S0263-7863 (96)00035-X
Akintola S Akintoye*
Department of Building and Surveying, Glasgow Caledonian University, Glasgow, G40BA, UK
Malcolm J MacLeod
1RISC Technical Services, International Loss Adjusters, 35 Seething Lane, London, EC3N 4AH, UK
The paper describes, on the basis of a questionnaire survey of general contractors and project
management practices, the construction industry's perception of risk associated with its activities
and the extent to which the industry uses risk analysis and management techniques. It concludes
that risk management is essential to construction activities in minimizing losses and enhancing
profitability. Construction risk is generally perceived as events that influence project objectives
of cost, time and quality. Risk analysis and management in construction depend mainly on
intuition, judgement and experience. Formal risk analysis and management techniques are
rarely used due to a lack of knowledge and to doubts on the suitability of these techniques for
construction industry activities. Copyright © 1996 Elsevier Science Ltd and IPMA.
Keywords: Risk perception, risk analysis, risk management, project managers, contractors
Organizations from many industries have recognized the regarding the industry response, and in particular the
increasing importance of risk management, and many techniques employed for risk analysis and management.
companies have established risk management departments Simister '° investigated the usage and benefit of project risk
to control the risks they are, or might be, exposed to. The analysis and management in 1992, based on a questionnaire
construction industry and its clients are widely associated survey of 37 members of the UK Association of Project
with a high degree of risk due to the nature of construction Managers. Simister's l° survey was comprised of respon-
business activities, processes, environment and organization. dents classified into five work-related groups: defence
Risk in construction has been the object of attention industry (36%), management consultancy (36%), systems-
because of time and cost over-runs associated with con- based information technology (12 %), telecommunications
struction projects. Although, Porter', Healey2 and Perry (12%) and engineering contracting (4%). The objective
and Hayes3 have expressed risk as an exposure to economic of the current study was to obtain feedback from con-
loss or gain arising from involvement in the construction struction contractors and construction project management
process; Mason 4 and Moavenzadeh5 have regarded this as practitioners on the following aspects of risk analysis and
an exposure to loss only. Bufaied 6 describes risk in relation management:
to construction as a variable in the process of a construction
project whose variation results in uncertainty as to the final • Risk perception by the construction industry
cost, duration and quality of the project. • Organizational risk management
It is generally recognized that those within the con- • Risk premium in construction projects
struction industry are continually faced with a variety of • Management of risk
situations involving many unknown, unexpected, frequently • Current usage of risk management techniques.
undesirable and often unpredictable factors 7. Ashley8 and
Kangari and Riggs9 have all agreed that these situations The research survey
are not limited to the construction industry; it is recognized
that risk is built into any commercial organization's profit The need to manage risks in construction is relevant to
structure and is a basic feature of a free enterprise system. all professionals and groups (client groups, design team,
Insofar as risk analysis and management is important to project management team, contractors, etc.) in the con-
the activities of the construction industry, little is known struction industry which are concerned with cost, time and
quality. The current research concentrated on two categories
of respondents: contractors and project management prac-
*Author for correspondence. tices. The sample for the survey was a total of 100 top firms
PM 15/I--I]
31
Risk analysis and management in construction: A S Akintoye and M J MacLeod
in the UK construction industry comprising 70 general catalogue determines the level of exposure to risk.
contractors and 30 project management practices ~. The William ~5on the other hand has categorized details of each
general contractors were selected randomly from a list of risk factor into event, impact, actions and contractual; and
100 contractors published in the 'Contractor File 1992 't2. used a process of project risk register to identify risks and
The 30 project management practices were those advertising to initiate the analyses for project risk management•
in Building during the period June 1994 to August 1994. Risk perception is generally believed to be influenced
Subject to limitation of the sampling, the firms surveyed by people's belief, attitudes, judgement and feelings. The
represent a large proportion of the UK construction industry report of The Royal Society claims that risk perception
• 16 "
population. The total turnover of the firms surveyed (£7000 cannot be reduced to a single subjective correlate of a
million) represents 20 % of UK contractors' output for 1994 particular mathematical model, such as the product of prob-
and had 50,000 employees. All the project management abilities and consequences because this imposes unduly
organizations are bona fide practices providing a wide restrictive assumptions about what is an essentially human
range of project management services. and social phenomenon• Choffray and Johnson ~7 and
The overall response to the survey comprised of 30 Ritchie and Marshall ~8 have identified factors influencing
general contractors (CTR) and 13 project management the formation of risk perception including educational
practices (PM) representing a 43% response rate. The background, practical experience, an individual's cognitive
response rate resulted from an initial mailing addressed to characteristics, the availability of information, peer group
the managing director of each firm and a reminder letter, influence, etc.
