Beruflich Dokumente
Kultur Dokumente
BETWEEN
Applicant (Appellant)
and
Guy Pratte, Nadia Effendi and Duncan Ault, for the respondent
On appeal from the judgment of Justice G. Patrick Smith of the Superior Court of
Justice, dated June 9, 2017, with reasons reported at 2017 ONSC 3560.
Laskin J.A.:
A. OVERVIEW
[1] This appeal concerns the interpretation of an agreement made in 1906 for
the construction of a bridge across the Kaministiquia River in Thunder Bay. The
parties to the agreement were the Town of Fort William, now amalgamated into
Page: 2
the appellant, the City of Thunder Bay, and the Grand Trunk Pacific Railway, now
[2] Grand Trunk Pacific built the Bridge, completing it in 1909. The Bridge is a
combined railway and roadway bridge: railway tracks run through the center; on
each side of the railway tracks is a single lane for vehicles; on each side of the
[3] The Bridge remained open for railway trains, cars, trucks, and people for
over 100 years. However, in 2013, CN briefly closed the Bridge because of a fire.
The fire caused only minor damage and CN reopened the Bridge three days later.
But it reopened the Bridge only for railway trains and pedestrians, not for motor
vehicles. It claimed that the Bridge could not safely be reopened for motor vehicles
because of the risk an “errant” or wayward vehicle would leave the roadway, go
across the sidewalk and into the river. In the over 100 year history of the Bridge,
[4] When CN refused to reopen the Bridge for vehicles, Thunder Bay brought
which Grand Trunk Pacific agreed to give Fort William “the perpetual right to cross
the said bridge for street railway, vehicle and foot traffic”; and s. 5, in which CN
[5] Before the application judge, Thunder Bay took the position CN is in breach
of its contractual obligation to keep the Bridge open perpetually for vehicles. CN
took the position that it could not do so safely without making significant structural
changes to the Bridge, which were beyond its obligation to “maintain” under s. 5 of
the Agreement. The application judge sided with CN. He made three findings:
The parties intended that CN would maintain the Bridge for the type of traffic
that existed at the time the 1906 Agreement was entered into: streetcars,
horse, and cart traffic, not motor vehicle traffic.
Thunder Bay had the onus to define clearly the relief it sought and the
changes needed to make the Bridge safe for motor vehicles, and it failed to
do so.
[6] On its appeal, Thunder Bay challenges these findings and contends that
they are tainted by legal error or are unreasonable. It submits the parties intended
that the citizens of Thunder Bay would have the perpetual right to cross the Bridge
by any kind of vehicle, and that, to enable them to do so, CN would have the
judge made no legal error, his findings are supported by the evidence, and so
appellate intervention is not warranted. As I view the appeal, it raises two broad
issues:
2. Did the application judge err in law by holding that Thunder Bay had the onus
to give the court a specific and detailed proposal to make the Bridge safe for
motor vehicles?
[7] I would answer the questions raised by these two issues as follows:
Bay to provide a proposal to make the Bridge safe for motor vehicles. CN
reopen the Bridge; it therefore has the onus to determine what maintenance
reopening.
Page: 5
[8] For any of the reasons given in answer to question 1, the application judge
erred in his interpretation of the 1906 Agreement. Under that Agreement, vehicle
traffic means any kind of vehicle traffic, including car and truck traffic. The parties
intended that Thunder Bay would have the right to cross the Bridge perpetually by
using any kind of vehicle, and that CN would be obliged to maintain the Bridge in
[9] I would allow the appeal, issue a declaration that CN breached the 1906
Agreement, and order CN to reopen the Bridge for motor vehicle traffic. What
[10] The application judge thoroughly reviewed the background giving rise to this
litigation. In my reasons, I will discuss only those facts necessary to resolve the
issues on the appeal. To put these issues in context, I will first discuss the 1905
Agreement, which preceded and gave rise to the 1906 Agreement. Then I will
discuss the terms of the 1906 Agreement, and describe the Bridge itself.
