1.5 C&S Yunchuang/Z 4 5/25/2018 0 50 7 0 57 0 29 7
hou Yingqi
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outstanding items related to damaged, def
commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” punch items, outstanding items will not d
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Performance Test.
94 0 48 6 0 54 44% 0 16 14 0 30
62 0 30 10 0 40 37% 0 44 3 0 47
0 0 0 0 0 0 0% 0 12 4 0 16
36 0 17 5 0 22 39% 0 21 0 0 21
0 0 0 0 0 0 0% 0 0 36 0 36
3 0 0 0 0 0 0% 0 1 3 0 4
related to damaged, defective or missing equipment, malfunction and missing document which must be completed prior to the start of
standing items will not delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
t.
Document No Punch List Summary Status (S
JIMT-C02-Q-13-20032-PCS002a PRE- COMMISSI
Total Punch
SN SYSTEM SUBSYSTEM
A B C D Total
Tank,Pump,FW Ringmain,spray system
1 Fire Water 3 124 90 0 217
12 Instrument Tel/Data,TAS,TG,TLAS,ACS,ESD 0 0 0 0 0
13 Mechanical(EOT Crane) EOT Crane 0 0 0 0 0
14 Mechanical(vapor Recovery) General,vapor Recovery 0 0 0 0 0
20 Process (5) Diesel System Tank 11,12 &13 IS,SS ,ES 0 57 84 0 141
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outstanding
the start of commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” punch item
subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Performan
14 5 19 0 11 3 0 14 50% 0 9 5
8 1 9 0 5 0 0 5 11% 0 23 17
13 2 15 0 12 1 0 13 57% 0 8 2
31 18 49 0 33 12 0 45 42% 0 29 32
25 31 56 0 15 23 0 38 28% 0 58 38
0 0 0 0 0 #DIV/0! 0 0 0
0 0 0 0 0 0 0 0 #DIV/0! 0 0 0
0 0 0 0 0 0 0% 0 6 1
0 0 0 0 0 0 #DIV/0! 0 0 0
4 8 12 0 1 4 0 5 12% 0 20 17
0 0 0 0 0 0 #DIV/0! 0 0 0
0 0 0 0 0 0 #DIV/0! 0 0 0
0 0 0 0 0 0 #DIV/0! 0 0 0
14 4 18 0 0 0 0 0 0% 0 20 4
3 24 20 47 2 13 2 0 17 14% 2 49 50
7 42 27 76 3 30 4 0 37 22% 5 56 68
8 36 21 65 5 25 3 0 33 20% 3 66 65
0 0 0 0 0 0 #DIV/0! 0 0 0
25 31 56 0 0 0 0 0 0% 0 57 84
12 13 25 0 0 0 0 0 0% 0 32 22
0 0 0 0 0 0 #DIV/0! 0 0 0
CIWEverified punch =560 PMC Verified Punch = 278 Total Remaining Punch = 994
nch items, outstanding items related to damaged, defective or missing equipment, malfunction and missing document which must be completed prio
CC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but must be cleared before signing-off each
0 14
0 40
0 10
0 61
0 96
0 0
0 0
0 7
0 0
0 37
0 0
0 0
0 0
0 24
0 101
0 129
0 134
0 0
0 141
0 54
0 0
0 994
Tank,Pump,FW Ringmain,spray
1.1 Tankage Fire Water system
Nong Siming
Tank,Pump,FW Ringmain,spray
1.6 Architecture Fire Water system
Tank,Pump,FW Ringmain,spray Malian/Sure
1.7 E&I Fire Water system sh
Tank,Pump,FW Ringmain,spray
1.8 HSE Fire Water system
Saravanan
Tank,Pump,FW Ringmain,spray
1.9 General Fire Water system
Wang
2.2 Pipe Fire Foam Foam system,Foam water ring main,Foam
Zhangyu
2.3 Mechanical Fire Foam Foam system,Foam water ring main,Foam Zhou Ji
2.4 Process Fire Foam Foam system,Foam water ring main,Foam Zeng Bin
Zhu
2.5 C&S Fire Foam Foam system,Foam water ring main,Foam
Yunchuang
Zhu
6.5 C&S Ancillary Buildings GH,DR,FWP,FS,LPS,TLB
Yunchuang
Malian/Sure
6.6 Architecture Ancillary Buildings GH,DR,FWP,FS,LPS,TLB
sh
6.7 E&I Ancillary Buildings GH,DR,FWP,FS,LPS,TLB
6.8 HSE Ancillary Buildings GH,DR,FWP,FS,LPS,TLB
6.9 General Ancillary Buildings GH,DR,FWP,FS,LPS,TLB
Remaining Punch for Ancillary building : 117 - 17 = 100
Zhu
9.5 C&S Sewarage Sewarage
Yunchuang
Add.Syst. for
15.1 TANK Additive system
Mogas,Diesel,Jetfuel
Add.Syst. for
15.2 Pipe Additive system
Mogas,Diesel,Jetfuel
Add.Syst. for
15.3 Mechanical Additive system
Mogas,Diesel,Jetfuel
Add.Syst. for
15.4 Process Additive system
Mogas,Diesel,Jetfuel
Add.Syst. for
15.5 C&S Additive system
Mogas,Diesel,Jetfuel
Add.Syst. for
15.6 Architecture Additive system
Mogas,Diesel,Jetfuel
Add.Syst. for
15.7 E&I Additive system
Mogas,Diesel,Jetfuel
Add.Syst. for
15.8 HSE Additive system
Mogas,Diesel,Jetfuel
Add.Syst. for
15.9 General Additive system
Mogas,Diesel,Jetfuel
16.1 TANK Process(1) Mogas 92 Syst Tank 03 IS,SS ,ES Nong Siming
Process(2) Mogas 95
17.1 TANK Tank 01 & 02 IS,SS ,ES Nong Siming
System
Process(2) Mogas 95
17.2 Pipe Tank 01 & 02 IS,SS ,ES
System
Process(2) Mogas 95
17.3 Mechanical Tank 01 & 02 IS,SS ,ES
System
Process(2) Mogas 95
17.4 Process Tank 01 & 02 IS,SS ,ES
System
Process(2) Mogas 95
17.5 C&S Tank 01 & 02 IS,SS ,ES
System
Process(2) Mogas 95
17.6 Architecture Tank 01 & 02 IS,SS ,ES
System
Process(2) Mogas 95
17.7 E&I Tank 01 & 02 IS,SS ,ES
System
Process(2) Mogas 95
17.8 HSE Tank 01 & 02 IS,SS ,ES
System
Process(2) Mogas 95
17.9 General Tank 01 & 02 IS,SS ,ES
System
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A”
missing document which must be completed prior to the start of commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification
but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleare
Punch List Summary Status (Discipline) Date Updated
PRE- COMMISSIONING 21/05/2018
Total Punch Verified by PMC/SPC Remaining Punc
Date To Close
A B C D Total A B C D Total % A B
5/10/2018 3 13 2 0 18 3 0 0 0 3 17% 0 13
5/10/2018 0 41 15 0 56 0 30 3 0 33 59% 0 11
5/15/2018 0 16 6 0 22 0 11 6 0 17 77% 0 5
5/15/2018 0 4 0 0 4 0 0 0 0 0 0% 0 4
5/15/2018 0 21 0 0 21 0 0 0 0 0 0% 0 21
0 0 0 0 0 0 0 0 0 0 0 0
5/25/2018 0 27 62 0 89 0 3 15 0 18 20% 0 24
5/25/2018 0 2 5 0 7 0 0 0 0 0 0% 0 2
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
5/10/2018 0 10 7 0 17 0 7 2 0 9 53% 0 3
5/15/2018 0 4 1 0 5 0 4 1 0 5 100% 0 0
5/15/2018 0 2 0 0 2 0 0 0 0 0 0% 0 2
5/15/2018 0 4 0 0 4 0 0 0 0 0 0% 0 4
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 20 8 0 28 0 11 3 0 14 0 9
0 0 0 0 0 0 0 0 0 0 0 0
5/10/2018 0 6 0 0 6 0 2 0 0 2 33% 0 4
5/15/2018 0 15 4 0 19 0 3 0 0 3 16% 0 12
5/15/2018 0 2 3 0 5 0 0 0 0 0 0% 0 2
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
5/15/2018 0 5 10 0 15 0 0 0 0 0 0% 0 5
0 0 0 0 0 0 0 0 0 0 0 0
5/15/2018 0 0 0 0 0 0 0 0 0 0 0 0
0 28 17 0 45 0 5 0 0 5 0 23
0 0 0 0 0 0 0 0 0 0 0 0
5/10/2018 0 10 1 0 11 0 9 0 0 9 82% 0 1
5/16/2018 0 6 1 0 7 0 3 1 0 4 57% 0 3
5/15/2018 0 4 1 0 5 0 0 0 0 0 0% 0 4
0 0 0 0 0 0 0 0 0 0 0 0
5/16/2018 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 20 3 0 23 0 12 1 0 13 57% 0 8
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
5/16/2018 0 12 1 0 13 0 4 0 0 4 31% 0 8
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
5/16/2018 0 12 0 0 12 0 11 0 0 11 92% 0 1
5/25/2018 0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 38 24 0 62 0 18 12 0 30 48% 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 62 25 0 87 0 33 12 0 45 52% 0 29
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
5/16/2018 0 6 4 0 10 0 5 2 0 7 70% 0 1
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
5/16/2018 0 7 6 0 13 0 6 5 0 11 85% 0 1
5/18/2018 0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 60 34 0 94 0 4 16 0 20 21% 0 56
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 73 44 0 117 0 15 23 0 38 32% 0 58
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
5/20/2018 0 6 1 0 7 0 0 0 0 0 0% 0 6
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 0 0 0 0 0 0 0 0 0 #DIV/0! 0 0
0 6 1 0 7 0 0 0 0 0 0% 0 6
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 21 21 0 42 0 1 4 0 5 0 20
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 21 21 0 42 0 1 4 0 5 0 20
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 5 2 0 7 0 0 0 0 0 0 5
0 11 2 0 13 0 0 0 0 0 0 11
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 4 0 0 4 0 0 0 0 0 0 4
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 20 4 0 24 0 0 0 0 0 0 20
5/18/2018 4 30 24 0 58 2 13 1 0 16 2 17
0 4 5 0 9 0 0 0 0 0 0 4
0 4 0 0 4 0 0 0 0 0 0 4
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 29 24 0 53 0 0 0 0 0 0 29
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
4 67 53 0 124 2 13 1 0 16 2 54
5/20/2018 8 63 54 0 125 3 30 4 0 37 5 33
0 4 5 0 9 0 0 0 0 0 0 4
0 4 0 0 4 0 0 0 0 0 0 4
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 39 32 0 71 0 0 0 0 0 0 39
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
8 110 91 0 209 3 30 4 0 37 5 80
5/24/2018 8 67 48 0 123 5 25 3 0 33 3 42
0 4 5 0 9 0 0 0 0 0 0 4
0 4 0 0 4 0 0 0 0 0 0 4
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0
0 41 32 0 73 0 0 0 0 0 0 41
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
8 116 85 0 209 5 25 3 0 33 3 91
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 45 77 0 122 0 0 0 0 0 0 45
0 0 0 0 0 0 0 0 0 0 0 0
0 4 0 0 4 0 0 0 0 0 0 4
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 30 24 0 54 0 0 0 0 0 0 30
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 79 101 0 180 0 0 0 0 0 0 79
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 4 0 0 4 0 0 0 0 0 0 4
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 33 24 0 57 0 0 0 0 0 0 33
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 37 24 0 61 0 0 0 0 0 0 37
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0
missioning activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, malfunction an
works.
ical Completion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning
C D Total
2 0 15
12 0 23
0 0 5
0 0 4
0 0 21
0 0 0
47 0 71
5 0 7
0 0 0
66 0 146
0 0 0
5 0 8
0 0 0
0 0 2
0 0 4
0 0 0
0 0 0
0 0 0
0 0 0
5 0 14
0 0 0
0 0 4
4 0 16
3 0 5
0 0 0
0 0 0
10 0 15
0 0 0
0 0 0
17 0 40
0 0 0
0 0 2
1 0 3
1 0 5
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
2 0 10
0 0 0
0 0 0
1 0 9
0 0 0
0 0 1
0 0 0
12 0 32
0 0 0
0 0 0
13 0 42
0 0 0
0 0 0
2 0 3
0 0 0
1 0 2
0 0 0
18 0 74
0 0 0
0 0 0
21 0 79
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
1 0 7
0 0 0
0 0 0
0 0 0
0 0 0
1 0 7
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
17 0 37
0 0 0
0 0 0
17 0 37
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
2 0 7
2 0 13
0 0 0
0 0 0
0 0 0
0 0 4
0 0 0
0 0 0
4 0 24
23 0 42
5 0 9
0 0 4
0 0 0
0 0 0
0 0 0
24 0 53
0 0 0
0 0 0
52 0 108
50 0 88
5 0 9
0 0 4
0 0 0
0 0 0
0 0 0
32 0 71
0 0 0
0 0 0
87 0 172
45 0 90
5 0 9
0 0 4
0 0 0
0 0 0
0 0
32 0 73
0 0 0
0 0 0
82 0 176
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
77 0 122
0 0 0
0 0 4
0 0 0
0 0 0
0 0 0
24 0 54
0 0 0
0 0 0
101 0 180
0 0 0
0 0 0
0 0 4
0 0 0
0 0 0
0 0 0
24 0 57
0 0 0
0 0 0
24 0 61
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
anding items will not delay or affect the applicable commissioning works
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-T001 12-May-2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub - system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : TANKAGE Date Sign Date Sign Date Sign
1.00 MAIN SYSTEM : FIRE WATER
Tank,Pump,FW ringmain & Spray CIWE Nong
1.01 JIMT-C02-Y-001 Fire Water Palani/ LHC 12-Apr-2018 Tank 61 & Tank 62 Name plate shoud be installed C 9-May-2018
system Verified Siming
Tank,Pump,FW ringmain & Spray CIWE
1.02 JIMT-C02-Y-001 Fire Water Palani/ LHC 12-Apr-2018 Tank 61 & Tank 62 Kick plate shoud be added at top of tank C 4-May-2018 Durai
system Verified
Tank,Pump,FW ringmain & Spray Davis / To conduct another round of cleaning of the interior of the fire water PMC
1.03 JIMT-C02-Y-001 Fire Water 15-Mar-2018 A 24-Apr-2018 Zhao Lei 24-Apr-2018 Davis 24-Apr-2018 Desmond
system Desmond tank (flooring and the water inlet under the tank roof). Verified
Tank,Pump,FW ringmain & Spray Davis / To provide a valve between the level gauge device and the tank nozzle PMC
1.04 JIMT-C02-Y-001 Fire Water 15-Mar-2018 A 24-Apr-2018 Zhao Lei 24-Apr-2018 Davis 24-Apr-2018 Desmond
system Desmond to facilitate future maintenance. Verified
For Tank 62, to patch up the coating at the welding seam between the
Tank,Pump,FW ringmain & Spray Davis / PMC
1.05 JIMT-C02-Y-001 Fire Water 15-Mar-2018 tank shell course of 1 and 2. Nippon paint supervisor is aware of the A 24-Apr-2018 Zhao Lei 24-Apr-2018 Davis 24-Apr-2018 Desmond
system Desmond Verified
location.
