Beruflich Dokumente
Kultur Dokumente
HSE
Page 1 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
6.0 INTRODUCTION
COMPANY recognizes that CONTRACTOR and subcontractor have existing Health,
Safety, Security, and Environment management system with established policies, safety
practices, processes and procedures in place. COMPANY will encourage their use where
they meet the intent of the SCOPE OF WORK as contained in SECTION IV.
CONTRACTOR shall not lose focus on the requirements of ISO 45001:2015 –
Occupational Health and Safety Management System and other relevant HSSE
Management system requirements.
This section of CONTRACT is divided into the following sections:
6.5 APPENDICES
These appendices list the main COMPANY standards, manuals and guides referred to
within the following sections.
SECTION 1 - GENERAL HSSE CONDITIONS
ARTICLE 1 – DEFINITIONS
1.1 All defined terms in this Exhibit E shall have the same meaning as set out in the
CONTRACT, unless otherwise stated as follows:
Page 2 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
“ALARP” (As Low As Reasonably Practicable) shall mean such level of reduction of risk
where the cost and effort of further reduction measures becomes unreasonably
disproportionate to the additional risk reduction obtained.
“SERVICES COMPANY HSSE REPRESENTATIVE’ shall mean the person appointed
from time to time by the COMPANY and notified in writing to the CONTRACTOR to act as
its representative for HSSE matters the purposes of this CONTRACT or in default of such
notification, the COMPANY HSSE REPRESENTATIVE.
“HSSE” shall mean Health, Safety, Security and Environment.
“HSSE HAZARD” shall mean an object, physical effect or condition with potential to harm
people, property or the environment.
“HSSE STANDARD(S)” shall mean, as referred to individually or collectively, HSSE
policies, standards and procedures applicable to the performance of the SERVICES under
the CONTRACT as specified herein and in Appendix 5 – Reference Documentation.
“LIFE-SAVING RULES” shall mean the twelve (12) ‘Seplat Life-Saving Rules’ adopted by
COMPANY and set out in Appendix 2. These rules highlight activities that carry a high
potential of serious injury or death.
”WORK SITE” shall mean the area of any physical site where SERVICES are actually
performed by CONTRACTOR and/or its SUBCONTRACTORS provided (1) such site(s) is
designated as such by COMPANY; or (2) owned or controlled by COMPANY and (2)
COMPANY made the area available to CONTRACTOR to perform THE SERVICES and
related activities.
Page 3 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
does not by reason of this clause assume or share in any obligation or liability otherwise
placed solely on CONTRACTOR under the CONTRACT, and this clause is not intended
and shall not be construed to relieve, shift or diminish any obligation or liability of
CONTRACTOR under the CONTRACT.
3.1.1 The CONTRACTOR shall have in place and maintain until the
completion/handover/final acceptance of the SERVICES a management system, which
provides assurance that each and all CONTRACTOR’S PERSONNEL meet all the
COMPANY HSSE competency requirements (including the specified HSSE training) and
meet the COMPANY’s minimum Health Management Standards for the SERVICES, and
that any tools and machinery it is providing are properly maintained and suitable for the
SERVICES.
ARTICLE 4 – SUBCONTRACTORS
4.1 SUBCONTRACTORS shall not be allowed to mobilize and start any part of the SERVICES
they shall perform until the CONTRACTOR has confirmed compliance with the
requirements of this CONTRACT and at the express approval of the COMPANY.
4.2 All articles in this Exhibit E shall apply equally to any aspect of the SERVICES that is
performed by or subcontracted to any member of the CONTRACTOR GROUP or other
subcontractors.
4.3 At the approval of the COMPANY, the CONTRACTOR shall ensure that each
SUBCONTRACTOR either adopts the CONTRACTOR’S HSSE MS and/or plan as
Page 5 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
approved by the COMPANY or has its own HSSE MS/plan, which shall be to the same or
a higher standard than the CONTRACTOR’S HSSE MS and ultimately that of the
COMPANY.
