Mine Admin. Offices & Workshop
Method Statement
Page 2 of 26
TABLE OF CONTENTS
Purpose 2
Scope 2
Responsibilities 2
Resources to be deployed 3
Erection Methodology 10
Quality Control 19
Safety Precautions 20
Attachments 21
1. PURPOSE
Mine Admin. Offices & Workshop
Method Statement
Page 3 of 26
The purpose of this document is to provide a detailed Method Statement
indicating the work procedures for erecting the steel structure to be carried for
the Mine Admin Office and Workshop.
2. SCOPE
• Lean concrete
• Reinforced concrete for the foundation ( anchor bolts and pedestal)
• Erection of steel structure Frames with Sheeting.
• Masonry Works
3. RESPONSIBILITIES
Project Manager shall be responsible for the overall organization, progress and
safe execution of the works.
Resident Engineer shall be responsible for ensuring the works are carried out in
accordance with the construction drawings and specifications and shall report to
the Project Manager. He is also in charge of the day to day organization,
execution and safe execution of the works. He shall also be responsible for
monitoring and assuring the quality of the works.
Surveyor shall be responsible for setting out of the works and shall report to the
Project manager.
Mine Admin. Offices & Workshop
Method Statement
Page 4 of 26
5 Resource to
be Deployed
Method Statement
Page 5 of 26
Light Duty Scaffolding Ladders
Method Statement
Page 6 of 26
Pop Rivet Puller
Grinder
10 mm Drill
Vice Grips
Aviation snips
Mine Admin. Offices & Workshop
Method Statement
Page 7 of 26
Ratchet Spanner Utility Knife
Method Statement
Page 8 of 26
Tool Belt and Bolt Bag Plumb bob Total Station
Spirit
Level
Measuring Tape
Mine Admin. Offices & Workshop
Method Statement
Page 9 of 26
Goggles
Welding Hood
Gloves
Safety Harness
Method Statement
Page 10 of 26
First Aid Kit
a) Project Manager
b) Assistant project Manger
c) Resident Engineer/Safety Officer
d) Surveyor
e) Foreman / Supervisor
f) Erection Crew
g) Carpenter with Assistants
h) Bar bender with Assistants
i) Operator
j) Concrete Labors
k) Mason
l) General Workers
Mine Admin. Offices & Workshop
Method Statement
Page 11 of 26
6
Erection
Methodology
• Lean Concrete
After the ground have been leveled by a grader and compacted
with a roller, the lean concrete can be pour.
After lean concrete is poured, it should be cured by water for a
minimum of one week.
Method Statement
Page 12 of 26
After all rebar are set in place, anchor bolts should be put in
accurate place with the help of steel plate to keep anchor bolts in
position during the pouring of the foundation.
After the anchor bolts and rebar are in their final position, the
foundation will be ready for pouring.
Curing for the foundation will be for not less than a week for the
concrete to gain the required strength of 30 Mpa.
Mine Admin. Offices & Workshop
Method Statement
Page 13 of 26
• Erection of steel structure
General
Erection Procedure
Step 1 : Stand main frame Columns and turn nuts on anchor bolts.
Mine Admin. Offices & Workshop
Method Statement
Page 14 of 26
Step 2 : Add wall girts
Step 3 : Add main frame rafter and secure with rope, tighten connection
bolts snug, using crane.
Mine Admin. Offices & Workshop
Method Statement
Page 15 of 26
Step 4 : Add another main Frame rafter and several roof purlins to
stabilize frame
First Frame of braced bay Second Frame of braced bay Roof Purlins
Mine Admin. Offices & Workshop
Method Statement
Page 16 of 26
Step 5 : Add cable bracing. Snug tighten only. Remove rope ties and
repeat the previous steps with other main frames.
Step 6 : Add corner columns, sidewall girts and eave struts. Then proceed
with endwall columns, rafters, remaining roof purlins and flange braces.
When the frame work is standing, the structure should be plumbed and
squared. Use a level as shown for wall columns. Square the roof with the
use of the cable braces as shown. Taking diagonal measurements and
Mine Admin. Offices & Workshop
Method Statement
Page 17 of 26
adjusting the tension of the xbracing will square the roof and aid in
plumbing the structure endwalls.
Method Statement
Page 18 of 26
Step 7 : Plumbing and squaring the framework .
Mine Admin. Offices & Workshop
Method Statement
Page 19 of 26
• Block Works
After columns are set and their alignment is checked, block work
will commence with the use of simple equipment and scaffolding
when needed
Method Statement
Page 20 of 26
7
Quality
Control
The safety and quality of erection will be ensured by engaging
qualified supervisor and technicians on the job.
Method Statement
Page 21 of 26
8
Safety
Precautions
For safety reasons there are precautions that
need to be taken during erection.
8.1 Make daily check on all lifting equipment. 8.9 Ensure that erection always starts at a
braced bay.
8.2 Make daily checks on all lifting slings.
8.10 Ensure permanent bracing and flange
8.3 Check that all access equipment is in good
stays are installed as work proceeds.
condition, including scaffolding and ladders.
8.11 Ensure that high strength bolts are used
8.4 Check weather conditions, strong winds are
where indicated.
dangerous during erection and sheeting.
8.12 maintain a clean and tidy site. Thus avoid
8.5 Check for overhead electric lines before
material loss or accident.
moving in with a crane.
8.13 Tie down Sheeting Once the bundle is
8.6 check that all erectors have the correct
opend.
personal safety equipment, helmet, safety
shoes, safety harness etc. 8.14 Ensure that high strength bolts are
correctly tightened.
8.7 ensure that there are sufficient guy wires
on site for temporary bracing 8.15 when walking on the roof, step in the
valley of the panels, not the ribs.
8.8 Check electric cables for hand tools, discard
frayed or split cables
Mine Admin. Offices & Workshop
Method Statement
Page 22 of 26
Mine Admin. Offices & Workshop
Method Statement
Page 23 of 26
Mine Admin. Offices & Workshop
Method Statement
Page 24 of 26
Mine Admin. Offices & Workshop
Method Statement
Page 25 of 26
Mine Admin. Offices & Workshop
Method Statement
Page 26 of 26