[11] At the turn of the 20th century, railways were being built to provide access to
the various parts of our vast country. The National Transcontinental Railway was
built to run from Moncton all the way to Winnipeg. Grand Trunk Pacific had already
Page: 6
built a line running from Winnipeg, across the Prairies, to Prince Rupert, British
Columbia.
[12] Grand Trunk Pacific also wanted to build a branch line to connect the
National Transcontinental Railway with Lake Superior. It chose Fort William as the
terminal port. The Lake Superior branch line would allow Grand Trunk Pacific to
carry grain from the Prairies to Fort William, for shipment by boat to Southern
[13] In 1905, Grand Trunk Pacific and Fort William entered into an agreement for
the construction of the Lake Superior branch line. Under this 1905 Agreement, Fort
William agreed to pay Grand Trunk Pacific $300,000 “for lands, docks, yards,
The Lake Superior branch line brought benefits to both parties – Grand Trunk
Pacific increased the profitability of its operations; and Fort William gained social
Town.
[14] In order for its Lake Superior branch line to be effective, Grand Trunk Pacific
had to build a railway bridge over the Kaministiquia River. The 1905 Agreement
did not provide for the building of a railway bridge over the river. But s. 6 of the
Agreement gave Grand Trunk Pacific an option to build a bridge for railway traffic.
If Grand Trunk built this bridge, Fort William agreed to pay it $50,000, and in return,
Page: 7
its citizens would have the perpetual right to cross the bridge by street railway,
[15] In 1906, Grand Trunk Pacific exercised its option under s. 6 of the 1905
Agreement, and entered into the 1906 Agreement with Fort William. In s. 1, Grand
Trunk Pacific agreed to build a “combined railway and highway bridge”, and in s.
6 Fort William agreed to pay $50,000 when the bridge was completed.
[16] Sections 3 and 5 are the key provisions of the 1906 Agreement. Under s. 3,
Grand Trunk Pacific agreed to give the citizens of Fort William the “perpetual right”
to cross the Bridge for street railway, vehicle, and foot traffic:
[17] Section 5 is ancillary to s. 3. To ensure that Fort William had the “perpetual
right” to cross the bridge, Grand Trunk Pacific agreed to “maintain the Bridge in
[18] Grand Trunk Pacific completed construction of the Bridge in 1909 at a cost
[19] In this court, CN suggested that the Bridge was, in fact, two separate
bridges: a railway bridge and a “roadway bridge”. The 1906 Agreement says
otherwise. It provides for one Bridge, “a combined railway and roadway bridge”.
[20] Most of Thunder Bay lies to the north of the Bridge; the Fort William First
Nation lies to the south. The Bridge is known as the James Street Swing Bridge. It
was originally designed to be a swing bridge to allow shipping on the river, but it is
[21] CN and its predecessors have used the Bridge continuously for railway
traffic. But the use of the roadway portion of the Bridge has changed over time.
Although the Bridge continued to be used by pedestrians and vehicles until the
Page: 9
2013 fire, after 1950 the roads were no longer used for street railway. Instead they
were used exclusively for vehicular traffic. Up until 1968, the route over the Bridge
was part of a major provincial highway, providing access to the city and to the Fort
William First Nation. That year, however, the Lakehead Express (Highway 61)
opened and the route over the Bridge became a minor arterial road.
[22] Still, the road over the Bridge remains a vital thoroughfare for the people of
Thunder Bay and the Fort William First Nation. Its importance is borne out by traffic
statistics, which show that in 2007 (the last year for which statistics are available)
an average of 8,871 vehicles traversed the Bridge every day. Now that the Bridge
is closed to cars and trucks, the only practical vehicle access for vehicles going to
Fort William First Nation is along Highway 61, a ten kilometre detour.