after two weeks, to those organizations that had not While it is generally recognized that the foregoing factors
responded to the original request. The response rate is may affect the respondents' perception of risk, they are not
typical of a construction industry questionnaire survey directly investigated in this study. However, in order to
and cannot be regarded as biased considering Moser and obtain the view of the industry on risk in construction, the
Kalton's j3 assertion that the results of a postal survey could respondents were asked to describe risk in construction
be considered as biased and of little value if the return rate projects.
was lower than 30-40%. The general contractors offered diversified opinions,
The questionnaires were completed by top management quoted as follows:
in the organizations (mainly directors and partners) and
almost all of them (more than 90%) had over 10 years of • "Factors which can adversely affect the successful com-
construction experience. The respondents thus have requisite pletion of a project in terms of budget and schedule,
professional and academic qualifications. On the basis of which in themselves are not always identifiable" (Project
position, work experience and educational and professional Control Manager, Turnover = £100 million, Employ-
background, it can be inferred that the respondents have ment = 2000).
adequate knowledge of the activities associated with • "Construction is a risk business--the main contractor
construction and associated risk. accepts all risks relevant to a contract in terms of cost,
Twenty-two per cent of the firms surveyed (all the 22 % time and quality of performance" (Director, Turnover =
are project management practices) have turnover less than £130 million, Employment = 900).
£10 million. Forty-nine per cent have turnover between • " T h e likelihood of physical, contractual or economic
£10 million and £100 million; 29% have turnover over conditions becoming more difficult than those allowed
£100 million. From this distribution of the responding for in the price" (Managing Director, Turnover = £80
firms, it can be concluded that the survey covers a spectrum million, Employment = 600).
of small, medium and large firms in the UK construction • " T h e opportunity to make a profit on a contract whilst
industry. satisfying the client quality, delivery and contract price
Twenty per cent of the contractors, and 8 % of the project requirements" (Deputy Managing Director, Turnover =
management practices, have designated risk managers• £100 million, Employment = 500 +).
This suggests that risk control is carried out as part of • "Loss of money, loss of reputation, and a chance of an
normal or regular activities of the firms rather than being accident occurring to persons on property" (Director,
designated, given that all respondents claimed to carry Turnover = £25 million, Employment = 200).
out risk analysis and management of the construction • "The likelihood of unplanned events occurring" (Director
business, process and activities in their organizations. Most of Business Development, Turnover = £45 million,
of the respondents (CTR = 67% and PM = 77%) did not Employment = 68).
have any formal risk management training. They claimed • "The degree of certainty that the financial objectives for
to be involved in risk management and the analysis of their each particular project will be achieved and the extent to
perceptions of risks involved in construction does in fact which risk factors can be quantified at bid stage and
suggest an awareness of what is involved in control of risk monitored closely" (Group Director, Turnover = £250
and its consequences. million, Employment = 2000).
• "Tender or on-site performance mistakes leading to
quality under performance, cost over-run and an impact
Risk perception on all of these from a variety of unforeseen circum-
Risk catalogue has been described as a combination of stances" (Finance Director, Turnover = £200 million,
threat and vulnerability which occurs when the two conditions Employment = 2000).
overlap ~4. A threat is something which has an adverse • " T h e probability of a construction activity costing more
effect on the activities of an organization. A vulnerability than allowed for in the tender" (Contract Manager,
is characterized by a physical system which, while being Turnover = £20 million, Employment = 60).
independent of any specific threat, allows a threat to be • "Cumulating liabilities that arise from a particular set of
exploited. The impact of risk from threat catalogue and contract terms for a construction project" (Managing
the frequency of occurrence of risk from the vulnerability Director, Turnover = £170 million, Employment = 800).
32
Risk analysis and management in construction: A S Akintoye and M J MacLeod
• " I n safety terms, as any sequence of events which are • To minimize loss by risk management in an industry
likely to result in the possibility of injury" (Chief where even normal contracting causes difficulties.