4.4 The CONTRACTOR shall ensure that contracts with all SUBCONTRACTORS include
suitable equivalent clauses to meet the requirements of this Exhibit E and an obligation to
comply with the requirements of the CONTRACT and in particular this Exhibit E, including
the SEPLAT LIFE-SAVING RULES (Appendix 2). The CONTRACTOR shall develop a set
of requirements for each SUBCONTRACTOR, which as a minimum, shall include the
specific HSSE Hazards associated with the SUBCONTRACTOR’S scope of SERVICES
and respective HSSE STANDARDS and provide the SUBCONTRACTOR with the
CONTRACT HSSE Plan. The requirements shall be in a format and level of detail that will
be readily understood by the SUBCONTRACTOR. The requirements shall:
• Ensure that the SUBCONTRACTOR familiarises itself with the relevant parts of the
CONTRACT HSSE Plan and its role in implementing the CONTRACT HSSE Plan;
• Ensure that the SUBCONTRACTOR submits its own project specific HSSE Plan and
SERVICES procedures, as demanded by the CONTRACTOR, for the CONTRACTOR’S
approval before commencement of the SERVICES to be performed by the
SUBCONTRACTOR;
• Ensure the SUBCONTRACTOR trains its personnel, including supervisors, in all HSSE
requirements, and have their personnel, including supervisors, undertake to adhere to the
instructions.
4.5 The CONTRACTOR shall perform SUBCONTRACTOR HSSE capability assessment
during the prequalification process. The COMPANY reserves the right to participate in the
evaluation of SUBCONTRACTOR HSSE capability and approve any SUBCONTRACTOR
HSSE capability accordingly. If provided in the CONTRACT and/or required by the
COMPANY, the CONTRACTOR shall inform the COMPANY in advance and in reasonable
time of any planned award of a subcontract.
Page 6 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
CONTRACT in accordance with the clause headed TERMINATION in the General Terms
and Conditions of the CONTRACT.
2.3 Competency
2.3.1 The CONTRACTOR shall minimise turnover of CONTRACTOR’S PERSONNEL where
possible and shall notify COMPANY in writing the release/replacement of KEY
PERSONNEL and/or any member of CONTRACTOR’S PERSONNEL who perform
SERVICES involving a specific risk.
2.4 Training
2.4.1 CONTRACTOR’S PERSONNEL travelling to company swamp facilities shall undertake
Basic Offshore Safety Induction and Escape Training (BOSIET) for any swamp visit
utilizing boat barge or vessel.
CONTRACTOR’S PERSONNEL travelling by boat barge or vessel to any COMPANY
location shall hold valid BOSIET certificates. Only BOSIET certificates issued by
recognised training providers (OPITO–“Offshore Petroleum Industry Training
Organisation”-accredited by DPR) shall be acceptable for the above purpose. BOSIET
provides passengers with the knowledge and skills necessary to react to and survive boat
capsizing and to be able to care for themselves in a water survival situation. Trainees
are required to pass a theoretical and practical assessment of their competence in Basic
Page 7 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
Offshore Safety Induction and Emergency Training Techniques before being Helicopter
Underwater Escape Training (HUET) certified. The CONTRACTOR shall have a duty to
ensure that all CONTRACTOR’S PERSONNEL (including employees of its
SUBCONTRACTORS) possess valid HUET certificates.
2.4.2 Any CONTRACTOR’S PERSONNEL assigned to SERVICES in any Seplat swamp
location or travelling by boat to any Seplat swamp location and who does not have BOSIET
certification shall have to first successfully undertake swimming training and certification
with PFD (Personal Floatation Device) before embarking on the trip to the swamp location.
Such training shall provide the personnel with the knowledge and skills necessary to react
to and survive boat capsizing and any other water related emergencies. The training and
certification shall be at the CONTRACTOR’s expense.
2.4.3 Unless specified otherwise herein, all training of CONTRACTOR’S PERSONNEL shall be
at the CONTRACTOR’s cost.
