Beruflich Dokumente
Kultur Dokumente
Table of Contents
GKW - Alliance ER / i
EMPLOYER’S REQUIREMENTS-FIN
GKW - Alliance ER / ii
EMPLOYER’S REQUIREMENTS-FIN
Figures
Figure 1-1Site locations ............................................................................................... 1-9
Figure 3-1 Outline Schedule (Phase 1a and Scenarios for Phase 1b) ..................... 3-14
GKW - Alliance ER / iv
EMPLOYER’S REQUIREMENTS-FIN
Figure 4-1 Overview Flow Chart of the Katosi DWTP Project .................................. 4-40
Figure 4-2 Option DWPM ND 1,400 mm ................................................................... 4-40
Tables
APPENDICES
APPENDIX D: FURNITURES
GKW - Alliance ER / v
EMPLOYER’S REQUIREMENTS-FIN
LIST OF ABREVIATIONS
GKW - Alliance ER / vi
1. INTRODUCTION
1.1 General
The Employer's Requirements presented herein define the location of the Site and the Works,
specify the purpose of the Works and particular requirements for the completed Works, including
functional requirements, quality, performance and scope, requirements for the supply of certain
items (such as consumables), special obligations and other details generally in accordance with
the Conditions of Contract for Plant and Design Build, First Edition 1999, published by FIDIC.
The technical Specifications are deemed to form and shall be construed as an integral part of the
Employer's Requirements.
1.4 Beneficiary
National Water and Sewerage Corporation (NWSC) was established in 1972 as a Government
Parastatal with the role of developing, operating and maintaining water supply and sewerage
services in urban areas of Uganda. NWSC falls under the Ministry of Water and Environment,
and currently operates in 165 towns in Uganda.
1-7
EMPLOYER’S REQUIREMENTS-FIN
NWSC operates under three year renewable Performance Contracts with the Government of
Uganda, which define the activities, objectives and indicators to be achieved within the 3-year
contract period.
1-8
EMPLOYER’S REQUIREMENTS-FIN
1-9
EMPLOYER’S REQUIREMENTS-FIN
Administration’s proposal. The information is not warranted by the Employer, and the Contractor
shall make use of and interpret the same on his own responsibility.
1.6.3 Climate
Endowed with an equatorial climate, the Project Area enjoys plenty of rain of above 1100 mm
per year and sunshine moderated by the relatively high altitude of ranging from 1136 to more
than 1300 masl.
The area around Katosi has a tropical rainforest climate. Rainfall is spread all over the year
however with two annual wet seasons. There is a long rainy season from August to December
and a short rainy season from February to June. However, the shorter rainy season sees
substantially heavier rainfall per month, with April typically seeing the heaviest amount of
precipitation at an average of around 169 millimetres of rain.
The mean annual temperature ranges from 17°C to 26°C with the highest temperatures of up to
36°C in January and February.
Detailed information concerning ambient temperature, relative humidity rainfall and wind speed
and direction is available from the Meteorological Services in Entebbe. The information given
herein is to assist the Contractor at the time of tendering. Such information shall be deemed to
be information provided on behalf of the Employer. The information is not warranted by the
Employer or the Employer's Representative and the Contractor shall make use of and interpret
the same as his own responsibility.
1-10
EMPLOYER’S REQUIREMENTS-FIN
2-11
EMPLOYER’S REQUIREMENTS-FIN
calculations and drawings for all structures, process and instrumentation diagrams,
electrical single lines diagrams and plant/machinery/electrical drawings.
• To supply all materials required for construction of the works. This may include
manufacture, collection, transportation and delivery to site. The Contractor will be
responsible for ensuring that all procedures are adequately covered and that the
materials fully conform to the contract requirements. These responsibilities will include all
necessary charges or duties related to insurance, freight, taxes (including customs and
excise duties, surcharges, etc.), and all testing and inspections for quality control.
• To provide all necessary staff (including designers, administrators, site supervision
personnel) and workmen (including all necessary specialists, operators, tradesmen,
artisans, etc., in addition to semi-skilled and unskilled workers) necessary for execution
of the works, up to completion. The Contractor shall provide all suitable facilities and
accommodation for the staff and workmen, and he shall make provision for all costs
related to such provisions and for medical, re-location, taxes or other expenses.
• To provide all equipment, machinery, tools, etc., and related spares, maintenance and
consumables necessary for implementation of the works.
• To provide all site offices, stores, workshops and facilities necessary for use by the
Employer, Employer’s Personnel and support staff, and for the Contractor himself and his
support staff.
• To undertake all operations necessary to construct the Works. These operations shall
include installation of main treatment units, blowers and compressors, chemical dosing
equipment, associated pipework, main pump/motor sets, all pipework, all cranes and
hoists, drainage systems, surge protection systems, pressure relief or control valves,
cooling water systems, as well as electrical plant and instrumentation and control
equipment, etc., and construction of all related concrete or other works, together with all
testing, commissioning and operation of the works as required.
• To commission equipment, start-up and trial-operate the plant for a period of three
months. During these period the Employer’s personnel has to be trained on the plant in
order to put them in the position to run the facilities later-on.
• To liaise with other Contractors on the site and to ensure harmonious co-operation with
them so that conflicts are avoided and areas of common interest, constructional interface
or potential overlaps are addressed without cost to the Employer or delays in completion.
• To prepare documentary records of the Works in the form of “as-built” drawings,
schedules, etc. and to produce Manuals for Operation and Maintenance of the Works.
• A Quality Assurance Procedure shall be implemented in accordance with Clause 4.9 of
the Conditions of Contract.
All the above works shall be performed in a professional way and with good engineering or
constructional practice. Upon completion of the works the scheme shall be fully operational with
minimum disruption or inconvenience to interested parties, including landowners, and there shall
be no outstanding matters requiring attention.
2-12
EMPLOYER’S REQUIREMENTS-FIN
3-13
EMPLOYER’S REQUIREMENTS-FIN
Figure 3-1 Outline Schedule (Phase 1a and Scenarios for Phase 1b)
Design Period Construction Period Defects Notifcation Period Possible Time Extensions
Phases
Testing
Project Months 3 6 9 12 15 18 21 24 27 30 33 36 39 42 45 48 51 54 57
1a Measures
3-14
EMPLOYER’S REQUIREMENTS-FIN
3.2 Insurances
The Contractor shall provide insurances, as shown below, by an insurance company registered
in the Republic of Uganda.
3-15
EMPLOYER’S REQUIREMENTS-FIN
In particular insurances for Employer’s and Engineer’s personnel, and the means of transport
(vehicles and boat), which will be provided by the Contractor and used by Employer’s and
Engineer’s personnel during the implementation period.
3.6 Environmental, Social, Health and Safety Management Site and Action Plan
The Employer has prepared an ESIA and Environmental and Social Management Plan (ESMP).
Prior to start of construction the Contractor has to prepare and submit his Environmental, Social,
Health and Safety Management Plan (ESMP) / Environmental and Social Site and Action Plan
(ESHS). This document has to be followed-up during the whole construction period and shall be
updated regularly on a quarterly basis.
3-16
EMPLOYER’S REQUIREMENTS-FIN
All drawings shall be in the form of black lines on a white background and shall bear the
following information within the title block and such other information as is required to be shown
to comply with the Quality Assurance requirements:
• Client:
• Contract Title:
• Project No:
• Drawing Title:
• Scale:
• Date:
• Drawing Number:
All drawings, shall be listed on a schedule and the schedule sub-divided into parts, i.e. process,
hydraulic, architectural, structural, building installation, mechanical and electrical.
All layout and arrangement drawings shall be to scale and shall include a graphical scale. All
dimensions shall be given in SI units. Drawings shall not exceed A1 format. All line thicknesses,
text height and text style shall comply with ISO standards. Calculations and other documentation
shall include a cover page giving at least the same information as required to be shown on the
drawings.
3-17
EMPLOYER’S REQUIREMENTS-FIN
3-18
EMPLOYER’S REQUIREMENTS-FIN
measures, and any other information required to clearly detail the proposed methods. The
statement shall be supported by sketches, diagrams or other supportive detail to enable a clear
understanding of the method and significance of each step of the operation or work. No work
shall be carried out until a method statement has been submitted to and approved by the
Engineer.
The Method Statement shall be submitted at least 28 days before commencement of the
proposed operation or work.
Any product or substance used by the Contractor or its Subcontractors, which is toxic or
hazardous shall be identified to the Engineer by the Contractor’s submission of a Material Safety
Data Sheet and in accordance with the ESHS proposed management and action plan.
3-19
EMPLOYER’S REQUIREMENTS-FIN
The manual shall be updated and complemented continuously, during the Commissioning and
Testing, as well as during the DNP. Prior to the end of the DNP the final O&M manual shall be
elaborated and submitted to the Engineer for approval.
3-20
EMPLOYER’S REQUIREMENTS-FIN
• Training needs;
• Job descriptions;
• Any particular requirements of the Authority responsible for the plant operation.
3-21
EMPLOYER’S REQUIREMENTS-FIN
Plan (SEPP)
7 Preliminary Design 3+1 Commencement date + 2 months
8 Draft Detailed Design 3+1 Commencement date + 4 months
9 Progress Reports 3+1 Monthly
10 Material approval, Method 2+1 28 days prior to execution
Statements, Shop drawings
11 Draft O&M Manual 3+1 21 days before substantial
completion
12 Plan for the commissioning 3+1 3 months before substantial
period completion
13 Financing Plan for O&M 3+1 21 days before substantial
Period completion
14 Training Plan + Contractor’s 3+1 6 months before substantial
staffing plan for the plant completion
15 Draft As-Built Drawings 3+1 21 days before substantial
completion
3-22
EMPLOYER’S REQUIREMENTS-FIN
The design and constructions shall follow stages. The definition of phases is shown in the
Administration’s proposal and described in the following chapters.
Contractor’s design shall include the detailed designs for Phase 1a and Phase 1b, for
construction purposes. All facilities, which will be required for Phase 2 shall be included in the
conceptual design, in order to define space requirements for future extensions. Where future
units are shown, provision must be made for easy connections. Distribution chambers and
similar structures shall be designed to allow for the connection of future units.
The Contractor shall design and construct the WTP to fit within the site boundary shown on the
general arrangement drawing of the Administration’s proposal. Within the limit of the WTP and
reservoir site boundaries, the Contractor is free to design, position and size the various elements
of the project facilities, as the Contractor considers best, but only to the extent that they comply
with the requirements set out in the Employer's Requirements and other relevant documents,
e.g. the Specifications.
The Contractor's design shall take the process solutions used in the conceptual design as a
guideline. If standby equipment has been designed in the Admin’s Proposal, it is mandatory for
the Contractor to reflect this in his design. Also, similar levels of redundancy shall be reached in
any alternative design.
The WTP shall be designed and constructed so that individual elements of the WTP such as
tanks, chambers, etc. can be isolated from the flows without affecting the overall operation of the
works. Furthermore, the WTP shall be designed for maximum flexibility of operation.
4-23
EMPLOYER’S REQUIREMENTS-FIN
However due to FIDIC contractual requirements, paper versions of selected documentation will
be requested by the Engineer.
4-24
EMPLOYER’S REQUIREMENTS-FIN
4.6 Drawings
4.6.1 Drawing Standards
Drawings submitted by the Contractor shall be clearly printed with black lines on white paper,
and shall be resistant to fading on exposure to light. If colours are used, only bold and strong
types shall be applied, which are clearly visible on white paper. Prints shall be on durable paper
of good quality and 80 g/m2 minimum weight.
Sheet sizes shall be in accordance with A series to ISO 216 and shall not be larger than A1 size,
unless otherwise agreed by the Engineer.
All drawings submitted by the Contractor shall use the English language and SI units.