Executive, Turnover = £35 million, Employment = 170). • To identify project risks and quantify the potential cost
• "Potential overspending against tender proposals" of each risk and plan for it; or work around it to alleviate
(Managing Director, Turnover = £50 million, Employ- the risk.
ment = 600). • To determine if the firm is making an adequate profit on
• "Evaluating the complexity associated with contracts, a particular project. The higher the risk the greater must
programming period and resource scheduling of labour be the potential reward.
and plant at tender stage" (Group Managing Director, • To avoid unsatisfactory projects and to enhance margins.
Turnover = £80 million, Employment = 480). • To control factors which will deter completion of pro-
• "Financial--due to vague information, tendering pro- jects within budget and schedule.
cedure. Legal--due to action of others. Safety problems-- • To keep insurance premiums to acceptable levels, and
due to the nature of construction business" (Group reduce losses.
Marketing Director, Turnover = £130 million, Employ-
ment = 600). Project management practices and contractors have dif-
ferent reasons for using risk management. The former seek:
The views expressed by the contractors are generally risk
• To limit professional indemnity claims.
elements associated with project objectives 7. In summary,
• To provide an understanding and control risks in the
the contractors perceived risk as the likelihood of unfore-
projects.
seen factors occurring, which could adversely affect the
• To allow appropriate measures to be taken, to control
successful completion of the project in terms of cost, time
the effects of risks and provide cost contingency for
and quality. One contractor, however, saw risk as an
clients.
opportunity to make profit and not something that will
• To protect the firm's credibility and reputation--not of
always have an adverse effect.
major importance in the past, but expected to become
The risk perception of construction by the project manage-
significant. Failure to manage risks on our clients'
ment practices were not markedly different from the general
projects carries some commercial risk as well as loss of
contractors. Some of their comments are quoted as follows:
credibility and reputation.
• " T h e activities/ocurrences which traditionally are likely
The contractors generally agreed that the industry within
(or to some degree will happen) to happen, and to have
which they work is associated with high risk and saw risk
an adverse effect upon programme and/or cost" (Planning
management as being essential to their overall construction
Manager, Turnover = £5 million, Employment = 35).
activities in order to minimize business losses. By means of
• "Risk is uncertainty with regard to events and their
analysis and control of the risks that they are exposed to,
effects which affects the project outcome in terms of
they can maximize their business profitability. Although all
cost, time, quality and any other relevant performance
respondents perceived risk in terms of project objectives
criteria" (Director, Turnover = £10 million, Employ-
of cost, time and quality, the contractors responses to the
ment = 100).
need for risk management showed most emphasis on risks
• "Something to be avoided or transferred" (Regional
associated with cost, understandably so given that this
Director, Turnover = £6 million, Employment = 70).
affects profitability.
• "Comes in varying forms--most projects are high
Although the project management practices are concerned
risk. People forget that construction is a people's busi-
with risk management in relation to the client's objectives,
ness" (Commercial Director, Turnover = £3.5 million,
the need to manage risk is important to them because of the
Employment = 70).
need to limit professional indemnity costs and to protect the
The project management practices, generally, recognized organization's reputation.
that the consequences of risks directly affect the client and
his objectives rather than their practices. This is not sur- Risk premium in construction
prising as project management practices provide consultancy
services on a fee basis and do not commit large volumes Perry and Hayes 3 and Mustafa and A1-Bahar '9 have iden-
of resources to construction projects in the manner of tified some risks sources central to the construction acti-
contractors. vities. These are physical, environmental, design, logistics,
financial, legal, political, construction and operation risks.
As these risk sources influence projects performance in
Organizational risk management terms of time, cost and quality, it is not uncommon for
The respondents were asked to indicate why risk manage- these to be assessed individually and a premium placed on
ment (identification, analysis, assessment and control) is each of them. A risk premium strategy which is often used
important to their organizations' activities. The following in construction projects is contingency allowance. Dey
et al. 2° produced a catalogue of risks and contingency
are a representation of the contractors responses:
allowance in petrochemical construction project. The
• To analyse and control risk as the key to profit, as con- study by Dey et al. 2° described a systematic procedure for
struction is a risky business. analysing project risk from the construction perspective.
