Sie sind auf Seite 1von 21

A Perspective on the Seismic

Design of Precast Concrete


Structures in New Zealand
The author describes trends and developments in the use of
precast concrete in New Zealand for floors, moment resisting
frames, and structural walls of buildings. Currently, almost all
floors, most moment resisting frames, and many one- to
three-story walls in buildings are constructed incorporating
precast concrete elements. Aspects of design and
construction, particularly the means of forming connections

Robert Park, Ph.D.


I between precast concrete elements, are discussed. The
paper emphasizes seismic design; the aim of the design
methods for frames is to emulate monolithic construction.
Examples of recent precast concrete buildings using the
Professor of Civil Engineering
University of Canterbury above discussed methods are presented.
Christchurch, New Zealand

In addition to his duties as a faculty ince the early 1 960s, there has formwork and site labor, and in
member in the Department of Civil
Engineering, Professor Park is Deputy
Vice-Chancellor of the University of
Canterbury and Chair of the Concrete
S been a steady increase in the
use of precast concrete for
structural components in buildings in
creased speed of construction. In par
ticular, with high interest rates and
pressure for new building space in the
New Zealand. The use of precast con mid 1980s, the speed advantage gave
Design Committee of Standards crete in flooring systems has been precast concrete a distinct cost advan
of New Zealand. During his long
commonplace since the 1 960s, making tage. Contractors adapted to precast
professional career, he has received
cast-in-place floor construction gener concrete construction with increased
many awards and honors, including
PCI’s Martin P. Korn Award (twice) ally uncommon. Also, precast con crane capacity, new construction tech
and ASCE’s T. Y. Lin Award. Under crete non-structural cladding for build niques, and off-site fabrication.
his leadership, the University of ings has been widely used. The increase in the use of precast
Canterbury is well known throughout During the boom years of building concrete in the 1980s required consid
the world for its pioneering research construction in New Zealand in the erable innovation because of New
in the seismic design of structures. mid to late 1980s, there was also a sig Zealand’s location in an active seismic
nificant increase in the use of precast zone; the seismicity of most of New
concrete in moment resisting frames Zealand is similar to that of California.
and structural walls. Precast concrete At the time, the New Zealand concrete
elements have the advantages of high design standard, NZS 3101:1982,’ like
quality control, a reduction in site the concrete codes of many countries,

40 PCI JOURNAL
contained comprehensive provisions Earthquake Engineering, and the Cen cally at the ultimate load.
for the seismic design of cast-in-place tre for Advanced Engineering at the In common with other countries, the
concrete structures but did not have University of Canterbury, was formed seismic design forces recommended
seismic provisions covering all aspects with the following objectives: for structures in the current New
of precast concrete structures. The de 1. Summarize data on precast con Zealand loadings standard for general
sign ultimate seismic forces used for crete design and construction structural design and design loadings
the design of ductile moment resisting 2. Identify special concerns for buildings, NZS 4203:1992, are
frames in the most seismically active 3. Indicate recommended practices significantly less than the inertia
parts of New Zealand are very similar 4. Recommend topics requiring fur forces induced if the structure re
to those recommended by the Uniform ther research sponded in the elastic range to a major
Building Code
2 in Zones III and IV of The outcome of the deliberations of earthquake. The design seismic force
the United States. the Study Group during 1988-91 was is related to the achievable structure
In the past, some framed structures the publication of a manual authored ductility factor = maxMy, where
incorporating precast concrete ele by the members of the Study Group ti max is defined as the maximum hori
ments have performed poorly in earth tled “Guidelines for the Use of Struc zontal displacement that can be im
quakes in many countries because of tural Precast Concrete in Buildings,” posed on the structure during several
poor connection details. As a result, which was first printed in August cycles of seismic loading without sig
precast concrete in moment resisting 1991. nificant loss in strength, and is de
frames was excluded in New Zealand A new revision of the New Zealand fined as the horizontal displacement at
for many years. Confidence in the use concrete design standard, NZS 3101: first yield assuming elastic behavior of
of precast concrete in moment resist 1995, is being published in 1995. This the cracked structure up to the design
ing frames required the development revision contains more provisions for seismic force.
of satisfactory methods for connecting the seismic design of structures in In the New Zealand loadings stan
the precast elements together. The de corporating precast concrete than its dard, NZS 4203:1992, for ductile
sign methods that were introduced in predecessor. structures, ji = 5 or 6 is used to deter
New Zealand in the 1980s for frames This paper describes aspects of the mine the appropriate spectra of seis
of buildings incorporating precast con design and construction of buildings in mic coefficients from the elastic re
crete elements generally aimed to New Zealand incorporating precast sponse spectra. The design ultimate
achieve behavior equivalent to that of concrete structural elements in floors, horizontal seismic forces typically
a completely cast-in-place concrete moment resisting frames, and struc vary between 0.03g and 0.20g. de
structure. That is, the objective of the tural walls. Design and construction pending on the seismic zone, the soil
design method is to emulate mono for seismic resistance are also empha category, the importance of the struc
lithic construction. sized because that is where the great ture and the fundamental period of vi
With the increase in the innovative est difficulties lie in the connection of bration of the structure.
use of precast concrete elements in precast concrete elements. For structures of limited ductility,
buildings in New Zealand came an in = 3 is used and the design ultimate
creasing concern that some of the de horizontal seismic forces typically
sign solutions should be more fully re SEISMIC DESIGN
vary between 0.03g and 0.39g. The
searched. Even if there were no reason CONCEPTS FOR PRECAST design ultimate seismic forces recom
to doubt the validity of extrapolating CONCRETE IN BUILDINGS mended in the New Zealand loadings
the results of design and construction 5 for cast-in-place concrete
standard
procedures that were originally devel General Requirements structures and for structures incorpo
oped for cast-in-place concrete, the For moment resisting frames and rating precast concrete elements of the
large number of important buildings structural walls constructed incorpo same available ductility, are identical.
employing precast concrete for seis rating precast concrete elements, the Note that as an alternative to ductile
mic resistance demanded that more re challenge lies in finding an economi structures, designers can design struc
search and testing be done to justify cal and practical means of connecting tures of limited ductility with higher
confidence in the structural systems. the precast concrete elements together design ultimate seismic forces but
In February 1988, a seminar at the to ensure adequate stiffness, strength, with less stringent requirements for
University of Canterbury, attended by ductility, and stability. The design detailing for ductility.
designers, researchers, fabricators and should consider the loadings during The exact characteristics of the
constructors, highlighted a growing the stages of construction and at the earthquake ground motions that can
need to investigate and verify aspects serviceability and ultimate limit states occur at a given site cannot be pre
of the performance of precast concrete during the life of the structure. The de dicted with certainty and it is difficult
in building structures designed for sign should ensure that the structure to evaluate all aspects of the complete
seismic resistance. Following the sem performs satisfactorily in the service behavior of a complex structure when
inar, a Study Group, jointly funded by load range, has a reasonable margin of subjected to a major earthquake. Nev
the New Zealand Concrete Society, safety before the ultimate load is ertheless, it is possible to design the
the New Zealand National Society for reached, and will not fail catastrophi structure to ensure the most desirable