Page 8 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
construed to relieve, shift or diminish any express or implied obligation or liability of
CONTRACTOR under the CONTRACT.
Other PPE such as, raincoat, Personal Floatation Device (PFD), swamp Wellington
boots, eye goggles, respirators, escape hoods, shin guards, aprons, hand gloves etc.,
shall be provided on a risk assessment basis in relation to the SERVICES.
3.2.4 CONTRACTOR shall ensure that PPE provided to CONTRACTOR’S PERSONNEL have
sufficient quality assurance certifications [CE markings and standard references] and that
the PPE manufacturers are certified to ISO 9000 or equivalent.
3.2.5 All PPE [Including Personal Floatation Devices] shall be inspected and approved by the
COMPANY’s HSSE REPRESENTATIVE before they are deployed for use by
CONTRACTOR’s PERSONNEL.
Page 10 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
• Not to use mobile communication and/or navigation devices whilst driving;
• To drive within the approved speed limit;
• Not to drive under the influence of alcohol, drugs, or medication that impairs the ability
of the driver to safely operate the vehicle;
• To follow prescribed Journey Management Plan;
• Ensure that every passenger in the vehicle wears a seat belt before moving the
vehicle and throughout the journey.
• As a minimum CONTRACTOR shall ensure that all passengers in any of its vehicles
engaged in the performance of the SERVICES:
Page 11 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
• personnel;
• Marine equipment pre-mobilisation;
• International Safety Management (ISM) code;
• MARPOL 73 / 78;
• SOLAS (SAFETY OF LIFE AT SEA);
• Standards of Training, Certification and Watch keeping for Seafarers. (STCW 95)
Convention;
3.5.4 CONTRACTOR shall in addition provide evidence of assurance process of compliance of
SUBCONTRACTORS with the above requirements.
3.5.5 CONTRACTOR shall ensure that all CONTRACTOR’S PERSONNEL comply with the
COMPANY’s Marine logistics safety programs and initiatives and follow all local
LEGISLATION when traveling on COMPANY business. Any non-compliance by any
person should be reported to the COMPANY HSSE REPRESENATIVE.
3.5.6 Boat masters shall comply with the following:
• Wear PPE while on-board vessels.
• Do not use mobile telephone while on duty manoeuvring (when leaving a jetty or
trying to approach a jetty);
• Sail within the appropriate speed limit at all times, and in particular under restricted
visibility;
• Boat masters should not sail under the influence of alcohol, drugs, or medication
that impairs the ability of the operator to safely operate the vessel;
• Follow prescribed Journey Management Plan;
• At a minimum, all passengers are expected to comply with the following:
- Wear a life jacket while on the deck;
- Not to distract the Boat master during the journey;
- Not to under any circumstances request or put pressure on the Boat Master to
violate safety rules or procedures;
• Passengers shall have the right to refuse to board or use a vessel, which is not
equipped with life jacket, and/or if the Boat Master refuses to adhere to safety rules.
Page 12 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
specification and all applicable LEGISLATION including, without limitation, the Factories
Act Cap F1 Laws of the Federation of Nigeria 2004. Copies of all survey certificates and
inspection records must be available at the WORK SITE and made available to
COMPANY on demand.
3.6.4 CONTRACTOR shall comply with COMPANY's colour coding system for lifting
equipment inspection and testing as set out in the above COMPANY standards.
3.6.5 CONTRACTOR shall comply with the interval of inspections: at least once a year for
Lifting appliances, and once in six months for lifting equipment and accessories.
3.6.6 CONTRACTOR shall ensure that only lifting related accessories, appliances and
equipment that have passed COMPANY Pre-mobilisation inspection are utilised for the
performance of the SERVICES.
3.6.7 All lifting and hoisting operations shall be carried out by suitably trained and experienced
CONTRACTOR’s PERSONNEL, who shall be certified by a competent authority and be
in possession of current and valid certificate of competence.