• To ensure that we are right more often than wrong, as yeo2, and Dey et al. 2° described the contingency allowance
right management of risk in construction determines the for a high risk project as a combination of management
ability to make profit. contingency and technical contingency; both of which are
• To assess and ascertain project viability because con- required to achieve a project objective(s).
struction development is a business with a high number The premium placed on each of the sources of risk may
of variables. depend on the risk exposure faced by individual firms from
33
Risk analysis and management in construction." A S Akintoye and M J MacLeod
4 3 2 1 0 4 3 2 1 0
Extent of risk premium: 4 = high; 3 = fairly high; 2 = low; 1 = fairly low; 0 = indifferent.
each of the sources, the likelihood of occurrence, the Construction risks, or job site related risks such as avail-
experience of the firm in dealing with the particular type of ability and productivity of labour, soil and site conditions,
risk, the attitude of the firm to risk, the extent of impact material shortages and quality, site safety, etc. are impor-
posed by the sources, etc. Some of the risk sources are tant to the contractors unlike the project management
more important to the construction industry than the others practices because these risks are related to construction
and this is recognized by the different premium put on process on site. The attitude of project management prac-
different risks associated with construction. tices to risk is expected to change in view of the current
The respondents were asked to indicate the extent of Construction (Design and Management) Regulations, 1994
premium their organizations applied to each risk source. (CONDAM) on health and safety, that demands that the
The responses are summarized in Table 1. The organization employers' agents responsible for design and supervision
risk premium index, representing the overall respondents' should provide information on details of risks and avoid
views of their organizations' premium on the sources of foreseeable risks to the health and safety of any person at
risk, is shown in Table 2. work carrying out the construction work, etc. 25.
The tables show that both the contractors and the project
managers are quite similar in the order of importance
attached to the sources of risk. The financial and contractual
Management of risk
risks are most important. These are recognized as having Methods of risk allocation take any one or combination
most adverse consequences on the successful completion of risk retention, risk transfer, risk reduction, and risk
of construction project. Building contracts deal with the avoidance 26-29.
relationships between parties in the contract and the alloca- Risk retention, according to Williams and Heims 3°,
tion of risks. Carr 22 and Ashley 23 advocate balancing of becomes the only option where risk prevention or transfer
risk allocation within construction project by the two major is impossible, avoidance is undesirable, possible financial
parties to the contract (building owner and the contractor) loss is small, probability of occurrence is negligible and
but, building contracts and procurement methods seldom transfer is uneconomic. Risk avoidance in construction is
achieved this. Contractual risks are those associated with generally recognized to be impractical as it may lead to
flaws in contract documents, inappropriate documents, or projects not going ahead or a contractor submitting an ex-
improper contractual relationships. The risk consequences cessively high bid for a project. Risk reduction techniques
or implications of contractual risks include claims and as a result, in terms of potential impact or probability of
disputes, disruption of work, stoppages of work, lack of co- occurrence, include the use of alternative contract strategies,
ordination, delays, and inflated c o s t s 6'24. Financial risk to different methods of construction, project redesign, more
contractors includes whether the building owner has enough detailed and further in-depth site investigations, etc. 3~.
money to complete the project, financial failure of the Risk transfer is described by Perry and Hayes3 who identify
building owner or subcontractors, availability of money to four methods used in construction projects and contracts
the contractor in a suitable manner and time to enable the involving the relationships between client, contractor, sub-
contractor to progress with the work, etc. Financial risk contractor, design team, insurer and surety.
influences the cash flow of construction contractors; it is Table 3 shows the views of the respondents on how their
hardly surprising therefore that this source of risk is highly firms tend to allocate risk involved in construction project.
important for them. The standard deviations show a wide variation on the
34
Risk analysis and management in construction: A S Akintoye and M J MacLeod
Table 3 Respondents' perceptions of how construction projects' risks are allocated by their firms (as a percentage)
Strategies for risk allocation Contractors Project management practices All firms
(risk response)
Mean (%) S.D. Mean (%) S.D. Mean (%) S.D.