All drawings shall be clearly and fully cross referenced to the specification and the Engineer's
drawings, as relevant.
Where drawings are revised, the revision letter or number shall be incorporated in the title block
and the revision shall be clearly indicated on the drawing with the revision letter or number
shown in an adjacent triangle.
4-25
EMPLOYER’S REQUIREMENTS-FIN
Drawings shall be drawn to specified scales or to such scales as are appropriate for clearly
detailing and conveying the Contractor’s proposals. Scales shall generally be 1:5, 1:10, 1:15,
1:100, 1:1000, or 1:25000. The scale used shall be shown on the drawings.
Drawings shall include cross references where appropriate and key information such as vital
levels and dimensions. All layout plans shall show the “north” direction.
The Contractor shall apply a reference numbering system for designs, drawings and documents
so that each number used is unique.
Working/Shop Drawings
Drawings for all items of plant constituting an operating system shall be submitted to the
Engineer concurrently and shall include diagrams showing circuit functioning and details for
erection. Plant working drawings prepared by subcontractors and manufacturers employed by
the Contractor shall be checked by the Contractor for accuracy and compliance with the Contract
as specified before being forwarded to the Engineer. Working drawings not so checked and
noted, will be rejected and returned to the Contractor without further examination.
Working drawings for mechanical, electrical, instrumentation and similar plant shall include but
not be limited to:
• Process and instrumentation (P&I) diagrams.
• Single line diagram for electrical distribution system from point of supply to final plant
connection.
• General arrangement drawings of the Works fully developed to show Plant layout and
dimensions.
• General arrangement drawings for all items of Plant, drawn to scale, fully dimensioned
and showing weights, foundation details and all clearances required for installation,
operation and maintenance.
• Layout drawings of switchboards and instrumentation and control panels showing
controls, instrumentation, mimics and inscription details of all labels.
• Alarm annunciator layout and engraving details.
• Electrical block, circuit and wiring diagrams for switchboards and control boards.
• Supplementary block, circuit and wiring diagrams for integrated control, protection,
metering and other schemes as required for a complete understanding of the
Contractor’s proposals.
4-26
EMPLOYER’S REQUIREMENTS-FIN
• Instrument configuration loop drawings which shall identify each element and its location,
all wiring and cable connections and all inputs to and outputs from programmable
devices. The drawings shall be prepared on A3 size sheets and presented in book
format.
• Block diagrams to show power control and instrumentation cabling systems with each
cable, cable core and associated equipment terminals identified as in the cable
schedules.
• Installation drawings showing cable routes and cable support system details. For cables
installed in ducts and direct in the ground, the drawings shall include sections to show
their disposition and the position of all marker posts, cable joints and draw-pits.
• Cable schedules, which shall include the cable number, type, voltage, conductor size,
number of cores and route length. The schedules shall additionally incorporate cable
core ferrule and equipment terminal numbers and the diagram number(s) of connected
equipment.
• Single line diagram showing the electrical system neutral earthing, earth terminal(s) and
electrode(s) and all circuit protective and equipment bonding conductors.
• Earthing installation layout showing conductor routes and the location of earth
terminal(s), test links, earth electrodes and associated connecting chambers.
• Earth terminal general arrangement.
• Lightning protection system installation drawings showing air termination details, the
location and route of down conductors, the location of bonds, test points and earth
electrodes, and the location of bonding points in reinforced concrete structures.
• Building services installation drawings showing the location of distribution boards,
luminaries, socket outlets, heaters, ventilation fans and ductwork, air conditioning units,
fire detectors and manual call points, intruder alarm switches and detectors, alarm
sounders etc., and associated switches, thermostats, control panels and distribution
board diagrams and/or schedules.
• Installation drawings for chemical treatment, water supply, sewage and waste water
systems.
• Fabrication drawings for metalwork including T platforms, floor plates and frames, hand-
railings etc.
• Complete and detailed schedules listing all items of plant, instruments and ancillary
equipment to be supplied by the Contractor.
• List of safety signs and drawings.
• All additional drawings required to supplement those identified above and for other work
not specifically identified.
4-27
EMPLOYER’S REQUIREMENTS-FIN
Complementary Drawings
The Contractor shall submit such further detailed drawings of the plant and any other equipment
being provided under the Contract as the Engineer may require for a proper understanding of the
works. These complementary drawings will not form part of the approval scheme, but shall be
included as appropriate with the record drawings, the operating instructions and the operation
and maintenance manual.
Such drawings may include but not necessarily be limited to:
• Sectional and detail arrangement drawings.
• Circuit diagrams for electrical equipment which shall include wire and terminal numbers
and circuit references and ratings for all components.
• Component part schedules for each item of Plant with references to the associated
drawings.
• Valve schedule listing each valve with identification number, size, type, connections,
rating, figure number and duty.
4-28
EMPLOYER’S REQUIREMENTS-FIN
The drawings of a specific piece of equipment shall identify components with the manufacturer's
part number of reference drawings number clearly indicated. If reference drawings are used, the
approval date of such drawings shall be included. The drawings shall indicate dimensions and
allowable tolerances.
4-29
EMPLOYER’S REQUIREMENTS-FIN
The design and construction shall ensure that the Design Life specified in these Employer's
Requirements will be attained, and that such components operate satisfactorily under all service
conditions.
All alarms and plant status shall be indicated on the local control panels and the central LED
touch screen panel.
For all Pumping Stations, it has to be determined if surge (water hammer) protection measures
are applicable and implemented, if necessary.
Preference shall be given to treatment processes, for which NWSC has gained positive
operation experiences in the last years;
Design shall ensure cost-efficiency in terms of investment and operation costs;
Availability (safe supply) of proposed chemicals is an asset.
The proposed treatment process is based upon the raw water quality of the Lake Victoria at
Katosi. However, the Contractor's proposed water treatment process must ensure to treat also
expected further deteriorated raw water quality to allowable limits.
Design shall be flexible in coping with varying raw water conditions and to allow for staged WTP
extension. Consequently, certain degree of space reserves has to be foreseen, for future
installation of additional treatment units, in order to cope with deteriorating raw water quality
and/or other non-favourable operational conditions. The following Table provides the range of
expected raw water deterioration:
4.7.2 Standardisation
Whenever possible, the Contractor shall provide equipment of a similar nature from the same
manufacturer, e.g. electric motors, in order to facilitate the spare part regime. Standardisation of
types of equipment shall also be adopted.
Wherever possible, the Contractor shall also consider standardisations within others, already
existing NWSC installation and facilities.
The Contractor shall note that particular attention will be paid to these requirements. In cases
where the proposed equipment is not standardised with regard to manufacturer and type, the
Contractor shall be required to provide conclusive technical justification; considerations of price
alone will not be accepted.
4-30
EMPLOYER’S REQUIREMENTS-FIN
4-31
EMPLOYER’S REQUIREMENTS-FIN
Change of key personnel shall only be possible upon written approval by the Engineer.
4-32
EMPLOYER’S REQUIREMENTS-FIN
• Net drinking water production and pumping facilities: 80,000 m³/d (1a); 160,000 m³/d
(1a+1b);
• Transmission from WTP to Nsumba Reservoirs: 3,850 m³/h (1a); 7,700 m³/h (1a+1b);
• Nsumba Reservoirs: 10,000 m³ (1a); 40,000 m³ (1a+1b).
General Data
nominal daily raw water flow to be treated (incl. filter backw ash w ater) m³/d 84.211 168.421 252.632
maximun daily raw water flow to be treated m³/d 91.866,0 183.732,1 275.598,1
maximum hourly raw water flow to be treated m³/h 3.827,8 7.655,5 11.483,3
3
chosen raw water design flow m /h 3.850 7.700 11.550
4-33
EMPLOYER’S REQUIREMENTS-FIN
4-34
EMPLOYER’S REQUIREMENTS-FIN
4-35
EMPLOYER’S REQUIREMENTS-FIN
4-36
EMPLOYER’S REQUIREMENTS-FIN
4-37
EMPLOYER’S REQUIREMENTS-FIN
4-38
EMPLOYER’S REQUIREMENTS-FIN
4.16 Fixed project scope and optional scope (Phase 1a & 1b)
The fixed project components (Phase 1a) are:
• Off Shore pipeline and Lake water intake for 255,000 m³/d (raw water, including internal
water losses for water treatment). Approx. length: 500 m, pipe diameter: 1,500 mm,
depth: max. 11 m.
• Raw water pumping station for 85,000 m³/d (raw water, including water losses in the
water treatment plant). Total head - approx. 45 m. Structure for screening process shall
be included, but not equipped.
• Water Treatment Plant for 80,000 m³/d (net water production).
• Sludge treatment (4% DS after thickening, 25% DS after dewatering/drying).
• Treated Water Pumping Station for 80,000 m³/d (net water production) and total pumping
head of estimated 155 m.
• Pump transmission main, pressure class PN 25 of diameter 1,200mm and length about
10 km to Nsumba Intermediate Reservoir.
• Intermediate Reservoir on top of Nsumba Hill; initial tank capacity 10,000 m³, shape
preferable round. The interface to the project “Gravity Drinking Water Transmission Main”
implemented by another Contractor, will be the outlet pipe of the Nsumba reservoir site.
4-39
EMPLOYER’S REQUIREMENTS-FIN
Capacity Phase 2
NRS NRS
I III
Tender Ph 1a (fix)
Inlet Distr.
Tender Ph 1b (opt) Chamber
NRS NRS
II IV
WT WT WT
Phase Phase Phase
1b 1a 2
DWST / DWPS
Phase 2
Gravity Mains
DWST / DWPS
Phase 1
WT: Water Treatment
ST ST ST ST: Sludge Treatment
Phase Phase Phase RWPS: Raw water pump station
Lake Victoria
1b 1a 2 DWST: Drinking water tank
RWPS
Intake / Abstraction DWPS: Drinking water pump station
NRS: Nsumba reservoir site
NRS NRS
V VI
NRS NRS
I III
NRS NRS
II IV
DWST / DWPS
Phase 2
Gravity Mains
DWST / DWPS
Phase 1
4-40
EMPLOYER’S REQUIREMENTS-FIN
1. Results of the topographical surveys (if any) in form of a report and drawings, stating
coordinates and levels of the existing terrain;
2. Results of the geo-technical survey (if any) in form of a report, calculations, soil profiles,
drawings, etc. with clear statements on soil characteristics, geo-technical design
parameters, recommendations for excavation, bracing and sheeting, recommendations for
keeping excavations free of groundwater, recommendations for foundations, expected
settlement and measures for settlement reduction for every building, tank, etc.;
3. Process design and calculations consisting of process description report; calculations in
tabular form for water treatment, sludge treatment, power demand, power generation,
sludge and residual disposal, internal water supply, chemicals use, etc.; detailed P&I
diagrams; flow charts; etc.;
4. Hydraulic calculation for water lines, sludge lines, plant internal wastewater, storm water etc.
and corresponding hydraulic profiles;
5. WTP site layouts (for phase 1, including outlines for phase 2, based on the surveys,
investigations and detailed process design and hydraulic calculations) showing location of
all tanks, channels, shafts, manholes, buried pipes, buried cable ducts, buried cables, site
lighting, position of outdoor instrumentation and installations, outdoor earthing and lightning
protection, remote data transmission cables, roads, footways, fence, gates, etc., providing
its coordinates and elevations;
6. Mechanical design: calculations and drawings (based on the detailed process design and
calculations) showing machine layout and pipe installations, static and dynamic loads,
supports, fittings, suspensions, etc.; machine data sheets in tabular form showing
capacities; lists detailing all plant, equipment and materials to be supplied with their location,
all details needed for erection, etc.;
7. Electrical design: calculations and drawings (based on the detailed process design and
calculations and detailed mechanical designs); single line, circuit and wiring diagrams; cable
lists; manufacturers’ brochures and catalogues; automation chart; power consumer lists and
calculations; simultaneous peak power demand; instrumentation lists, etc.;
8. Design and calculations for heating – ventilation - air - condition (HVAC) and sanitary
installations.