May-June 1995 41
behavior. The rational approach for
achieving this objective in the design
for earthquake resistance is to choose
irn
the most suitable mechanism of post-
elastic deformation for the structure irn
and to ensure, by appropriate design
procedures, that yielding of struc
iLL Frame
tural members will occur only in the
chosen manner during a major earth
quake and that the available ductility
is adequate.
5

4
If all the elements of the structure
resisting seismic forces are detailed
for ductility in accordance with the
seismic provisions of the concrete de Coupled structural walls
and mechanism
4 adequate ductility is
sign standard,
considered to be provided. Fig. 1. Possible mechanisms of post-elastic deformation for equivalent monolithic
moment resisting frames and structural walls of buildings during severe seismic
loading.
Capacity Design
To ensure that the most suitable
mechanism of post-elastic deformation ral strength of the plastic hinge regions.
occurs in a structure during a major These factors include an actual yield
earthquake, New Zealand standards strength of the longitudinal reinforcing
NZS 4203:l992 and NZS 3101: steel, which is higher than the lower
l995 require that ductile structures be characteristic yield strength,* and ad
the subject of capacity design. In the ditional longitudinal steel strength due Type 1
earn

capacity design of structures, elements to strain hardening at large ductility


of the primary lateral earthquake load factors. Due to these two factors, the
resisting systems are suitably designed
and detailed for adequate strength and
ductility for a major earthquake. All
steel overstrength in New Zealand is
taken to be 1.25 times the lower char
acteristic yield strength when calculat
1-
Precast concrete
hollow-core unit
other structural elements and possible ing the probable maximum flexural concrete
failure modes are then provided with strength in the plastic hinge regions. Type 2
sufficient strength so that the chosen As a result, the shear reinforcement
means for achieving ductility can be in the plastic hinge regions, and all Cores broken out Cast-in-place
/‘“concrete topping
maintained throughout the deforma flexural reinforcement in parts of the Na_.___
Precast concrete
tions that may occur.
5

4 structure away from plastic hinge re
ik• 4.1 unit
For moment resisting frames and gions, will need to be designed for
of cores to be
structural walls of buildings, the best shear forces and bending moments filled with concrete
means of achieving ductile post-elastic that are at least 1 .25I times the shear beam
concrete

deformations is by flexural yielding at forces and bending moments associ Type 3


selected plastic hinge positions. With ated with the design bending moments
Fig. 2. Types of support using precast
proper design, the plastic hinges can be of the plastic hinge regions. This en
concrete beams for hollow-core floor
made adequately ductile. To ensure that sures that non-ductile failures do not
units (Ref. 3).
failure in flexure cannot occur in parts occur elsewhere, where 1.25 is the
of the structure not designed for ductil steel overstrength factor and is the
ity, or that failure in shear cannot occur strength reduction factor used for de strength of steel in beams.
4
anywhere in the structure, the maxi signing the flexural reinforcement at The use of capacity design has
mum forces likely to be imposed on the the plastic hinge, taken as 085 in New given designers confidence that struc
structure should be calculated from the 4 If plastic hinges in columns
Zealand. tures can be designed for predictable
probable maximum flexural strengths at of moment resisting frames are to be behavior during major earthquakes. In
the plastic hinges. This is done by tak avoided (that is, strong column-weak particular, brittle elements can be pro
ing into account all the possible factors beam behavior is sought), the design tected and yielding can be restricted
that may cause an increase in the flexu column bending moments may need to to ductile components as intended by
be amplified by much more than the designer. The capacity design pro
1 .25/p in order to guard against higher cedure has enabled structures incorpo
The lower characteristic yield strength is defined as
mode effects and concurrent earth rating precast concrete elements to be
the value of the yield strength below which not more
than 5 percent of production tests in each size fall. quake forces as well as the over- designed for ductile behavior, because

42 PCI JOURNAL
any brittle connections between ele
ments can be designed to remain 665 Mesh
(5.3mm dIameter at 150mm
in the elastic range during a major Topping centres both ways)
earthquake. 750 420 750
7
TIE CONNECTION
Preferred Modes of TYPE I OF
SPECIMEN I
Post-Elastic Deformation
Fig. 1 shows mechanisms of post- Hollow-core unit j \—.ri Grade 300
elastic deformation that could occur in —.. __—_
Seating length
Precast Beam Type I 50mm Test B
equivalent monolithic moment resist 0mm Test A
ing frames and structural walls due to
the formation of plastic hinges during Topping 10 10 665 Mesh
a severe earthquake. These mecha 750 J400[ /Z
nisms are idealizations in that they in lv
volve behavior under the typical TIE CONNECTION
equivalent static seismic forces recom TYPE 2 OF
SPECIMEN 2
mended by codes, which are based
mainly on the first mode of vibration. LI 0\_2-D16
45
\
Grade 300
The actual dynamic situation for mo L Precast Beam Type 2
ment resisting frames and coupled
structural walls can be different due to Topping 10 10 665 Mesh
the effects of higher modes of vibra 750 140011 750 /
tion that can result in the plastic
hinges in the beams forming in a few TIE CONNECTION
stories at a time and moving in waves TYPE 8 OF
SPECIMEN 3
up the structure during the earthquake.
Nevertheless, the static mechanisms of
Fig. 1 give designers a reasonable
sense for the actual situation.
As shown in Fig. 1, if yielding be Mesh
gins in the columns of a moment re Tie 016
/
sisting frame before it begins in the

1
TYPICAL Topping
beams, a column sidesway mechanism CROSS Hollow-core
can form. In the worst case, the plastic SECTION unit
hinges may form in the columns of
only one story because the columns of 1197
the other stories are stronger. Such a
mechanism can make very large cur Fig. 3. Types of special support reinforcement at the ends of hollow-core floor units
vature ductility demands on the plastic tested at the University of Canterbury (Ref. 13).
hinges of the critical story,
6 particu
larly for tall buildings.
On the other hand, if yielding begins frames should have sufficient flexural hinges in any story simultaneously at
in the beams before it begins in the strength to avoid the formation of col the top and bottom ends, while plastic
columns, a beam sidesway mechanism umn sidesway mechanisms as far as hinges develop in some beams only,
will develop, which makes much more possible. Thus, a strong column-weak typically only in the beams at or near
moderate demands on the curvature beam approach to design is advocated. the exterior columns (see the mixed
ductility required at the plastic hinges The New Zealand concrete design sidesway mechanism in Fig. 1). Such
in the beams and at the column bases. 4 has two exceptions to this
standard frames are required to be designed for
Therefore, a beam sidesway mecha rule: design seismic forces which may be
nism is the preferred mode of post- 1. In some buildings in areas of low higher than for frames with beam
elastic deformation, particularly be seismicity and/or where beams have sidesway mechanisms.
cause ductility can be more easily long spans, the gravity load considera 2. For ductile frames of one- or two-
provided by reinforcing details in tions may govern and make a strong story buildings, or in the top story of a
beams than in columns. column-weak beam design impractica multistory building, the New Zealand
As a result of the above considera ble. In such a case, the interior standard permits column sidesway
tions, the New Zealand concrete de columns of gravity load dominated mechanisms (that is, a strong beam-
sign standard
4 requires that columns of ductile frames three stories or higher weak column approach) because the
multistory ductile moment resisting may be designed to develop plastic curvature ductility demand at the plastic