Retention 24 23 27 23 25 23
Reduction 21 13 17 14 19 14
Transfer 31 21 39 38 34 26
Avoidance 24 20 17 22 22 21
Total 100 100 100
allocation of risks amongst the firms, suggesting that firms life of a project and it has capacity to evaluate the con-
within the construction industry tend to treat risk allocation sequences of factors such as delay and inflation, and changes
differently. However, the firms show more tendency to to the market or to production r a t e s 34. Such computer-based
transfer risk associated with construction projects. methods recognize the dynamic project environment. The
Table 4 shows the firms' strategies for transferring risks use of traditional methods which assess risk involved in
involved in construction projects. Most of the contractors projects in a deterministic way has been criticized for failing
(63%) use a 'back-to-back' sub-contract agreement to the to take into account the sequential nature of construction
main contract with specialist and domestic subcontractors. management process 35. Huseby and Skogen 35 are of the
Another method popular with the contractors is insurance. opinion that in a realistic risk model, project uncertainty
The project managers choose to transfer risks using profes- must be modelled as a dynamic process in which the
sional indemnity and through the wordings of contract decision-maker can revise his/her plans as the project runs.
conditions with client and designers. This is possible for Subjective probability uses the experience gained from
project management practices because they provide pro- similar projects undertaken in the past by the decision-
fessional services rather than site construction involving maker, where decision-making is characterized by risk, to
substantial direct resource commitment. decide on the likelihood of risk exposure and the outcomes.
Risk premiums in construction projects take the form of
contingencies or added margins to an estimate to cover
Current usage of risk management techniques unforeseen eventualities. The amount of the premium varies
Techniques of risk analysis in construction projects include between projects and is mostly dependent upon attendant
risk premium, risk adjusted discount rate, subjective prob- risk and the decision-maker's risk attitude.
ability, decision analysis, sensitivity analysis, Monte Carlo The respondents were asked to identify which of these
simulation, stochastic dominance, Caspar and intuition 29-32. risk analysis techniques they are familiar with, and ones
Methods of decision analysis are algorithms, mean end that are being used by their firms for project risk analysis
analysis, bayesian theory and decision trees. These provide and management. Table 5 shows that the use of risk analysis
decision-making tools in an uncertain environment. An techniques by the responding firms is generally low in con-
algorithm contains a sequence of instructions for problem struction projects with the exception of intuition/judge-
solving. Mean end analysis is a method of clarifying a chain ment/experience. This tends to support Birch and McEvoy j4
of objectives to identify a series of decision points. The that the approach to risk analysis is largely based on the use
decision tree shows sequence of known choices (a number of checklist by managers, who try to think of all possible
of alternatives) and their possible outcomes graphically in risks and take appropriate action. Jamieson and LOW 36
a tree form such that the decision maker can identify best have faulted this method of risk analysis by maintaining
alternatives that achieve the objectives of a major project. that, although it is possible to make a long list that is
The decision tree method is useful in deciding methods of reasonably comprehensive, this approach gives little con-
construction, choosing alternative projects, and in contractual fidence that all risks have been identified. The table shows
problems such as whether to proceed with a claim and that most of the respondents are familiar only with sensitivity
assessing the likelihood of a claim succeeding 33. analysis technique (CTR = 53 %, PM = 69%). This is fol-
Monte Carlo analysis is a form of stochastic simulation. lowed by decision trees, Monte Carlo simulation and
Using this method the probability of project outcome is subjective probability.
obtained by carrying out a number of iterations, depending Checklists based on intuition/judgement/experience which
on the degree of confidence required. Caspar is a computer recorded the highest familiarity with respondents cannot be
aided simulation for project appraisal and review. It is a regarded as a formal technique. Although the sample from
project management tool designed to model the interaction project management practices is smaller, the results tend
of time, resources, cost and revenue throughout the entire to suggest that the project managers, compared with the
Table 4 How risks are transferred by firms
No. % No. %
To subcontracting (including specialist contractors)--on back-to-back
subcontract agreement 19 63 0 0
Contractual terms--qualification of tender, procurement route and contractual
exclusions where possible 5 17 2 15
To design teams/consultants 6 20 2 15
To clients 4 13 1 8
To insurance/professional indemnity 10 33 4 31
Contractors 0 0 3 23
35
Risk analysis and management in construction: A S Akintoye and M J MacLeod
contractors, have more awareness of risk analysis and • Risk analysis of construction projects is seldom formally
management techniques. requested by clients--clients expect project management
Almost all organizations depend on intuition/judgement/ practice to set up projects risk-flee.
experience to manage risks involved in construction. This is • Risk analysis in commercial terms is not always viable
followed by sensitivity analysis (CTR = 53 %, PM = 38 %). on projects.