[23] The Bridge itself is around 150 metres long. As I have said, the railway tracks
run along the middle of the Bridge. The two driving lanes – one on either side of
the railway tracks – are cantilevered on the outside of steel trusses, and rely on
the railway structure for support. Wooden railings run between the railway tracks
and the roadways. Wooden timbers on the wood deck on each side of the
roadways form roughly six by six inch curbs. Although the pedestrian sidewalks
are not separated from the roadways by a railing, they are raised from the
roadways by the height of these wooden curbs, six inches. The sidewalks are
between 1 metre and 1.7 metres wide, and have railings on the outside.
Page: 10
[24] The Bridge is structurally sound and can carry a heavier load than that
required of a modern bridge. But each of the two driving lanes is narrow, 2.85
metres wide, which is 15 centimetres less than the minimum 3 metres required
under current bridge design standards. To alleviate any safety concerns, the speed
limit on the Bridge has been reduced from 40 kilometres per hour to 20 kilometres
[25] Over the years, CN has made numerous repairs and upgrades to the Bridge,
including a major overhaul between 1984 and 1985. These repairs and upgrades
are itemized at para. 70 of the application judge’s reasons. Still, the expert
evidence called on the application suggests that the sidewalks are too weak to
support a vehicle that leaves the roadway, and in the absence of crashworthy
barriers, a wayward vehicle might go in the river. No vehicle has done so for the
C. THE ISSUES
[26] The application judge gave thorough reasons for his decision, 30 single
space pages. But his analysis of how he interpreted the 1906 Agreement is
[27] The standard for appellate review of a trial judge’s interpretation of a contract
such as the 1906 Agreement, which is not a standard form contract, is now well
mixed fact and law: the application of the legal principles for interpreting a contract
to the words of the contract and the context in which those words were used. A
trial judge’s interpretation, like any finding on a question of mixed fact and law, is
process of interpretation. And the Supreme Court of Canada has said “courts
contractual interpretation”: see H.L. v. Canada (Attorney General), 2005 SCC 25,
[2005] 1 S.C.R. 401, at paras. 4, 55-56, and 69-71; Sattva Capital Corp. v. Creston
Moly Corp., 2014 SCC 53, [2014] 2 S.C.R. 633, at para. 54; and Teal Cedar
Products Ltd. v. British Columbia, 2017 SCC 32, [2017] 1 S.C.R. 688, at para. 45.
[28] Thunder Bay submits that the application judge’s finding that the parties
intended to maintain the Bridge solely for the type of traffic that existed in 1906
both reflects extricable errors of law and is unreasonable. CN submits that the
the evidence, reveals no error of law, and thus appellate intervention is not
warranted.
[29] In my view, the application judge’s finding that the parties intended to
maintain the Bridge only for streetcar, horse, and cart traffic – in other words, the
vehicle traffic that existed in 1906 – is both unreasonable and is tainted by two
extricable errors of law, the first more important than the second. In summary:
[30] The principles of contract interpretation are also well established. They were
2007 ONCA 59, 85 O.R. (3d) 616, by Winkler C.J.O. in Salah v. Timothy’s Coffees
of the Worlds Inc., 2010 ONCA 673, 268 O.A.C. 279, and recently by Brown J.A.
1007, 13 C.E.L.R. (4th) 28. The overriding principle is that the meaning of an
agreement and the intent of the parties in entering into it must be derived from the
words the parties used and the context in which they used those words. In
Dumbrell, at paras. 52 and 53, Doherty J.A. quoted an important paragraph from
Professor Swan’s text on contract law, and then concisely summarized the
[31] In this case, the central debate was over the meaning of the words “vehicle
traffic” or “vehicular traffic” in the 1906 Agreement, and the parties’ intent in using
these words. The application judge interpreted the words narrowly to mean only
the vehicle traffic that existed in 1906 – streetcars, horses, and carts. CN asks this
court to uphold his interpretation. Thunder Bay argues for a broad meaning and
submits that the parties intended vehicle or vehicular traffic to include any kind of
vehicle, including the vehicles that now almost exclusively use the Bridge: cars and
[32] I begin with the words of the 1906 Agreement. Under it, the citizens of
Thunder Bay have the right to cross the Bridge by vehicle traffic, and CN has the
Page: 15
obligation to maintain the Bridge for vehicular traffic. The Agreement does not
define vehicle or vehicular traffic, nor does it limit vehicle traffic to carts and horses;
instead the phrases vehicle traffic and vehicular traffic are open ended. And the
right and obligation are not time limited; instead they are said to be perpetual or
last in perpetuity. Inevitably, the way people get from point A to point B will change
over time, as indeed did the way the citizens of Thunder Bay have used the Bridge.