May-June 1995 43
inforcing details and structural config
urations can be arranged to ensure that
Cast4n-place
concrete and Cast-In-place concrete the plastic hinging occurs away from
steel In column I and top steel In beam the jointing faces of precast concrete
Mldspan members and cast-in-place concrete
joints, but plastic hinging in regions
including the jointing faces is permit
ted if appropriately designed.

Precas1’ Precast
beam unit beam unit Detailing for Ductility

(a) System 1-Precast Beam Units Between Columns The most important design consider
ation for ductility in the plastic hinge
regions of reinforced concrete mem
Precast or
cast-In-place bers is the provision of adequate longi
column unit tudinal compression reinforcement as
Mldspan
Cast-in-place concrete cast-in-place well as tension reinforcement, and the
Mortar or
grout Joint\ and top steel In beam _,folnt provision of adequate transverse rein
.1’
forcement in the form of rectangular
stirrups, or hoops overlapping or with
cross ties, or spirals.
Precast or Precast beam unit
This ensures they act as shear rein
Cast-In-place forcement, to confine and, hence, to
column unIt enhance the ductility of the com
(b) System 2- Precast Beam Units Through Columns pressed concrete, and to prevent pre
mature buckling of the compressed
longitudinal reinforcement. A center-
precast •l
MIdpan
to-center spacing of transverse bars not
Mortar or Cast-In-place exceeding six longitudinal bar diame
grout joint joint ters in plastic hinge regions is consid
ered necessary to control bar budding.
4
Failure modes to be prevented are
those due to diagonal tension or diago
Precast T- unit
nal compression caused by shear, ex
cessive plastic hinge rotation of heav
ily loaded columns, sliding shear
(C) System 3-Precast T-Unlts along construction joints or other
Notes: Precast Concrete cast-in-place concrete jointing faces or in plastic hinge re
gions, buckling of compressed longi
Reinforcement in precast concrete not shown tudinal reinforcement, and bond fail
ure along lapped splices or at
Fig.4. Arrangements of precast concrete members and cast-in-place concrete for anchorages. All of these undesirable
constructing reinforced concrete moment resisting frames (Refs. 14 and 15). failure modes lead to premature
strength degradation and reduced duc
tility. They can be avoided by use of
hinges of the columns in such cases of the chosen plastic hinge position con the capacity design procedures.
4
low frames is not high and can be pro trols both the strength and post-elastic Joint core regions of beam-to-column
vided by proper reinforcing detailing. deformation capacity of the structure. connections need special attention be
The preferred mechanisms of post- When the connections between the cause of the critical shear and bond
elastic deformation for structural walls precast concrete elements are placed in stresses that can develop there during
are also shown in Fig. 1. For cantilever critical (potential plastic hinge) re seismic loading.
46
walls, a plastic hinge forms at the base gions, the design approach in New
of the wall. For coupled structural Zealand ensures that the behavior of
PRECAST CONCRETE
walls, yielding also occurs in the cou the connection region approaches that
pling beams and, ideally, the beams of a monolithic cast-in-place structure IN FLOORS
should yield before the wall bases. (equivalent monolithic); thus, mono As is common in many countries,
In summary, a capacity design ap lithic construction is emulated. floors in New Zealand buildings in
proach is used in New Zealand to en Possible brittle connections between early years were mainly of cast-in-
sure that, in the event of a severe earth members are made over-strong in place reinforced concrete construction.
quake, flexural yielding of members at order to not be in critical regions. Re- Significant use of post-tensioning was

44 PCI JOURNAL
also made in cast-in-place concrete
floors in the 1950s and 1960s. How
ever, since the 1960s, precast concrete
elements have become widely used in
floors in New Zealand.
Currently, the majority of floors in
New Zealand buildings are con
structed of precast concrete units,
spanning one-way between beams or
walls. The precast concrete units are
made of either pretensioned, pre
stressed concrete or reinforced con
crete (solid slabs, voided slabs, rib
slabs, single tees or double tees) and
generally act compositely with a cast-
in-place concrete topping slab of at
least 50 mm (2 in.) thickness and con
taining at least the minimum rein
forcement required for slabs.
Alternatively, precast concrete ribs Fig. 5. Rnforced concrete building frame incorporating precast concrete elements
spaced apart with permanent form- in the beams between columns as used in System 1.
work of timber or thin precast con
crete slabs spanning between are used
acting compositely with a cast-in-
place concrete slab. The most com Cast-in-place
mon floors are constructed of precast Beam longitudinal column
reinforcement only
concrete hollow-core floor units. The shown
most frequently used depth of hollow-
core unit is 200 mm (7.9 in.) plus a Top bars slid Cast-in-place
65 mm (2.6 in.) thick cast-in-place into place joint concrete
concrete topping. Typical spans are 8
I,
or 9 m (26 or 30 ft) long.
This trend of precast concrete floors
in New Zealand has come about be
cause of the reduction in site costs re
sulting from reduced site labor and
fast erection, and also because most
precast concrete floors are lighter than Precast beam
cast-in-place floors, resulting in I—. 2 or h 8 db -g
whichever is less
smaller dead loads and seismic forces.
The current New Zealand practice of Cast-In-place ‘— g (hooks to terminate
column at the far side of
using mainly precast concrete floors the joint core)
contrasts markedly with the practice of
r
most overseas countries that use Note: db = bar diameter
mainly cast-in-place concrete floors.
f= development length of
hooked anchorages
Support Details for
Precast Concrete Floors Fig. 6. Hooked lap of bottom bars within joint core for System 1.