The popularity of sensitivity analysis compared with any • Project risk management is about people not scientific
other formal techniques of project risk analysis and man- models.
agement is probably because it provides answers to a whole • Lack of expertize in the techniques.
range of 'what if' questions, it is comparatively simple to
Lack of familiarity featured prominently amongst the
use and has the ability to focus on a particular estimate 28.
reasons provided by the respondents for non-use of formal
The technique provides information on the project risk
risk management techniques. This is followed by the claim
variables which are considered to be of potentially serious
that the amount of calculations involved using the techniques
impact on project cost and time estimates. Other techniques
is unwarranted in order to meet that project's objectives of
such as subjective probability and Monte Carlo simulation
time, cost and quality. The comments are not particularly
require quantification of probability of occurrence and
surprising considering the lack of formal training in risk
probability distribution of risk factors before the procedures
analysis and management techniques by most of the respon-
involved in calculations can be undertaken. The computer-
dents. S c h o n ' s 37 assertion, supported by the respondents'
based techniques like stochastic dominance, Caspar, mean
comments, becomes relevant in the situation that "Managers
end analysis and algorithms are not used by the firms. With
have become acutely aware that they are often confronted
the exception of checklists and sensitivity analysis, these
with unique situations to which they must respond under
results generally contradict those obtained by Simister t°,
conditions of stress and limited time which leave no room
this could be explained by the work-related background
for extended calculation or analysis". The evidence that the
of his respondents with some skewness towards IT-related construction industry business management decisions, like
fields. most decision-making processes involving professionals
The respondents were asked for the reasons why some of (see Reflective Practitioners37), depends substantially on
these techniques are not used in their firms. The responses intuition and experience, rather than quantitative analysis
from the contractors have been separated from the project
irrespective of educational and professional qualification,
managers.
is supported by the firms' attitudes to risk analysis and
The reasons provided by contractors for not using the
management techniques.
techniques of risk analysis and management were:
• Lack of familiarity with the techniques. Discussion and conclusion
• The degree of sophistication involved in the techniques
is unwarranted for project performance. Risk elements associated with construction projects influence
• Time plus lack of information and knowledge. the time, cost and quality performance of the project. Risk
• Doubts whether these techniques are applicable to the management therefore becomes a continuing activity in
construction industry. project development, from inception and throughout the
• Most construction projects are seldom large enough to life of the project.
warrant the use of these techniques or research into them. The responses to the strategies for dealing with risks in
• They require availability of sound data to ensure construction suggest that the industry is mostly risk averse.
confidence. The contractors transfer risks to their domestic and specialist
• The vast majority of risks are contractual or construction sub-contractors and through insurance premiums. Project
related and are fairly subjective, hence they are better managers resort to professional indemnity insurance to
dealt with based on experience from previous contracts transfer risks associated with services provided to clients.
undertaken by the firm. Although, it is generally recognized that risk should be
• It is difficult to see the benefits. transferred to the party that is in the best position to deal
with it, the process where a contractor transfers all risks
The reasons provided by the project managers were par- involved in a project does not bode well for innovation
ticularly reflective of the services they provide to their initiative within the industry. Contractors have a tendency
clients: to contract out all the work packages involved in a project
36
Risk analysis and management in construction: A S Akintoye and M J MacLeod
to sub-contractors and undertake 'contract management' as to re-engineer the industry. Ho and Pike 38, for example,
part of a strategy to reduce or eliminate their risk. The are of the opinion that the increasing widespread use of
implication therefore is that the general contractors with the microcomputers in financial modelling packages will add to
means to do so, either fail to or have no incentive to the potential, ease of use and efficiency of risk analysis in
undertake research as part of the strategies to reduce the capital budgeting. The extent to which this can be achieved
risks associated with their construction business activities. in the construction industry hasA),et to be seen in view of
It is therefore unsurprising to hear that the construction low usage of IT in constructions.
industry ranks poorly in terms of research activities. The respondents' doubts that risk analysis and manage-
The questionnaire survey of contractors and project man- ment techniques are applicable to the construction industry
agement practices within the UK construction industry shows calls for concern. Construction texts and construction
that both perceive risk in construction as the likelihood of research in related fields should address this issue if such
unforeseen events occurring which could adversely affect techniques are to be of practical value to the construction
the potential completion of the project, i.e. in terms of cost, industry.
