Program (Project) Management and Review Technique (PERT) and
Critical Path Method (CPM) are two popular statistical tools used by the
business entities for the management of the project. These two methods are used in
the successful completion of a project and hence used in conjunction with each
other. Nevertheless, the truth is that CPM is different from PERT in a way that the
former cost based while the latter is timebased. In the same manner, there are
many differences between PERT and CPM, which we are going to discuss in this
article.
1. Comparison Chart
2. Definition
3. Key Differences
4. Conclusion
Comparison Chart
BASIS FOR
PERT CPM
COMPARISON
http://keydifferences.com/differencebetweenpertandcpm.html 2/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
BASIS FOR
PERT CPM
COMPARISON
Click on video to unmute
De¶nition of PERT
PERT is an acronym for Program (Project) Evaluation and Review Technique, in
which planning, scheduling, organising, coordinating and controlling of uncertain
activities take place. The technique studies and represents the tasks undertaken to
complete a project, to identify the least time for completing a task and the
minimum time required to complete the whole project. It was developed in the late
1950s. It is aimed to reduce the time and cost of the project.
PERT uses time as a variable which represents the planned resource application
along with performance specification. In this technique, first of all, the project is
divided into activities and events. After that proper sequence is ascertained, and a
network is constructed. After that time needed in each activity is calculated and the
critical path (longest path connecting all the events) is determined.
http://keydifferences.com/differencebetweenpertandcpm.html 3/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
De¶nition of CPM
Developed in the late 1950’s, Critical Path Method or CPM is an algorithm used for
planning, scheduling, coordination and control of activities in a project. Here, it is
assumed that the activity duration are fixed and certain. CPM is used to compute
the earliest and latest possible start time for each activity.
The process differentiates the critical and noncritical activities to reduce the time
and avoid the queue generation in the process. The reason behind the identification
of critical activities is that, if any activity is delayed, it will cause the whole process
to suffer. That is why it is named as Critical Path Method.
In this method, first of all, a list is prepared consisting of all the activities needed to
complete a project, followed by the computation of time required to complete each
activity. After that, the dependency between the activities is determined. Here,
‘path’ is defined as a sequence of activities in a network. The critical path is the
path with the highest length.
1. PERT is a project management technique, whereby planning,
scheduling, organising, coordinating and controlling of uncertain
activities is done. CPM is a statistical technique of project management
in which planning, scheduling, organising, coordination and control of
welldefined activities takes place.
2. PERT is a technique of planning and control of time. Unlike CPM,
which is a method to control costs and time.
3. PERT is set according to events while CPM is aligned towards
activities.
4. A deterministic model is used in CPM. Conversely, PERT uses
probabilistic model.
5. There are three times estimates in PERT i.e. optimistic time (to), most
likely time ™, pessimistic time (tp). On the other hand, there is only
one estimate in CPM.
http://keydifferences.com/differencebetweenpertandcpm.html 4/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
6. PERT technique is best suited for a high precision time estimate,
whereas CPM is appropriate for a reasonable time estimate.
7. PERT deals with unpredictable activities, but CPM deals with
predictable activities.
8. PERT is used where the nature of the job is nonrepetitive. In contrast
to, CPM involves the job of repetitive nature.
9. There is a demarcation between critical and noncritical activities in
CPM, which is not in the case of PERT.
10. PERT is best for research and development projects, but CPM is for
nonresearch projects like construction projects.
11. Crashing is a compression technique applied to CPM, to shorten the
project duration, along with least additional cost. The crashing concept
is not applicable to PERT.
Conclusion
The difference between these two project management tools is getting blurred as
the techniques are merged with the passage of time. That is why, in most projects,
they are being used as a single project. The primary point that distinguishes PERT
from CPM is that the former gives the extreme importance of time, i.e. if the time is
minimised, consequently the cost will also be reduced. However, cost optimisation
is the basic element, in the latter.
Click on video to unmute
http://keydifferences.com/differencebetweenpertandcpm.html 5/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
Filed Under: Business
Comments
karan chovatiya says
April 13, 2016 at 1:57 am
mind blowing …! very easy to understand anybody ….really like that
concept..thanks …:)
Reply
gowtham says
June 1, 2016 at 4:48 pm
Awesome … just mind blowing it is very easy to understand.
Reply
http://keydifferences.com/differencebetweenpertandcpm.html 6/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
shashikumar says
July 2, 2016 at 2:48 pm
nice easy to understand and was very important
Reply
Tuabur says
July 13, 2016 at 2:57 pm
Truly it it very easy and quite descriptive as well as so much helpful to
understand why need pert and cpm
Reply
rudolph says
September 8, 2016 at 12:52 pm
good one
Reply
K. A. Sreekrishna says
October 11, 2016 at 7:58 pm
A good insight to PERT & CPM.
Reply
Bikash says
http://keydifferences.com/differencebetweenpertandcpm.html 7/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
December 15, 2016 at 7:22 am
This a great article. Simple and lucid…
Reply
Surbhi S says
December 15, 2016 at 9:39 am
Thanks all of you for sharing your views with us.
Reply
Amad Ahmad says
January 7, 2017 at 9:59 pm
great and easy. thank U for sharing
Reply
Leave a Reply
Your email address will not be published. Required fields are marked *
Comment
Name *
http://keydifferences.com/differencebetweenpertandcpm.html 8/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
Email *
Website
POST COMMENT
Custom Search
TOP 5 DIFFERENCES
Difference Between Management and
Administration
Difference Between Developed
Countries and Developing Countries
Difference Between Savings Account
and Current (Checking) Account
Difference Between Formal and
Informal Communication
Difference Between Pvt Ltd and Public
Ltd Company
http://keydifferences.com/differencebetweenpertandcpm.html 9/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
Click on video to unmute
RELATED DIFFERENCES
Difference Between Performance
Appraisal and Performance
Management
Difference Between Training and
Development
Difference Between Internal Audit and
External Audit
Difference Between Centralization and
Decentralization
Difference Between Budget and
Forecast
NEW ADDITIONS
Difference Between Discrete and
Continuous Variable
Difference Between Local Time and
Standard Time
Difference Between MLA and MP
Difference Between Act and Law
Difference Between Fog and Mist
http://keydifferences.com/differencebetweenpertandcpm.html 10/11
3/9/2017 Difference Between PERT and CPM (with Comparison Chart) Key Differences
Difference Between High Court and
Supreme Court
Differences Between Skewness and
Kurtosis
Difference Between State and Union
Territory
Difference Between Exponent and
Power
Difference Between Latitude and
Longitude
Key Differences
3,686 likes
Like Page Contact Us
http://keydifferences.com/differencebetweenpertandcpm.html 11/11