The supports for precast concrete


floor units may be either simple or moment fixity at the ends suits the fied by the New Zealand Guidelines,
3
continuous. Both supports have their more general commercial and residen can be divided into the three groups
advantages in different applications. tial type of construction, but requires shown in Fig. 2. The difference among
Simple support suits long span or attention to detail in order to ensure these types of support is the depth of
heavily loaded structures where it that the required degree of continuity the supporting beam prior to place
would be difficult and costly to pro can be achieved. ment of the cast-in-place concrete.
vide the required degree of negative The types of support for precast Some aspects of these three types of
moment restraint at the supports. Sup concrete hollow-core or solid slab support are:
port of precast concrete flooring with flooring units seated on beams, identi Type 1 — The presence of well

May-June 1995 45
the beams of ductile moment resisting
frames to elongate when forming plas
tic hinges. This can cause an increase
in the distances spanned by precast
concrete floor members.
7

3
In the design of the length of the
seating in the direction of the span, al
lowances must be made for tolerances
arising from the manufacturing pro
cess, the erection method, and the ac
curacy of other construction. Also, al
lowances must be made for the
long-term effects of volume changes
due to concrete shrinkage, creep and
temperatures effects, as well as for the
effects of earthquakes.
Some concern has been expressed in
New Zealand that there were cases in
tconcrete beam corner unit construction where the support pro
being lowered into place using vided for precast concrete floors was
temporary plastic tubes as guides inadequate. The New Zealand stan
dards for design and construction in
(c) Column bars 8 had no specific require
the 1980s”
after being grouted ments for the support of precast con
in the joint core of a crete floors.
precast concrete As a result, the revised New Zea
beam unit land concrete design standard NZS
3l0l:l995 recommends that for pre
cast concrete floor or roof members,
A with or without the presence of a cast-
in-place concrete topping slab and/or
continuity reinforcement, unless
shown by analysis or test that the per
Fig. 7. Construction formance of alternative details at the
of a 22-story building supports will be acceptable, each
using System 2 in
member and its supporting system
New Zealand.
shall have design dimensions selected
so that, under a reasonable combina
compacted cast-in-place concrete shear strength and prevent the devel tion of unfavorable construction toler
against the ends of the precast con opment of negative bending moment ances, the distance from the edge of
crete floor unit enables reliable nega actions in the floor units. However, the support to the end of the precast
tive moment continuity to be devel the depth of the supporting beam is member in the direction of its span is
oped. It is recommended that the cores greater and, hence, less shoring is re at least 1/180 of the clear span but not
of hollow-core flooring units be bro quired when precast units are erected. less than: 50 mm (2 in.) for solid or
ken out at the ends and that the ends Type 3 — This support system may hollow-core slabs or 75 mm (3 in.) for
be filled with cast-in-place concrete to be used for perimeter beams or walls. beams or ribbed members.
enhance the shear strength. However, No formwork for the cast-in-place The above recommendation requir
due to the reduced depth of the sup concrete topping slab is required. ing proven alternative support details,
porting beam at the stage when the Adequate support of precast con unless the specified end distances are
precast floor units are erected, more crete floor units is one of the most provided, is similar to that being con
shoring is generally required than with basic requirements for a safe structure. sidered by ACI Committee 318 for the
the other support types. It is essential that floor systems do not revision of the current ACT Building
Type 2 — If the vertical gaps be collapse as the result of imposed 9 The above end distances are
Code.
tween the supporting beam and the movement caused by earthquakes or similar to those recommended by
floor units are too small, there may be other effects that reduce the seating ACI-ASCE Committee 550.10
difficulty in compacting cast-in-place length. One source of movements dur One method of providing the alter
concrete both in the gaps and in the re ing severe earthquakes that could native details that permit smaller seat
cesses of the hollow-core units for this cause precast concrete floor units to ing lengths is to use special reinforce
type of support. This can reduce the become dislodged is the tendency of ment between the ends of the precast

46 PCI JOURNAL
/ su3;

(a) Construction overview of building

Fig. 8. Construction of 152 m (499 ft)


Coopers and Lybrand Tower using
System 2 in New Zealand.

concrete floor units and the supporting


beam that can carry vertical load in the
event of the precast concrete floor
units losing their seating. The special
reinforcement should be able to trans
fer the end reactions by shear friction
across the vertical cracks at the ends
of the units if the crack widths are rel
atively narrow or by kinking of the re
inforcement crossing the cracks if the
crack widths are large.
This reinforcement can be in the
form of hanger or saddle bars, or hori
zontal or draped reinforcement, as rec
ommended by the New Zealand should the seating be lost, because the draped reinforcement with hooked
3 the Precast/Prestressed
Guidelines, topping slab may split away from the ends shown as tie connection Types 1
Concrete Institute,’ and the Fédération precast concrete units. and 3 in Fig. 3 are favored, because it
Internationale de la Précontrainte.’
2 Recent tests conducted at the Uni was found that they could undergo
This special reinforcement passes over 3 on special rein
versity of Canterbury substantial plastic elongation when the
or is anchored to the supporting beam. forcement. placed in filled cores at the precast concrete units were pulled hor
For example, for precast concrete ends of hollow-core units and passing izontally off their 50 mm (2 in.) wide
hollow-core units, the reinforcement over precast supporting beams, have seating and subjected to significant
may be either placed in some of the investigated the three types of special vertical displacement. Plain round end
cores that have been broken out at the support reinforcement shown in Fig. 3. hooked reinforcement was found to
top and filled with cast-in-place con All three types were able to support at perform better than deformed rein
crete or grouted into the gaps between least the service gravity loads of the forcement because bond failure propa
the units. Note that reinforcement in a floor, in the event of loss of end seat gating along the plain round bars al
cast-in-place topping slab alone can ing, when no significant horizontal lowed extensive yielding along the
not be expected to provide an ade displacement of the floor occurred. bar, thus allowing substantial plastic
quate load path to support the units, However, the plain round straight or elongation before fracture.’
3

May-June 1995 47
Diaphragm Action
The floor system also has to act as a
diaphragm during horizontal loading
due to earthquakes in order to transfer
the in-plane diaphragm forces from
the floor into the lateral load resisting
components, such as frames and
structural walls. When floors are con
structed of precast concrete units, it is
essential to ensure that diaphragm
forces can be transferred between the
units and to the supporting structure
so that shear transfer over the floor is
achieved. In New Zealand, a cast-in-
place reinforced concrete topping slab
at least 50 mm (2 in.) thick containing
at least the minimum reinforcement
required for slabs is considered an ex
cellent means for transferring the in-
plane diaphragm forces. Some limited
use of precast concrete elements in
floors without a cast-in-place topping
slab has also been made, but with
adequate shear connection between
the elements.