Tank,Pump,FW ringmain & Spray Davis / To replace all bolt and nut securing the free-vent to galvanized CIWE
1.06 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B 7-May-2018 Nong Siming
system Desmond material specification for all tanks Verified
Tank,Pump,FW ringmain & Spray Davis / To provide provision for either barricade or hardness hook-on point CIWE
1.07 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B 18-May-2018 Nong Siming
system Desmond for future tank vent maintenance at tank top Verified
Tank,Pump,FW ringmain & Spray Davis / Ensure that all bolt and nut securing joints for the stair case and CIWE
1.08 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B 20-May-2018 Nong Siming
system Desmond platform grating are properly secure and tighten Verified
Tank,Pump,FW ringmain & Spray Davis / To touch up on the corroded patch at the external roof surface of the CIWE
1.10 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B 20-May-2018 Nong Siming
system Desmond fire water tank Verified
Tank,Pump,FW ringmain & Spray Davis / To ensure that there is a stoppage mechanism to hold the manhole
1.11 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B Open
system Desmond cover when in open position at tank top for all tanks
Tank,Pump,FW ringmain & Spray Davis / To provide provision for the maintenance of the lighting at the tank top CIWE
1.12 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B 20-May-2018 Nong Siming
system Desmond and the stair case leading to the tank top Verified
Tank,Pump,FW ringmain & Spray Davis / To ensure all lamp pole are properly secure and ensure that all screw
1.14 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B Open
system Desmond and nut are fixed up as according to design.
Tank,Pump,FW ringmain & Spray Davis / To provide proper stairs access of 1.5 meter in width for the tank
1.15 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B Open
system Desmond bottom manhole for all tanks.
Grating to be provided for the tank drainage pit and to raise the height
Tank,Pump,FW ringmain & Spray Davis / of the base of the pit to be in-line with the piping leading to the outfall
1.16 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B Open
system Desmond system. This is to eliminate water trapping which will result in
mosquito breeding
Tank,Pump,FW ringmain & Spray Davis / To provide additional lock nut at the hinge of the earthling pit cover,
1.17 JIMT-C02-Y-001 Fire Water 15-Mar-2018 B Open
system Desmond the earthling pit housing should be secure properly
3.00 UTILITY-1
4.00 UTILITY-2
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-T001 12-May-2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub - system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : TANKAGE Date Sign Date Sign Date Sign
4.01 JIMT-C02-Y-004 Utility-2
5.00 MAIN BUILDING
5.01 JIMT-C02-Y-005
7.00 CIVIL
7.01 JIMT-C02-Y-007
8.00 SAFETY
8.01 JIMT-C02-Y-008
9.00 SEWERAGE
9.01 JIMT-C02-Y-009
10.00 WASTE WATER
10.01 JIMT-C02-Y-010
11.00 ELECTRICAL
11.01 JIMT-C02-Y-011
12.00 INSTRUMENT
12.01
13.00 MECHANICAL(EOT CRANE)
13.01
14.00 MECHANICAL(VAPOR RECOVERY)
14.01
PROCESS (1) Mogas 92 Import System,Storage System Level transmitter power and indtrument cables are tight together, it
16.32 JIMT-C02-Y-016 Rav 23-Apr-2018 B Open
system & Export System should be separate
PROCESS (1) Mogas 92 Import System,Storage System Roof top rusty nearby circulation vent, it should be clean and need
16.36 JIMT-C02-Y-016 Palani 23-Apr-2018 C Open
system & Export System painting touch-up
PROCESS (1) Mogas 92 Import System,Storage System Centre of the roof top had rusting particles, its should be remove and
16.37 JIMT-C02-Y-016 Palani 23-Apr-2018 C Open
system & Export System provide painting touch-up
PROCESS (1) Mogas 92 Import System,Storage System some places screws used for clamp the floating drum, it should be SPC
16.52 JIMT-C02-Y-016 SPC 20-Apr-2018 A 15-May-2018 Nong Siming 16-May-2018 Davis 16-May Desmond
system & Export System changed to bolt & Nuts Verified
PROCESS (1) Mogas 92 Import System,Storage System Add earthing line for near sampling hatch for gauging type/ sampling CIWE
16.57 JIMT-C02-Y-016 SPC 20-Apr-2018 B 15-May-2018 Nong Siming
system & Export System earth clip Verified
Tank 01
PROCESS (2) Mogas 95 Level transmitter power and instrument cables are tight together, it
17.34 JIMT-C02-Y-017 Import,Storage & export System LEE 20-Apr-2018 B Open
system should be separate
PROCESS (2) Mogas 95 Centre of the roof top had rusting particles, its should be remove and
17.41 JIMT-C02-Y-017 Import,Storage & export System LEE 20-Apr-2018 B Open
system provide painting touch-up
PROCESS (2) Mogas 95 Fire water sprinkler pipeline need painting touch-up near by stairway
17.48 JIMT-C02-Y-017 Import,Storage & export System Palani 20-Apr-2018 C Open
system end
PROCESS (2) Mogas 95 Stairway lighting calble damage at intermediate plateform, it must be
17.51 JIMT-C02-Y-017 Import,Storage & export System Rav 20-Apr-2018 B Open
system replace
PROCESS (2) Mogas 95 some places screws used for clamp the floating drum, it should be Nong
17.56 JIMT-C02-Y-017 Import,Storage & export System SPC 20-Apr-2018 A Open 9-May-2018
system changed to bolt & Nuts Siming
PROCESS (2) Mogas 95 Add earthing line for near sampling hatch for gauging type/ sampling CIWE
17.61 JIMT-C02-Y-017 Import,Storage & export System SPC 20-Apr-2018 B 15-May-2018 Nong Siming
system earth clip Verified
Tank 02
PROCESS (2) Mogas 95 Level transmitter power and indtrument cables are tight together, it
17.34 JIMT-C02-Y-017 Import,Storage & export System LEE 20-Apr-2018 B Open
system should be separate
PROCESS (2) Mogas 95 Centre of the roof top had rusting particles, its should be remove and
17.41 JIMT-C02-Y-017 Import,Storage & export System LEE 20-Apr-2018 B Open
system provide painting touch-up
PROCESS (2) Mogas 95 Fire water sprinkler pipeline need painting touch-up near by stairway CIWE Nong
17.48 JIMT-C02-Y-017 Import,Storage & export System Palani 20-Apr-2018 C 19-May-2018
system end Verified Siming
PROCESS (2) Mogas 95 Stairway lighting calble damage at intermediate plateform, it must be
17.51 JIMT-C02-Y-017 Import,Storage & export System Palani 20-Apr-2018 B Open
system replace
PROCESS (2) Mogas 95 some places screws used for clamp the floating drum, it should be SPC
17.56 JIMT-C02-Y-017 Import,Storage & export System SPC 20-Apr-2018 A 15-May-2018 Nong Siming 16-May-2018 Davis 16-May Desmond
system changed to bolt & Nuts Verified
PROCESS (2) Mogas 95 Add earthing line for near sampling hatch for gauging type/ sampling CIWE
17.62 JIMT-C02-Y-017 Import,Storage & export System SPC 20-Apr-2018 B 15-May-2018 Nong Siming
system earth clip Verified
PROCESS (3) Mogas 98 Import System,Storage System some places screws used for clamp the floating drum, it should be SPC
18.56 JIMT-C02-Y-018 SPC 20-Apr-2018 A 15-May-2018 Nong Siming 16-May-2018 Davis 16-May Desmond
system & Export System changed to bolt & Nuts Verified
PROCESS (3) Mogas 98 Import System,Storage System Add earthing line for near sampling hatch for gauging type/ sampling CIWE
18.61 JIMT-C02-Y-018 SPC 20-Apr-2018 B 15-May-2018 Nong Siming
system & Export System earth clip Verified
Tank 05
PROCESS (3) Mogas 98 Import System,Storage System
18.01 JIMT-C02-Y-018 Palani 25-Apr-2018 Earthing Plug to be provide for TANK 05 Stairway B Open
system & Export System
PROCESS (3) Mogas 98 Import System,Storage System Tank bottom plate Minor rust found some places. It should be clean SPC
18.06 JIMT-C02-Y-018 Palani 25-Apr-2018 B 9-May-2018 Zhao Lei 16-May-2018 Davis 16-May-2018 Desmond
system & Export System and provide painting touch-up Verified
PROCESS (3) Mogas 98 Import System,Storage System Floating roof PE wiper seal not properly sealed, repair all PE Wiper SPC
18.21 JIMT-C02-Y-018 Palani 25-Apr-2018 B 9-May-2018 Zhao Lei 16-May-2018 Davis 16-May-2018 Desmond
system & Export System Joints Verified
PROCESS (3) Mogas 98 Import System,Storage System Level transmitter power and instrument cables are tight together, it
18.31 JIMT-C02-Y-018 Rav 25-Apr-2018 B Open
system & Export System should be separate
PROCESS (3) Mogas 98 Import System,Storage System Roof top rusty nearby circulation vent, it should be clean and need
18.35 JIMT-C02-Y-018 Palani 25-Apr-2018 C Open
system & Export System painting touch-up
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-T001 12-May-2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub - system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : TANKAGE Date Sign Date Sign Date Sign
PROCESS (3) Mogas 98 Import System,Storage System Centre of the roof top had rusting particles, its should be remove and
18.36 JIMT-C02-Y-018 Palani 25-Apr-2018 C Open
system & Export System provide painting touch-up
PROCESS (3) Mogas 98 Import System,Storage System Cable conduit pipe broken for Stairway 2nd light pole, it should be
18.49 JIMT-C02-Y-018 Rav 25-Apr-2018 B Open
system & Export System replace
PROCESS (3) Mogas 98 Import System,Storage System some places screws used for clamp the floating drum, it should be SPC
18.51 JIMT-C02-Y-018 Palani 25-Apr-2018 B 9-May-2018 Zhao Lei 16-May-2018 Davis 16-May-2018 Desmond
system & Export System changed to bolt & Nuts Verified
PROCESS (3) Mogas 98 Import System,Storage System some places screws used for clamp the floating drum, it should be CIWE Nong
18.55 JIMT-C02-Y-018 SPC 20-Apr-2018 A 19-May-2018
system & Export System changed to bolt & Nuts Verified Siming
PROCESS (3) Mogas 98 Import System,Storage System Add earthing line for near sampling hatch for gauging type/ sampling CIWE
18.60 JIMT-C02-Y-018 SPC 20-Apr-2018 B 15-May-2018 Nong Siming
system & Export System earth clip Verified
Import System,Storage System All the tank's Shell Manhole platform stairway direction to standardise
20.43 JIMT-C02-Y-020 Process(5) Diesel Sysrtem SPC 9-May-2018 B
& Export System and to provide handrail.
Tank 12
Closed by CIWE and Verified by PMC Closed by CIWE, Pending on Verification of PMC
CATOGERY
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, malfunction and missing document which must be completed prior to the start of commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Performance Test.