9. Design for civil works including tanks, chambers, channels, and buildings, earthworks.
Architectural drawings showing machine and pipe installations, gratings, handrails, ladders,
floor, walls, wall covering, insulation, ceilings, roofs, doors, windows, sanitary installations,
HVAC, interior furnishing, switchboards, building installations (lighting, socket outlets etc.),
cable trays/conduits, telephone systems, remote data transmission, etc., providing
coordinates and elevations;
10. Structural and foundation calculations for all tanks, chambers, channels, and buildings,
based on the approved geotechnical report, architectural drawings, site layout and sections
presenting excavation lines. The earthquake class or zone shall be clearly indicated;
11. Formwork and reinforcement drawings, based on the approved architectural drawings and
structural calculations for all tanks, chambers, channels, and buildings, including formwork
plans, bar bending schedules for the steel reinforcement, pre-cast concrete units including
the cast-in units such as fasteners, jointing materials lifting provisions and all steel work
constructions including anchor-bolts, supports, etc.;
12. Structural calculations for all buried pipe work based on the approved geo-technical
investigations, site layout, and its longitudinal sections;
13. Working drawings for bracing and sheeting for trenches and excavations;
4-41
EMPLOYER’S REQUIREMENTS-FIN
14. Working drawings for keeping trenches and excavations free of groundwater;
15. Technical specifications of proposed measures and equipment;
16. Health and safety measures;
17. Environmental mitigation measures.
4-42
EMPLOYER’S REQUIREMENTS-FIN
A new raw water off-shore pipeline, HDPE - DN 1500, shall be constructed on the lake bottom,
with length approximately 500 m from the intake and the lake shore, into the lake, in order to
abstract raw water from approx. 11 m depth (invert level to mean WL). The off-shore pipe shall
cope with a capacity of 255,000 m³/d raw water.
The pipe could be laid above the lake bottom without trench. In order to avoid floating and
movement, the pipe shall be secured and protected against physical damage (e.g. from boat
anchors). The pipe shall be equipped with all necessary anchorages, according to Contractor’s
structural calculations, to safeguard it against buoyancy.
The pipe shall be laid with continuous slope upwards, to the raw water intake and high points
shall be avoided in any case. The pipe end shall be clearly marked with a buoy and be equipped
with a strainer, with appropriate slit width.
At the inlet to the intake structure a penstock shall be installed in order to isolate the intake from
the abstraction pipeline.
The raw water off-shore pipeline’s length shall be extendable with HDPE DN 2000, in order to
cope with Phase 2 requirements. The pipe’s end shall be prepared already appropriately.
4-43
EMPLOYER’S REQUIREMENTS-FIN
4-44
EMPLOYER’S REQUIREMENTS-FIN
The raw water pump main shall be designed to convey the Phase 2 raw water flow
(255,000 m³/d) from the new raw water pumping station to the distribution chamber of the new
Katosi Water Treatment Plant.
A cement lined, ductile iron pipe, having appropriate diameter and length, shall be foreseen for
the raw water pumping main; the flow velocity shall be in reasonable engineering range. In order
to compensate the forces, the Contractor has to conduct structurally dimensioning of trust blocks
and safeguard every bend of the raw water main.
To measure the raw water quantity, an electromagnetic flow-meter shall be installed in the raw
water pumping main between the raw water pumping station and the distribution chamber.
4-45
EMPLOYER’S REQUIREMENTS-FIN
4.18.8 Clarifiers
Phase 1a scope:
A minimum of 4 clarifier blocks per treatment line shall be constructed. Contractor’s design shall
assure even distribution (e.g. by adjustable overflow weirs) to the individual clarifier units.
The sizing of the clarification plant (one treatment line) shall be based on a total input of not less
than 3,850 m³/h. The maximum surface load shall be 3.50 m³/(m²xh).
4-46
EMPLOYER’S REQUIREMENTS-FIN
The clarified water shall be conveyed to the filter inlet, via overflow weirs and channels. The
maximum allowable weir load shall not exceed 8 m³/(mxh).
Clarifiers shall be with hopper shaped bottoms for sludge collection and removal. Equal sludge
abstraction rate over the clarifier surface has to be ensured. Each hopper shall be equipped with
its individual sludge removal line conveying the sludge to lateral channels, where the sludge
quality and flow can be controlled. The volume of sludge hoppers shall not be less than 500 m³
per treatment line. Further on, the sludge shall be conveyed to the sludge treatment system.
To avoid the negative impact of direct sunlight (algae growth) a complete coverage of the
clarifiers by an appropriate roof construction shall be foreseen.
The tanks shall be equipped with appropriate bottom drainage facilities, to allow drainage by
gravity to the drainage system.
Flotation process may be considered as an alternative.
Phase 1b scope (optional):
4 clarifiers, identical as for Phase 1a, shall be built, for Phase 1b.
Phase 2 scope (only design):
4 clarifiers, identical as for Phase 1a, shall be built, for Phase 2.
4-47
EMPLOYER’S REQUIREMENTS-FIN
As for the clarifiers, also for the filters a complete coverage by an appropriate roof construction
shall be constructed, in order to avoid the negative impact of direct sunlight.
The filters shall be equipped with appropriate bottom drainage facilities, which allow drainage by
gravity.
Filter control by constant level can be an alternative to constant rate.
The mechanical equipment of the filters shall be designed for:
• Isolation of each filter unit for maintenance and repair purpose without disturbance of
other filters.
• Water distribution shall be designed to ensure equal distribution of flows to all filters in
operation.
• Automatic operation of filtration using constant flow or constant level.
• Automatic backwash system.
All valves (e.g. Filter inlet, Filtered water outlet, Backwash, Air scour, Wash water outlet, Main
backwash regulation) shall be electrical actuated.
Phase 1b scope (optional):
Minimum 8 filters, identical as for Phase 1a, shall be built, for Phase 1b.
Phase 2 scope (only design):
Minimum 8 filters, identical as for Phase 1a, shall be built, for Phase 2.
Pumping Station
4-48
EMPLOYER’S REQUIREMENTS-FIN
The new Drinking Water Pumping Station shall provide sufficient space to accommodate the
required pump sets, which draw water from the reservoir and pump it to the Nsumba reservoir.
The civil structure shall be appropriate to accommodate the pumps for Phase 1a and Phase 1b.
However only 3 Drinking Water Pumps shall be installed under Phase 1a.
In addition, the following equipment shall be accommodated in the pumping station:
• Backwash pumps: Installation in Phase 1a - 1 duty + 1 standby. Space shall be provided
for Phases 1a and 1b (2 duties + 1 standby).
• Chlorine-water booster pumps: Installation in Phase 1a - 2x (1 duty + 1 standby). Space
shall be provided for Phases 1a and 1b - 2x (2 duties + 1 standby).
• Process and drinking water pumps or booster station (already to fit Phase 2
requirements)
• Electrical powered overhead crane.
• All flow control equipment
All low voltage switch gears and control panels shall be installed in a separate control room or
control building, adjacent to the pumping station structure. However, the Contractor is free to
include the control devices in the same pump house, but different rooms.
All duty pumps shall operate in parallel and shall be equipped with variable speed devices, soft
start/stop systems and appropriate surge (water hammer) protection (e.g. surge vessel).
As per Administration’s Proposal the drinking water pumps unit shall have the following main
characteristics. In accordance with Contractor’s design other arrangements and consequently
another value for the hydraulic head is possible.
• Capacity (combined): 3,850 m³/h
• Combined efficiency (pumps and motor): >80%.
• Max. Hydraulic head (4 pumps combined – 1b flow): 155 m
• No: 2 duty + 1 standby
The suction side of all pumps shall be equipped with strainers and electrical actuated valves.
The pressure side shall be equipped with pressure gauges, check valves and electrical actuated
valves.
Phase 1b scope (optional):
Same pumping station building shall serve Phase 1b. The following shall be installed:
• Three additional drinking water pumps (2 duty + 1 standby)
• One additional backwash pump
• Two additional chlorine water booster pumps
Phase 2 scope (only design):
Construction of a new structure with similar arrangement as for Phase 1a, to accommodate 3
more drinking water pumps (2+1). Chlorine contact tanks shall have only a 50% volume. Process
and drinking water pumps or booster station for Phase 2 have been included already in Phase
1a.
4-49
EMPLOYER’S REQUIREMENTS-FIN
The transmission main shall be designed to convey the drinking water from the new drinking
water pumping station to the Nsumba reservoirs. A cement lined, ductile iron pipe, diameter
1200 mm, length approx. 10 km, pressure class 25, has been foreseen for the pumping main.
To compensate pump forces, the Contractor has to install appropriately dimensioned trust
blocks, in order to safeguard the bends of the transmission main.
Please note, that in Uganda power cuts happen frequently. The surge protection for the water
transmission main shall be through surge control measures at the pump station (e.g. surge
vessel incl. compressor, soft start/stop systems, etc.) and the line (e.g. air valves). The surge
control should meet the criteria as detailed below:
• Maximum Positive Surge = 20 % above the maximum working head pressure
• Minimum Surge = Atmospheric pressure minus 2 m
To measure the treated water quantity, a flow meter shall be installed in the pumping main after
the drinking water pumping station. The meter shall be accommodated in a metering chamber,
including valve arrangements, bypass and drainage. The signal shall be readable at the local
control and be transferred to the SCADA system.
Phase 1b scope (optional):
Optional design and construction of pipeline DN 1400 instead of DN 1200.
Phase 2 scope (only design):
Design of additional pipeline DN 900, and ancillary components, taking in consideration that only
DN 1200 under Phase 1a, has been installed.
4-50
EMPLOYER’S REQUIREMENTS-FIN
The backwash sedimentation tanks shall receive appropriate bottom drainage facilities, which
allow drainage by gravity.
Phase 1b scope (optional):
Two sedimentation tanks, identical as for Phase 1a, shall be built, for Phase 1b.
Phase 2 scope (only design):
Two sedimentation tanks, two backwash pumps (1 duty, 1 standby), and two blowers (1 duty, 1
standby), room for blower installation, shall be installed, for Phase 2.
4-51
EMPLOYER’S REQUIREMENTS-FIN
2 Feeder Pumps (1 duty +1 standby), variable speed, max. capacity 100 m³/h,
valve and check valve at pressure side, flow meter;
2 sludge recycling Pumps (1 duty +1 standby), variable speed, max. capacity
50 m³/h, valve and check valve at pressure side, Flow meter;
• Supernatant recycling pumping station;
2 Supernatant Water Pumps (1 duty +1 standby), variable speed, non-clogging
impeller, capacity 800 m³/h;
Valves at suction and pressure side, check valve;
Flow meter;
• Sludge pumping station for thickened sludge (if necessary and indicated by Contractor’s
design);
2 Sludge Pumps (1 duty +1 standby), horizontal-dry well installation, non-
clogging impeller, capacity 100 m³/h;
Valves at suction and pressure side, check valve;
Flow meter;
• Mechanical sludge dewatering;
Pre-dewatering units (e.g. thickeners, centrifuges, etc.), outlet min. 4% DS.
Building, including dewatering machines, polymer preparation/dosing, conveyor
system, containers, etc.
Roofed dewatered sludge storage plate 7 days storage.
The Contractor is free to design alternative ways of the sludge dewatering system, considering
an inflow concentration of 0.4% – 0.6% DS and reaching a dewatering level of 25% DS. Also the
recycling streams and an appropriate sludge container feeding system shall be considered. The
dewatered sludge, which reaches the specified dewatering results will have to be disposed-off by
the Employer.