MOMENT RESISTING
FRAMES WITH PRECAST
REINFORCED ELEMENTS
Moment resisting frames incorporat
ing precast reinforced concrete ele
ments are widely used in New
Zealand. The main challenge in the
design of such structures is finding an
economical and practical method for
connecting the precast concrete ele
ments together. In New Zealand, if the
connections between the precast con
crete elements in frames are placed in
Fig. 9. Construction of a 1 3-story building using System 3 in New Zealand.
critical regions, such as potential plas
tic hinge regions, the approach is to
design and construct connections that
possess stiffness, strength, and ductil of the perimeter and interior frames. Note that if the perimeter frame
ity similar to that of cast-in-place con If the perimeter frames are relatively beams are fairly deep, and the
crete monolithic construction.’
5 In

4 stiff, the columns of the interior columns are close and small, it may be
other words, monolithic construction frames will carry mainly gravity load difficult to ensure strong column-weak
is emulated. ing. Also, the interior columns can be beam behavior. Hence, the relative di
The general trend in New Zealand placed with greater spacing between mensions of the beams and columns in
for multistory buildings with moment columns. For the perimeter frames, the tall ductile frames should be such that
resisting frames is to design the depth of the beams may be large with strong column-weak beam behavior
perimeter frames with sufficient stiff out affecting the clear height between can be achieved. Details of several
ness and strength to resist most of the floors inside the building and the buildings in New Zealand constructed
horizontal seismic loading. The more columns can be at relatively close cen in the late 1980s and early 1990s that
flexible interior frames will be called ters. The use of one-way perimeter incorporate significant quantities of
on to resist only a small proportion of frames avoids the complexity of the precast concrete in their frames and
the horizontal forces, the exact amount design of beam-to-column joints of floors are described elsewhere.’
2
depending on the relative stiffnesses two-way moment resisting frames. Several possible arrangements of

48 PCI JOURNAL
precast reinforced concrete members
and cast-in-place concrete forming
ductile moment resisting multistory re
Cast-In-place joint
inforced concrete frames have been
[JYoIumn
415 Arrangements commonly
identified.’ coIumL]
used in New Zealand for strong col
unm-weak beam designs are shown in
Fig. 4. These three arrangements can
also be used in a modified form when
,1 L:.J 5
L4
J
4 .-4 I \_• Precast
one- or two-story frames with strong Precast e 2d÷e.
•“—
beam-weak column design are permit
ted. The objective in design of the sys (a) Conventional Straight Bar Lap
tems is to achieve behavior emulating
a monolithic structure. The three ar (çln.lace Joint
rangements are described below. Colu.j

System 1
An arrangement involving the use of
precast reinforced concrete elements Precast
to form the lower part of the beams is beam
shown in Fig. 4(a). The precast beam (b) Hooked Lap
elements are placed between columns,
seated on the cover concrete of the Cast-In-place j
previously cast-in-place reinforced Column
Column
concrete column below, and supported
under the precast elements (see Fig.
5). In some cases, there may be two
precast beam elements per span with a
cast-in-place joint at midspan where Precast beam Precast beam
the longitudinal beam bars are spliced.
A precast concrete floor system is (c) Double Hooked Lap
placed seated on the top of the precast
beam elements and spanning between Overstrength stub
them. The reinforcement is then /oint Column
placed in the top of the beam, the top Column
ping slab over the floor system, the
beam-to-column joint core, and the
next story height of column. Lastly,
the cast-in-place concrete is placed.

[
The frame can be designed using the
provisions for totally cast-in-place
1Diagon Precast
concrete structures. Precast J welded to beam
beam Steel plates
This system leads to a large reduc steel plate bolted together
tion in the quantity of site formwork (d) Diagonal Beam Reinforcement
necessary. A difficulty with the con
Notes: Transverse reInforcement Is not shown
nection detail is that the bottom longi
tudinal bars of the beams, protruding i= development length of hooked anchorage
from the precast beam elements, need = development length of straight bar
to be anchored in the joint cores (see
Fig. 6). Hence, the column dimensions
need to be reasonably large to accom Fig. 10. Some details for midspan connections between precast reinforced
modate the required development concrete beam elements that have been used in New Zealand (Ref. 3).
length and to reduce the congestion of
the hooked reinforcement. joint between the cast-in-place con To make the transfer of vertical
Another possible problem is that the crete of the joint core and the end of shear possible, it is recommended that
critical section of the potential plastic the precast beam. This is permitted by either the end of the precast beam
hinge region in the beam occurs at the the New Zealand standard, NZS should be clean, free of laitance and
column face where there is a vertical 3lOl:l995. intentionally roughened to a full am-

May-June 1995 49
plitude of not less than 5 mm (0.2 in.), forcement in the precast beam, and the struction. A possible constraint is that
or alternatively, a mechanical key precast floor system supported on the precast elements are heavy and
should exist at the end of the beam. A ledges on the sides of the precast crane capacity may be an important
well prepared joint at the end of the beams. The columns of the next story consideration.
precast beam at the critical section at are then positioned above the beams Fig. 9 shows a perimeter frame of a
the column face is no worse than a using grouted steel sleeves or ducts to 13-story office building constructed
similarly placed construction joint be connect the vertical bars if the using precast concrete cruciform-
tween pours of cast-in-place concrete columns are precast or using normal shaped units with columns two stories
in totally cast-in-place construction. reinforced concrete details if the in height and two levels of beam
Also, it is recommended that the top columns are cast in place. stubs. Reinforcement projects from the
surface of the precast concrete beam An advantage of this system is that beam stubs to be incorporated in cast-
unit be clean, free of laitance and in the potential plastic hinge regions in in-place hooked splices at the midspan
tentionally roughened to a full ampli the beams occur within the precast el of each beam. The column joint be
tude of not less than 5 mm (0.2 in.). ements away from the jointing faces tween the precast units consists of an
between the precast elements. Also, epoxy grouted bedded joint and
this system makes extensive use of grouted steel sleeves. Note the long
System 2 precast concrete and eliminates the spans of the beams of the more flexi
fabrication of complex reinforcing de ble interior frames.
An arrangement that makes more
extensive use of precast concrete and tails during construction. A possible
avoids placement of cast-in-place con difficulty is the tighter tolerances nec
essary when assembling the precast Midspan Connections
crete in the congested beam-to-column Between Precast Concrete
joint core regions is shown in Fig. concrete elements.
Figs. 7 and 8 show two buildings Beam Elements
4(b). The reinforced concrete columns
can be either precast or cast-in-place during construction in New Zealand Some details for cast-in-place
to occupy the clear height between using this system. The structure of midspan connections in beams that
beams. The precast portions of the re both buildings consists of stiff mo have been used are illustrated in Fig.
inforced concrete beams extend from ment resisting perimeter frames with 10. The New Zealand concrete design
near midspan to midspan, and, hence, interior frames carrying mainly only standard, NZS 3101:1995, requires
include within the precast element gravity loading. In both buildings, the that no portion of any lap splice of the
over the columns the complex ar columns between the precast beam longitudinal reinforcement in the
rangement of joint core hoop rein units were cast in place. The floors beam be located within a length of one
forcement that is fabricated at the pre consisted of precast concrete with a effective depth of beam from the criti
casting site. The precast portions of cast-in-place concrete topping. For the cal section of the potential plastic
the beams are placed seated on the Coopers and Lybrand Tower, a con hinge region. This normally means
concrete column beneath, with suit struction time of 4 to 5 days per office that lap splices in beams cannot com
able material between, and supported floor was achieved regularly through mence closer than one effective beam
for construction stability. out the construction period.