The text alone of the 1906 Agreement is inconsistent with the application judge’s
narrow interpretation, which freezes vehicle traffic to the vehicle traffic used to
[33] The full context in which the 1906 Agreement was signed unquestionably
supports the broad interpretation of vehicle traffic put forward by Thunder Bay. The
application judge referred to much of this context early in his reasons but did not
seem to consider it at all when, later in his reasons, he made his finding on the
unsupported.
vehicle or vehicular traffic in the 1906 Agreement: the purpose of both the 1905
and the 1906 Agreements; the reasonable expectations of the parties in entering
into the 1906 Agreement; and the coming of the automobile era. Each of these
considerations was known or reasonably capable of being known at the time. Even
apart from the words of the Agreement, by failing to take these contextual
Page: 16
considerations into account, the application judge made a finding on the parties’
intent that was unreasonable and that justifies the intervention of this court.
consideration: see Dumbrell, at para. 55. Here, in my view, the purpose of the 1906
Agreement has to be looked at together with the purpose of the 1905 Agreement
judge made a “core finding” that the two Agreements were distinct. At para. 65 of
his reasons, the application judge did say that the two Agreements “are separate
and distinct” because the 1905 Agreement gave no contractual rights or imposed
any obligations concerning the Bridge. Literally, the application judge was correct.
But commercially these two agreements, made one year apart, were intertwined:
the 1905 Agreement included a clause that gave Grand Truck Pacific the option to
construct the Bridge, which, when exercised, gave rise to both the 1906 Agreement
[36] And five paragraphs earlier in his reasons, at para. 60, when considering
their purpose, the application judge sensibly viewed the two Agreements together.
He found that the Agreements were intended to promote long term growth and
[37] The application judge’s finding about an expected larger population was
supported by the statistics. Between 1902 and 1906 the population of Fort William
more than doubled from 4,799 to 10,032. By the time the Bridge was built in 1909,
the population had nearly doubled again to 18,003. Yet the application judge’s
overall finding on the purpose of the Agreements sits uncomfortably with his later
important contextual consideration. Both parties expected great gains from these
the paragraph of his reasons just quoted above. More specifically, Grand Trunk
rail to water transport at Fort Williams. In turn, Fort William was expected to be “the
Page: 18
greatest port on the lakes”, offering “great promise for the future”, and expecting
[39] The application judge made a key finding at para. 61 of his reasons about
[40] That finding echoes the language of the 1906 Agreement, in which the right
to use the Bridge and the obligation to maintain it are to be in perpetuity. But this
finding is quite inconsistent with the application judge’s narrow interpretation of the
1906 Agreement. It makes little sense to acknowledge on one hand that the parties
expected a long term increase in growth, industrial activity, and population, and
expected the Bridge to be used “for many years”, while concluding on the other
hand that the Bridge was only to be maintained for what amounts to horse and
buggy carriage. This inconsistency is even more glaring when the third contextual
[41] CN seeks to support the application judge’s finding on the parties’ intent in
two ways: by relying on the motion passed by the Municipal Council of Fort William
authorizing the 1906 Agreement; and by relying on the near absence of cars and
[42] Fort William Council did pass an authorizing motion, and the motion said
that the roadways should “be sufficient to accommodate streetcar, horse traffic and
foot traffic”. The motion is a piece of extrinsic or external evidence, which might
reveal Fort Williams’ “subjective intention” in entering into the 1906 Agreement.
