 Tillings in toilets 4 6 5
25 COH-1.7.2 tilling in kitchen 5 8 6
26 COH-1.8 Plumbing 7 7 6
27 COH-1.9 Finishing 10 8 6
28 COH-1.9.1 Paint 5 7 6
29 COH-1.9.2 Doors 6 8 6
30 COH-1.9.3 Windows 8 7 6
31 COH-1.9.4 Polishing floor 3 6 5
erage Time Calculation Time Risk
Min. Time Pert Category S.D.

16 24.3 Engineering 2.4


20 28.7 Engineering -2.9
4 5.8 Engineering 0.6
21 24.0 Labour 2.4
4 5.8 Labour 0.6
5.0 Labour 0.5
3 4.0 Labour 0.4
5 6.2 Labour 0.6
4 5.8 Labour 0.6
4 5.7 Labour 0.6
2 3.0 Labour 0.3
2 3.0 Labour 0.3
100 128.3 Labour 12.8
5 6.2 Electrician 0.6
4 5.8 Electrician 0.6
4 5.0 Electrician 0.5
2 3.0 Plumber 0.3
5 6.2 Plumber 0.6
24 25.0 Mason 2.5
5 6.2 Mason 0.6
5 6.3 Mason 0.6
4 5.8 Mason 0.6
4 5.0 Mason -0.5
4 6.0 Mason 0.6
4 5.8 Plumbing 0.6
5 6.2 Labour 0.6
4 5.8 Labour 0.6
5 6.2 Labour 0.6
4 5.8 Labour 0.6
4 5.0 Labour 0.5