2 depth from the column face.
The protruding longitudinal column For short span beams of perimeter
bars from the reinforced concrete col frames, a straight lap splice in the
System 3 midspan region may be too long to
umn below pass through preformed
vertical holes in the precast beam ele A third possible arrangement incor meet this requirement. In this case, the
ment and protrude above the top sur porating T-shaped precast reinforced conventional straight bar lap of Fig.
face of the element. The holes in the concrete elements is shown in Fig. 10(a) can be shortened using hooked
precast beam elements are preformed 4(c). The vertical column bars in the laps, as shown in Figs. 10(b) and (c).
using corrugated steel ducting and are precast T units are connected using The double hooked lap of Fig. 10(c)
grouted after the column bars have grouted steel sleeves or ducts. At the is the most convenient hooked lap to
passed through. The protruding bars of midspan of the beams, the bottom bars construct because the protruding ends
the precast beam elements are con can be connected in a cast-in-place of the reinforcement from the precast
nected in a joint to be cast in place at concrete joint. An alternative to the T concrete beam elements do not over
midspan. shaped precast concrete units is the lap, and therefore, the beam elements
A precast concrete floor system is use of cruciform-shaped units with the can be positioned during construction
placed seated on the precast beam ele joints between columns occurring at without difficulty. The lap is made
ments and spanning between them. the midheight of the stories. Precast using “drop in” bars, which consist of
The reinforcement is then placed in concrete floor systems can be used as short lengths of bar with a hook at
the top of the beam and the topping with the other systems. each end.
slab, and the cast-in-place concrete is An advantage of System 3 is the ex Diagonal reinforcement has been
placed. Alternatively, the total depth tensive use of precast concrete and the used where the shear forces in the
of the beam can be precast, including elimination of the fabrication of com beams are large [see Fig. 10(d)]. The
the top and bottom longitudinal rein- plex reinforcing details during con- design and detailing of this connection

50 PCI JOURNAL
detail require particular care. The ends
of the diagonal bars are welded to steel Grout ‘top off’
plates that are bolted together at as necessary

midspan during construction to make ,,/corruated ducts


1
Precast
the connection. Significant vertical ties concrete
beam
are required between the bends in the
diagonal reinforcement to resist the Precast concrete
beam
vertical component of the force in the
diagonal bars. Also, bearing failure of
LW—Grout level
the concrete should not occur under the rouGmut
bends of the diagonal reinforcement. Column
Seal
Grout// Air and grout

Grouting of a Sealed
Column
Beam-to-Column Joint
Fig. 11 illustrates a typical arrange
Fig. 11. Grouting of abeam-to-column joint (Ref. 3).
ment of a precast concrete beam ele
ment placed on a cast-in-place or pre
cast concrete column, as used in
System 2 of Fig. 4(b). The beam ele
ments can be seated on leveling shims.
The column bars pass through corru
gated metal ducts, cast in the precast
concrete beam. The diameter of the
duct should accommodate the toler
ances, plus a recommended additional
10 mm (0.39 in.) clearance between
::::
the duct wall and bar surface to allow tconcrete
beam
grout to flow between the duct wall
and bar. Typically, the duct diameters
(b) Cruciform Unit
range from two to three times the (a) Full Height Column Mid Height Column Joint
nominal diameter of the bar. The two Upward Sleeving

principal methods of grouting a pre


cast concrete beam-to-column joint
are as follows:
3
Method 1 — The horizontal joint at
the beam-to-column interface is first
sealed around the outside and then
grout (typically non-shrink cement-
based) is pumped in at an inlet port (or
tube) at one corner of the horizontal
joint to displace air progressively
across the interface (see Fig. 11). If
the grout has a high viscosity, it may
start to flow up the open ducts, start
ing at the duct closest to the grout (d) Cruciform Unit
(c) ‘T’ Precast Unit
inlet. It is recommended that outlet Beam and Column Mid Height Column Joint
Cast Together Downward Sleeving
ports be provided at the other three
corners of the interface. These are pro
Fig. 12. Typical connections between precast concrete column elements (Ref. 3).
gressively plugged once grout without
air bubbles flows out.
When all the outlets are plugged, a way that grout runs down in contact down one corner duct. Progressively,
further pumping of grout will result in with the reinforcing bar to avoid air the grout will flow across the interface
the ducts being filled upwards from locks. The inlet tube or port is plugged and up the remaining ducts. It is rec
the bottom. The duct nearest the inlet once injection is completed. ommended that, as with Method 1,
should fill first while the one furthest Method 2 — The horizontal joint at outlet ports be used to confirm the
away (opposite corner) may require the beam-to-column interface is first progress of the grouting of the inter
topping up by use of a tremie tube, or sealed around the outside and then face. Topping off of ducts remote
by pouring-in from a dispenser in such grout is poured in from a dispenser from the filling position may be neces

May-June 1995 51
sary. Again, care must be exercised so
that no air is trapped in the ducts. Rebar (upper)
(lapped beside)
The grouting operation must be con
ducted using proper quality assurance 1LRebar Gro Ut and air
procedures to ensure that all voids are Precast Precast
properly and solidly grouted. 11 concrete concrete
ember
9
fj member