time and quality of performance. Although risk manage-
ment techniques have been used in other industries for a
References
long time, the construction industry has approached risk
management in terms of individual intuition, judgement and 1 Porter, C E Risk Allowance in Construction Contracts M.Sc. Thesis,
experience gained from previous contracts. One major University of Manchester, UMIST (1981)
2 Heale, J R 'Contingency funds evaluation' Transaction of American
drawback of risk analysis techniques is that the more Association of Cost Engineers (1982) B3.1-B3.4
powerful and sophisticated the technique, the more data and 3 Perry, J G and Hayes, R W 'Risk and its management in construction
time is required. Construction industry activity is con- projects' Proceedings of Institution of Civil Engineers, Part 1, June
strained by time because construction production is mostly (1985) Vol. 78, 499-521
employed just-in-time for the client's production requirement. 4 Mason, G E A Quantitative Risk Management Approach to the Selection
of a Construction Contract Provisions Ph.D. Thesis, Department of
It is unsurprising that some of the respondents have iden- Civil Engineering, Stanford University (1973)
tified project time constraint as one of the major reasons for 5 Moavenzadeh, F and Rossow, J 'Risks and risk analysis in construction
not using risk analysis and management techniques. management' Proceech'ng of the C1B W65, Symposium on Organisation
The increased availability of computers, which has and Management of Construction, US National Academy of Science,
Washington DC, USA, 19-20 May (1976)
allowed the topic of project risk analysis to mature in other 6 Bufaied, A S Risks in the Construction Industry: their Causes and their
related field, does not appear to have made much impact on Effects at the Project Level Ph.D. Thesis, University of Manchester,
the tools being used for risk analysis and management in the UMIST (1987)
construction process. 7 Fong, S W 'Risk management' The Cost Engineer 25 (1987) 12-16
The need for the risk analysis assessment and manage- 8 Ashley, D B Construction Project Risk Sharing Technical Report No.
220, The Construction Institute, Department of Civil Engineering,
ment practitioners to develop proven techniques (such as Stanford University, Stanford, CA, July (1977)
risk simulation techniques) other than intuitive methods is 9 Kangari, R and Riggs, L S 'Construction risk assessment by
endorsed by Ho and Pike 38 who asserted that risk analysis linguistics' IEEE Transaction of Engineering Management 36 (1989)
should formalize managers' judgements about project un- 126-131
10 Simister, SJ 'Usage and benefits ofproject risk analysis and manage-
certainty in a more precise way and should allow them to ment' International Journal of Project Management 12 (1994) 5-8
modify their judgement in the light of information available 11 MacLeod, M J Perception and Management of Risk in the UK
to them. Construction Industry Unpublished M.Sc. Dissertation, Glasgow
Most of the respondents are aware of what is involved in Caledonian University (1994)
risk management. However, due to lack of familiarity, the 12 New Builder, Contractors File 1992, Who Does What, a supplement
to New Civil Engineer andNew Builder (Edited by Winney, M) 45-49
industry uses few formal techniques of risk analysis and 13 Moser, C A and Kalton, G Survey Methods in Social Investigation
management involving calculations due to lack of familiarity. Heinemann Educational, UK (1971)
Ho and Pike 3s also found that the major limitations most 14 Birch, D G W and McEvoy, M A 'Risk analysis for information
frequently found for application of risk analysis include systems' Journal of Information Technology 7 (1992) 44-53
15 William, T M 'Using a risk register to integrate risk management in
managers' inadequate understanding of the risk analysis project definition' International Journal of Project Management 12
approach. These findings may have implications for the (1994) 17-22
curriculum in Construction Management education. The 16 The Royal Society "Risk: analysis, perception and management'
implementation of project risk analysis and management, in Report of a Royal Society Study Group, London (1992)
view of the implications for construction business profit- 17 Choffray, J M and Johnson, P E 'Measuring perceived pre-purchase
risk for a new industrial product' Industrial Marketing Management
ability, may demand education and training of the con- 8 (1977) 333-334
struction project managers and professionals in risk 18 Ritchie, B and Marshall, D Business Risk Management Chapman and
management techniques to bridge the gap between theory Hall, UK (1993)