3.6.8 CONTRACTOR’s PERSONNEL who are required to conduct lifting and hoisting
operations shall be required to successfully complete the COMPANY’s Driver Education
Programme (DEP) and be in possession of a current and valid DEP Permit.
3.6.9 CONTRACTOR shall maintain a register of all lifting accessories, appliances and
equipment available at the WORK SITE and all CONTRACTOR’s PERSONNEL who
may conduct lifting and hoisting operations.
3.6.10 CONTRACTOR shall ensure that all lifting accessories, appliances and equipment
available at the WORK SITE are maintained in accordance with the manufacturer’s
instructions and all statutory requirements. Records of such maintenance shall be kept
by the CONTRACTOR and made available to COMPANY on demand.
3.6.11 CONTRACTOR shall ensure that no lifting and hoisting operation is carried out without
a proper Lift Plan prepared and endorsed by a competent person.
Page 13 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
4.2.1 The COMPANY reserves the right to nominate CONTRACTOR’s PERSONNEL to
positions within the (local) emergency response organization.
4.2.2 In Line with the COMPANY Standard Medical Emergency Response (MER),
CONTRACTOR shall provide secondary and definitive care to their personnel that are
ill/injured, adopting a risk based approach for MER. This shall embrace two key concepts:
i) it should apply a time-dependent tiered set of responses to an incident and ii) set
different response requirements depending on the nature of the hazards and the activities
on the WORK SITE in addition to the site category. The secondary care should be
accessible within 1.5 hours of the first MER call-out request.
Page 14 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
1.2.3. Where the CONTRACTOR is contractually obliged to transport COMPANY
equipment/tools or supplies from one location to another, the CONTRACTOR shall at its
own initiatives and at no extra cost to the COMPANY provide appropriate security cover
including but not limited to security escorts for the safe movement or conveyance of such
items to its destination.
1.2.4. Appropriate and valid permits/licenses for all equipment/vehicles used for the execution
of the CONTRACT - The CONTRACTOR shall ensure that all its equipment, including
vehicles used for the execution of services to Seplat must have valid and authentic
Government or regulatory permits or approvals and shall not hold Seplat liable for any
downtime arising from equipment seizure or SERVICES delays due to none possession
of such permits.
1.2.5. Incident reporting and Investigation Management - Every CONTRACTOR, and
CONTRACTOR’s PERSONNEL shall upon becoming aware of any security incident
associated with this CONTRACT report to Seplat Security department as well as the
appropriate Government Security agent as well as assist where necessary in the
prosecution of such cases
1.2.6. Employment of locals as guards - Where Company Community Relations department has
identified engagement of local security guards as a requirements of the CONTRAC, and
where the CONTRACTOR’s equipment are likely to remain unused and therefore
abandoned at WORK SITE for whatever reasons, the CONTRACTOR shall be required
to engage members of the local community to watch over his equipment without prejudice
to the use of Government Security Forces (GSFs) if the risk assessment so dictates.
Page 15 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
2.5 Where determined by COMPANY Security Risk Assessment, certain categories of vehicle
may not be allowed entry into COMPANY facilities. Vehicles may be subject to geographic
parking restrictions at any time.
2.6 The COMPANY reserves the right to refuse entry to personnel or vehicles at any time and
without warning.
2.7 Any CONTRACTOR’s PERSONNEL who does not, or is unwilling to, comply with the
requirements above, may be refused access into or removed from the COMPANY
PREMISES without any liability to the COMPANY. CONTRACTOR shall be wholly liable
for any costs or claims arising directly or indirectly from such circumstances and hereby
undertakes to indemnify and hold harmless the COMPANY for any such costs or claims.
Page 16 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
Corporate Security in connection with the performance of the contract. These “ad hoc”
guidelines will be issued by and through COMPANY notification, e-mail, SMS alert or
COMPANY HSSE REPRESENTATIVE / CONTRACTOR engagement.