Connections Between Precast 1 grout


High strength -‘
Duct
Concrete Column Elements
Fig. 12 shows typical connections
Grout
between precast concrete column ele Shims
3 Some
ments using grouted splices. Bedding
connections are made by bars protrud mortar Rebar (lower)
ing downwards from the precast col
umn element above, with the bars lo (a) Steel sleeve
Rebar 25 mm minimum
cated in pregrouted corrugated metal (upper) and code spacing
ducts or proprietary steel sleeves [see requirements
Fig. 12(d)]. The other configurations (b) Corrugated
Rebar (lower)
Metal Duct
have bars protruding upwards into
Duct
corrugated metal ducts or proprietary
Section A-A
steel sleeves that are post-grouted.
The precast column elements may be
Fig. 13. Steel sleeve splices and corrugated metal ducts used for column
seated on leveling shims. The hori
connections (Ref. 3).
zontal joint can be grouted or can con
sist of a bed of cement or epoxy-based
mortar. tails, is a critical operation. Weld to cyclic loading in the post-elastic
The two types of duct used in col throat thicknesses should be carefully range, which simulated the effects of
umn splices, namely, proprietary steel monitored. severe earthquakes.
sleeves and corrugated metal ducts, Six full-scale subassemblies of
are shown in Fig. 13. When using the frames were subjected to simulated
proprietary steel sleeves, the bars are Tests on Connections 7 Two of the sub-
seismic loading.
butted in the sleeve. When using cor Between Precast Reinforced assemblies were of cruciform shape
rugated metal ducts, the bar in the duct Concrete Elements and had precast concrete beam ele
is lapped with the bar or bars in the ments connected in two different ways
A research project at the University
adjacent precast concrete. For post at the beam-to-column joint, repre
of Canterbury has investigated the
grouting with either type of duct con senting Systems 1 and 2 of Fig. 4.
seismic performance of connections
figuration, it is necessary to have an
between precast reinforced concrete el At the vertical construction joints of
inlet tube at the base of each duct and
ements of moment resisting frame sys the System 1 subassembly, which in
an outlet tube at the top for bleeding
tems commonly used in buildings in terfaced precast and cast-in-place con
air and grout.
7 This research was nec
New Zealand. crete, the ends of the precast beams
essary because the solutions proposed were clean and free of laitance, but
Pinned Joints by designers and contractors for these with only a small amount of rough
Pinned joints can be used to connect frames have normally been extrapola ness, approximately 1 mm (0.04 in.)
secondary beams to primary beams. tions from code provisions for cast-in- full amplitude, to represent the worst
They are sometimes also used at place concrete. This stems from the conditions normally encountered in
beam-to-column joints to reduce the fact that New Zealand codes, even in construction practice. The precast con
moment input from the beam to the the had only limited provi crete beam of the System 2 subassem
column. An example of a pinned joint sions for precast concrete construction. bly had corrugated metal ducts in the
at a secondary beam to main beam The design objective for these joint region through which the vertical
connection is shown in Fig. 14. The frames incorporating precast concrete column bars passed and were grouted.
typical 20 mm (0.79 in.) tolerance gap, elements is to achieve behavior as for The columns of both subassemblies
between the end of the secondary totally cast-in-place concrete struc were cast-in-place concrete. During the
beam and the side of the main beam, tures. That is, monolithic construction cyclic horizontal loading, horizontal in
implies that the precaster and contrac is emulated. The research project in terstory drifts of up to at least ±3 per
tor are required to work to very strin vestigated whether the frames could cent occurred. (Horizontal interstory
gent tolerances. Also, the welding achieve stiffness, strength and ductile drift is horizontal displacement given
of reinforcing bars to rectangular hol behavior similar to completely cast-in- as a percentage of the story height.)
low steel sections, or to other steel de place concrete frames when subjected Both subassemblies performed with no

52 PCI JOURNAL
significant difference in behavior from
.Top continuity
monolithic construction.
7 Pair of RHS hanger brackets reinforcement
with U-bars welded on
Another four full-scale subassem
blies were of H shape and were tested Cast-in-place concrete Precast concrete
subjected to simulated seismic
7 to investigate the perfor
loading
topping
\ floor
dbsr)
mance of the four details for midspan
connections between precast concrete —

t mont
beam elements shown in Fig. 10. The ( 7aliy used)
details shown in Fig. 10(a), (b), and Bearing angle
(c) were found to perform very satis
factorily in that the beams showed no Precast concrete _......,7
significant difference in behavior from secondary beam 20mm gap ..4.. Precast concrete
main beam
monolithic construction. The tests
confirmed that the splice could begin Fig. 14. Example of secondary beam to main beam connection using a rectangular
hollow steel (RHS) section seated on a steel angle (Ref. 3).
at a distance of one effective beam
depth from the critical section of the
beam at the column face. This finding

I
means that beams with relatively small
span-to-depth ratios can be used, Proprietary floor system
and cast-In-place
which is often a desirable feature in reinforced concrete
the configuration of moment resisting topping
perimeter frames.
The test on the detail shown in Fig.
10(d) indicated that a problem could
exist in the regions of the bends of the
diagonal beam bars, if the design of
that reinforcement does not consider Reinforced
the possible bearing stresses on the ccncrete
concrete at the inside of the bend. column
Also, the three-dimensional effects
caused by the arrangement of the lon Cast-in-place
gitudinal reinforcement in that region concrete beam Pretensloned
requires the presence of significant tie precast concrete U-beam
reinforcement in the form of closed
stirrups. However, it was found that Fig. 15. Construction details of a structural system using precast, prestressed
the detail can be designed to perform concrete U-beams and cast-in-place reinforced concrete (Ref. 22).
7
satisfactorily.
An interesting aspect of the test re
sults from the six subassemblies
7 was precast concrete floor systems due to cast-in-place reinforced concrete core
the large permanent elongation of the an increase in the span between sup has been cast. The precast U-beams
beams that was measured after yield porting beams. Hence, there must be support the self weight and construc
ing of the longitudinal reinforcement special support reinforcement at the tion loads and act compositely with
occurred. This was due to residual ends of precast concrete floors, as the reinforced concrete core when sub
plastic tensile strains in that steel dur shown in Fig. 3, unless seating lengths jected to other loading in the com
ing cyclic loading. are adequate. pleted structure. A building under con
The elongation of the beams gradu struction is shown in Fig. 16.
ally increased during the loading cy MOMENT RESISTING The precast concrete U-beams are
cles. At horizontal displacements cor generally not connected by reinforce
responding to interstory drifts of about
FRAMES WITH PRECAST,
ment to the cast-in-place concrete of
±2 percent, the total length of the PRESTRESSED ELEMENTS the beam or column. Reliance is nor
beams of the subassemblies had in Another building system that has mally placed on the bond between the
creased by 20 to 30 mm (0.8 to 1.2 in.) become popular in New Zealand in roughened inner surface of the precast
as a result of the deformations of the volves the use of precast concrete U-beam and the cast-in-place concrete
longitudinal bars in the two plastic beam shells as permanent formwork core to achieve composite action. Oc
hinge regions of each subassembly. for beams (see Fig. 15). The precast casionally, protruding stirrups or ties
A practical consideration is that this beam shells are typically pretensioned, from the U-beams have been used to
beam growth during a severe earth prestressed concrete U-beams and are improve the interface shear strength.
quake could result in loss of support of left permanently in position after the During construction, it is very impor