Phase 1b scope (optional):
The requirements for the second sludge dewatering line are principally identical to Phase 1a.
Phase 2 scope (only design):
Identical to Phase 1a.
4-52
EMPLOYER’S REQUIREMENTS-FIN
4-53
EMPLOYER’S REQUIREMENTS-FIN
stirring process and transferred to points of application by metering pumps. Two dosing pumps,
with capacity of 120 l/h, shall be installed (1 + 1). The plant shall be suitable for preparing
solution from powdered or granulate polymer, delivered in bags. The dosing point shall be before
the flocculation units.
There shall be the possibility to drain and flush the tanks and pipes to the chemical waste
system, by gravity.
Phase 1b scope (optional):
Same arrangement as for Phase 1a.
4-54
EMPLOYER’S REQUIREMENTS-FIN
Chlorination
Please note: in the Requirements below the use of chlorine-gas has been described, as per
Admin’s Proposal. Instead of use of chlorine-gas, the design and construction of “Chlorine Self
Electrolysis” is specifically encouraged by these Employer’s Requirements and the Contractor
could provide such alternative solutions.
Pre-Chlorination
Phase 1a scope:
in order to inactivate organisms when needed during algae and shrimp blooms, a pre-
chlorination, or other type of appropriate algae removal, shall be installed.
The preparation of the Cl-solution shall take place in the Chlorine Dosing House. The building
shall be equipped with appropriate gates and forced ventilation above roof, sufficiently sized and
easy accessible storage area for chlorine tanks. Access for easy delivery of the chlorine tanks
must be ensured.
The Chlorine Dosing House shall be weather proofed, adequately lit, drained and fire-resistant.
Each room or store shall have an emergency exit door opening outwards. The levels of ceilings
shall be sufficiently high to allow satisfactory maintenance and replacement of parts. The floor
level of the chlorine house shall be above ground level in order to prevent flooding.
Special consideration shall be given to floor drainage of all rooms. The grids on the drainage
channels shall be made of chlorine corrosion resistant material.
Heating facilities shall be provided to avoid cold spots near chlorine gas lines and chlorinators so
as to prevent re-liquefaction of the chlorine gas.
There shall be no external windows and only artificial lighting shall be used. To safeguard
personnel in the event of a chlorine leak, gas tight sealed windows shall be provided in internal
walls so that all areas may be observed from an adjacent room.
The storage facilities shall be able to accommodate the full and empty drums on appropriate
supports. An emergency safety pit to dump a leaking chlorine drum, shall be located in the
loading area. In the event of a severe leak from a cylinder, the cylinder shall be submerged in the
water filled pit. The pit shall be designed to immerse a standard drum under not less than 1
meter of water. The pit shall be dimensioned sufficiently to facilitate handling of a cylinder under
emergency conditions.
The chlorinators shall be fed by two rows of eight drums. An automatic device shall make
changeover from empty to full drums. It shall however be possible to switch the changeover
device manually.
Pre- Chlorination will be enabled with liquefied Cl2-gas. 3 chlorinators (2 duty; 1 standby) shall
deliver chlorination capacity 38.5 kg/h, with a concentration ranging between 4-10 mg/l. Three
dosing pumps (2 duty; 1 standby) shall generate a flow of 11.55 m³/h towards the dosing point, in
the raw water main.
All interconnecting pipework between the various items of plant shall be provided and laid out.
Phase 1b scope (optional):
Same arrangement as for Phase 1a.
Phase 2 scope (only design):
Same arrangement as for Phase 1a.
4-55
EMPLOYER’S REQUIREMENTS-FIN
Disinfection
Phase 1a scope:
The preparation of the Cl-solution shall take place in the Chlorine Dosing House, which has been
described above.
Disinfection will be enabled with liquefied Cl2-gas. 2 chlorinators (1 duty; 1 standby) shall deliver
chlorination capacity 11.6 kg/h, with a concentration ranging between 2-3 mg/l. Three dosing
pumps (2 duty; 1 standby) shall generate a flow of 6.93 m³/h towards the dosing points.
The free available chlorine concentration after the contact tank shall be not less than
0.5 mg Cl2/l.
All interconnecting pipework between the various items of plant shall be provided and laid out.
Phase 1b scope (optional):
Same arrangement as for Phase 1a.
Phase 2 scope (only design):
Same arrangement as for Phase 1a.
4-56
EMPLOYER’S REQUIREMENTS-FIN
drawing in the Admin’s Proposal. Connection details shall be coordinated with the “Transmission
Main Pipeline” – Contractor.
The connection point shall be prepared with sleeve connection and an air valve shall be placed
at the highest point, before starting to slope down. When crossing the access road, the pipeline
shall be safeguarded and protected in appropriate manner (e.g. precast concrete ducts or
concrete surround), in order to stand the traffic loads.
One ultrasonic flow meter for the transmission DN 1400 shall be provided inside a metering
chamber, which shall have appropriate access. A local display shall be installed outside the
chamber to take easy readings. The Ultrasonic bulk flow meter shall be of the split in line or split
insertion type complete with (flanged connection) main display unit and insertion transducer and
from a reputable manufacturer. The meter shall be suitable for accurately recording data on
pipes up to diameter of 2000mm. The guaranteed margin of error shall not exceed + 0.5%. The
meter shall be suitable for flow measurement of potable water and shall be installed as directed
by the Engineer and in accordance with the manufacturer’s recommendations.
The meter shall have strong inbuilt Anti-interference dual-balance signal differential
receiver/driver circuit to avoid interference of converter, TV tower, high voltage line etc. and an
automatic recording function for totalizer data of at least 1 year as well as the records of the flow
meters working status in the previous month (30 days).
Phase 1b scope (optional):
Optional design and construction of three additional reservoirs – 10,000 m³ each. Additional
construction of necessary road and walkway infrastructure to reach the additional reservoirs.
Phase 2 scope (only design):
Design of two additional reservoirs – 10,000 m³ each. Construction of gravity main DN 1200 to
interface, including flow metering system – similar to 1a scope. Additional construction of
necessary road and walkway infrastructure to reach the new reservoirs.
4-57
EMPLOYER’S REQUIREMENTS-FIN
Please note that staff houses shall be ready for use, 6 months before the overall completion
date. This will enable the Employer to recruit and settle-in the O&M staff at the site, at an
appropriate moment of time, prior to the start of training.
The construction of all buildings shall follow the Building Regulations for Uganda. Finishes and
other room details are given in the following table and the requirements of the Specifications are
also applicable:
Table 4-7 Building Requirements and Finishes
Building Requirements and Finishes
Building Type Plant Rooms
Roofs Aluminium sheeting
Floors – Admin. Building, kitchens, Screed plus tile finish, skirting boards
bathrooms, laboratory
Floors – Laboratory Screed plus acid resistant tile finish, skirting
boards
Floors – workshops, machine Screed plus epoxy floor finish, paint skirting
rooms, pumping stations, etc.
Floors - offices Screed plus parquet or carpet tiles, skirting
Floors – control rooms Computer flooring system (double floor)
Walls Block work
Internal wall finish Plastered and painted
External wall finish Plastered and painted
Ceilings – general Plastered and painted
Ceilings – administration, offices, Suspended ceilings
control and welfare rooms
Doors in Admin. Building, or similar Hardwood oiled
Doors in process buildings, Aluminium or steel
Pumping Stations, etc.
Windows – general Sun exposed windows shall be shadowed by
shutters or similar.
Good natural light levels during daylight and
adequate cross ventilation.
Windows - process buildings, Aluminium, simple glazing.
Pumping Stations, etc.
Windows – in buildings with HVAC Aluminium, double glazing.
All operational rooms and control HVAC to be provided
rooms
Building services Small power and lighting, Hot and cold water
supplies, sewerage, Rainwater collection
and disposal,
4-58
EMPLOYER’S REQUIREMENTS-FIN
4-59
EMPLOYER’S REQUIREMENTS-FIN
each of the identified Worksites, establish a Site Environmental Protection Plan (SEPP), all in
accordance with the ESHS Specifications.
These Plans are required assets, respectively by the Authorities of Uganda and the Donor
Agencies and have to fulfil the respective requirements. The plans have many similarities in
between themselves and shall be developed together and harmonised before submission to the
Engineer.
The Environmental and Social Impact Assessment Study, with its mitigation measures, and the
ESHS Specifications have to be read in conjunction and applied.
4-60
EMPLOYER’S REQUIREMENTS-FIN
Hydrants shall be provided at appropriate locations with suitable hoses of sufficient length
according to Ugandan legislation. The hoses shall be kept permanently accessible in
conspicuous storage units.
Hydrants and hose enclosures shall be painted distinctively red to differentiate them from wash
water points. Portable appliances (CO2 extinguishes, dry powder extinguishers and fire blankets)
shall be provided in the various plant areas in accordance with the regulations.
Phase 1b scope (optional):
Same requirements like for Phase 1a, in order to cover Phase 1b tap points.
Phase 2 scope (only design):
Same requirements like for Phase 1a, in order to cover Phase 2 tap points.
4-61
EMPLOYER’S REQUIREMENTS-FIN
4-62
EMPLOYER’S REQUIREMENTS-FIN
Hard-standings shall be provided at all the key operational areas, to facilitate personnel and
vehicle access for operational and maintenance purposes. All access roads and hard standings
shall be designed to prevent standing water and all necessary drainage shall be provided.
The roadway and clearances between and into buildings shall allow a clear and safe approach
and manoeuvring for all types and size of operational vehicle required for the operation and
maintenance of the Works. Vehicle access provisions shall be provided at all locations where
required as part of the Works to facilitate personnel and vehicle access for operational and
maintenance purposes.
Where appropriate, ramps shall be provided at equipment access doors to enable a vehicle to be
driven into the building. With the exception of access ramps, road gradients shall not exceed
12%.
Turning areas shall permit a vehicle to manoeuvre into the final discharge or pick-up position.
Surface markings shall be provided to identify areas allocated as turning areas and
parking/unloading bays.
A minimum of 20 car parking spaces shall be provided.
Hard paved, lighted pedestrian walkways 1 metre wide shall be provided to all access points to
tanks, chambers and building entrances unless these are beside road ways. The paved routes
shall follow logical lines likely to be used by the maintenance workers.
Phase 1b scope (optional):
Additional road construction, in accordance with the requirements of Phase 1b at the Reservoir
site, to access all areas.
Phase 2 scope (only design):
Additional road construction, in accordance with the requirements of Phase 2 at the WTP and
the Reservoir site, to access all areas.
4-63
EMPLOYER’S REQUIREMENTS-FIN
4-64
EMPLOYER’S REQUIREMENTS-FIN
• Front loader - (e.g. Caterpillar 930G, 110 kW, 13 t, or similar) with bucket and loader
rake;
• Container Loader - (e.g. MAN or similar) for disposal of sludge, Diesel Engine, 130 kW,
7.5 t, self-lifting of 7m³ containers;
• Telehandler – (e.g. Manitou, MT 732 or equivalent), 3.2 t lifting capacity, diesel engine,
75 kW, lifting height 6.9 m, including attachments for crane function and (4 in 1) bucket;
• Pick-up truck – (e.g. Toyota Hilux or similar), 4+1 passengers, Minimum engine size
2000 cc.
Consumable spares (oil filters, brake pads etc.) shall be supplied for the operation of these
vehicles as specified in the schedule of spare parts. All vehicles shall be covered by a three year
guarantee.
Phase 1b scope (optional):
N.a.