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-P001 5/12/2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub-system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : PIPING Date Sign Date Sign Date Sign
1.00 MAIN SYSTEM : FIRE WATER
Tank,Pump,FW ringmain & Labelling of tank number and pipelines on the drencher pipelines for fire water line have not been CIWE Wang
1.06 JIMT-C02-Y-001 Fire Water Randy 9-Mar-2018 B 16-May-2018
Spray system done yet. Verified Zhangyu
Tank,Pump,FW ringmain & The wapping protection for the fire water pipeline between underground and aboveground is PMC Wang
1.18 JIMT-C02-Y-001 Fire Water Randy 13-Mar-2018 C 16-May-2018 16-May-2018 Randy
Spray system insufficient. Verified Zhangyu
Tank,Pump,FW ringmain & To check with the Vendor for the need of having flange connection at the two outlets of the PMC Wang
1.23 JIMT-C02-Y-001 Fire Water Randy 13-Mar-2018 B 16-May-2018 16-May-2018 Randy
Spray system pressure water sensing line; Verified Zhangyu
Tank,Pump,FW ringmain & The type of high temperature resistance paint at the exhaust shall be checked and replaced if it is PMC Wang
1.25 JIMT-C02-Y-001 Fire Water Randy 13-Mar-2018 C 16-May-2018 16-May-2018 Randy
Spray system necessary; Verified Zhangyu
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-P001 5/12/2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub-system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : PIPING Date Sign Date Sign Date Sign
Tank,Pump,FW ringmain & Pipe end shall be changed to flange connection instead of pipe cap to prevent dead-leg for the fire PMC Wang
1.26 JIMT-C02-Y-001 Fire Water Randy 15-Mar-2018 B 16-May-2018 16-May-2018 Randy
Spray system water main ring near main entrance and washing bay. Verified Zhangyu
Tank,Pump,FW ringmain & The PRV and isolating valve at the inlet for all the hose reels has not installed yet for office PMC
1.28 JIMT-C02-Y-001 Fire Water Randy 15-Mar-2018 B 5-Apr-2018 Durai 16-May-2018 Randy
Spray system building, workshop, changing room, truck loading bays, fire pump station & pump station. Verified
Tank,Pump,FW ringmain & The pipe routing for the hose-reel is not tally with piping layout, which was supposed routed CIWE Wang
1.29 JIMT-C02-Y-001 Fire Water Randy 15-Mar-2018 B 16-May-2018
Spray system inside shelter instead of outside. Verified Zhangyu
Tank,Pump,FW ringmain & The ROs(30-RO-001, 30-RO-002, 20-RO-001 and 61-RO-002) after the deluge valve and flowmeter PMC
1.30 JIMT-C02-Y-001 Fire Water Randy 15-Mar-2018 B 4-May-2018 Durai 20-Apr-2018 Randy
Spray system have not been installed yet Verified
Tank,Pump,FW ringmain & One or two spray nozzle was blocked by the structure for tank T-03, T-04, T-05 and T-07
1.36 JIMT-C02-Y-001 Fire Water Randy 19-Mar-2018 C Open
Spray system respectively
Tank,Pump,FW ringmain & Flange connection leak between hydrant and pipeline for hydrants, including 00-HY-001, 00-HY- PMC
1.41 JIMT-C02-Y-001 Fire Water Randy 19-Mar-2018 B 9-Apr-2018 Zhouji 16-May-2018 Randy
Spray system 002, 00-HY-010 and 00-HY-011. Verified
Tank,Pump,FW ringmain & Leak was discovered at the flange joint at 2nd row of the sprinkler lines (i.e. East side) at product PMC Wang
1.43 JIMT-C02-Y-001 Fire Water Randy 23-Mar-2018 B 16-May-2018 16-May-2018 Randy
Spray system pump station. Verified Zhangyu
Tank,Pump,FW ringmain & The sprinkler at the 2nd row and 8th row shall be checked because it was partially plugged at PMC Wang
1.44 JIMT-C02-Y-001 Fire Water Randy 23-Mar-2018 B 16-May-2018 16-May-2018 Randy
Spray system product pump station. Verified Zhangyu
Tank,Pump,FW ringmain & The drain line of resetting the deluge valve shall be piped to another area to avoid water flow on
1.45 JIMT-C02-Y-001 Fire Water Randy 23-Mar-2018 B Open
Spray system top of the electrical junction box at deluge valve area;
Tank,Pump,FW ringmain & CIWE shall provide valid signed document to show the type of sprinklers that have installed are CIWE Wang
1.46 JIMT-C02-Y-001 Fire Water Randy 23-Mar-2018 C 16-May-2018
Spray system correctly at truck loading bay and product pump station. Verified Zhangyu
Tank,Pump,FW ringmain & To rectify the position indicator since the "Open" and "Close" position was installed wrongly for
1.56 JIMT-C02-Y-001 Fire Water Randy 4-Mar-2018 C Open
Spray system butterfly valve 00-BFV-233.
Foam system,foam water main Labelling of tank number and pipelines on the drencher pipelines for foam line have not been done
2.06 JIMT-C02-Y-002 Foam Randy 12-Mar-2018 B Open
ring & foam yet.
Foam system,foam water main To check the slope of the pipeline as per P&ID drawing and confirm that the pipeline is able to PMC Wang
2.11 JIMT-C02-Y-002 Foam Randy 15-Mar-2018 C 16-May-2018 16-May-2018 Randy
ring & foam drain up. Verified Zhangyu
Foam system,foam water main Drain holes was discovered at the foam water ring main around the tanks. CIWE to check and PMC
2.17 JIMT-C02-Y-002 Foam Randy 22-Mar-2018 C 9-Apr-2018 Zhouji 16-May-2018 Randy
ring & foam clarify it is compliance with code requirements. Verified
3.00 UTILITY-1
3.01 JIMT-C02-Y-003 Utility-1 Potable Water LEE/ MAO 5-Apr-2018 Tag number for all valves and instruments have not been installed yet. B Open
PMC Wang
3.02 JIMT-C02-Y-003 Utility-1 Potable Water LEE/ MAO 5-Apr-2018 Touch-up paint for all pipe and pipe fittings is required. B 16-May-2018 16-May-2018 Randy
Verified Zhangyu
CIWE Wang
3.03 JIMT-C02-Y-003 Utility-1 Potable Water LEE/ MAO 5-Apr-2018 To lable the different piping material. B 16-May-2018
Verified Zhangyu
3.04 JIMT-C02-Y-003 Utility-1 Potable Water LEE/ MAO 5-Apr-2018 To clarify why two gaskets were installed on the pipeline at the potable water pump skid. B Open
PMC Wang
3.05 JIMT-C02-Y-003 Utility-1 Potable Water LEE/ MAO 5-Apr-2018 Valve at suction of pump No. 2 is found leaking B 16-May-2018 16-May-2018 Randy
Verified Zhangyu
Daniel Drain connection to common drainange not complete for all the safety shower at truck loading bay
3.06 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018 B Open
/Randy area.
4.00 UTILITY-2
PMC Wang
4.07 JIMT-C02-Y-004 Utility-2 Service Air System MAO 26-Apr-2018 Bypass line to be added for the air receiver drain line as per Vendor's recommendation. B 16-May-2018 16-May-2018 Randy
Verified Zhangyu
PMC Wang
4.08 JIMT-C02-Y-004 Utility-2 Service Air System MAO 26-Apr-2018 Drain line of the air reciever shall be diverted to oily water sump as per Vendor's recommendation. B 16-May-2018 16-May-2018 Randy
Verified Zhangyu
Drain line to be provided for the two water filter (one in the pipeline, the other one is inside air compressor PMC Wang
4.09 JIMT-C02-Y-004 Utility-2 Service Air System MAO 26-Apr-2018
enclosure) and discharge to oily water sump as per Vendor's recommendation.
B 16-May-2018 16-May-2018 Randy
Verified Zhangyu
1" vent with valve to be added for the pipeline between air compressor and air reciever as per Vendor's PMC Wang
4.10 JIMT-C02-Y-004 Utility-2 Service Air System MAO 26-Apr-2018
recommendation.
B 16-May-2018 16-May-2018 Randy
Verified Zhangyu
PMC Wang
4.11 JIMT-C02-Y-004 Utility-2 Service Air System MAO 26-Apr-2018 The door has clashed with the discharge pipeline of the PSV. B 16-May-2018 16-May-2018 Randy
Verified Zhangyu
5.00 MAIN BUILDING
5.01 JIMT-C02-Y-005 M.Bldg.
6.00 ANCILLARY BUILDINGS
6.01 JIMT-C02-Y-006 A.Bldg.
7.00 CIVIL
7.01 JIMT-C02-Y-007 Civil
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-P001 5/12/2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub-system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : PIPING Date Sign Date Sign Date Sign
8.00 SAFETY
8.01 JIMT-C02-Y-008 Safety
9.00 SEWERAGE
9.01 JIMT-C02-Y-009 Sewerage
10.00 WASTE WATER
10.01 JIMT-C02-Y-010 W.W
11.00 ELECTRICAL
11.01 JIMT-C02-Y-011 Electrl.
12.00 INSTRUMENT
12.01 Instr.
13.00 MECHANICAL(EOT CRANE)
13.01 Mechl.1
14.00 MECHANICAL(VAPOR RECOVERY)
14.01 Mechl.2
15.00 ADDITIVE SYSTEM
ADS for MO,DO,JF CIWE Wang
15.01 JIMT-C02-Y-015 Add.sys. LEE 8-May-2018 Different type of gaskets have been installed B 20-May-2018
Verified Zhangyu
ADS for MO,DO,JF The orientation for all check valves shall be rechecked. Example the unit at Bay 8 is in wrong CIWE Wang
15.06 JIMT-C02-Y-015 Add.sys. LEE 8-May-2018 C 20-May-2018
direction Verified Zhangyu
Peocess(1)-Mogas
CIWE Wang
16.02 JIMT-C02-Y-016 92 System Tank 03 Import System LEE 8-May-2018 Addition support shall be provided for the 1 ½” drain valve B 20-May-2018
Verified Zhangyu
Peocess(1)-Mogas
CIWE Wang
16.03 JIMT-C02-Y-016 92 System Tank 03 Import System LEE 8-May-2018 The bolt length for the drain valves are long. It should change with standard length C 20-May-2018
Verified Zhangyu
Peocess(1)-Mogas
16.04 JIMT-C02-Y-016 92 System Tank 03 Import System LEE 8-May-2018 Spectacle blind shall change to normally open type for all five (5) nos. Mogas Tank B
Peocess(1)-Mogas
The short spool piece that remove for line purging between all Mogas tank nozzle and MOV shall CIWE Wang
16.05 JIMT-C02-Y-016 92 System Tank 03 Import System LEE 8-May-2018 C 20-May-2018
reinstate back Verified Zhangyu
Peocess(1)-Mogas
CIWE Wang
16.06 JIMT-C02-Y-016 92 System Tank 03 Import System LEE 8-May-2018 The 2” Drain valve shall be closed and covered with blind flange C 20-May-2018
Verified Zhangyu
Peocess(1)-Mogas
16.07 JIMT-C02-Y-016 92 System Tank 03 Import System LEE 8-May-2018 Tag number for the TRVs shall be provided and supplement with calibration certificates C
Peocess(1)-Mogas
16.08 JIMT-C02-Y-016 92 System Tank 03 Import System LEE 8-May-2018 Touch up paint shall be given for the TRV and isolating valves. The valve stem shall be greased B
Peocess(1)-Mogas
16.09 JIMT-C02-Y-016 92 System Tank 03 Import System LEE 8-May-2018 Record for the Spring support installation shall be supplemented B
Peocess(2)-Mogas
The short spool piece that remove for line purging between all Mogas tank nozzle and MOV shall CIWE Wang
17.05 JIMT-C02-Y-017 95 System Tank 01 & 02 Import System LEE 8-May-2018 C 20-May-2018
reinstate back Verified Zhangyu
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-P001 5/12/2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub-system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : PIPING Date Sign Date Sign Date Sign
Peocess(2)-Mogas
CIWE Wang
17.06 JIMT-C02-Y-017 95 System Tank 01 & 02 Import System LEE 8-May-2018 The 2” Drain valve shall be closed and covered with blind flange C 20-May-2018
Verified Zhangyu
Peocess(2)-Mogas
17.07 JIMT-C02-Y-017 95 System Tank 01 & 02 Import System LEE 8-May-2018 Tag number for the TRVs shall be provided and supplement with calibration certificates C
Peocess(2)-Mogas
17.08 JIMT-C02-Y-017 95 System Tank 01 & 02 Import System LEE 8-May-2018 Touch up paint shall be given for the TRV and isolating valves. The valve stem shall be greased B
Peocess(2)-Mogas
17.09 JIMT-C02-Y-017 95 System Tank 01 & 02 Import System LEE 8-May-2018 Record for the Spring support installation shall be supplemented B
Peocess(3)-Mogas
The short spool piece that remove for line purging between all Mogas tank nozzle and MOV shall CIWE Wang
18.05 JIMT-C02-Y-018 98 System Tank 04 & 05 Import System LEE 8-May-2018 C 20-May-2018
reinstate back Verified Zhangyu
Peocess(3)-Mogas
CIWE Wang
18.06 JIMT-C02-Y-018 98 System Tank 04 & 05 Import System LEE 8-May-2018 The 2” Drain valve shall be closed and covered with blind flange C 20-May-2018
Verified Zhangyu
Peocess(3)-Mogas
18.07 JIMT-C02-Y-018 98 System Tank 04 & 05 Import System LEE 8-May-2018 Tag number for the TRVs shall be provided and supplement with calibration certificates C
Peocess(3)-Mogas
18.08 JIMT-C02-Y-018 98 System Tank 04 & 05 Import System LEE 8-May-2018 Touch up paint shall be given for the TRV and isolating valves. The valve stem shall be greased B
Peocess(3)-Mogas
18.09 JIMT-C02-Y-018 98 System Tank 04 & 05 Import System LEE 8-May-2018 Record for the Spring support installation shall be supplemented B
Closed by CIWE and Verified by PMC Closed by CIWE, Pending on Verification of PMC
CATOGERY
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, malfunction and missing document which must be completed prior to the start of commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Performance Test.