Page 17 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
f) CONTRACTOR agrees to investigate promptly, at its own initiative and at no
additional cost to the COMPANY any allegations made by the COMPANY or any third
party of acts or omissions of CONTRACTOR’s PERSONNEL directly or indirectly
engaged in the performance of the CONTRACT that may be inconsistent with the
Voluntary Principles. CONTRACTOR shall keep the COMPANY currently informed of
the progress of its investigations, of the outcome of such investigations and of any
preventive or remedial measures taken in accordance with the following sub-clause.
g) CONTRACTOR, at its own initiative and at no additional cost to the COMPANY, shall
take, or as the case may be, shall ensure that its relevant SUBCONTRACTORS
and/or agents shall take, all appropriate remedial and preventive measures to address
any acts or omissions found to be inconsistent with the Voluntary Principles, including,
without limitation, disciplinary action against responsible CONTRACTOR’S
PERSONNEL , irrespective of whether such findings are based upon an investigation
by the COMPANY, by CONTRACTOR or otherwise.
h) Without prejudice to the clause headed Termination in the GENERAL TERMS AND
CONDITIONS, and without prejudice to its further rights under the CONTRACT or at
law, the COMPANY shall be entitled to terminate the CONTRACT by providing
CONTRACTOR written notice to that effect if CONTRACTOR, any of its
CONTRACTOR’s PERSONNEL, agents, or their respective staff shall, in relation to
this CONTRACT, have committed any act or omission, whether before, on or after the
date of this CONTRACT, which is inconsistent with the Voluntary Principles.
Additionally, the COMPANY shall be entitled to terminate the CONTRACT by
providing CONTRACTOR written notice to that effect if CONTRACTOR breaches any
of the provisions of this Article.
7.2 Without prejudice to clause 7.1 above, as a minimum performance standard, the
CONTRACTOR in providing, receiving and/or using security services (whether private
(civilian) guards or Government security forces) in the performance of the SERVICES
or execution of the CONTRACT shall maintain and implement the following standards
and guidelines (as applicable) as part of its contractual obligations:
1. The CONTRACTOR shall ensure that all COMPANY policies regarding ethical conduct
and human rights are strictly observed.
2. Where the use of Government Security Forces (GSF) is involved, CONTRACTOR
shall set mutually agreed Rules of Engagement (ROE) on the use of force. The
CONTRACTOR shall induct the GSF personnel involved, and ensure that all
CONTRACTOR’S PERSONNEL are trained, to meet the standard set out in the ROE
on the use of force.
3. All incidents involving the use of force, violation of human rights or illegal acts involving
CONTRACTOR’s PERSONNEL in the course of executing the contract shall be
reported to the company as soon as practicable.
4. The CONTRACTOR shall record and investigate all incidents involving the use of
force, violations of human rights or other illegal acts such as assault, harassment and
molestation of workers and/or members of the public by GSF or civilian guards and
shall communicate its findings in writing to the COMPANY. The CONTRACTOR
should in addition report the matter to the nearest Police Station as may be required
by local law and/or take disciplinary action where necessary.
Page 18 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
5. The CONTRACTOR shall ensure that where force is used, it should be extremely
necessary and proportionate to the threat and that medical care is provided for the
injured including the offender.
6. The CONTRACTOR shall adopt a documented procedure to ensure that where it
becomes necessary for civilian guards to effect arrest in the course of performing their
duties, the arrested persons are promptly handed over to the Nigeria Police for further
investigation and possible prosecution.
7. The CONTRACTOR shall establish a policy for investigation of allegations of human
rights violations and illegal acts against its employees or civilian guards and forward
written report to the COMPANY.
8. Where defensive equipment such as batons are required by civilian guards, the
CONTRACTOR shall provide these and ensure that the civilian guards are properly
trained in their use. The CONTRACTOR shall also implement guidelines to control the
use of such equipment.
9. The CONTRACTOR shall conduct background investigation as part of its employment
screening process and shall maintain verifiable personnel record of all its security
guards to screen out those implicated in human rights violations.