Phase 2 scope (only design):
N.a
4-65
EMPLOYER’S REQUIREMENTS-FIN
N.a
4-66
EMPLOYER’S REQUIREMENTS-FIN
4-67
EMPLOYER’S REQUIREMENTS-FIN
shall therefor install a suitable photovoltaic power generation system, which will suit the power
requirements. Emphasis shall be put in the installation of high efficiency solar panels,
appropriate power storage facilities and low end consumer consumption (e.g. LED bulbs).
The photovoltaic power generation system shall be backed-up by a standby generator of suitable
size.
Phase 1b scope (optional):
N.a
Phase 2 scope (only design):
N.a
4-68
EMPLOYER’S REQUIREMENTS-FIN
Parameters related to the filter shall be indicated in the filter control gallery for the backwash
flow, on the individual filter consoles. However the signal shall be fed to the SCADA system and
to be displayed in the central control room.
Level signal and alarms of the reservoir in Nsumba shall be conveyed to the WTP. The system
shall have channel capacity to handle all future reservoirs, at the Nsumba site, as well.
4-69
EMPLOYER’S REQUIREMENTS-FIN
5-70
EMPLOYER’S REQUIREMENTS-FIN
Before entering to any additional working sites, the Contractor shall obtain and forward to the
Engineer a copy of written consent of the owner and occupier or authority having charge of the
land, stating the purposes for which such land is to be used by the Contractor, and defining the
extent and periods of his occupation for which such consent is granted. Notwithstanding the
requirements of such consent, additional working sites shall be protected by fences or barriers or
other works as required by the Engineer. Wherever practicable, a passage shall be maintained
for vehicles and pedestrians along public roads and to all adjacent properties.
5-71
EMPLOYER’S REQUIREMENTS-FIN
The Contractor shall make his own arrangements for any diversion or removal of services, which
he may require for his own works. He shall obtain the prior approval of the Engineer to such
arrangements.
5-72
EMPLOYER’S REQUIREMENTS-FIN
5.4.14 Advertisements
The Contractor shall not undertake or allow bill posting or advertising of any kind concerning the
works without the written consent of the Engineer.
5-73
EMPLOYER’S REQUIREMENTS-FIN
The Contractor shall submit to the Engineer the W-ESMP Plan, including a Health and Safety
section, within 28 days after Commencement date. This HS Plan section shall comply with
international good practice, local safety codes, laws and regulations including a comprehensive
AID/HIV prevention plan for the construction site.
Where any part of the Works is not covered by the Contractor’s Safety Policy, or is a high risk
activity, the Contractor shall, before commencing work on that part of the Works or activity,
submit to the Engineer a Working Method Statement for safety for approval. No related work
shall be commenced unless the Engineer has approved the proposed methods.
The Contractor shall nominate a responsible person for the organisation and supervision of first-
aid measures and facilities, throughout the contract period. The Contractor shall conduct H&S-
training for all his personnel on a regular basis, familiarising them with H&S measures.
The Contractor shall introduce an “Operator Permit to Work” system after adequate operator
training to ensure that the operator is adequately trained to carry out the required work on any
equipment.
On site a first-aid facility, in accordance with the ESHS Specifications shall be provided. Medical
supplies for first aid provision shall be clearly marked and labelled, easy to identify and easy
accessible.
The Contractor shall provide for emergency arrangements in order to mobilise quickly labour-
force outside the normal working hours to carry out any work needed for an emergency
associated with the works. The Engineer shall be provided at all times with a list of addresses
and telephone numbers of the Contractor's staff who are currently responsible for organising
emergency works. The Contractor shall familiarise himself and his employees with any relevant,
existing, local arrangement, which deal with emergencies.
5-74
EMPLOYER’S REQUIREMENTS-FIN
5-75
EMPLOYER’S REQUIREMENTS-FIN
equipment. In steep slope sections, the upper surface layer shall be made of gravel material,
which prevents slippery conditions after rainstorms.
All temporary roads shall be maintained by the Contractor in good condition throughout the
period of construction. If the Contractor fails to maintain the roads as required, the Engineer may
instruct a third party to carry out the work at the cost of the Contractor.
The Employer and the Engineer and their employees as well as other contractors (if any)
working on the site for the Employer shall at all times have free use of the temporary roads
prepared by the Contractor.
5-76
EMPLOYER’S REQUIREMENTS-FIN
The Contractor shall provide septic tanks as necessary for the disposal of sewage. The tanks
shall be emptied on a regular basis and the removed faecal sludge shall be disposed-off safely.
The Contractor shall also provide for the removal and disposal of all rubbish and household solid
waste from offices and quarters with regular collections being made at least twice weekly.
Where the construction of septic tanks or water-borne sewerage is not feasible, the Contractor
shall send an alternative proposal to the Engineer for approval.
5.15.1.2 Water, Electricity and Gas
The Contractor shall provide a constant supply of clean potable water suitable for human
consumption, as well as the necessary electric power at 220 V AC to the offices.
Electric power shall be supplied to the offices during working hours and if necessary extended,
for working purposes.
5.15.1.3 Maintenance
The Contractor shall provide all labour, equipment and material which may be necessary to keep
all accommodation in a neat and clean condition and any repairs shall be done immediately upon
the request of the Engineer.
5-77
EMPLOYER’S REQUIREMENTS-FIN
5-78
EMPLOYER’S REQUIREMENTS-FIN
In addition, all electrical equipment shall be suitably protected against corrosion and incidental
damage to the satisfaction of the Engineer. Temporary leads shall be fitted to electrical
equipment to enable anti-condensation heaters to be energised when the plant is in store, and
such heat shall be applied by the Contractor when climatic conditions so require.
All items shall be packed to withstand land and sea transportation, and rough handling in transit.
Packages shall be suitable for outside-storage. The Contractor shall be held responsible for an
item being packed so that it reaches its destination intact and undamaged. Packages containing
dangerous or breakable goods shall be packed and marked, in accordance with the legal
requirements and international good practice.
All crates and packages shall be correctly and adequately marked as follows:
• Employer’s name;
• Title of contract;
• Contractor’s name;
• Title of work location;
• Designation and item number identical with consented to schedules;
• Usual commercial markings.
5.17.2 Delivery
The Contractor shall be responsible for the delivery of items to the site, including their handling
and safekeeping.
The Contractor shall keep the Engineer fully informed of the state of deliveries of items, and shall
send by air mail copies of all shipping documents to the Employer and to the Engineer, in
accordance with instructions to be issued to him from time to time by the Engineer. All shipping
documents shall be accompanied by copies of test certificates as required.
Delivery of items shall comprise the following, but not be limited to:
• Loading and transporting items by sea, land or air freight, including insurances.
• Taking charge of items at the port of entry or rail or air terminal in eastern Africa,
including payment of port charges, wharfage, demurrage, intermediate storage, off-
loading at terminal points, reloading and transporting to the site.
• Taking delivery of items at the site, off-loading and appropriate temporarily storing in
store buildings or under cover until such time as they are required for installation in the
works.
The Contractor shall examine all equipment upon delivery at the site. Should the Contractor
discover any damages he shall draw the attention of the Engineer thereto, who will inspect and
give instructions for further treatment of the case. Items with short shelf-life such as chemical
reagents shall be delivered in the shortest possible time before use with the plant.
Any item rejected by the Engineer shall be immediately removed and replaced by the Contractor.
5.17.3 Storage
The Contractor shall provide all facilities for the safe and proper storage and handling of all
equipment as recommended by the manufacturers, with particular consideration given to
temperature, rain, sunlight, wind and ground conditions.
5-79
EMPLOYER’S REQUIREMENTS-FIN
Stored items shall be laid out by the Contractor to facilitate their retrieval for use in a
programmed order.
Stacked items shall be protected from damage by spacers on load distributing supports and shall
be safely arranged. No metalwork shall be stacked directly on the ground.
Small items shall be held in suitable bins, boxes or racks and shall be clearly labelled.
Items shall be handled and stored so that they are not subjected to excessive stresses and so
that their protective coatings are not damaged.
1. Before the order to commence the Works, the Contractor is required to implement the
Environmental and Social Management Plan (ESMP) as specified in the updated ESMP,
prepared for the Katosi water works Project. The plan spells out how the Contractor should
achieve environmental targets and objectives specified in the ESMP and agreed upon by
the NWSC and NEMA. The plan shall include, to the extent practicable and reasonable, all
the steps to be taken by the Contractor to protect the environment in accordance with the
5-80
EMPLOYER’S REQUIREMENTS-FIN
5-81
EMPLOYER’S REQUIREMENTS-FIN
5. The NWSC environmental staff in conjunction with the NEMA shall inspect significant sites
where the Works have been carried out and proposed mitigation measures implemented
and shall give certification regarding the adequacy or inadequacy of rehabilitation
(restoration) measures carried out on the bio-physical environment and compensation for
socio-economic disruption resulting from implementation of the Works.
6. If the Contractor fails to implement the approved Environmental Management Plan, NWSC
shall seek legal redress through NEMA and appropriate penalties shall be instituted in
accordance with the provisions of the relevant policies/acts.
7. Furthermore, payment to the contractor will be made subject to compliance to the
environmental (and social) management plan (ESMP).
Material Excavation
• Contractors shall obtain appropriate licenses/permits from relevant authorities to operate
quarries or borrow areas.
• The location of quarries and borrow areas shall be subject to approval by relevant
authorities including traditional authorities if the land on which the quarry or borrow areas
fall is traditional land and by the Environmental Management Authority.
• Extraction sites shall not be located in the vicinity of settlement areas, cultural sites,
wetlands or any other valued ecosystem component and shall not be located at less than
10 km from such areas.
5-82
EMPLOYER’S REQUIREMENTS-FIN
• Extraction sites shall not be located adjacent to stream channels wherever possible to
avoid siltation of river channels. Where they are located near water sources, borrow pits
and perimeter drains shall surround quarry sites.
• Extraction sites shall not be located in forest reserves. However, where there are no
other alternatives, permission shall be obtained from the National Forest Authority (NFA)
and an environmental impact study shall be conducted.
• Extraction sites shall not be located on high or steep ground or in areas of high scenic
value.
• Only sites that can easily be rehabilitated (restored) shall be chosen. Areas with minimal
vegetation cover such as flat and bare ground or areas covered with grass only or
covered with shrubs with height of less than 1.5 m.
• Extraction site boundaries shall be demarcated and marked to minimize vegetation
clearing.
• Vegetation clearing shall be restricted to the area required for safe operation of
construction work. Vegetation clearing shall not be done for more than three months in
advance of operation.
• Extraction site shall not be located in archaeological areas. Excavations in the vicinity of
such areas shall proceed with great care and shall be done in the presence of staff of
Ministry of Tourism, Wildlife and Antiquities.
• Stockpile areas shall be located in areas where trees can act as buffers to prevent dust
pollution. Perimeter drains shall be built around stockpile areas. Sediment and other
pollutant traps shall be located at drainage exits from workings.
5-83
EMPLOYER’S REQUIREMENTS-FIN
Traffic Management
Location of access roads/detours shall be done in consultation with the local community
especially where access road shall traverse important ecosystem component. Access
roads shall not traverse wetland areas.
Upon the completion of the Works, all the roads shall be rehabilitated.
Access roads shall be sprinkled with water at least 5 times a day in settled areas and 3
times a day in unsettled areas to suppress dust emissions.
5-84
EMPLOYER’S REQUIREMENTS-FIN
• The Contractor in advance of the construction work shall mount an awareness and
hygiene campaign. Workers and local residents shall be sensitized on health risks
particularly of AIDS.
• The Contractor should provide personal protective equipment to the workers. Workers
will be encouraged to wear the equipment provided, for their own safety and penalties
enforced for non-compliance.
• Adequate road signs to warn pedestrians and motorists of construction activities,
diversions, etc. shall be provided at appropriate points.