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
1.00
Tank,Pump,FW
1.01 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.02 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.03 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.04 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.05 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.06 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.07 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
Tank,Pump,FW
1.08 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.09 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.10 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.11 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.12 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.13 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.14 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
Tank,Pump,FW
1.15 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.16 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.17 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.18 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.19 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.20 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.21 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
Tank,Pump,FW
1.22 JIMT-C02-Y-001 Fire Water Mao 12-Mar-2018
Ringmain,Spray system
2.00
Foam system,foam
2.01 JIMT-C02-Y-002 Foam Mao 15-Mar-2018
water main ring & foam
Foam system,foam
2.02 JIMT-C02-Y-002 Foam Mao 15-Mar-2018
water main ring & foam
Foam system,foam
2.03 JIMT-C02-Y-002 Foam Mao 15-Mar-2018
water main ring & foam
Foam system,foam
2.04 JIMT-C02-Y-002 Foam Mao 15-Mar-2018
water main ring & foam
Foam system,foam
2.05 JIMT-C02-Y-002 Foam Mao 15-Mar-2018
water main ring & foam
3.00
Daniel
3.10 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
Daniel
3.11 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
Daniel
3.12 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
Daniel
3.13 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
Daniel
3.14 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
Daniel
3.15 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
Daniel
3.16 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
Daniel
3.17 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
Daniel
3.18 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
Daniel
3.19 JIMT-C02-Y-003 Utility-1 Potable Water 17-Apr-2018
/Randy
4.00
Daniel/
4.01 JIMT-C02-Y-004 Utility-2 Service Air System Randy/ 20-Apr-2018
MAO
Daniel/
4.02 JIMT-C02-Y-004 Utility-2 Service Air System Randy/ 20-Apr-2018
MAO
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
Daniel/
4.03 JIMT-C02-Y-004 Utility-2 Service Air System Randy/ 20-Apr-2018
MAO
5.00
MAO/
5.06 JIMT-C02-Y-005 Main Building Off.Bldg,CR,SS,WH,CR 13-Apr-2018
MinMin
MAO/
5.07 JIMT-C02-Y-005 Main Building Off.Bldg,CR,SS,WH,CR 13-Apr-2018
MinMin
MAO/
5.08 JIMT-C02-Y-005 Main Building Off.Bldg,CR,SS,WH,CR 13-Apr-2018
MinMin
MAO/
5.11 JIMT-C02-Y-005 Main Building Off.Bldg,CR,SS,WH,CR 18-Apr-2018
MinMin
MAO/
5.12 JIMT-C02-Y-005 Main Building Off.Bldg,CR,SS,WH,CR 13-Apr-2018
MinMin
MAO/
5.13 JIMT-C02-Y-005 Main Building Off.Bldg,CR,SS,WH,CR 13-Apr-2018
MinMin
6.00
CR&RA,GH,FWP/FS,L MAO/
6.01 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
CR&RA,GH,FWP/FS,L MAO/
6.02 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
CR&RA,GH,FWP/FS,L MAO/
6.03 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
CR&RA,GH,FWP/FS,L MAO/
6.04 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
CR&RA,GH,FWP/FS,L MAO/
6.05 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
CR&RA,GH,FWP/FS,L MAO/
6.06 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
CR&RA,GH,FWP/FS,L MAO/
6.07 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
CR&RA,GH,FWP/FS,L MAO/
6.08 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
CR&RA,GH,FWP/FS,L MAO/
6.09 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
CR&RA,GH,FWP/FS,L MAO/
6.10 JIMT-C02-Y-006 Ancillary Buildings 18-Apr-2018
PS,TLB MinMin
7.00
7.01 JIMT-C02-Y-007
8.00
8.01 JIMT-C02-Y-008
9.00
9.01 JIMT-C02-Y-009
10.00
10.01 JIMT-C02-Y-010
11.00
11.01 JIMT-C02-Y-011
12.00
12.01
13.00
13.01
14.00
14.01
15.00
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
ADS for DO
15.01 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.02 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.03 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.04 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.05 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.06 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.07 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.08 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.09 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.10 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
ADS for DO
15.11 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.12 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
ADS for DO
15.13 JIMT-C02-Y-015 Additive System Mao 8-May-2018
ADS for JF
16.00
17.00
18.00
19.00
19.01 JIMT-C02-Y-019
20.00
21.00
22.00
22.01
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outst
commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” pu
Cat "C" - Punch items must be cleared before initial products filling.
DOCUMENT NO
PRECOMM
JIMT-C02-Q-13-20031-PC-M001
REVISION : 0 PROJECT : JURONG
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Pe
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
MAIN SYSTEM : FIRE WATER
SPC
To rectify the I/O communication module for 61-FWP-03. B 9-Apr-2018 Zhouji
Verified
SPC
Panel below wood piece to be taken out B 6-Apr-2018 Durai
Verified
SPC
Fuel tank metal platform need chain and kicking plate B 7-Apr-2018 Durai
Verified
SPC
Fuel inlet pipe line need support C 7-Apr-2018 Durai
Verified
SPC
Battery to be covered C 7-Apr-2018 Durai
Verified
SPC
Air Release Valve for 61-FWP-01 is leak. B 9-Apr-2018 Zhouji
Verified
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
Tightening of the water cooling connection for the pump bearing to SPC
C 9-Apr-2018 Zhouji
avoid water splash for 61-FWP-02. Verified
SPC
To rectify the leak for the water coolant for fire water pumps; B 9-Apr-2018 Zhouji
Verified
SPC
Protection cover shall be provided for the battery. B 9-Apr-2018 Zhouji
Verified
CIWE
To provide tag numbering for the equipment; B 9-Apr-2018 Zhouji
Verified
SPC
Touch up paint is required; C 9-Apr-2018 Zhouji
Verified
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
To liaise with the Vendor to provide the “measuring scale” for the
SPC
fixed water monitor with respect to the angular movement position. C 28-Apr-2018 Zhouji
Verified
i.e. up/down and left/right
CIWE to clarify the reason of having two fire pumps running during
SPC
the test because the water demand for product pump station is only C 28-Apr-2018 Zhouji
Verified
342 m3 as per design requirement;
Fire Water Pump, Jockey Pump control panel and FW Diesel tank SPC
B 9-Apr-2018 Zhouji
name plate with its tag number shall be provided. Verified
Fire Water Pump and Jockey Pump operating instruction shall be SPC
B 17-Apr-2018 Zhouji
provided at each control panel. Verified
CIWE
Water trapping within fire water pump skid shall be rectified. B 9-Apr-2018 Zhouji
Verified
The pump casing is leak between pump and motor for Lead Jockey SPC
B 14-May-2018 Zhouji
Pump. Verified
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
To relocate the fire hose box nearby 00-HY-009, 00-HY-007 since it SPC
B 9-Apr-2018 Zhouji
has blocked the access way to operate the valves. Verified
Foam System
Water retain at skid, CIWE to clean and ensure that there is no SPC
B 9-Apr-2018 Zhouji
block at all drain holes. Verified
To Label the tag number of foam pump 62-FFP-01 and 62-FFP-02 SPC
B 9-Apr-2018 Zhouji
on the base plate. Verified
SPC
To clean the top area of foam tank. C 9-Apr-2018 Zhouji
Verified
SPC
Foam tank manhole cover to be fulling bolted B 9-Apr-2018 Zhouji
Verified
UTILITY-1
Chemical cleaning is required for the corrosion portion of the Water
C Open
Tank.
To replace the bolt since the bolt length for bracket supports is CIWE
C 20-May-2018 Venky
short Verified
To improve the access ladder design to meet industrial practice
C Open
requirements
To change HHL setting since the overflow level located below HHL CIWE
B 20-May-2018 Venky
for the water tank. Verified
The float valve inside the water tank was found leakage B Open
Justification shall be given for the tank seal is suitable for outdoor
B Open
application.
SPC
Rusty of eyewash cover for 30-SE-01 at truck loading bay area B 14-May-2018 Zhouji
Verified
Grouting require to fill the gap to the pad for the safety shower. B Open
SPC
Pipe thread connection leaking for the safety shower. B 14-May-2018 Zhouji
Verified
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
Labelling for all the safety shower and eyewash as per P&ID B Open
20-SE-02 too close to LCP 20-LCP-004, protection for LCP require B Open
CIWE
The safety shower has not been installed yet at VRU. B 28-Apr-2018 Zhouji
Verified
UTILITY-2
Tag number has not been provided for the air compressor and air SPC
C 28-Apr-2018 Zhouji
reciever. Verified
SPC
Anchor bolts have yet to tighten. B 28-Apr-2018 Zhouji
Verified
SPC
All Fire extinguishers to be tagged (Office building) B 28-Apr-2018 Zhouji
Verified
Labels for the outdoor (CU) units has not been installed yet. B Open
The power supply system (Normal & Emergency) for the outdoor
B Open
units (CU) has to verify
The isolator rating for the conference room CU unit shall be
B Open
checked and verified
Date for carry out Inspection / test for the fire extinguisher(s) has SPC
B 28-Apr-2018 Zhouji
not been indicated yet. Verified
The type and capacity of the fire extinguisher(s) do not tally with CIWE
B 28-Apr-2018 Zhouji
RFC drawings. Verified
The location of the fire extinguisher is not tally with the RFC CIWE
C 28-Apr-2018 Zhouji
drawings. The related drawings need to be updated. Verified
ANCILLARY BUILDINGS
Date for carry out Inspection / test for the fire extinguisher(s) has SPC
B 14-May-2018 Zhouji
not been indicated yet. Verified
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
The type and capacity of the fire extinguisher(s) do not tally with
RFC drawings. CIWE to provide justification as if the current is
CIWE
better than the type indicated in the RFC drawing, then drawing B 28-Apr-2018 Zhouji
Verified
need to be updated. Otherwise, the fire extinguishers need to be
changed.
The location of the fire extinguisher is not tally with the RFC CIWE
C 28-Apr-2018 Zhouji
drawings. The related drawings need to be updated. Verified
3mm hole to be provided for all the outdoor fire extinguisher(s) to SPC
C 28-Apr-2018 Zhouji
avoide accumulate water. Verified
Relocate the fire extinguisher at the air compressor area as per SPC
B 28-Apr-2018 Zhouji
SPC requirement. Verified
Tag number has not been installed completely for all the fire SPC
B 14-May-2018 Zhouji
extinguisher(s). Verified
The safety certificate and inspection sticker of 3kg fire extinguisher SPC
B 14-May-2018 Zhouji
(outdoor) have not been provided at sub-station area. Verified
The hose of one of the fire extinguisher(s) at additive injection area SPC
B 14-May-2018 Zhouji
is missing. Verified
The hose hook of the fire extinguisher(30-DPE-002) at truck CIWE
C 14-May-2018 Zhouji
loading bay is missing. Verified
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
SAFETY
SEWERAGE
WASTE WATER
ELECTRICAL
INSTRUMENT
MECHANICAL(EOT CRANE)
MECHANICAL(VAPOR RECOVERY)
ADDITIVE SYSTEM
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
Nameplate for all the additive tanks has not been installed yet; B
Isolation valve have not been installed for the level gauge B
CIWE
Additive tanks have not been cleared yet B 21-May-2018 Zhouji
Verified
CIWE
Tank label shall be provided (product, capacity) B 21-May-2018 Zhouji
Verified
The tag number of pumps, valves, PVRV and PSV has not been CIWE
B 21-May-2018 Zhouji
installed yet Verified
CIWE
The site installation is not fully tally with P&ID drawings B 21-May-2018 Zhouji
Verified
Check valve has been added on the additive filling line as per CIWE
B 21-May-2018 Zhouji
SPC’s requirement Verified
To update the P&IDs drawing for the 1” end flange connection consistent CIWE
with the site condition
B 21-May-2018 Zhouji
Verified
CIWE
All tag numbers for instrument (FT, FV) shall be provided B 21-May-2018 Zhouji
Verified
Combined the pressure gauge and pressure switch on pump CIWE
B 21-May-2018 Zhouji
discharge Verified
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
CIWE
The blind flange has not been installed for the drain line C 21-May-2018 Zhouji
Verified
CIWE
Carbon steel bolts shall be replaced by Stainless steel bolts B 21-May-2018 Zhouji
Verified
CIWE
The painting has not been finished yet C 21-May-2018 Zhouji
Verified
PROCESS (1) Mogas 92 system
CATOGERY
activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, malfunction and missing document which must
etion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but must be cleared befo
DATE UP
PRECOMMISSIONING PUNCH LIST
22-May
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1
PUNCH LIST C
Description of Remedial Works
CAT Status CIWE
DISCIPLINE : MECHANICAL Date Sign
equipment, malfunction and missing document which must be completed prior to the start of
e applicable commissioning works but must be cleared before signing-off each subsystem MCC.
DATE UPDATED
22-May-2018
Page 1 of 1
PUNCH LIST COMPLETION
PMC SPC
Date Sign Date Sign
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-CS001 12-May-2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : CIVIL & STRUCTURE Date Sign Date Sign Date Sign
LHC/Glodys/M To provide the platform for all the operating valves, crossover platform of the CIWE
1.01 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 9-Mar-2018 B 16-May-2018 Sundy
XH bundwall and access, wherever necessary. Verified
LHC/Glodys/M To provide grating or enclosed drainage in front of all hydrants, fixed monitors CIWE
1.02 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 9-Mar-2018 B 17-May-2018 Sundy
XH and operational areas. Verified
LHC/Glodys/M The foundation of pipe support and platform have not been constructed
1.03 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 9-Mar-2018 B Open
XH completely;
LHC/Glodys/M CIWE
1.04 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 9-Mar-2018 Water trap at the pump skid shall be rectified; B 16-May-2018 Sundy
XH Verified
To enlarge the concrete plinth for the fire water monitor 00-FWM001 near the fire CIWE
1.05 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system Barnabas 19-Mar-2018 B 17-May-2018 Sundy
water tank pit shall be enlarged Verified
CIWE
1.06 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system LHC/MXH 19-Mar-2018 To provide proper platform for the elevated fire water monitor 00-FWM002 B 21-May-2018 Sundy
Verified
To provide stopper for the grating of intermediate platform of the spiral staircase
1.07 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system LHC/MXH 19-Mar-2018 B Open
for all the tanks.
Anthony/ To grout the gap between all steel support base plate, bolts and ground to
1.08 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B Open
Gladys prevent rusting.
Anthony/ To provide a 6m clear width or hardstand of (6m x 15m) hardstand for fire engine
1.09 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B Open
Gladys access, as per SCDF's requirements.
Anthony/ To provide opening for lightning protection and earthing pit for maintanence CIWE
1.10 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B 16-May-2018 Sundy
Gladys purposes. It should not on the fire engine access. Verified
Anthony/ To clean up the silt in drains and ensure the gradient is sufficient for rain water CIWE
1.11 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B 16-May-2018 Sundy
Gladys flow. Verified
Anthony/ CIWE
1.12 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 To tighten all steel structure bolt connection and checked by RE. B 16-May-2018 Sundy
Gladys Verified
Anthony/ To provide 2 nos of permanent makers on each tank for future settlement
1.13 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B Open
Gladys monitoring.
