(S35051)
SIGNATORIES / DISTRIBUTION
Reviewed by M+W Approved by
Approved by
Prepared M+W Project
Construction
by Package QA/QC EHS /
Manager
Contractor Owner Manager Manager Construction
(MEP/CSA)
Director
Signature
Name Phan Anh Tuấn
Date 02/06/2018
FIRST SOLAR DONG NAM 2, DMT2
(S35051)
1.0 Introduction
This document statement describes the procedure, quality control, environment management and
safety control of fiber/cooper cable pulling work.
2.0 Resources
2.1 Materials
All materials used on site must be approved type and they are as follows:
Manpower plan:
Designation / Name Key Person Quantity
Manager: Phan Anh Tuấn * 01
Supervisor: Nguyễn Thắng Huân * 03
Nguyễn Văn Duy
Lê Phú Đức
EHS: Nguyễn Phi Long * 01
QA/QC: Nguyễn Đăng Hiếu * 01
Worker: N/A 10
Contact information:
Designation / Name Email Mobile
Manager: Phan Anh Tuấn tuan.phan@one.com.vn 0906307547
Supervisor: Nguyễn Thắng Huân huan.nguyen@one.com.vn 0903121077
Nguyễn Văn Duy duy.nguyenvan@one.com.vn 0913934848
Lê Phú Đức duc.le@one.com.vn 0917565355
EHS: Nguyễn Phi Long long.nguyen@one.com.vn 0908930459
QA/QC: Nguyễn Đăng Hiếu hieu.nguyen@one.com.vn 0938616173
3.1 Receiving
All incoming materials shall be verified as per packing list. Witness inspection shall be
carried out and requested to M+W QA/QC Group at least one day prior to materials
delivery for the first shipment of every material. Succeeding incoming materials shall also
be requested for M+W QA/QC inspection and/or be internally inspected and documented
for monitoring purposes.
3.2 Handling
Material will be handling by fork lift, hand lift and mobile manpower.
3.3 Storage
FIRST SOLAR DONG NAM 2, DMT2
(S35051)
We store on our work or one location on factory, decide and confirm the storage are for this
material by M+W.
Storage area shall not obstruct any access and must be properly barricade with proper
signage.
12-fiber 5 121
12-fiber 132 66
Toolbox meeting
prior to start
Preparation work:
- Two workers work with the cable drum service worker is working above
and reel holder to feed cable
Broken lift-up Visual check over-head space
- One worker on the scissor lift at the before lift-up
enter of cable tray to feed cable. Signal Cable tray/ladder not
properly done/handing Check ground condition
man on the ground.
over before lift-down
- Two workers at the other end to operate Drop of cable Don’t stand under while
the winch machine to pull fiber cable. tray/ladder/support workers are working at height
due overload
- Cooper cable will be pulled by man Scaffold must be inspected
power using fish wire Over speed limit
and approved by M+W EHS
Electrial shock with green tag
- After pulling completed, worker on the
scissor lift then fix the cable to cable tray No person is to be on the
using cable tight and install the label scaffold while it is moving
marking.
Equipment and materials
Step 3: Cable Marking: must be either removed from
- Cables must be identified along cable the scaffold or secured to
runs, using cable labels, showing the prevent anything from falling
reference of each cable.
from the scaffold during the
move
- This identification shall be according to
the following principles: every 150 m, The ground conditions of the
changes in direction, both ends new working area must be
inspected prior to the move to
Step 4: Fiber welding and cooper cable ensure it is free of
termination obstructions and is suitable to
- Only the qualified personnel must be carry the load of the scaffold
allowed to do welding and cooper cable
termination Check document,
certification of lift-up
- Carefully follow the fiber plan. operator license and check
working area
- Fiber cable will be coil to the fiber slack
loop in the NDR, MDF, BSR room then Check the working radius
welding to the ODF with fiber welding quarantine area to place sings
FIRST SOLAR DONG NAM 2, DMT2
(S35051)
- At IDF, fiber cable will be coil and Signalman and operator are
install at the side, inside of the rack then to stay in constant
welding to the ODF with fiber welding communication at all time
machine. during the operation
Inspection and Test Plans (ITP) shall include inspection at the following stage.
ITP shall also address the “Hold Point”, where approval on the work activity is required.