• Construction vehicles shall not exceed maximum speed limit of 40 km per hour.
• All necessary first aid arrangements will be available on site.
• Emergency procedures and communication protocols will be in place prior to any activity
on site in order to deal with any emergency, which may arise; and, maintaining a safe
and healthy place of work.
• Prior to any activity on site a formal agreement will be established with a local Medical
Doctor (Doctor on call) to support any medical treatment which may be required.
• A briefing about safety and health precautions referred to as a tool box talk, will be
conducted regularly by all the supervisors and the foremen to their respective workforce.
• Enough toilets and urinals will put in place at assigned locations on site and will be
maintained clean and dry. Contents of these facilities will be contained so as to avoid
environmental pollution.
• Safe drinking water will be provided on site and workers will be encouraged to drink
enough water.
• Alcohol, intoxicants and non-prescribed medicine shall not be permitted on site and the
persons suspected to be under their influence shall not be allowed onto the site.
The Contractor will implement the provisions in the Workers Compensation Act (of 2000) and
more importantly, will sensitize workers about their pay and other entitlements like
compensation, insurance, taxation, etc.
5-85
EMPLOYER’S REQUIREMENTS-FIN
6.1 Testing
The Contractor shall perform all necessary tests to demonstrate compliance of the Works with
the Specifications, the Plant performance requirements and the Process Performance
Guarantees. All tests specified herein and/or found necessary for the Works shall be carried out
under responsibility and at the cost of the Contractor.
The procedures required to be undertaken and documentation necessary shall be in accordance
with the requirements described in the Conditions of Contract. During the testing the Contractor
shall demonstrate to the satisfaction of the Engineer that:
• The Works are suitable to produce the required water quality standard and that the
sludge dewatering system meets the specified performance requirements;
• The power and chemical consumption do not exceed the specified limits.
• The Works complies with the Specifications.
The Contractor shall demonstrate that the Plant operates satisfactorily when operated in both
manual and automatic control.
The testing shall include, but not be limited to:
• Quality Control and testing during construction;
• Inspection and testing at the manufacturers' premises;
• Tests on Completion.
In addition to any specific obligations for sampling and testing, the Contractor shall be
responsible for routine inspection sampling and testing of all materials, workmanship, plant and
measuring devices, in order to control the quality of work and to ensure compliance with the
Specification and approved samples.
6-86
EMPLOYER’S REQUIREMENTS-FIN
6-87
EMPLOYER’S REQUIREMENTS-FIN
6-88
EMPLOYER’S REQUIREMENTS-FIN
In order to start the performance tests, it shall be ensured that the period for continuous
operation will not be interrupted for adjustment or breakdown. Any such interruption will render
the test void.
The performance tests shall be conducted continuously during a period of 14 days, uninterrupted
by other tests. The object of the tests shall be to obtain a comprehensive set of data to show that
system performance meets the requirements set-out in the performance guarantees. After a
period of plant stabilisation all parameters shall be measured and recorded for comparison
against performance guarantees made.
• Water samples shall be taken and tested in accordance with the national regulations for
drinking water plants.
• Drinking water spot samples: At minimum, 95% of the drinking water spot samples taken
during the tests shall comply with the specified drinking water quality.
• Combined drinking water samples: Combined 24h drinking water samples shall comply
to 100% with the specified drinking water quality.
• Sludge samples: Per 5m³ dewatered sludge one sample shall be taken and analysed.
100% of the samples shall comply with the value, specified in these Employer’s
Requirements. Test procedures, in accordance with the relevant standard of the selected
dewatering equipment, shall be issued to the Engineer for approval together with the
Testing Programme.
• Test of daily production capacity: The daily drinking water production capacity shall be
tested and checked, using the daily average flow meter records of the Drinking Water
Pumping Station, generated by the SCADA system.
• Test of annual production capacity: The annual drinking water production capacity shall
be tested and estimated, using the flow meter records of the Drinking Water Pumping
Station, generated by the SCADA system.
Any deficiencies or deviations from the guaranteed or specified performance of the plant
disclosed by the tests shall be corrected by the Contractor and tests shall be repeated as
necessary until acceptable commissioning tests of the plant are achieved to the satisfaction of
the Engineer.
The Contractor shall submit to the Engineer for consent the commissioning test records in such
format as the Engineer may require, and after consent, shall provide the Employer with copies
thereof. The Contractor shall be responsible for collecting and collating all data for such records.
Satisfactory completion of the tests on completion is the prerequisite for the issuance of the
Taking-Over Certificate.
6-89
EMPLOYER’S REQUIREMENTS-FIN
• Combined drinking water samples: combined 24h drinking water samples shall comply to
100% with the specified drinking water quality.
• Sludge samples: Per 5m³ dewatered sludge one sample shall be taken and analysed.
100% of the samples shall comply with the value, specified in these Employer’s
Requirements. Test procedures shall be equal to the Tests on Completion.
• Test of daily production capacity: The daily drinking water production capacity shall be
tested and checked, using the daily average flow meter records of the Drinking Water
Pumping Station, generated by the SCADA system.
• Test of annual production capacity: The annual drinking water production capacity shall
be tested and checked, using the flow meter records of the Drinking Water Pumping
Station, generated by the SCADA system.
6-90
EMPLOYER’S REQUIREMENTS-FIN
procedures including electricity power failure. Commissioning tests shall be carried out for
individual equipment and on the works as a whole.
6-91
EMPLOYER’S REQUIREMENTS-FIN
6-92
EMPLOYER’S REQUIREMENTS-FIN
• Electrical power
6-93
EMPLOYER’S REQUIREMENTS-FIN
7. PROVISIONAL SUMS
Provisional Sums are allowed for and are shown in the Price Schedules. Provisional Sums shall
be used strictly in accordance with the Contract.
Provisional sums are foreseen for the following items only:
7-94
EMPLOYER’S REQUIREMENTS-FIN
All administrative and technical issues, concerning this optional component, like performance
guarantees, commissioning requirements, works programme, DNP, etc. will be discussed and
decided between Employer and Contractor at this stage, before the start of the works. Terms
and conditions of the main contract will principally also apply for these works.
7-95
EMPLOYER’S REQUIREMENTS-FIN
Sludge recycling Pumps, variable speed, max. capacity 150 m³/h, valve and
check valve at pressure side, Flow meter;
• Supernatant recycling pumping station;
Supernatant Water Pumps, variable speed, non-clogging impeller, capacity
2400 m³/h;
Valves at suction and pressure side, check valve;
Flow meter;
• Sludge pumping station for thickened sludge (if necessary and indicated by Contractor’s
design);
Sludge Pumps, horizontal-dry well installation, non-clogging impeller, capacity
300 m³/h;
Valves at suction and pressure side, check valve;
Flow meter;
• Mechanical sludge dewatering;
Pre-dewatering units (e.g. thickeners, centrifuges, etc.), outlet min. 4% DS.
Building, including dewatering machines, polymer preparation/dosing, conveyor
system, containers, etc.
Roofed dewatered sludge storage plate 7 days’ storage.
The Contractor is free to design alternative ways of the sludge dewatering system, considering
an inflow concentration of 0.4% – 0.6% DS and reaching a dewatering level of 25% DS. Also, the
recycling streams and an appropriate sludge container feeding system shall be considered. The
dewatered sludge, which reaches the specified dewatering results will have to be disposed-off by
the Employer.
7-96
EMPLOYER’S REQUIREMENTS-FIN
The following offices with a total plan area of 90 m2, complete with furnishings and equipment, all
as specified, is required at the water treatment works site:
• 1 No desk (minimum 2000 mm x 900 mm) with six lockable drawers and swivel armchair to
suit.
• 3 Nos. desks (minimum 1800 mm x 900 mm) with six lockable drawers and swivel
armchair to suit.
• 2 Nos. desks (minimum 1200 mm x 750 mm) with four lockable drawers and swivel
armchair to suit.
• 1 No conference table(s) (minimum 6000 mm x 2000 mm).
• 2 Nos. tables to match desk (minimum 2000 mm x 1000 mm).
• 12 Nos. upholstered upright chairs to suit conference table.
• 4 Nos. kitchen chairs and kitchen table to match.
• 5 Nos. plan chests with six drawers to suit AO size drawings.
• 5 Nos. dustproof lockable cupboards (1800 mm x 900 mm x 540 mm) with four shelves.
• 5 Nos. lockable filing cabinets each with four drawers.
• 2 Nos. drawing filing chests (hanging) to suit AO size drawings.
• 4 Nos. bookcases (1200 mm x 450 mm x 900 mm height).
• 6 Nos. Pinboards (3 sqm).
• 6 Nos. wastebaskets.
• 3 Nos. clothes lockers 0.5 m x 0.5 m x 1.80 m.
• 1 worktop, minimum 4 m long for viewing drawings.
7-97
EMPLOYER’S REQUIREMENTS-FIN
• 1 No four-burner gas stove with oven, complete with two 25-kg gas bottles.
• 1 No single bowl sink with draining board.
• 1 No 340-liter capacity refrigerator.
• 1 No drinking water fountain.
• Crockery and cutlery (8 sets each, minimum), ironmongery, and utensils.
• 2 Nos. first-aid lots.
• 4 Nos. flashlights.
Office Sundries:
Stationeries:
For all Offices the Contractor shall supply all necessary Office supplies, stationary and
consumables, including requirements of pens, pencils, paper, erasers, notebooks, surveying
books, sharpeners, staplers, adhesive tape, drawing accessories, chemicals for copying
machine, bottled gas, cleaning materials, etc. for the duration of the contract to the requirements
of the Engineer.
7-98
EMPLOYER’S REQUIREMENTS-FIN
• 1 No:
Boat
10 passengers, roofed
7-99
EMPLOYER’S REQUIREMENTS-FIN
Normal Operation and maintenance costs (including fuel) to be borne by the Contractor.