Anthony/ Bolts for anchoring some fire water pipes and their supports around fire water CIWE
1.14 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B 21-May-2018 Sundy
Gladys tank onto the foundation are missing. CIWE to rectify. Verified
Anthony/
1.15 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 To provide cover (concrete slab/ grating) for drains which are deeper than 1 meter. B Open
Gladys
Anthony/
1.16 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 To submit drawings for road signages, (e.g. height limit signs, etc.) B Open
Gladys
Anthony/ CIWE
1.17 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 To provide cover/ grating for fire water tank back flow pit to minimise falling risk. B 16-May-2018 Sundy
Gladys Verified
Anthony/ Fire bund walls at all firefighting system areas has to meet the 2.5m height. CIWE
1.18 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B Open
Gladys to rectify the areas where height is insufficient.
Anthony/ CIWE
1.19 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 To rectify all areas with ponding problem. B 16-May-2018 Sundy
Gladys Verified
Anthony/ Fencing by the sea area to clear ISPS (International Ship and Port Facility
1.20 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B Open
Gladys Security).
Anthony/ Warehouse - Walls of the washing bay structure is too high. CIWE to rectify for CIWE
1.21 JIMT-C02-Y-001 Fire Water Tank,Pump,FW Ringmain,Spray system 21-Mar-2018 B 21-May-2018 Sundy
Gladys easy access. Verified
2.01 JIMT-C02-Y-002 Foam Foam system,foam water main ring & foam Min Min 15-Mar-2018 Chamber should be provided for Foam pump plinth (not sharp edge) B Open
CIWE
2.02 JIMT-C02-Y-002 Foam Foam system,foam water main ring & foam Min Min 15-Mar-2018 To clean cement stain on firepump station floor and footing of pipe support B 16-May-2018 Sundy
Verified
2.03 JIMT-C02-Y-002 Foam Foam system,foam water main ring & foam Min Min 15-Mar-2018 Grouting/ welding/ bolt & nuts for pipe supports B Open
CIWE
2.04 JIMT-C02-Y-002 Foam Foam system,foam water main ring & foam Min Min 15-Mar-2018 To indicate how many people can stand on draw pit cover slab B 21-May-2018 Sundy
Verified
3.00 UTILITY-1
3.01 JIMT-C02-Y-003 Utility-1 Potable Water
4.00 UTILITY-2
4.01 JIMT-C02-Y-004 Utility-2 Service Air system
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-CS001 12-May-2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : CIVIL & STRUCTURE Date Sign Date Sign Date Sign
5.00 MAIN BUILDING
7.00 CIVIL
7.01 JIMT-C02-Y-007
8.00 SAFETY
8.01 JIMT-C02-Y-008
9.00 SEWERAGE
To provide document that license surveyor/License plumber check invert level and top
9.01 JIMT-C02-Y-009 Sewerage Min Min 24-Apr-2018 B
level of IC
9.02 JIMT-C02-Y-009 Sewerage Min Min 24-Apr-2018 To update drawing JIMT-C02-L-16-20101-002 (Rev 3). 4 no. IC behind office building B
9.03 JIMT-C02-Y-009 Sewerage Min Min 24-Apr-2018 To update RFC drawing JIMT-C02-L-16-20108-002 (Rev 2). Last IC-12 is circular shape. B
9.04 JIMT-C02-Y-009 Sewerage Min Min 24-Apr-2018 To patch up/ grout cement for honey cone concrete surface in IC-02 and IC-04 C
9.05 JIMT-C02-Y-009 Sewerage Min Min 24-Apr-2018 IC-05 top level is higher than road kerb behind visitor carpark B
9.06 JIMT-C02-Y-009 Sewerage Min Min 24-Apr-2018 IC-05, IC-06,IC-07 &IC-12(last IC) are flooding. To check PUB approval to open last IC B
9.07 JIMT-C02-Y-009 Sewerage Min Min 24-Apr-2018 To make brick wall for Ext’g Manhole to prevent top soil collapse B
10.00 WASTE WATER
10.01 JIMT-C02-Y-010
11.00 ELECTRICAL
11.01 JIMT-C02-Y-011
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-CS001 12-May-2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : CIVIL & STRUCTURE Date Sign Date Sign Date Sign
12.00 INSTRUMENT
12.01
Closed by CIWE and Verified by PMC Closed by CIWE, Pending on Verification of PMC
CATOGERY
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, malfunction and missing document which must be completed prior to the start of commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Performance Test.
DOCUMENT NO
PR
JIMT-C02-Q-13-20031-PC-AR001
REVISION : 0 PROJECT :
1.00
2.00
2.01 JIMT-C02-Y-002 Foam
2.02 JIMT-C02-Y-002
3.00
3.01 JIMT-C02-Y-003 Utility-1 Potable Water
4.00
4.01 JIMT-C02-Y-004 Utility-2
5.00
DOCUMENT NO
PR
JIMT-C02-Q-13-20031-PC-AR001
REVISION : 0 PROJECT :
10.00
10.01 JIMT-C02-Y-010
11.00
11.01 JIMT-C02-Y-011
DOCUMENT NO
PR
JIMT-C02-Q-13-20031-PC-AR001
REVISION : 0 PROJECT :
12.00
12.01
13.00
13.01
14.00
14.01
15.00
15.01
16.00
DOCUMENT NO
PR
JIMT-C02-Q-13-20031-PC-AR001
REVISION : 0 PROJECT :
16.01
17.00
17.01
18.00
18.01
19.00
19.01
DOCUMENT NO
PR
JIMT-C02-Q-13-20031-PC-AR001
REVISION : 0 PROJECT :
20.00
20.01
21.00
21.01
22.00
22.01
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outstanding it
works.
DOCUMENT NO
PR
JIMT-C02-Q-13-20031-PC-AR001
REVISION : 0 PROJECT :
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” punch items
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Performance
PRECOMMISSIONING PUNCH LIST
UTILITY-1
UTILITY-2
MAIN BUILDING
PRECOMMISSIONING PUNCH LIST
Plastering around external switches & controls done shabbily. (near ramp staircase) C Open
Minimum 40mm clear space between railing and wall is compromised by presence of lightning
C Open
conductor. (TOP item) ( ramp area)
To have tactile tile at the bottom of the ramp. (TOP item) Ramp Area C Open
Colour of the timber skirtings are not consistent. Need to have a consistent varnishings. C Open
Exit sign is not straight. Support for exit sign needs to be painted white. C Open
Colour for operable wall groove line needs to match laminate colour. C Open
Wall opposite conference room: Plastering is wavy and not even. C Open
Door frames and wall groove lines are uneven and finishes are poorly executed. (toilet doors) C Open
Toilet doors: Door closer extension arm is too short, causing scratches on the door frame.
C Open
(handicapped toilet)
Pantry entrance: To replace carpet where the edges are frayed. C Open
Male toilet: space in between assisted urinal and wash basin is insufficient (min 1.5m) (TOP
C Open
item)
Conference room: Gaps between wall and power point casing. C Open
PRECOMMISSIONING PUNCH LIST
Sliding glass door is missing in the male toilet at the locker C Open
ANCILLARY BUILDINGS
Step need to have yellow paint to highlight the drop in level. (TOP item) Guard House C Open
Painting around the door frame is peeling off. (Guard House) C Open
Cable trays penetrating through the ceiling boards are not cut out properly. (Guard House) C Open
Cable trunkings not done properly and workmanship is very poor.(Guard House) C Open
PRECOMMISSIONING PUNCH LIST
Gaps around power point covers not patched up properly. (Guard House) C Open
External cable trunkings not supported & secured to the ground. - Cable trunkings are not
C Open
painted for weather protection. (Guard House)
Not consistent parts (Chrome & PVC U-pipes) (Female toilet - Changing room) C Open
Exposed copper pipe to be painted with matching wall tile colour. (male toilet - Changing room) C Open
Stainless steel extension pipes should be used instead of copper pipes to match chrome fitting.
C Open
(male toilet - Changing room)
CIVIL
SAFETY
SEWERAGE
WASTE WATER
ELECTRICAL
PRECOMMISSIONING PUNCH LIST
INSTRUMENT
MECHANICAL(EOT CRANE)
MECHANICAL(VAPOR RECOVERY)
ADDITIVE SYSTEM
CATOGERY
items, outstanding items related to damaged, defective or missing equipment, malfunction and missing document which must be completed prior to
PRECOMMISSIONING PUNCH LIST
. For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but must be cleared before signing-off each su
To update the Engineering P&ID drawings to consistent with the Vendor drawing
Tank,Pump,FW since the accessories of the diesel day tank are not tally with P&ID drawing,
1.01 JIMT-C02-Y-001 Fire Water Mao Xiong 12-Mar-2018 B Open
Ringmain,Spray system such as level gauge, vent, etc. CIWE shall check if there is impact and still
compliance with Hazop requirements.
Mismatch of the branch connection at site for fire water hydrant connecting
Tank,Pump,FW stations and pipeline versus P&IDs, including 00-HY-009, 00-HY-002, FW-7301-
1.02 JIMT-C02-Y-001 Fire Water Mao Xiong 12-Mar-2018 B Open
Ringmain,Spray system 1D-2 1/2" and FW-7501-1D-2 1/2". CIWE shall check if there is impact and still
compliance with Hazop requirements
To confirm the drain holes at the fire water ring lines on top of the tanks is
Tank,Pump,FW
1.03 JIMT-C02-Y-001 Fire Water
Ringmain,Spray system
Mao Xiong 20-Mar-2018 compliance with the design code requirements and has catered for in the water B Open
supply design calculation.
Tank,Pump,FW To update the Engineering P&ID drawings to consistent with the Vendor drawing
1.04 JIMT-C02-Y-001 Fire Water Mao Xiong 20-Mar-2018 B Open
Ringmain,Spray system since the schematic of deluge valves are not tally with P&ID drawing.
Foam system,foam water To update the Engineering P&ID drawings to consistent with the Vendor drawing such
2.01 JIMT-C02-Y-002 Foam Mao Xiong 12-Mar-2018 B Open
main ring & foam as field indicator, remote indicator and local ESD, etc.
Foam system,foam water To update the Engineering P&ID drawings since mismatch of the branch connection at
2.02 JIMT-C02-Y-002 Foam Mao Xiong 12-Mar-2018 B Open
main ring & foam site for foam hydrant (00-FH-005) connecting stations and pipeline versus P&IDs.
3.00 UTILITY-1
3.01 JIMT-C02-Y-003 UTILITY-1 Potable Water LEE/ MAO 4-May-2018 The P&ID drawing Rev 5 does not tally with site piping configuration. B Open
3.02 JIMT-C02-Y-003 Utility-1 Potable Water LEE/ MAO 4-May-2018 Flow meter pit should be clean. C
3.03 JIMT-C02-Y-003 Utility-1 Potable Water LEE/ MAO 4-May-2018 To Record water meter readings. C
3.04 JIMT-C02-Y-003 Utility-1 Potable Water LEE/ MAO 4-May-2018 To provide Tank cleaning & internal inspection report. C
There are lots of different between the latest P&ID JIMT-C02-C-17-20038 – Rev 5 versus
3.05 JIMT-C02-Y-003 UTILITY-1 Potable Water LEE/ MAO 4-May-2018 B Open
the approved Rev 4 P&ID drawing.
4.00 UTILITY-2
Daniel/ Randy/ The P&ID(Rev 5) drawing of Air Compressor Vendor Package does not tally with Vendor
4.01 JIMT-C02-Y-004 UTILITY-2 Service Air system 20-Apr-2018 B Open
MAO drawing/ site piping configuration.
Daniel/ Randy/
4.02 JIMT-C02-Y-004 UTILITY-2 Service Air system 20-Apr-2018 The capacity, power of the air compressor does not tally with P&ID drawing. B Open
MAO
Daniel/ Randy/
4.03 JIMT-C02-Y-004 UTILITY-2 Service Air system 20-Apr-2018 To provide set pressure for the auto water drain valve C Open
MAO
Daniel/ Randy/ The P&ID(Rev 5) drawing of Air Compressor Vendor Package does not tally with Vendor
4.04 JIMT-C02-Y-004 UTILITY-2 Service Air system 20-Apr-2018 B Open
MAO drawing/ site piping configuration.
Daniel/ Randy/
4.05 JIMT-C02-Y-004 UTILITY-2 Service Air system 20-Apr-2018 The capacity, power of the air compressor does not tally with P&ID drawing. B Open
MAO
11.00 ELECTRICAL
11.01 JIMT-C02-Y-011
12.00 INSTRUMENT
12.01
13.01
14.01
15.01
16.01
17.01
18.01
19.01
20.01
21.01
22.01
Closed by CIWE and Verified by PMC Closed by CIWE, Pending on Verification of PMC
CATOGERY
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, malfunction and missing document which must be completed prior to the start of commissioning
works.
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-PR001 5/12/2018
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
CIWE PMC SPC
Item Test Pack System Sub system Initiator Date CAT Status
DISCIPLINE : PROCESS Date Sign Date Sign Date Sign
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Performance Test.