But extrinsic evidence of a party’s subjective intent in entering into a contract has
no place in contract interpretation for at least two reasons: first, resort to a party’s
contract; and second, the parties may not have a common subjective intention
because one party’s subjective intention may not be shared by the other party: see
Dumbrell at para. 50. Thus, the parties’ intent and the meaning of their contract
must be ascertained by looking at the actual words they used and the context in
which they used them, but not by their subjective intention in using them.
[43] CN is on firmer ground in relying on the near absence of cars and trucks
when the 1906 Agreement was made. This near absence was relied on by the
application judge. Back then, streetcars, horses, and carts were the predominant
means of vehicle travel. But, as I have said, the meaning of vehicle traffic was not
so limited in the Agreement itself; it was unlimited. And Thunder Bay’s citizens had
the right to cross the Bridge by vehicle not for just a few years, but well into the
future, in fact perpetually. Back in 1906, the parties can reasonably have been
taken to know that soon, not even many years in the future, automobiles would
[44] Indeed, even earlier, in 1887, in its official report, the Ontario authority
responsible for roads had observed: “[M]otor carriages may be seen on the streets
of the larger cities, and present indications are that they will soon become an
had already passed the second version of the An Act to regulate Speed of
[45] Though admittedly with the benefit of now knowing the pervasive use of cars
and trucks in our society, I cannot conceive why we should limit the meaning of
vehicle traffic on the roadways of the Bridge to carts and horses. I regard the
application judge’s finding on the parties’ intent in entering into the 1906
the first issue. But I would also allow the appeal for a second and related reason:
the application judge’s failure to give any effect to the words “perpetual” and “in
perpetuity”.
[46] Another important principle of contract interpretation is that the court should
interpret the contract as a whole, and avoid an interpretation that does not give
effect to all of its terms or that renders one or more of its terms ineffective. A failure
to apply this principle is an error of law: see Salah, at para. 16; and Teal Cedar, at
Page: 21
para. 44. Thunder Bay submits that in interpreting the 1906 Agreement, the
application judge failed to apply this principle because he failed to give effect to
the important words “perpetual” and “in perpetuity” in the 1906 Agreement. He
submission.
[47] Grand Trunk Pacific received what it bargained for in the 1906 Agreement:
a bridge over the river for its rail traffic. That Bridge was important to its operation
of the Lake Superior branch line. And CN continues to use the Bridge for its rail
[48] In exchange, the fundamental right Fort William bargained for in the 1906
Agreement was the right of its citizens to cross the Bridge perpetually, either by
using their vehicles or on foot. To ensure that this right was protected, CN was
[49] Early in his reasons, the application judge recognized two critical points: first,
terminated unilaterally; and second, the 1906 Agreement does not have an expiry
date or a provision giving either party a right to terminate its obligations. To these
two points, I would add a third: the words of the Agreement do not in any way
said, the word “vehicle” is not defined or limited to any particular kind of vehicle.
Page: 22
[50] When, however, the application judge came to interpret the 1906
Agreement, he failed to take into account the points he had made earlier: that the
right of the people of Thunder Bay to use their vehicles to cross the bridge did not
expire, but continued perpetually, in other words permanently or forever; and that
[51] In 1906, motor vehicle traffic was admittedly limited in this province. But it
was increasing, and was being regulated. As I have already suggested, back in
1906, it would not have taken much imagination to realize that in the future, cars
and trucks would become a far more common way than horses and carts to get
from one place to another. Yet, on the application judge’s finding, the use of the
Bridge for vehicular traffic was to be static, frozen in time, limited to the traffic that
then mainly existed: streetcars, horses, and carts. That finding gives no effect
whatsoever to the right of the people of Thunder Bay to use the Bridge for their
[52] CN’s answer to Thunder Bay’s submission is essentially twofold. Its first
answer is that interpreting the 1906 Agreement to give a perpetual right to cross
the Bridge when Fort William paid only $50,000 produces a “commercial
absurdity”. I do not accept this argument. The words of the Agreement are clear.