The Contractor shall provide and maintain the following surveying equipment:
7-100
EMPLOYER’S REQUIREMENTS-FIN
7-101
EMPLOYER’S REQUIREMENTS-FIN
Physical Examination
7-102
EMPLOYER’S REQUIREMENTS-FIN
Microbiological analysis:
• Total coliform
• Thermotolerant (faecal) coliforms
• Faecal streptococci
• Heterotrophic plate count
• Salmonella
• Entero viruses
Laboratory equipment
I Microbiological analysis and Microscope test
Item Description Quantity
1 Digital Incubators - 80 litre with Thermostat and thermometer (+/ 0.2°C) 1
2 Water bath or heat sink incubator, 44.5° (+/-0.2°) C 1
3 Vertical Autoclave 65 litre 1
4 GW-Bunsen Bunsen Burner Complete 2
5 Digital Hot Air Sterilizing Oven 160 to 170°C. 1
6 Refrigerator (2 -10°C) - 300 lt. 1
7 Inoculation Equipment 1
8 Vacuum pump complete with suction pipes 1
9 Sampling Thermometer 0-50 °C 2
10 Waterladle thermometer with substitute Thermometer 1
11 Biosafety Cabinet-Level 2 1
12 pH/Cond/O2 : HQ40d Multimeter, pH 1
13 Triple beam balance 1
14 AC Filter Membrane 0.45um,47mm 100P each /for
2 years
15 Advantec Vacuum Filtration Manifolds with 3 valves 1
16 Dispersing machine with dispersing tool 1
17 Chlorine Test Kits 1
18 Indicator paper pH 0-14
7-103
EMPLOYER’S REQUIREMENTS-FIN
Laboratory equipment
19 Emergency shower and eyewash 1
20 Metallic forecepts 2 pairs
21 Bi-Distillation unit with accessories 1
I.1 Microscope Test -Scale room
Item Description Quantity
1 Microscope and Light Source (10X to 15X with a diffused light developed 1
by cool white fluorescent lamps) with camera
2 ACN Filter Membranes,0.45um,47mm 100P 5
3 Colony counter 1
4 Fume Hood with air extraction 1
5 Ultraviolet UV Sterilizer Cabinet 1
6 Moisture analyser (Accuracy of the weighing 1 mg; Reproducibility: Initial 1
sample weight > 1 g; (%): ± 0,20; Readability: 0,01 %
7 Analytical balance Capacity: 230 g 1
Readability: 0,1 mg
8 Emergency shower and eyewash 1
I.2 Reagent for microbiological analysis like:
Item Description Quantity
1 Dehydrated lauryl sulfonate tryptose (LST) broth -Reagent grade water for 2
years
2 HiCrome E. coli Agar for 2
years
3 E. Coli Agar 90mm Plates 10 Pack for 2
years
4 MFC Agar 65mm Plates 10 Pack for 2
years
5 Ethanol 99.9% 2.5L for 2
years
6 Adsorbent pads for 2
years
7 Acetone 2 litres
8 Quanty tray sealer for colilert method for 2
years
9 Rubber sealing tray holders (quanti disc) - big trays 1
10 Rubber sealing tray holders (quanti disc) - small trays 1
11 UV light viewer-colilert method 1
12 Quanty tray pack of
100
13 Quanty tray 2000 pack of
100
14 Colilert 18 media pack of
200
I.3 Glassware for Microbiological Analysis
Item Description Quantity
1 Draining rack of wire 4
2 Corrosion resistant test tube racks 4
3 Petri dish 100
7-104
EMPLOYER’S REQUIREMENTS-FIN
Laboratory equipment
4 Erlenmeyer flask, 50ml, 2
5 Erlenmeyers flask, 100ml 2
6 Erlenmeyers flask, 250,ml 2
7 Erlenmeyers flask, 500ml, 2
8 Erlenmeyers flask,1000ml 2
9 Measuring Cylinder 1 Litre 2
10 Measuring Cylinder 50ml 1
11 Measuring Cylinder 100ml 2
12 Measuring Cylinder 250 ml 2
13 Measuring Cylinder 500 ml. 2
14 Measuring Cylinder 1000 ml. 2
15 Glass Measuring Pipette - 1ml 2
16 Glass Measuring Pipette - 5ml 2
17 Glass Measuring Pipette - 10ml 2
18 Safety pipette filler universal for bulb/graduated pipettes all sizes 2
19 Durham Tubes 20
20 Glass Beakers, 50ml 2
21 Glass Beakers, 100 ml 4
22 Glass Beakers, 250 ml 4
23 Glass Beakers, 500 ml 4
24 Glass Beakers, 1000 ml 2
25 Watch glass 3
26 Stirring rods 2
27 Borosilicate glass Burettes 10 ml 1
28 Borosilicate glass Burettes 25 ml 1
29 Borosilicate glass Burettes 50ml 1
30 Borosilicate glass Burettes 100 ml 1
31 Borosilicate Glass Culture Tubes 20
32 Fermentation Tubes 3
33 Dilution Bottles closed with glass stoppers or plastic screw caps (Pyrex), 2
100ml
34 Dilution Bottles closed with glass stoppers or plastic screw caps (Pyrex), 2
250 ml
35 Dilution Bottles closed with glass stoppers or plastic screw caps (Pyrex), 2
500 ml
36 Dilution Bottles closed with glass stoppers or plastic screw caps (Pyrex), 2
1000ml
37 Sampling Bottles 500 ml 30
38 Sampling Bottles 1000 ml 30
39 Transfer loops 2
40 Bottle Wash 500ml 2
41 Sampling stick 2,3 m with beaker 1000 ml 1
42 Vacuum pump complete with suction pipes 1
II Physico -Chemical analysis
7-105
EMPLOYER’S REQUIREMENTS-FIN
Laboratory equipment
Item Description Quantity
1 Photometer complete with accessories (last generation) 1
2 Spectrophotometer complete with accessories (last generation) 1
3 BOD 5 Day system complete with spare bottles and chemicals. Spares 1
for 2 years
4 COD Digestor 25 place with cover 2
5 Fume Hood with air extraction for Physico-chemical 1
6 Fume Hood with air extraction for Reagent preparation room
7 Moisture analyser 1
8 Refrigerator (2 -10°C) - 300 lt. 1
9 Portable Multimeter or similar with spare probes and calibration kit 1
10 Portable Meter for pH, ORP, Ion, Conductivity, TDS, Salinity, Resistivity, 1 each
Dissolved Oxygen, Temperature. With Spare probes, maintenance and
calibration Kit.
11 Sediment cone set with rack 1
12 Dispersing machine with dispersing tool 1
13 Desiccator
14 Drying oven 1
15 BOD Refrigerated Incubator 1
16 Bi-Distillation apparatus with accessories - 1
17 Hot plate 1
18 Chlorine Test Kits 1
19 Jar Testing Equipment with accessories 1
20 Indicator paper pH 0-14 1
21 Analytical balance Capacity: 520g, Readability: 0,1 mg 1
22 Thermometers 0-100 Celsius 2
23 Sampling thermometer 0-50°C 2
24 Turbidity Meter :HF – Micro 100 WL Turbidity Meter 1
25 Open balance 2 kg. 1
26 Lovibond comparator with Chlorine discs. 0- 5.0mg/l 1
27 Emergency shower and eyewash 1
28 Electric stirrer 1
29 Digital titrator 1
30 Flow meter 1
31 Van dorn water sampler 1
II.1 Reagent for Physico Chemical analysis like:
Item Description Quantity
1 Ammonia range 0.2 +B96:B109-2.5 mg/l N 100 vials 3
2 Ammonia vial test reagents set COD VIALS Vario > 0 - 150mg/l 25 vials for 2
years
3 COD vials Vario > 0 - 1 500mg/l for 2
years
4 Vario NITRA X Reagent Unit set for 2
years
7-106
EMPLOYER’S REQUIREMENTS-FIN
Laboratory equipment
5 Nitrite range: 0.01 to 0.5 mg/l N Nitrite tablets for 2
years
6 Nitrite LR Tablets for 2
years
7 Phosphate, ortho: Range: 0.05 to 4 mg/l PO4 tablets L/R 1 for 2
years
8 Phosphate, No. 2 LR tablets for 2
years
9 Phosphate, ortho, Range: 1 - 80 mg/l PO4 Phosphate HR P1 tablets for 2
years
10 Aluminium test, range: 0.01 – 0.3 mg/l Al CELL & LID - PC CHECKIT for 2
years
11 Aluminium No. 1 Tablets for 2
years
12 Ammonia test, Range: 0.02 - 1.0 mg/l N CELL & LID - PC CHECKIT 12 for 2
Pack years
13 Ammonia No. 1 Tablets for 2
years
14 Chloride T1 Tablets 100 Tests for 2
years
15 Chloride free range: 0.01 – 6 mg/l Cl, DPD No.1, tablets for 2
years
16 Hardness (Total), Range: 2 – 50; 20 - 500 mg/l CaCO3 Cell & Lid - PC for 2
CHECKIT years
17 Hardcheck tablets for 2
years
18 Manganese, Range: 0.2 - 4 mg/l Mn CELL & LID - PC CHECKIT for 2
years
19 Manganese LR NO 1 Tablets for 2
years
20 Iron II, III Soluble, Range: 0.1 - 3mg/l Fe - W 100/OG/50mm CELL CELL for 2
& LID - PC CHECKIT years
21 Iron total Ferro 10ml sample, Powder Pillows for 2
years
22 Nitrate Range: 0.5 - 14 mg/l N, Nitrate Cuvette test unit for 2
years
23 Vario Nitrite Powder Pillows for 2
100 Powder Pillows years
24 Sulphate, range: 2 to 100 mg/l SO4, CELL & LID - PC CHECKIT for 2
years
25 Sulphate Vario sulpha 4 F10- Powder Pillows for 2
years
26 D.P.D Tablets No.3 for 2
years
27 D.P.D Tablets No.1 for 2
years
28 EDTA 0.02Mol solution standard 5l for 2
years
29 Bromocresol Green 25g for 2
years
7-107
EMPLOYER’S REQUIREMENTS-FIN
Laboratory equipment
30 Methyl red sodium salt 25g for 2
years
31 Phenophtalyne disoduim salt 25 g for 2
years
32 Sodium thiosulphate 250g for 2
years
33 Sodium Hydroxide 250g for 2
years
34 Sodium sulphite 100g for 2
years
35 Sodium Carbonate 250g for 2
years
36 Ammonium Hydroxide 250g for 2
years
37 Potassium dihydrogen phosphate 250g for 2
years
38 Methyl Orange powder 50g for 2
years
39 Ammonium chloride 250g for 2
years
40 Silver Nitrate 250g for 2
years
41 TITRISOL Solutions. for 2
years
42 Potassium permanganate 1 Normal for 500ml for 2
years
43 Hydrochloric acid 0.1 Molar for 500ml for 2
years
44 Nitric acid 0.1 Molar for 500ml for 2
years
II.2 Chemicals
Item Description Quantity
1 Hydrochloric acid 33% x 2.5 l for 2
years
2 Ammonia solution for 2
years
3 Chloroform 2.5 l for 2
years
4 Nitric acid 2.5l for 2
years
5 Sulphuric acid 2.5l for 2
years
6 Acetic acid for 2
years
7 Isopropyl alcohol 2.5l for 2
years
II.3 Glassware Physico
Item Description Quantity
1 Wide neck bottle, PP 100ml 2
2 Wide neck bottle, PP 250 ml 2
7-108
EMPLOYER’S REQUIREMENTS-FIN
Laboratory equipment
3 Wide neck bottle, PP, 500 ml 2
4 Wide neck bottle, PP, 1000ml 2
5 Wide neck bottle, glass 100ml 2
6 Wide neck bottle, glass 250 ml 2
7 Wide neck bottle, glass, 500 ml 2
8 Wide neck bottle, glass, 1000ml 2
9 Sampling Bottles 500 ml 30
10 Sampling Bottles, 1000ml 30
11 Distilled water wash bottle 2
bottles
12 Beaker, PP low form 100 ml 5
13 Beaker, PP low form 250 ml 5
14 Beaker, PP low form 500 ml 5
15 Beaker, PP low form 1000 ml 5
16 Beaker, glass low form 100 ml 5
17 Beaker, glass low form 250 ml 5
18 Beaker, glass low form 500 ml 5
19 Beaker, glass low form 1000 ml 5
20 Spatula spoon 2
21 Aluminium weighing dishes 4
22 Filter flask 1
23 Vacuum Flask 1
24 Vacuum pump 1
25 Filter pads for 2
years
26 Volumetric wide tip pipettes, 25 ml 2
27 Volumetric wide tip pipettes, 50,ml 2
28 Volumetric wide tip pipettes, 100 ml 2
29 Borosilicate glass Burette 50 ml capacity 4
30 Burette capacity 25 ml
31 Micro burette capacity 10 ml 2
32 Burette stand 2
33 Burette stand clamps double 2
34 Volumetric flask 50ml
35 Volumetric flask 100ml 2
36 Volumetric flask 250ml 2
37 Volumetric flask 500ml 2
38 Volumetric flask 1000ml 2
39 Volumetric flask capacity 250 ml 2
40 Volumetric flask capacity 100 ml 2
41 Pipettes capacity 5ml 2
42 Pipette capacity 10 ml 2
43 Pipette capacity 25 ml 2
7-109
EMPLOYER’S REQUIREMENTS-FIN
Laboratory equipment
44 Beakers capacity 100ml 2
45 Beakers capacity 250ml 2
46 Beakers capacity 500ml 2
47 Beakers capacity 1000ml 2
48 Measuring cylinders 50ml 2
49 Measuring cylinders 100ml 2
50 Measuring cylinders 250ml 2
51 Measuring cylinders 500ml 2
52 Measuring cylinders 500ml 2
53 Dropper bottles 75ml 3
54 Dropper bottles 100ml 3
III Others
Item Description Quantity
1 Certified Safety Glasses (for eye protection ) 10
2 Acid Resistant Neoprene Gloves (package of) 10
3 First Aid Kit in a Weather-proof Container (as per the NWT 4
General Safety Regulations)
4 Cooler 3
5 Ice packs 10
IV Furniture
Item Description Quantity
6 PC latest generation, for office purpose, incl. Basic software (Win, MS 9
Office, antivirus, ACAD preview),internet available
11 Telephone tables 9
12 Telephone units 9
13 Telephone exchange (9 lines) 9
7-110
EMPLOYER’S REQUIREMENTS-FIN
APPENDIX D: Furniture
The Contractor shall provide and place the following furniture for Administration Building,
Canteen, Laboratory, Workshop, Guard houses, Staff houses:
7-111
EMPLOYER’S REQUIREMENTS-FIN
7-112
EMPLOYER’S REQUIREMENTS-FIN
7-113
EMPLOYER’S REQUIREMENTS-FIN
2 worktops covered with acid and lye proof ceramic tiles (pointed acid
and lye proof), length: 300 cm, height: 85 cm, depth: 70 cm,
10 floor units (length = 60 cm) below worktop, a) with 1 to 3 shelves and
doors, b) with 4 drawers,
5 wall units (length = 60 cm, height: 60 cm, depth: 40 cm) above worktop,
with 1 to 3 shelves and doors,
1 worktops covered with acid and lye proof ceramic tiles (pointed acid
and lye proof), with double ceramic sinks (produced in one piece), acid
and lye resistant batteries (hot / cold water), length: 120 cm, height:
85 cm, depth: 70 cm,
1 AC unit of capacity sufficient to the gross volume of the room complete
with all supports, electrical and plumbing work, indoor conditions to be
achieved: max. air temperature 30°C, air humidity: 60-80% (cooling
capacity not less than 1,500 W),
4 grounded sockets
2 grounded sockets connected to the circuit for UPS,
1 emergency shower head with ripcord,
1 emergency eye washing units,
1 fire extinguisher, wall mounted,
1 first aid kit, wall mounted,
7-114
EMPLOYER’S REQUIREMENTS-FIN
7-115
EMPLOYER’S REQUIREMENTS-FIN
7-116
EMPLOYER’S REQUIREMENTS-FIN
7-117
EMPLOYER’S REQUIREMENTS-FIN
7-118
EMPLOYER’S REQUIREMENTS-FIN
Workshop, total 210 Note: Machines and tools are specified in other Sections in this document
(mechanical
heavy duty,
mechanical,
electrical)
Guard houses 1 office desk ≥ 1 m², with mobile file drawer (on 4 rolls) and drawers, all
lockable incl. keys,
1 armchair with 5 rolling casters,
1 bookshelves (4 shelves, lower 2 shelves with doors), 80 cm x 200 cm,
40 cm deep,
1 coat rack,
1 waste basket,
2 grounded sockets.