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
PMC
1.01 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Bare earthing conductor shall be provided with green / yellow insulation C 8-May-2018 suresh 16-May-2018 murugan
Verified
1.02 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Cable tag shall be provided for all the cables C
1.03 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 FWP control panel “H-O-A” switch shall have missing protection cover C
PMC
1.04 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Battery support shall be anchored permanently on the floor C 9-May-2018 suresh 16-May-2018 murugan
Verified
PMC
1.05 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Provide overall protection cover for the battery C 8-May-2018 suresh 16-May-2018 murugan
Verified
1.06 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Provide insulated cap for battery terminals C
PMC
1.07 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Provide cable tray for Battery cabling and shall be dress neatly in the cable tray C 9-May-2018 suresh 16-May-2018 murugan
Verified
1.08 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Lighting cable dressing shall be completed in the FWP area C
1.09 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Re-orientate the lighting switch for those having cable gland from top entry C
1.10 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Provide calibration certificates for all the pressure gauges B
Lightning tape shall be fixed firmly on the structure with test link box in the FWP
1.11 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 C
area
Extend the cable tray for FWP Diesel tank level switch cabling works and its
excess cable coiling shall be reduced to single coil (100mm dia is
1.18 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 C
sufficient).Conduit end shall be installed with rigid support. Provide tag plate for
level Switch
1.19 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Stainless steel cable tie shall be used for field instrument cable dressing works C
Those lighting installed at FWP diesel tank platform shall increase its height since PMC
1.20 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 C 11-May-2018 suresh 16-May-2018 murugan
it is hitting the head Verified
All the PAPER tag provided in the FWP skid for instruments shall be replaced with
1.21 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 C ciwe verified 20-May-2018 suresh
stainless steel plate
PMC
1.22 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Those flexible conduits damaged in the FWP skid shall be rectified. C 8-May-2018 suresh 16-May-2018 murugan
Verified
1.23 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Provide tag plate with its description for 61-PT-011 C
1.24 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Cable tag to provide for jockey pump control panel cables C ciwe verified 20-May-2018 suresh
Pressure gauge shall be re-orientate to viewable direction from the jockey pump
1.25 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 C ciwe verified 20-May-2018 suresh
control panel
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
1.26 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Cable tray to be provided for jockey pump control panel cables. C
Fire water return line flow meter indicator shall be protected with
1.27 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 canopy.Calibration done on 3rd Jan 2017 thus its validity shall be confirmed. PVC C
drain shall be replaced with SS tube
PMC
1.28 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Incomplete cabling works for 20-FT-001 shall be completed C 9-May-2018 suresh 16-May-2018 murugan
Verified
PMC
1.29 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Incomplete lightning works for FWP shelter shall be completed C 8-May-2018 suresh 16-May-2018 murugan
Verified
At FWP area, Cable ladder “90 Degree Bend” fitting started bend. Provide PMC
1.30 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 C 11-May-2018 suresh 16-May-2018 murugan
additional support Verified
PMC
1.31 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Incomplete 60-LT-002 works shall B 11-May-2018 suresh 16-May-2018 murugan
Verified
60-MOV-001 / 002, Cable tray shall be installed on the support instead of just PMC
1.32 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 C 11-May-2018 suresh 16-May-2018 murugan
placing it on the floor Verified
PMC
1.33 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Fire water tank earth pit shall be raise it to finished floor level C 11-May-2018 suresh 16-May-2018 murugan
Verified
1.34 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Those earth pits installed on the road shall be relocated at FWP area C
1.35 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Provide tag plate with description for FWP and Jockey pump control panel C
1.36 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Provide tag plates with stainless steel wire instead of cable tie C
1.37 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 12-Mar-2018 Drain line shall be provided for all the pressure gauges. C
1.38 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 To ensure the door for the engine control panel be able to swing open fully C
Ferrules shall be provided for all the wiring in the local control panel and field
1.39 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 B
equipment on all the E&I equipment
1.40 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 Return line fire water flow meter unit shall in m3/h instead of GPM B
Electrical cables shall not be coiled either at panel side or field side equipment
1.41 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 C
hence excess cable shall be dressed neatly in the tray / ladder.
PVC dummy plug shall be replaced with appropriate metal plug as per the
1.42 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 hazardous area classification for all the spare gland entry in the Fire water line C
MOV and wherever applicable in the project.
Cable stress observed in the fire water line MOV cable gland side hence extend
1.43 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 C
the cable tray up to the equipment to dress the cable in the tray.
1.44 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 Provide 20% spare space in the electrical & instrument cable tray / ladder C
1.45 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 Provide cable tray / ladder cover for all the E&I cable tray / ladder C
Cable tray / ladder earthing shall be provided at each splice plate and at the end of
1.46 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 C
cable tray / ladder.
1.47 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 Electrical and Instrument cables shall be installed in a separate cable tray /ladder. B
End cap shall be provided for unistruct which are used for E&I Equipment PMC
1.48 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 C 15-May-2018 suresh 16-May-2018 murugan
installation. Verified
Unistruct supports shall be welded on the structure to install E&I equipment and
1.49 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 C
remove the unnecessary supports.
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
Touch up paint shall be done for all the cut edges such as unisturct, cable tray / PMC
1.50 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 C 11-May-2018 suresh 16-May-2018 murugan
ladder etc., Verified
Damper shall be provided for the discharge pressure gauge for FW pump 1 & 2
1.52 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 B ciwe verified 8-May-2018 suresh
against vibration
Positive terminal(s) at the cranking relays shall be properly insulation for FW
1.53 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 B
engine 1 & 2
PMC
1.54 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 Battery box shall be provided for storage of batteries for FW engines B 8-May-2018 suresh 16-May-2018 murugan
Verified
Jocky Pump control Panel Setting of the humidity relay inside the control panel(s)
1.55 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 B
shall be checked / adjusted as per Vendor recommendation
Jocky Pump comtrol panel Setting of the motor overload relay inside the control
1.56 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 B
panel(s) shall be checked / set as per Vendor recommendation
Jocky Pump -To provide a summary of all the pre-programmed parameters for the
1.57 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 B
control monitor display unit that install at the LCP panel(s)
To clarify the different in PI pressure reading at the pump discharge versus the
1.58 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 B
pressure display at the control panel for Jockey Pump No. 2
To provide insulation test report(s) for the motor(s) for Jockey Pump No. 1 & No 2.
1.59 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 13-Mar-2018 B
The report shall be endorsed by PMC
The bolts / nuts for adjusting the open / close limits for the valve shall be marked
1.60 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 C
with Red for all the MOVs
Difference between manual dip (6140mm) and level transmitter (6200mm) is about
1.61 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 B
300mm. (6140-240=5900-6200=300mm) shall be corrected for FW TK-61
Difference between manual dip (6370mm) and level transmitter (6163mm) isabout
1.62 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 B
(-)33mm. (6370-240=6130-6163=(-)33mm) shall be corrected for FW TK-62
The 28 seconds opening / closing time for the MOV as show in the MOV FAT
1.63 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 report is different from the test carried out of which is only 18 sec for 60-MOV-001 C
& 002
There is no current and torque value recording in the FAT report as well during
1.64 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 B
the fucntional test at site for 60-MOV-001 & 002
1.65 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 The starting / running current for the jockey pumps have yet to verify B
Fault simulation for the engine driven pump while running is unable to carry out
1.67 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 B
because of absence of the Vendor
The “fault” display in the TAS for 2nd duty pump and standby pump shall be
1.68 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 rectified to change the color display to “Yellow” for FWP B
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
There is only “Local” and “Remote” conditions been considered in the logic
programming instead of “Local”, “Off” and “Remote”. CIWE shall refer to the
1.69 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 B
comments given in the control logic and FAT punch lists for FWP, MOV, Jockey
Pump etc.,
The TAS logic for “remote start” from CCR while the FW pump is on “Local mode”
1.70 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 shall be rectified. It shall include the “Permissive” signal from the field,i.e. ONLY B
when the selector switch is on “Remote”. This is to enhance operation safety
CIWE to check the series nos. of the MOV is consistent with the no. as shown in
1.71 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 C
the FAT report
Prevention of water trapping in the gland flange area shall be rectified for all the
1.72 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 C
MOVs
1.73 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 To provide all the “settings” as programmed in the MOVs C
The reference point on top of the tank in carry out the hand dip has not yet
1.74 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 27-Mar-2018 established for FW tank C
Labellings for lightings which are installed in the FWP/JP/Foam System area shall
1.75 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 C
be in metal plate instead of sticker
Cable tag shall be provided for lightings, Switches, SSO, LDP& EDP panel cables
1.76 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 C
which are installed in the FWP/JP/Foam System area
Method of lighting switch installation on the "I" beam was rejected by PMC hence
1.77 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 B
the method of installation shall be as discussed with CIWE's PM by PMC PM
End cap shall be provided for unistruct which are installed at the Fire pump PMC
1.78 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018
station area and unistruct egdges shall be burs free.
C
Verified 15-May-2018 suresh 16-May-2018 murugan
Provide service description to the breakers & components for 60-LDP-001 at fire
1.79 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 C
water station area
1.80 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 "Spare" breakers shall be identified by labelling of "Spare" in the 60-LDP-001 C
1.81 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 Name Plate (Specfication plate) shall be provided for 60-LDP-001 C
1.82 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 Breakers identification shall be as F1, F2, F3….. C
Lighting installation arrangement in the fire water station area is not as per the
1.83 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 C
JIMT-C02-E-16-20010 Rev 3.
1.84 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 61-LF01-005 emergency light is not working in the fire water stattion area B
Lighting test link shall be installed on the base plate as explained to charlie (ciwe)
1.85 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 at site for those installed installed at FWP area and wherever applicable in the C
terminal
Lightining tape and air terminal are shall be screwed on the fire station shelter
1.86 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 C Open
roof sheet instead of pating it with the kind of glue
lightning down conductor tape shall be fixed by means rigid support instead of
1.87 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 C
fixing with the clamp
Earth pits which are installed on the road shall be relocated to more suitable
1.88 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018 B
location at the Fire water pump station
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
Pipe cross over platform earthing shall be completed for which is installed in the
1.89 JIMT-C02-Y-001 Fire Water System Tank,Pump,FW ringmain,Spray system Murugan 20-Apr-2018
fire pump station
B ciwe verified 17-May-2018 suresh
3.00 UTILITY-1
3.01 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Booster Pump control panel body and its support earthing to be completed B ciwe verified 8-May-2018 suresh
3.02 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Pressure gauge dial size shall be minimum of 100mm B
3.03 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Water pressure tank drain line shall be extended to out of the skid C
3.04 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Provide drawing holder for Booster pump control panel instead of plastic file case C
3.05 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Provide specification plate for booster pump control panel C
3.06 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Confirm the IP rating with reference to certificate for booster pump control panel C
3.07 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Provide protection cover for control transformer in the booster pump panel C
Labels shall be in trofolite material instead of sticker for all the components in the
3.08 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 C
control panel
Confirm the operating temperature and humidity requirements for the control
3.09 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 C
board in the panel
3.10 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Provide shelter for the booster pump control panel C
3.11 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Manual valve tag plate shall be in stainless steel plate instead of trofolite Plate. C
3.12 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Pressure switch calibration reports shall be submitted C
3.13 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 Unbalance running current for the pump 1 shall be clarified B
3.14 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 High Starting current for pump 2 shall be clarified B
Provide pressure gauge for water pressure tank in order to monitor the pressure
3.15 JIMT-C02-Y-003 Utility-1 Potable Water Murugan 4-May-2018 B
in the vessel
4.00 UTILITY-2
EDG Room Lighting installation method is not as per the PMC accepted drawing
Main office building,control
(JIMT-C02-E-16-20013 Rev 3) which suppose to be wall mount type. CIWE to as-
5.42 JIMT-C02-Y-005 Main Building room,substation,warehouse & PMC 26-Mar-2018
built the layout as per the site condition and confirm the whether the lux level
C
workshop,changing room & Rest area
meets the requirement.
Guard House,FWP,FS,Loading Pump Suitable size BOLT shall be provided for the pump alignment instead of placing PMC
6.02 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
NUT to maintain the length on 20-PP-001 B Verified 8-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Product pump motor power shutdown shall also to cut off the control power in the
6.03 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
local control station B
Guard House,FWP,FS,Loading Pump Local control stations indication lights such as run / stop shall be more visible in
6.04 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
the day time B
Guard House,FWP,FS,Loading Pump Green / Yellow sleeveshall be provided for bare earthing conductor in the pump
6.05 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
station B
Earth pits which are installed on the road shall be relocated to more suitable
Guard House,FWP,FS,Loading Pump
6.06 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018 location and ensure the earth pit top is inline with the finished floor level instead B
of raised earth pit on the road to prevent tripping hazard.
