Combustion Inspection
• Combustion Liners
• Combustion Endcovers
• Fuel Nozzles
• Transition Pieces
• Cross Fire Tubes
• Flow Sleeves
• Purge Valves
• Check Valves
• Flex Hoses
Combustion Inspection
Combustion Inspection
Primary Mode
cpd
Primary Gas Purge
Dual fuel only
GSV
Primary
SRV GCV
FD
Secondary
GTV
Transfer
cpd
Transfer Purge
Operation 9: Remove the false start drain tubing
Operation 10: Remove the secondary fuel nozzle
Operation 11: Remove the spark plugs
Operation 12 and 13: Remove the eleventh stage cooling and
sealing air
Operation 14: Remove fuel nozzle – end cover assemblies
Operation 15: Remove the crossfire tube retainers
Operation 15: Remove the combustion liners
Operation 15: Remove the crossfire tubes
Operation 16: Remove the access port blank flange from upper
turbine casing or other upper section of the atomizing air
extraction manifold
Operation 17: Remove the outer combustion casings and
flow sleeves
Operation 18: Remove transition pieces