Accommodation Clear height: 3.27 m (top of floor slab till lower edge of beams)
“White Collar”
One semi-
detached house
Veranda / entry 5
Living room 26 4 grounded sockets.
Dining room 17 4 grounded sockets.
Kitchen 10 1 base cabinet L = 2.00 m, one with kitchen-counter on top, with
recessed double kitchen sink covered with stone tiles, including two
recessed double stainless steel sinks, battery (hot / cold water),
1 base cabinet L = 3.00 m, with built in gas cooker / oven with 4 stove
tops,
1 wall cabinet L = 2.00 m,
1 wall cabinet L = 3.00 m,
4 grounded sockets.
Shower + toilet 4 1 hot water boiler, capacity: 50 liter, 2.5 kW elec.
1 standard western toilet including flush box and toilet roll holder,
1 wash basin with mirror, plate shelf and soap dish,
1 shower basin, with swivel arm and soap dish.
Bedroom 6 3 grounded sockets.
Bedroom 16 3 grounded sockets.
Bedroom 16 3 grounded sockets.
7-119
EMPLOYER’S REQUIREMENTS-FIN
7-120
EMPLOYER’S REQUIREMENTS-FIN
ASSESSEMNT OF COMPENSATION
1. Introduction
As already indicated an update of the old valuation report was conducted by Alliance
Consultants Ltd in June and October 2016, intended to estimate the current compensation
values. This section presents valuation methodology and the budget estimates.
The purpose of the cadastral and valuation exercise is to provide a framework through which
people that will be affected by the construction of the WTP and expropriation of land are
adequately identified, and subsequently fairly and appropriately compensated or resettled before
commencement of the construction works.
Cadastral Surveys
The actual valuation was preceded by the cadastral survey that involves:
1. Obtaining the cadastral data and other relevant information necessary to identify all
property owners and other persons that likely to be affected by the project, using
maps and drawings that show the land tenure system and affected land along the
alignment
2. Definition of the land tenure through which the project route runs
3. Surveying and documentation of land and built structures that are located within the
demarcated corridor
4. Production of the cadastral strip map that shows the boundaries and ownership of
the land parcel, that guides the valuation and land acquisition process
5. After the compensation exercise, the mutation, subdivision surveys, land title
processing and return of the residue land titles to the PAPs is expected to follow,
however this will exclude land in the Mukono-Katosi road reserve that has already
been acquired by UNRA/ Government of Uganda
6. A cadastral survey to amalgamate all the subdivided parcels of land so as to
produce one title for Government/ NWSC will be undertaken.
Valuation Methodology
The valuation was done following International Valuation Standards for the purpose of
ascertaining the quantum of compensation payable for the affected assets. The process
incorporated valuation principles and guidelines as issued by the Chief Government Valuer. The
exercise of land and property valuation for compensation followed the five stages outlined below;
• Reconnaissance and stakeholder’s engagement
• Community mobilization and sensitization
• Land surveys done by the Land Surveyor
• Inspection and referencing of buildings and structures, and enumeration and
assessment of economic trees, fruit trees and crops (trees outside NFA land)
7-121
EMPLOYER’S REQUIREMENTS-FIN
The valuation of the land taken was guided by the cadastral surveys undertaken by the project
surveyor. The land surveyor provided the valuation team with acreage of land taken from each
individual (PAP) as affected by the water treatment project, in respect to the nature of interest in
the land, for instance, Private Mailo, Lease or Kibanja. In the field, the Land Survey Teams fixed
pegs to visually indicate the extent of the project area and to mark the various interests in land
along the project area including that of registered land and customary land. Then valuer started
the valuation exercise. The valuation team, assisted by Local Leader (LC1) of the affected
villages, in the presence of neighbours and property owners, identified, referenced and recorded
the stakeholders’ properties on their respective Bibanjas/land holdings. The property included all
land, developments/structures and crops belonging to the project affected person.
All buildings/structures affected by the Project were photographed with their respective
owners/claimants standing in front of them. The same L.Cs (and neighbours) signed
witnessed/confirmed all the property items recorded on the assessment/crop forms for valuation
of each claimant property located in the project area.
a) Ownership/Tenure: The WTP affects different types of land tenure (e.g. Mailo/Freeholds,
Leaseholds and Customary holdings) and these were assessed appropriately. The biggest
category of PAPs on the land falls under Licencees (on NFA land) followed by Bibanja holdings
on titled land.
b) Land: The proposed water works at Ssumbwe landing site, part of the pipe line and the water
reservoir on Nsumba hill will affect land belonging to National Forest Authority land, and the
PAPs on that land are considered to be Licensees, growing crops and having temporary/semi-
permanent structures. The PAPs will not compensated for the land but only perennial crops and
their temporary/semi-permanent structures.
On the other hand, the private property owners will be compensated for their land and
improvement on the (structures and crops). The individual acreages of land that is affected by
the Project is indicated on the land surveyor’s Strip Map, Valuation Report and Summary Values
as well as on the respective Compensation Assessment Forms. The total land area for private
land owners (including Titled land) that is to be affected by the project is yet to be determined by
the Land Surveyor on acquiring all requisite data from the Lands Office. Nonetheless, the total
land may not exceed 12.00 acres.
d) Crops: Both perennial and seasonal crops will be affected by the project. However, the
assessment concentrated on all and only perennial crops and trees within the project area
(excluding the tree on NFA land). Seasonal crops were left out of assessment because will be
ready for harvest between the time of assessment and compensation payment and/or the time of
giving up vacant possession of land before construction phase.
7-122
EMPLOYER’S REQUIREMENTS-FIN
The valuation was computed on the basis of the Laws governing compensation as provided for
under The Uganda Constitution, 1995, The Land Act, 1998 (Amended) and The Land Acquisition
Act, 1965. They all emphasize “open market values”.
a) Land
Land values were based on comparable market values/sales of land/holdings in the area and as
evident in the different locations along the project area. A rapid and thorough survey was carried
out in the project area and neighbourhood in order to determine the land market values.
The market value of land is the price that would be obtained in a situation of a willing seller and a
willing buyer in normal market conditions and is indicated by the indicative price for a standard
size of land in an area/neighbourhood. Speculative land deals entered into as a result of the
proposed Project were ignored in arriving at the comparable land values.
b) Buildings/Structures
These were referenced/measured, details of construction, finishes, areas, accommodation,
quality of workmanship and condition recorded. These details formed the basis of the
compensation assessments for such structures. All buildings/structures in the Project Area were
photographed for record/verification purposes.
a) For buildings and structures constructed in permanent materials, the valuation was
based on their replacement costs.
c) For Crops, valuation was based on the current “Approved” Mukono District Area
Compensation Rates as prepared by Mukono District Land Board. Only Perennial crops,
trees, etc. within the Project Area were physically counted per owner/stakeholder’s holding.
It should be noted that where there was evidence of excessive/big numbers of crops, as would
not be in line with normal agricultural department planting/spacing recommendations or normal
crop husbandry, those figures were adjusted to be commensurate with the normal
recommendations. Where such adjustments were made, the remarks were footnoted on the
Compensation Assessment Forms.
2.4 Recording
All field data that was captured in the field was recorded on Compensation Assessment Forms
which state/clarify the construction details, areas, numbers, nature/type and qualify/condition of
the assets (especially trees and crops).
7.2.5 Disturbance Allowance
In compliance with The Land Act, 1998 (Amended) and other Statutes governing compensation,
a “Statutory” Disturbance Allowance has been added on top of the total (land,
buildings/structures and crops) compensation figure. A Statutory” Disturbance Allowance of 30
% has been added on top of the total compensation assessment figure ((land,
buildings/structures and crops). This is on the assumption that the project affected persons shall
be given less than 6 months to give up their interests in the land and relocate elsewhere.
It should be noted that there may be some claims for compensation at a later date which
will/might arise out of “Injurious Affection” as a result of/in the course of the Project works. Such
7-123
EMPLOYER’S REQUIREMENTS-FIN
cases will be considered for assessment for compensation at the appropriate time.
Compensation may also be considered where the residue portion of land is so small that it is
rendered useless to the stakeholder (“Severance”).
The provisional total compensation assessed in respect of the (304) Project Affected
Persons’/owners’/claimants’ interests (so far identified) in the proposed NWSC Project Area is in
the region of UGX 550,000,000/= (Five Hundred and Fifty Million, only).
Schedules of Summary Values and the respective Crop/Assessment Forms showing details of
valuation will be attached to the final Valuation Report (bound separately).
That budget estimate excludes the proposed resettlement assistance proposed for Sumbwe
landing site, which is presented in the next chapter.
7-124