The right to cross and the obligation to maintain are to continue in perpetuity.
$50,000 in 1906 dollars is what the parties agreed to. Grand Trunk Pacific got its
Page: 23
rail crossing; Fort William got its perpetual right to cross the Bridge by vehicles or
[53] CN’s second and main answer focuses on its obligation to maintain. CN
draws a distinction between maintaining the Bridge and making structural changes
to the Bridge. The former, it says, is its obligation under the Agreement; the latter
is not. Then, drawing on the expert evidence it led before the application judge,
CN contends that making the Bridge safe for cars and trucks would require
structural changes to the Bridge, changes that exceed its maintenance obligation.
[54] The jurisprudence lends some support to the distinction CN has drawn. As
[55] This maintenance obligation is limited. On some of the authorities it does not
include changing the structure of a bridge, making it, for example, stronger or more
durable: see Attorney General v. Great Northern Rail Co., [1916-17] All. E.R. Rep.
[56] But I view the distinction between maintenance and structural changes to be
the position that the many repairs and upgrades it has made to the Bridge over the
Page: 24
years were matters of maintenance, not structural changes. Yet those repairs and
upgrades, all falling within CN’s maintenance obligation, have been sufficient to
allow cars and trucks to drive safely across the Bridge. The “errant” vehicle CN
risk free. But the risk of an errant vehicle going into the river must be minimal with
three speed bumps and a speed limit of 20 kilometres per hour on the Bridge. One
might have thought that, having repaired the minor damage caused by the fire, CN
could simply have reopened the Bridge, and maintained it for vehicular traffic as it
and its predecessors have done, without incident, for over 100 years.
[57] Even more significant, the distinction CN draws between its maintenance
proceedings. CN’s argument that the Bridge cannot be reopened safely for
vehicular traffic without altering the structure of the Bridge is, in substance, an
argument that it should be relieved of its contractual obligation under the 1906
Agreement to maintain the Bridge. CN sought this very relief even before Thunder
Bay started its application. However, its action for an order that it not be required
to reopen the roadway portion of the Bridge was stayed by the order of Fregeau
J.: see Thunder Bay (City) v. CN Rail, 2016 ONSC 469, 49 M.P.L.R. (5th) 148.
[58] Faced with a stay, CN still seeks in this proceeding to avoid what is
otherwise a clear breach of its contractual obligation by claiming it cannot open the
Bridge safely for vehicles unless it exceeds its maintenance obligation. In other
Page: 25
directly.
[59] But as Thunder Bay has pointed out, CN’s position is tantamount to relying
show that the 1906 Agreement, at least for vehicle traffic, has become “incapable
proceeding, especially in this court. The application judge made no finding that the
1906 Agreement was at an end, nor could he. He did not even make a finding that
comply with the 1906 Agreement and reopen the Bridge for cars and trucks.
[60] Because the application judge committed an extricable error of law by failing
to give effect to all the terms of the 1906 Agreement, he adopted an interpretation
of the parties’ intent not supported by the text of the document. The right to cross
the Bridge perpetually, and the obligation to maintain the Bridge in perpetuity, can
only mean that the parties intended the Bridge to be open for any kind of vehicle,
[61] In addition to what I have already discussed, the trial judge made a second
interpretation on the subsequent conduct of the parties, even though the text of the
1906 Agreement was not ambiguous. This error also warrants appellate
intervention.
[62] In his interpretation of the 1906 Agreement, the application judge said that
he took into account the subsequent conduct of the parties. The rationale for
that “it may be helpful in showing what meaning the parties attached to the
document after its execution, and this in turn may suggest that they took the same
view at an earlier date”: see S.M. Waddam’s, The Law of Contracts, 3rd ed
(Toronto: Canada Law Book, 1993), para. 323; and Montreal Trust Co. of Canada
at the time they entered into an agreement. The dangers of reliance on the parties’
Blackmont Inc., 2016 ONCA 912, 404 D.L.R. (4th) 512, at paras. 39-46. Because
only if the contract remains ambiguous after considering its text and its factual
matrix”.