10. The CONTRACTOR shall maintain the confidentiality of information obtained in the
course of performing its functions as a security service provider (where applicable)
within the limits allowed by law.
11. The CONTRACTOR shall establish a training program for the security guards to
include training in Voluntary Principles and First Aid.
12. The CONTRACTOR shall respect the human rights of the security guards and
implement documented measures to promote and protect the human rights of its
security guards.
7.3 The COMPANY may at its sole discretion, conduct audits and reviews of the
performance of the CONTRACTOR by using either its internal resources or engaging
the services of an independent external human rights organization to monitor
compliance with the Voluntary Principles standards and guidelines.
7.4 The COMPANY shall conduct compliance monitoring on a regular basis and upon
receipt of report of human rights violation and/or allegations of violations of these
Voluntary Principles, human rights and other illegal acts.
Page 19 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
Drafting Note to Contract Specialist / Contract Holder (THIS IS NOT PART OF THIS
CONTRACT AND NOT INTENDED FOR USE BY THE CONTRACTOR): Prior to signature by
COMPANY and CONTRACTOR of the final CONTRACT document, insert the CONTRACT
HSSE Interface Document, which identifies all STANDARDS for the Hazards identified in the
scope of SERVICES. The CONTRACT Hazard and Effects Register should be used to ensure
the CONTRACT HSSE Interface document is full and complete.
For further assistance with HSSE standard requirements not included in the General and Local
HSSE clause specification in section IV-A and B above, please check and contact the appropriate
Subject Matter Expert (SME List in appendix 4 attached) for guidance and assistance.
Page 20 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
Page 21 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
APPENDIX 2 – COMPANY LIFE-SAVING RULES
3: Verify isolation
before work begins and 4: Obtain authorisation
use the specified life before entering a confined
protecting equipment space
IF YOU VIOLATE ANY OF SEPLAT LIFE SAVING RULES, YOU HAVE CHOSEN NOT TO
WORK FOR SEPLAT
Page 22 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
Page 23 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
• Disrupts COMPANY operations in any way;
• Constitutes a risk to lives and property;
• Exhibits abusive, violent, threatening, bullying, offensive or menacing behaviour;
• Is suggestive of criminal, illegal or scandalous intentions or tendency.
CONTRACTOR shall promptly withdraw and remove from COMPANY PREMISES or WORK
SITE, all or any CONTRACTOR’S PERSONNEL who behave(s) in such unacceptable manner.
Where CONTRACTOR’S PERSONNEL misbehave, exhibit or fail to desist from any of the
conducts set out above, such misbehaviour or conduct shall be regarded as a default on the
part of the CONTRACTOR and COMPANY shall suspend or terminate the CONTRACT for
default and any of the costs which arises from such default shall be recoverable from the
CONTRACTOR under the CONTRACT. CONTRACTOR shall comply with this policy, which
now forms part of the CONTRACT.
Page 24 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
APPENDIX 5 - CONTRACTOR’S PERSONNEL COMPETENCE AND CAPABILITY
Page 25 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
APPENDIX 6 - CONTRACTOR HSSE REPORTING REQUIREMENTS
CONTRACT TITLE Contract Number
CONTRACTOR
CONTRACTOR
REPRESENTATIVE
Fatalities
Lost Time Injury
Work-Related Illness
Security Incidents
Safety Inductions
HSSE Inspections
Page 26 of 27
ANOH PROJECT PART 5C: SITE CIVIL CONSTRUCTION – MAJOR BUILDINGS
HSE
Contract Representatives
Evidence of
Service procedures
completion
HSSE induction
Driving License
Other Licenses
Medical Cert
Fire Warden
PPE issued
Inoculation
Onshore)
BOSIET
First Aid
PTW
Contracted Personnel Name Contact details
Contracted Personnel Name Contact details
HSSE Representatives
HSSE meeting
calendar
CONTRACTOR
Forum calendar
Page 27 of 27