Guard House,FWP,FS,Loading Pump Stainless Steel cable tag with PVC insulated stainless steel cable tie shall be
6.07 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
provided for all the electrical cable installation C ciwe verified 20-May-2018 suresh
Guard House,FWP,FS,Loading Pump Stub up conduit which are installed in the pump stattion shall be clamped with the PMC
6.08 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 29-Mar-2018
pump plinth C Verified 11-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Stub up conduit which are installed in the pump station shall be filled with the PMC
6.09 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 29-Mar-2018
foam C Verified 11-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Cables are shall be dressed neatly for detectors, lightings instaled in the pump
6.10 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 29-Mar-2018
station C ciwe verified 20-May-2018 suresh
Guard House,FWP,FS,Loading Pump Pump Station: SS Bolt nut shall be replaced with GI bolt nut since the LCS
6.11 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 29-Mar-2018
stanchion material is GI in order to prevent galvanic corrossion
C ciwe verified 20-May-2018 suresh
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
Guard House,FWP,FS,Loading Pump Pump Station: Wherever rust appears, touch up paint shall be done for the LCS PMC
6.12 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 29-Mar-2018
stanchion support C Verified 15-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Pump Station: Pump Skid earthing cable stub up conduit saddle clamp corrosion PMC
6.13 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 29-Mar-2018
shall be rectified C Verified 15-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Pump Station: Stub up conduit shall be filled with foam upon completion of PMC
6.15 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
cabling works C Verified 11-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Pump Station: Unused stub up conduits in the pump station area shall be PMC
6.16 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
removed and plug the opening C Verified 11-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Pump Station: Provide cable tray from the stub up conduit to the LCS in order to
6.17 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
dress the cable neatly C ciwe verified 11-May-2018 suresh
Guard House,FWP,FS,Loading Pump Pump Station: Improper cable gland gasket installation issue shall be rectified for
6.18 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
the main cable gland & dummy plug of 20-PP-011 B ciwe verified 20-May-2018 suresh
Guard House,FWP,FS,Loading Pump Pump Station: LCS Stanchion wobbling shall be prevented by providing bracing
6.19 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
support C ciwe verified 20-May-2018 suresh
Guard House,FWP,FS,Loading Pump Pump Station: Damaged earth cable copper strand and embeded earth cable PMC
6.21 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
issue shall be recified for 20-PP-007 and wherever applicable B Verified 11-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Pump Station: Two diagonal corners of each skid earth bossing's earthing shall
6.22 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
be completed for the pump skid
B
Guard House,FWP,FS,Loading Pump Pump Station: Suitable size bolt but shall be provided instead of placing "NUT" in PMC
6.23 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
between for pump alignment
B Verified
8-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Pump Station: The indicator light at the local control station is invisible. CIWE to
6.24 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018
rectify B
Pump Station: The “Power On” light at the local control station is “On” even when
Guard House,FWP,FS,Loading Pump
6.25 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 2-Apr-2018 the main breaker for the pump at the switch-room is “Off” and the local selector B
switch is at ‘Off’ position. CIWE shall check and rectify
Pump Station: The cable insulation test report as presented by CIWE that carried
Guard House,FWP,FS,Loading Pump
6.26 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018 out during the construction phase shall include “phase to phase” information B
instead of only “phase to earth”
Guard House,FWP,FS,Loading Pump Pump Station: Those earth pit installed on the road shall be relocated to more
6.28 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
suitable location
B
Guard House,FWP,FS,Loading Pump Pump Station: Stainless Steel cable tag with UPVC insulated cable tie shall be
6.29 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
provided for electrical & instrument cables
C
Guard House,FWP,FS,Loading Pump Pump Station: Wiring ferrule shall include the respective terminal number in the
6.33 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
LCS
B
Guard House,FWP,FS,Loading Pump Pump Station: Rotating direction shall be marked on the pump instead of marking
6.34 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
by pen
B
Guard House,FWP,FS,Loading Pump Pump Station: Those earthing cable has been coiled at the motor side shall be
6.39 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
dressed neatly in the tray or the excess cable shall be cut and do the termination
C
Guard House,FWP,FS,Loading Pump “Trip light” for pump 20-PP-01 (Mogas 95) that tested on 2nd Apr 2018 was “on”.
6.40 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
CIWE to check and verify
B
The manufacturer “Supermec” (Singapore) for the Local control station was not
Guard House,FWP,FS,Loading Pump
6.41 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018 submitted to PMC for acceptance. This is different from the original proposal, B
which is DTS France (ABB Supplier) submitted through the DMS
Guard House,FWP,FS,Loading Pump Ensure that no wires have been resting on the edge of gland entry in the other
6.43 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
motors terminal box except 20-PP-007 which was rectified on the spot by CIWE
B
Guard House,FWP,FS,Loading Pump Smoke detector cables shall be laid either in the tray / conduit instead of hanging PMC
6.44 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
between the trunking and the detector
C Verified
11-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Provide the trunking cover for trunking those installed above the ceiling instead PMC
6.48 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
of using cable tie around the trunking to dress the cable
C Verified
11-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Spare breakers to provided as per the SLD JIMT-C02-E-17-20002-014 Rev 3 for 75-
6.50 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
MDB-001 (@change room)
B
Guard House,FWP,FS,Loading Pump Changing room male toilet fan circuit is combined with the lighting circuit. CIWE
6.54 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
to rectify
B
Guard House,FWP,FS,Loading Pump Dispatch room lighting switch shall be installed as per the drawing (JIMT-C02-E-
6.56 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
16-20015-002 Rev 2) instead of installing on top of fire extinguisher box (S-01)
B
Guard House,FWP,FS,Loading Pump Labelling on the lighting fixture and SSO shall be either as per the drawing or as-
6.57 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
built the drawing as per site condition for disptach room
C
Guard House,FWP,FS,Loading Pump Installed light wattage is 2x14.5W which is contradict to the layout i.e 2x18W in
6.58 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
the dispatch room
C
CIWE to confirm whether the self-contained battery for emergency light shall be
Guard House,FWP,FS,Loading Pump
6.59 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018 one tube light or for two tube light. In the drawing it is specified as one lighting B
fitting which is contradict to the installation.
Guard House,FWP,FS,Loading Pump Labelling for panel components shall be provided as per the drawing for 74-EDP-
6.61 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
001 in the dispatch room. C
Guard House,FWP,FS,Loading Pump Quantity of spare breakers shall be as per the JIMT-C02-E-17-20002-013 Rev3 for
6.64 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 26-Mar-2018
74-EDP-001 B
Guard House,FWP,FS,Loading Pump Labelling for panel components shall be provided as per the drawing for 73-MDB-
6.66 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
001 in the dispatch room. C
Guard House,FWP,FS,Loading Pump Left top corner anchor bolt is started to bend which shall be rectified for 73-MDB-
6.72 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
001 B
Guard House,FWP,FS,Loading Pump Labelling for panel components shall be provided as per the drawing for 73-MDB-
6.74 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
001 in the dispatch room. C
Guard House,FWP,FS,Loading Pump Tag number shall be provided for all the SSO as specified in the layout for lighting PMC
6.76 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
& SSO in the workshop & Warehouse C Verified 12-May-2018 suresh 16-May-2018 murugan
Guard House,FWP,FS,Loading Pump Labelling for SSO & Lighings shall be either as per the drawing or CIWE to as-
6.77 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
built the drawing as per the site condition C
To provide proper base plate to fix the test link and lightning tape on the "I" beam
Guard House,FWP,FS,Loading Pump
6.81 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018 structure instead of fixing by the clip which is not rigid enough to hold the tape B
and test link
Guard House,FWP,FS,Loading Pump Lightning tape shall be fixed by means of screw on the pump station shelter sheet
6.82 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
instead of using kind of glue to stick the lighting tape. B
Guard House,FWP,FS,Loading Pump Crack found on the Ex.proof lighting fixture (for 20-LF02-002 @ above 20-PP-012).
6.83 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
CIWE to rectify it immediately since this fixture is located in the hazardous area. B
Guard House,FWP,FS,Loading Pump Ex.proof lighting cable glands are hand tighten and some not even tighten fully.
6.84 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
CIWE to tighten the cable gland with the recommonded torque by vendor. B ciwe verified 11-May-2018 suresh
Guard House,FWP,FS,Loading Pump Earth pits which are installed on the road shall be relocated to more suitable
6.86 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
location at the loading pump station
B
Guard House,FWP,FS,Loading Pump To provide tag plates for 20-S-01, 20-S-02 & 20-S-03 lighting switches in the
6.91 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
loading pump station area C
Guard House,FWP,FS,Loading Pump Receptacle 20-SSO-001 (Ex.proof Single phase SSO) at pump station has yet to
6.92 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
install B ciwe verified 20-May-2018 suresh
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
Guard House,FWP,FS,Loading Pump Receptacle 20-SSO-002 (Ex.proof Three phase SSO) at pump station has yet to
6.93 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
install B ciwe verified 20-May-2018 suresh
Guard House,FWP,FS,Loading Pump To provide tag plates with the test value &date for earth pits which are installed PMC
6.94 JIMT-C02-Y-006 Ancillary Buildings
Station,Truck Loading Bay Area
PMC 20-Apr-2018
around the loading pump station C Verified 8-May-2018 suresh 16-May-2018 murugan
7.00 CIVIL
8.00 SAFETY
9.00 SEWERAGE
ELECTRICAL
11.01 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Tag Plate to be provided for 73-CAM-01 Guard house camera B
11.02 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Tag Plate to be provided for 74-CAM-01 Dispatch Room camera B
Installed CCTV Pole is not suitable for the CCTV System and it is wobbling
11.03 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 even for the normal wind. And refer 4th Apr 2018 dated email from PMC for C
the same.
11.04 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Method of CCTV cable buried is unknown D
Each camera shall have its own individual DB junction box as shown in the
11.05 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 JIMT-C02-VD406E-DWG-E03 Rev 1 - CCTV Coverage Layout for JIMT C
instead of cable laying directly from the main junction box.
11.06 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 CCTV Pole earthing shall be completed B
Cable shall be glanded as per the vendor drawing shown the details to the
11.07 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 camera instead of just entering the cable into the camera where there is a B
possible for water & moisture ingress into the camera
Cat-6 cable bending radius shall be in complience with the cable vendor
11.08 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 C
recommondation for the CCTV
11.09 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Provide junction box for Camera as per the drawing B
11.10 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Provide sunshade / canopy for the cameras C
11.11 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Tag plate shall be provided for camera B
11.12 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Cable tag shall be provided for camera C
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
11.14 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Camera Base plate bolt nut shall be installed with the washer C
11.16 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Flexible conduit is insufficiant length to the cable in the CCTV System B
11.17 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Camera Base plate bolt nut shall be installed with the washer C
00-CAM-14 not yet install at the bin point side gate area hence camera
11.18 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 B ciwe verified 20-May-2018 suresh
installation location to be confirmed by CIWE
30-CAM-01 to 04 (@ the truck loading bay side bund wall) - These four
11.19 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Camera have been installed on the bundwall hence confirm the suitability B
of camera with reference to the area classification
Wherever the cable crossing the bundwall to the CCTV System shall be
11.21 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 C
protected by means of metal conduit or tray.
Plastic cap shall be replaced with appropriate classification metal plug for PMC
11.23 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 B 15-May-2018 suresh 16-May-2018 murugan
spare cable entry in the CCTV System (20-CAM-01 & 02 @ Pump Station) Verified
Sharp edges of cable tray / condutis to the CCTV System shall be PMC
11.24 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 C 15-May-2018 suresh 16-May-2018 murugan
protected with rubber grommet or rubber bush. Verified
CCTV cable installed in the fire alarm system trunking shall be separated PMC
11.25 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 C 15-May-2018 suresh 16-May-2018 murugan
and provide individual tray or conduit for 78-CAM-01 & 02 CCTV Cables Verified
72-CAM-04 CCTV Camera not installed yet in the Equipment room of CCR
11.26 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 B
as per the layout.
11.27 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Tag Plate shall be provided for the Junction Box B
11.28 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Sunshade / Canopy shall be provided for the Junction Box C
PMC
11.29 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Cable tag shall be provided for Junction Box in & outgoing cables C Verified
15-May-2018 suresh 16-May-2018 murugan
PMC
11.30 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Rubber grommet shall be provided at the cable tray sharp edges C Verified
15-May-2018 suresh 16-May-2018 murugan
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
End cap shall be provided for unistruct which are installed for CCTV
11.31 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 C
System and unistruct egdges shall be burs free.