Page: 27
[64] Even if admitted to resolve ambiguity in the parties’ intent when they entered
into an agreement, the cogency or reliability of the evidence will vary depending
[65] In the present case, although the application judge said that “it is difficult to
ascertain the intention of the parties at the time they signed the 1906 agreement”,
he made no express finding that the meaning of the Agreement was ambiguous.
If its meaning and the parties’ intent were not ambiguous, as in my view they were
not, then the application judge made an extricable error of law in relying on the
[66] If, however, the meaning of the 1906 Agreement was ambiguous, the
application judge failed to consider the relevant subsequent conduct of the parties.
The only subsequent conduct he seemed to consider was CN’s “consistent view
the structural changes to the Bridge were beyond the scope of its contractual
obligation”. CN’s own view of how it categorized its work of repairing and upgrading
Page: 28
the Bridge hardly deserves much weight. Its views are not the acts of both parties,
and furthermore are the views of the corporation, not of the individuals who carried
[67] At best, CN’s view of the work it did could shed some light on the question
changes to the Bridge to ensure its safe operation. For the reasons I have already
proceedings. Even so, CN’s views of its maintenance obligation combined with the
undisputed fact that not a single vehicle has ever gone into the river, show that CN
can comply with the 1906 Agreement and still ensure the safety of motor vehicle
[68] Moreover, if any relevant ambiguity exists in the meaning of the 1906
Agreement, that ambiguity relates not to the scope of CN’s maintenance obligation,
but to the meaning of vehicle traffic. Does it mean only vehicles that mainly existed
in 1906, streetcars, horses, and carts? Or does it also includes cars and trucks?
operation of the roadways on the Bridge for the exclusive use of cars and trucks
supports Thunder Bay’s position that vehicle traffic in the 1906 Agreement was
meant to include the advent of motor vehicle traffic. CN’s subsequent conduct has
reliable indicator that under the 1906 Agreement motor vehicle traffic, as well as
streetcars, carts, and horses, would have the perpetual right to cross the Bridge,
and CN would have the perpetual obligation to maintain the Bridge for that
purpose.
[69] For these reasons, I conclude that the application judge erred in his
interpretation of the 1906 Agreement. Under the Agreement cars and trucks have
a perpetual right to cross the Bridge, and to ensure that right is preserved, CN has
terminate its obligation CN would have to seek a court order that its obligation to
(2) Did the application judge err in law by holding that Thunder Bay had
the onus to give the court a specific and detailed proposal to make
the Bridge safe for motor vehicles?
[70] The application judge found that under the 1906 Agreement, CN was only
obliged to maintain the Bridge for the vehicle traffic existing at the time. His finding
seems to suggest that CN has no obligation to maintain the Bridge for cars and
trucks, even though CN has done so since motor vehicles started crossing the
Bridge.
[71] Yet the application judge went on to consider whether the Bridge could be
made safe for motor vehicles, implicitly suggesting that if he was satisfied that it
could, he would grant the relief Thunder Bay sought. But he held that Thunder Bay
Page: 30
had the onus to provide him with a specific and detailed proposal for the changes
needed to make the Bridge safe for motor vehicles, and further that Thunder Bay
failed to meet its onus. Thus, he dismissed Thunder Bay’s application. He wrote at
He also held that Thunder Bay’s pleading was deficient and could not support the
relief it requested.