and practice. 19 Mustafa, M A and AI-Bahar, J F 'Project risk assessment using the
analytic Hierarchy process' lEE Transactions of Engineering
Various options for dealing with this could be in the form Management 38 (1991) 46-52
of formal and/or informal education and training 39. Formal 20 Dey, P, Tabucanon, T and Ogunlana, S O 'Planning for project
education could be postgraduate studies in risk management, control through risk analysis: a petroleum pipeline-laying project'
which managers could undergo on a part-time basis; Glasgow International Journal of Project Management 12 (1994) 23-33
Caledonian University, for example, currently run a full- 21 Yeo, K T 'Risk classification of estimates and contingency' Journal
of Engineering Management 6 (1990) 458-470
time/part-time postgraduate programme in Construction 22 Carr, R I 'Paying the price for construction risk' Journal of Con-
Management with an option in Risk Management. Informal struction Division, ASCE 103 (1977) 152-161
education and training could be in form of CPD programmes 23 Ashley, D B 'Construction project risks: mitigation and management'
organized by academic establishments or interest groups Proceedings of PMI International Symposium, Boston, USA (1981)
24 Doherty, N A Corporate Risk Management McGraw Hill, New York,
within professional bodies such as the Association of USA (1985)
Project Managers. It may not be expected that this will be 25 HMSO, Health and Safety, The Construction (Design and Manage-
an immediate panacea, but it is a move in the right direction ment) Regulations No. 3140, HMSO (1994)
37
Risk analysis and management in construction: A S Akintoye and M J MacLeod
26 Ribakoff, S 'Construction contract arrangements' Construction Risks 40 McCellar, T EDl in the UK Construction Industry Unpublished M.Sc.
and Liability Sharing Conference, American Society of Civil Engineers, Dissertation, Glasgow Caledonian University, UK (1995)
Arizona, 24-26 January (1979)
27 Perry, J G 'Dealing with risks in contracts' Building Technology and
Management (April 1986) 23-26 Dr Akintola Akintoye is senior
28 Flanagan, R and Norman, G Risk Management and Construction lecturer in construction cost studies
Blackwell, UK (1993) in the Department of Building and
29 Raftery, J Risk Analysis in Project Management E & FN Spon, UK Surveying, Glasgow Caledonian
(1994) University. He has presented papers
30 Williams, C A and Heims, R M Risk Management and Insurance, at international conferences and has
McGraw Hill, New York, USA (1989) published widely in the subject areas
31 Toakley, A R and Ling, S M C 'Risk management and the building of construction economics and con-
procurement process' Innovation and Economics in Building struction management. His research
Conference, Brisbane, Australia, (September 1991) 63-67 interests include construction price
32 The Association of Project Managers, 'Project risk analysis and man- and market modelling, construction
agement' in Project, The Bulletin of the Association of Project Managers risk management, and construction
(Compiled by Norris, C, Perry, J and Simon, P) 4 (April 1992) procurement.
33 Thompson, P and Perry, J Engineering Construction Risks--A Guide
to Project Risk Analysis and Risk Management Thomas Telford
Services, London, UK (1979)
34 Willmer, G Development of Risk Models for Engineering Construction
Projects Ph.D. Thesis, University of Manchester, UMIST (1988)
35 Huseby, A B and Skogen, S "Dynamic risk analysis: the DynRisk Malcolm J MacLeod holds a master
concept' International Journal of Project Management 10 (1992) degree from the Glasgow Caledonian
160-164 University. His educational and pro-
36 Jamieson, R and Low, G 'Local area network operations: a security fessional background is in quantity
control and audit perspective' Journal of Information Technology 5 surveying. He has worked with UK
(1990) 63-72 construction firms and quantity
37 Schon, D A The Reflective Practitioner: How Professionals Think in surveying practices on major projects.
Action Basic Books, USA (1983) His research interest is in risk man-
38 Ho, S S M and Pike, R H 'The use of risk analysis techniques in capital agement of construction projects. He
investment appraisal' in Risk Analysis Assessment and Management is currently working with an inter-
(Edited by Ansell, J and Wharton, F) John Wiley and Sons, NY national firm of loss adjusters as a
(1992) 71-94 construction risk analyst.
39 Akintoye, A 'Construction management education in UK--A survey
of the content of postgraduate taught courses' Construction Papers,
The Chartered Institute of Building, No. 45 (1995)
38