11.32 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Cable tray cover shall be provided C
Cables shall be dressed neatly with stainless steel cable tie instead of PVC
11.33 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 C
tie
11.34 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Cable tray earth bonding shall be completed at all the splicing joints C ciwe verified 20-May-2018 suresh
11.35 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Body earthing shall be completed for CCTV Junction box B
Found (rain ??) water seepage into the junction box and its strain can be
11.36 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 B ciwe verified 20-May-2018 suresh
seen. CIWE to rectify
11.37 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Labelling shall be provided for inside cables in the junction box C ciwe verified 20-May-2018 suresh
11.38 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Ethernet POE Switch not installed properly and found shacking with it C
IP Rating shall be confirmed for the Junction box (JB certified for water
11.40 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 B
proof)
11.41 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 Junction box specification plate shall be provided B
Few cables are glanded outside of the gland plate in the junction box thus
11.42 JIMT-C02-Y-011 ELECTRICAL CCTV System PMC 27-Apr-2018 B
to confirm the certificate validity for the junction box
12.00 INSTRUMENT
IINSTRUMENT
13.01
14.01
ADS for DO Panel, pump A/B sequence running and fault lights was not shown
15.01 JIMT-C02-Y-0115 Additive System Lee 8-May-2018 B
ADS for JF deviating from P&ID
ADS for DO
15.02 JIMT-C02-Y-0115 Additive System
ADS for JF
Lee 8-May-2018 Cable entry routing tot the panel shall be checked C
ADS for DO
15.03 JIMT-C02-Y-0115 Additive System
ADS for JF
Lee 8-May-2018
Instrument termination work (FT,FV,FIQ) for all the additive injection at truck B
loading bay has yet to complete
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
ADS for DO
15.04 JIMT-C02-Y-0115 Additive System
ADS for JF
Lee 8-May-2018 Panel tag number has not been installed C
General,Mogas92 import system,Mogas92 Space shall be maintain between the conduits by providing proper supports
PROCESS (1) Mogas 92
16.05 JIMT-C02-Y-016
system
storage system, PMC 11-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C ciwe verified 20-May-2018 suresh
Mogas 92 export system 031~032)
General,Mogas92 import system,Mogas92
PROCESS (1) Mogas 92
16.06 JIMT-C02-Y-016
system
storage system, PMC 11-Apr-2018 Body earthing works to be completed for MOVs 10-MOV-031~032 B
Mogas 92 export system
General,Mogas92 import system,Mogas92
PROCESS (1) Mogas 92
16.07 JIMT-C02-Y-016
system
storage system, PMC 11-Apr-2018 Greasing to applied for stem of MOVs 10-MOV-031~032 B ciwe verified 20-May-2018 suresh
Mogas 92 export system
General,Mogas92 import system,Mogas92 Extend the conduit upto the cable gland by maintaining 300mm clearance
PROCESS (1) Mogas 92
16.08 JIMT-C02-Y-016
system
storage system, PMC 11-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C
Mogas 92 export system cables for (10-MOV-031~032)
General,Mogas92 import system,Mogas92 Stroke time for Opening and closing for the MOVs have recorded. CIWE is
PROCESS (1) Mogas 92
16.12 JIMT-C02-Y-016
system
storage system, PMC 11-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
Mogas 92 export system 031~032)
General,Mogas92 import system,Mogas92 Space shall be maintain between the conduits by providing proper supports
PROCESS (1) Mogas 92
16.36 JIMT-C02-Y-016
system
storage system, 11-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C ciwe verified 20-May-2018 suresh
Mogas 92 export system 004~006)
General,Mogas92 import system,Mogas92
PROCESS (1) Mogas 92
16.37 JIMT-C02-Y-016
system
storage system, 11-Apr-2018 Stainless Steel cable tie shall be provided for the cables(10-MOV-004~006) C
Mogas 92 export system
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
General,Mogas92 import system,Mogas92 Extend the conduit upto the cable gland by maintaining 300mm clearance
PROCESS (1) Mogas 92
16.40 JIMT-C02-Y-016
system
storage system, 11-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C Open
Mogas 92 export system cables for (10-MOV-004~006)
General,Mogas92 import system,Mogas92 Stroke time for Opening and closing for the MOVs have recorded. CIWE is
PROCESS (1) Mogas 92
16.44 JIMT-C02-Y-016
system
storage system, 11-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
Mogas 92 export system 004~006)
General,Mogas92 import system,Mogas92
PROCESS (1) Mogas 92 High-high level to shutdown the inlet MOV from Tank level gauge shall be
16.45 JIMT-C02-Y-016 storage system, 11-Apr-2018 B
system
Mogas 92 export system tested (10-MOV-004~006)
As per the discussion at site with CIWE Pre-com manager Mr.Ding and
General,Mogas92 import system,Mogas92
PROCESS (1) Mogas 92 SPC Operation Team (Desmond & Fahran) Acutuator orientation shall be
16.47 JIMT-C02-Y-016 storage system, 11-Apr-2018 B ciwe verified 20-May-2018 suresh
system
Mogas 92 export system changed to the MOVs so that the handwheel operation can be done from
the platform easily for 10-MOV-004~006
Mogas 95 import system,Mogas 95 storage Extend the conduit upto the cable gland by maintaining 300mm clearance
PROCESS (2) Mogas 95
17.08 JIMT-C02-Y-017
system
system, PMC 10-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C Open
Mogas 95 Export system cables for (10-MOV-011~012)
Mogas 95 import system,Mogas 95 storage Stroke time for Opening and closing for the MOVs have recorded. CIWE is
PROCESS (2) Mogas 95
17.11 JIMT-C02-Y-017
system
system, PMC 10-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
Mogas 95 Export system 011~012)
Mogas 95 import system,Mogas 95 storage Space shall be maintain between the conduits by providing proper supports
PROCESS (2) Mogas 95
17.19 JIMT-C02-Y-017
system
system, PMC 11-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C ciwe verified 20-May-2018 suresh
Mogas 95 Export system 021~022)
Mogas 95 import system,Mogas 95 storage Extend the conduit upto the cable gland by maintaining 300mm clearance
PROCESS (2) Mogas 95
17.23 JIMT-C02-Y-017
system
system, PMC 11-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C
Mogas 95 Export system cables for (10-MOV-021~022)
Mogas 95 import system,Mogas 95 storage Stroke time for Opening and closing for the MOVs have recorded. CIWE is
PROCESS (2) Mogas 95
17.27 JIMT-C02-Y-017
system
system, PMC 11-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
Mogas 95 Export system 021~022)
Mogas 95 import system,Mogas 95 storage
PROCESS (2) Mogas 95 High-high level to shutdown the inlet MOV from Tank level gauge shall be
17.28 JIMT-C02-Y-017 system, PMC 11-Apr-2018 B
system
Mogas 95 Export system tested (10-MOV-021~022)
Mogas 95 import system,Mogas 95 storage
PROCESS (2) Mogas 95 Overriding feature when liquid level is at high-high level shall be tested (10-
17.29 JIMT-C02-Y-017 system, PMC 11-Apr-2018 B
system
Mogas 95 Export system MOV-021~022)
Mogas 98 import system,Mogas 98 storage Space shall be maintain between the conduits by providing proper supports
PROCESS (3) Mogas 98
18.06 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C ciwe verified 20-May-2018 suresh
Mogas 98 Export system 041~042)
Mogas 98 import system,Mogas 98 storage
PROCESS (3) Mogas 98
18.07 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 Body earthing works to be completed for MOVs 10-MOV-041~042 B
Mogas 98 Export system
Mogas 98 import system,Mogas 98 storage
PROCESS (3) Mogas 98
18.08 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 Greasing to applied for stem of MOVs 10-MOV-041~042 B ciwe verified 20-May-2018 suresh
Mogas 98 Export system
Mogas 98 import system,Mogas 98 storage Extend the conduit upto the cable gland by maintaining 300mm clearance
PROCESS (3) Mogas 98
18.09 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C Open
Mogas 98 Export system cables for (10-MOV-041~042)
Mogas 98 import system,Mogas 98 storage Stroke time for Opening and closing for the MOVs have recorded. CIWE is
PROCESS (3) Mogas 98
18.13 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
Mogas 98 Export system 041~042)
Mogas 98 import system,Mogas 98 storage Space shall be maintain between the conduits by providing proper supports
PROCESS (3) Mogas 98
18.21 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C ciwe verified 20-May-2018 suresh
Mogas 98 Export system 051~052)
Mogas 98 import system,Mogas 98 storage
PROCESS (3) Mogas 98
18.22 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 Stainless Steel cable tie shall be provided for the cables(10-MOV-051~052) C
Mogas 98 Export system
Mogas 98 import system,Mogas 98 storage Extend the conduit upto the cable gland by maintaining 300mm clearance
PROCESS (3) Mogas 98
18.25 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C
Mogas 98 Export system cables for (10-MOV-051~052)
Mogas 98 import system,Mogas 98 storage Stroke time for Opening and closing for the MOVs have recorded. CIWE is
PROCESS (3) Mogas 98
18.29 JIMT-C02-Y-018
system
system, PMC 13-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
Mogas 98 Export system 051~052)
General,diesel import system,diesel storage Space shall be maintain between the conduits by providing proper supports
PROCESS (5) DIESEL
20.06 JIMT-C02-Y-020
SYSTEM
system, PMC 12-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C
diesel export system 111~112)
General,diesel import system,diesel storage Extend the conduit upto the cable gland by maintaining 300mm clearance
PROCESS (5) DIESEL
20.09 JIMT-C02-Y-020
SYSTEM
system, PMC 12-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C
diesel export system cables for (10-MOV-111~112)
General,diesel import system,diesel storage Stroke time for Opening and closing for the MOVs have recorded. CIWE is
PROCESS (5) DIESEL
20.13 JIMT-C02-Y-020
SYSTEM
system, PMC 12-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
diesel export system 111~112)
DOCUMENT NO DATE UPDATED
PRECOMMISSIONING PUNCH LIST
JIMT-C02-Q-13-20031-PC-EI001 13-Apr-18
REVISION : 0 PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works
Item Test Pack System Sub system Initiator Date CAT Status CIWE PMC SPC
DISCIPLINE : ELECTRICAL & INSTRUMENTATION Date Sign Date Sign Date Sign
General,Jet Fuel Import System,Jet Fuel Space shall be maintain between the conduits by providing proper supports
21.05 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C ciwe verified 20-May-2018 suresh
jet fuel export system 061~062)
General,Jet Fuel Import System,Jet Fuel Extend the conduit upto the cable gland by maintaining 300mm clearance
21.08 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C
jet fuel export system cables for (10-MOV-061~062)
General,Jet Fuel Import System,Jet Fuel Stroke time for Opening and closing for the MOVs have recorded. CIWE is
21.12 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
jet fuel export system 061~062)
General,Jet Fuel Import System,Jet Fuel Space shall be maintain between the conduits by providing proper supports
21.19 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C ciwe verified 20-May-2018 suresh
jet fuel export system 071~072)
General,Jet Fuel Import System,Jet Fuel Extend the conduit upto the cable gland by maintaining 300mm clearance
21.22 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C Open
jet fuel export system cables for (10-MOV-071~072)
General,Jet Fuel Import System,Jet Fuel Stroke time for Opening and closing for the MOVs have recorded. CIWE is
21.26 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
jet fuel export system 071~072)
As per the discussion at site with CIWE Pre-com manager Mr.Ding and
General,Jet Fuel Import System,Jet Fuel
SPC Operation Team (Desmond & Fahran) Acutuator orientation shall be
21.29 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 B ciwe verified 20-May-2018 suresh
jet fuel export system changed to the MOVs so that the handwheel operation can be done from
the platform easily for 10-MOV-071~072
General,Jet Fuel Import System,Jet Fuel Space shall be maintain between the conduits by providing proper supports
21.36 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 to the conduit instead of tieing together with the cable tie (10-MOV- C ciwe verified 20-May-2018 suresh
jet fuel export system 131~132)
General,Jet Fuel Import System,Jet Fuel Extend the conduit upto the cable gland by maintaining 300mm clearance
21.40 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 between the gland & tray/conduit support in order to prevent stress on the C Open
jet fuel export system cables for (10-MOV-131~132)
General,Jet Fuel Import System,Jet Fuel Stroke time for Opening and closing for the MOVs have recorded. CIWE is
21.44 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 required to clarify this is compliance with design requirements (10-MOV- C
jet fuel export system 131~132)
As per the discussion at site with CIWE Pre-com manager Mr.Ding and
General,Jet Fuel Import System,Jet Fuel
SPC Operation Team (Desmond & Fahran) Acutuator orientation shall be
21.48 JIMT-C02-Y-021 PROCESS (6) JET FUEL Storage system, PMC 13-Apr-2018 B ciwe verified 20-May-2018 suresh
jet fuel export system changed to the MOVs so that the handwheel operation can be done from
the platform easily for 10-MOV-131~132
Closed by CIWE and Verified by PMC Closed by CIWE, Pending on Verification of PMC
CATOGERY
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, malfunction and missing document which must be completed prior to the start of commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but must be cleared before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared before Final Performance Test.
DOCUMENT NO
PRECOMMISSI
JIMT-C02-Q-13-20031-PC-HSE001
REVISION : 0 PROJECT : JURONG ISL
Item Test Pack System Initiator Date
Sub system
Tank,Pump,FW
1.02 JIMT-C02-Y-001 Fire Water Lee/Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.03 JIMT-C02-Y-001 Fire Water Lee/Mao 12-Mar-2018
Ringmain,Spray system
Tank,Pump,FW
1.07 JIMT-C02-Y-001 Fire Water Lee/Mao 12-Mar-2018
Ringmain,Spray system
10.00
10.01 JIMT-C02-Y-010
11.00
11.01 JIMT-C02-Y-011
12.00
12.01
13.00
13.01
DOCUMENT NO
PRECOMMISSI
JIMT-C02-Q-13-20031-PC-HSE001
REVISION : 0 PROJECT : JURONG ISL
Item Test Pack System Initiator Date
Sub system
14.00
14.01
15.00
15.01
16.00
16.01
17.00
17.01
18.00
18.01
19.00
19.01
DOCUMENT NO
PRECOMMISSI
JIMT-C02-Q-13-20031-PC-HSE001
REVISION : 0 PROJECT : JURONG ISL
Item Test Pack System Initiator Date
Sub system
20.00
20.01
21.00
21.01
22.00
22.01
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activities. For “A” pun
be completed prior to the start of commissioning works.
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion Certification (MC
before signing-off each subsystem MCC.
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that must be cleared b
DATE UPDATED
PRECOMMISSIONING PUNCH LIST
12-May-2018
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works CAT Status
CIWE PMC
CIWE
Fire pump controller must be lock B 6-Apr-2018 Durai
verified
CIWE
Provide SWL working platform signages C 6-Apr-2018 Durai
verified
CIWE
Fuel tank metal platform need chain & kicking plate C 6-Apr-2018 Durai
verified
WASTE WATER
ELECTRICAL
INSTRUMENT
MECHANICAL(EOT CRANE)
DATE UPDATED
PRECOMMISSIONING PUNCH LIST
12-May-2018
PROJECT : JURONG ISLAND MARKETING TERMINAL Page 1 of 1
PUNCH LIST COMPLETION
Description of Remedial Works CAT Status
CIWE PMC
MECHANICAL(VAPOR RECOVERY)
ADDITIVE SYSTEM
CATOGERY
oning activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, malfunction and missing docu
Completion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable commissioning works but mus
1.00
2.00
3.01 JIMT-C02-Y-003
4.00
5.00
5.01 JIMT-C02-Y-005
6.00
6.01 JIMT-C02-Y-006
7.00
7.01 JIMT-C02-Y-007
8.00
8.01 JIMT-C02-Y-008
9.00
9.01 JIMT-C02-Y-009
10.00
10.01 JIMT-C02-Y-010
11.00
11.01 JIMT-C02-Y-011
12.00
12.01
13.00
13.01
14.00
14.01
15.00
15.01
16.00
16.01
17.00
17.01
18.00
18.01
19.00
19.01
20.00
20.01
21.00
22.00
22.01
Cat "A" - Punch items must be cleared before electrical power energized pre-commissioning activit
Cat "B" - Punch items must be cleared before signing-off each subsystem Mechanical Completion
Cat "C" - Punch items must be cleared before initial products filling.
Cat "D" - Punch items, as per mutually agreed by main contractor, consultant and client, but that m
PRECOMMISSIONING PUNCH LIST
Date
CATOGERY
commissioning activities. For “A” punch items, outstanding items related to damaged, defective or missing
echanical Completion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the
t and client, but that must be cleared before Final Performance Test.
PRECOMMISSIONING PUNCH LIST
Foam System
UTILITY-1
UTILITY-2
MAIN BUILDING
ANCILLARY BUILDINGS
CIVIL
SAFETY
SEWERAGE
WASTE WATER
ELECTRICAL
INSTRUMENT
MECHANICAL(EOT CRANE)
MECHANICAL(VAPOR RECOVERY)
ADDITIVE SYSTEM
PROCESS ( 7) SRC
CATOGERY
g activities. For “A” punch items, outstanding items related to damaged, defective or missing equipment, ma
pletion Certification (MCC). For “B” punch items, outstanding items will not delay or affect the applicable com