[72] Thunder Bay submits that the application judge erred in placing the onus on
it to show how the Bridge could be made safe for cars and trucks and that
misplacing the onus is an error of law. CN submits that the application judge
correctly placed the onus on Thunder Bay, as the City was asking for what
Page: 31
amounted to an order for specific performance, and any order for specific
[73] I agree with Thunder Bay’s submission. Thunder Bay was entitled to two
heads of relief: a declaration that by refusing to reopen the Bridge for motor
vehicles, CN had breached the 1906 Agreement; and an order that CN reopen and
maintain the Bridge for motor vehicle traffic. It had no onus to show the court how
the Bridge could be reopened safely for motor vehicles. If the onus lay anywhere,
it lay with CN, which maintains over 7,000 bridges across Canada, and which
under its Bridge Maintenance Program, is required to ensure the safe operation of
[74] On the application, each side provided expert evidence from three
judge. The experts on both sides agreed that, though the Bridge is structurally
sound, the pedestrian walkways cannot support the weight of a wayward vehicle
and the existing curbs and railings would not prevent a wayward vehicle from going
[75] CN’s experts gave the opinion, implicitly accepted by the application judge,
that the risk of an errant vehicle going into the river was sufficiently high to warrant
closing the Bridge to vehicular traffic until this risk could be addressed by
as I have said, CN contends that structural changes are beyond its maintenance
[76] I question the credibility of CN’s expert opinion. Since the Bridge’s inception,
CN has maintained it for all types of vehicular traffic, and for nearly 70 years
exclusively for motor vehicle traffic. In all this time, CN never claimed that the
Bridge posed a safety hazard. It has not claimed that the fire in 2013, which caused
only minor damage, in any way damaged the roadways over the Bridge or impaired
their safety. And yet not once has a car or truck gone off either roadway and into
the river. Somehow, a Bridge that was seemingly entirely safe for motor vehicle
traffic up until the time of the fire – and especially so after the speed limit was
reduced and speed bumps were installed – has now become unsafe and cannot
be reopened unless the Bridge is structurally altered. I find it hard to fathom how
CN can claim that a safety hazard now exists and can only be alleviated by
[77] But neither the credibility nor the reliability of the expert evidence needs to
The citizens of Thunder Bay had a contractual right to cross the Bridge by motor
vehicle and CN has a contractual obligation to maintain the Bridge for that purpose
in perpetuity. By refusing to reopen the Bridge to cars and trucks, CN has breached
the 1906 Agreement. To rectify the breach, it must reopen the Bridge and maintain
Page: 33
the roadways for motor vehicle traffic. How it chooses to do so is for it to decide.
CN, not Thunder Bay, is the expert in bridge maintenance. As I have said, it
maintains over 7,000 bridges. The Bridge Maintenance Program, referred to by the
application judge early in his reasons, but not in his analysis, governs its
[78] That program, mandated by the Railway Safety Act, R.S.C., 1985, c. 32 (4th
Supp.) and Transport Canada, takes precedence over any agreement. Under it,
CN assumes responsibility for the condition of bridges over which CN and other
railway companies operate trains. CN has admitted that its Bridge Maintenance
Program applies to this Bridge, and not just to the railway tracks but as well to the
admitted that because a bridge does not comply with modern design standards,
as this Bridge does not, is not a reason to close a bridge. Under the Bridge
standards. It does so by making any repairs and upgrades needed to mitigate any
safety risk from outdated designs. If any doubt exists about onus, the Bridge
[79] Through its experts, Thunder Bay did put forward at least one suggestion
for how to alleviate the safety concerns raised by CN’s experts. But it had no
obligation to do so. It is entitled simply to an order that CN reopen the Bridge for
cars and trucks and maintain it in accordance with its contractual obligation under
Page: 34
the 1906 Agreement. To repeat what I said earlier, at bottom, CN wants this court
to relieve it of its contractual obligation on the premise that the Bridge cannot be
used safely by cars and trucks without structural changes, which are beyond CN’s
maintenance obligation. I doubt the validity of the premise of CN’s request. But
whether valid or not, the relief underlying it was not sought by CN in this litigation,
nor ordered by the application judge, and is precluded by the 2016 stay order of
Fregeau J.
D. CONCLUSION
[80] I would allow the appeal, set aside the order of the application judge and in
its place:
b) Order CN to reopen the Bridge for vehicle traffic and maintain the Bridge in
accordance with the 1906 Agreement.
[81] Thunder Bay is entitled to its costs of the appeal and the application in the