May-June 1995 53
curvature occurs at that section. Seis Properly designed walls have a large
mic design recommendations for this inherent strength and their ample stiff
type of construction are available.
22 ness means that displacements during
Reinforced concrete beams incorporat severe earthquakes are reduced, thus
ing precast, prestressed concrete beam providing a high degree of protection
shells and cast-in-place reinforced against damage to structural and non-
concrete cores are suitable for use in structural elements.
ductile moment resisting frames. Comprehensive design provisions
exist for cast-in-place reinforced
concrete structural walls.
4 In New
STRUCTURAL WALL- Zealand, it is considered that well pro
FLEXIBLE FRAME portioned ductile cast-in-place rein
SYSTEMS forced concrete coupled walls form
the best earthquake resisting structural
Structures comprising both rein system. The recent trend towards mo
forced concrete structural walls and ment resisting frames, rather than
frames offer advantages. The struc structural walls, in New Zealand has
tural walls, normally of cast-in-place been mainly due to the preference of
concrete, can be designed to resist al architects for the more open spaces of
most all of the horizontal forces acting floors when walls are not present.
Fig. 16. Construction of a moment on the building. The frames, which are
resisting frame using precast concrete
Most structural walls for multistory
much more flexible than the walls, buildings in New Zealand have been
U-beams.
will resist only a small proportion of made of cast-in-place reinforced con
the horizontal forces, the amount de crete, but there has been significant
pending on the relative stiffnesses of use of precast concrete walls for
tant to ensure that the inside surfaces
the walls and frames. smaller buildings.
of the shell beams are clean when the
The columns of such frames are pre Precast reinforced concrete struc
cast-in-place concrete is cast, other
sent in the building mainly to carry the tural wall construction usually falls
wise sufficient bond between the shell
gravity loading. When such systems into two broad categories:
3 monolithic
and core cannot develop. are used in seismic regions, the frames
Tests have been conducted in New or jointed. In monolithic wall con
can be designed for limited ductility if struction, the precast concrete ele
Zealand in which full-scale subassem it can be shown that when the ductile
blies, typical of moment resisting ments are joined by “strong” rein
walls have deformed in the post- forced concrete connections that
frames constructed using this building
elastic range to the required displace possess stiffness, strength, and ductil
system, have been subjected to simu
ment ductility factor or drift during se ity approaching that of cast-in-place
lated seismic loading.
22 No stirrups or
vere seismic loading, the ductility de
ties protruded from the precast concrete concrete monolithic construction. In
mand on the frames is not large. jointed wall construction, the connec
U-beams. The resistance to seismic A New Zealand building employing
forces was designed to come from the tions are “weak” relative to the adja
this design is shown in Fig. 17. The cent wall panels and, therefore, govern
cast-in-place reinforced concrete core
central cast-in-place reinforced con the performance of the building.
of the U-beams. The tests were con crete walls, forming the service core
ducted because doubts had been ex of the building, were designed to resist
pressed by some designers and building the seismic loading. The perimeter Monolithic Precast Concrete
officials concerning the ability of this
frame of precast concrete beams Structural Wall Systems
form of composite construction to per
(formed in the shape of trusses for
form as ductile moment resisting lightness) and the columns (formed
Monolithic precast reinforced con
frames. It was felt that cracking may using precast concrete tubes infilled crete structural wall systems are
concentrate in the beam at the column designed according to the code re
with cast-in-place concrete) were de
face at the discontinuity caused by the signed mainly for gravity loading.
quirements of cast-in-place concrete
end of the precast concrete U-beam. 3
construction.
22 demonstrated
However, the tests Horizontal joints between precast
that during severe seismic loading, STRUCTURAL WALLS concrete wall panels are usually
there is a tendency for the plastic hing grouted connections. The vertical re
WITH PRECAST
ing to spread along the cast-in-place inforcement is usually connected
reinforced concrete core within the
CONCRETE ELEMENTS there using either grouted steel sleeve
precast U-beam due to some break Structural reinforced concrete walls splices or a lap formed by grouting a
down of bond. Hence, the plastic in buildings have long been recog bar extending from the end of one
hinge rotation does not concentrate in nized in New Zealand as efficient precast panel into a corrugated metal
the beam at the column face and, as a structural systems for resisting hori duct in the matching panel. Some typ
result, no undesirable concentration of zontal forces due to earthquakes. ical details of monolithic horizontal

54 PCI JOURNAL
joints are shown in Fig. 18.
When corrugated metal ducts are
used, the starter bars that project into
the ducts are usually designed for a
full lap length. In general, central
starter bars are lapped with pairs of
smaller bars, one on each face of the
precast concrete wall section. Alterna
tively, all of the main flexural rein
forcement is lapped on the precast
concrete wall centerline and some ad
ditional basketing cover reinforcement
is provided.
The horizontal joint between precast
concrete panels is usually roughened
to avoid a sliding shear failure.
Vertical joints between precast con
crete wall panels are typically vertical
strips of cast-in-place concrete. Hori
zontal reinforcement from the ends of
the adjacent panels protrude into the
joint zone and are lapped. The width
of the cast-in-place concrete joint
zone is determined by the code re
quirements for lap lengths of horizon
tal reinforcement. Typical details of
monolithic vertical joints are shown
in Fig. 19.
Vertical joints shown as Types D
and E need to be detailed with extreme
care. During construction, once the (a) Perimeter structure
lapping bars have been overlapped,
the ability for lowering the wall panels (b) Typical floor plan
over the starter bars is very restricted.
These details will typically work only
when grouted steel splice sleeves are
used to splice the vertical flexural re
inforcement and when the laps of the
vertical bars in the joints are made
near floor level.
As an example, Fig. 20 shows part
of the construction of a two-story
building that uses full height precast
concrete structural wall panels to
provide support for the precast con
crete floor system and the roof. The
precast concrete walls, which pro
vide the lateral load resistance of the
building, were designed as can
tilevered structural walls of limited
ductility to the seismic requirements
of what was the current New Zealand
concrete design code.’
The connection detail between the
walls and foundations was designed to
withstand the larger seismic forces
corresponding to the elastic response
of the structure to a severe earthquake. Fig. 17. Building with a precast reinforced concrete perimeter frame with seismic
The vertical joints between panels, forces resisted mainly by cast-in-place reinforced concrete interior structural walls.

May-June 1995 55
Grout outlet vent
Steel splice Preformed metal duct
sleeve filled with expansive grout
)ut outlet Lap bars to lap with
‘pairs of vertical bars
inlet tube
rung strips

topping over
hollow core
floor planks
Lap bar
Precast wall panels Precast wall panels

Monolithic Precast Concrete Monolithic Precast Concrete


Wall Construction Wall Construction
Horizontal Joint Type A - Horizontal Joint Type B -

Lap bars in preformed metal ducts


or grouted steel splice sleeve.
Area of lap bar 2 x Area of
vertical bars

Horizontal S
reinforcement :.:.:.:.:.:.:::.:.:::::.:::::.:.:.:::::::.:::::.:.:.:::::..::::......:.:l\Lap bars lap with pairs
of vertical bars
Section A-A
Alternative 1

Reinforcement same as Alternative 1


‘- except horizontal shear reinforcement
I Y is tied directly to the preformed metal
I ‘
ducts or grouted splice sleeve

Section A-A
Alternative 2

Full length bars lap within full height preformed


metal ducts or full length lap bars spliced with
grouted steel splice sleeves.

Vertical basketing
Section A-A reinforcement
Alternative 3

Monolithic Precast Concrete Wall Construction


Alternative Sections A-A

Fig. 18. Details of horizontal joints in monolithic precast reinforced concrete wall construction (Ref. 3).

56 PCI JOURNAL
shown during construction in Fig.
20(a), consist of horizontal overlap
Cast-in-place d for horlz. bars All horizontal shear
reinforcement lap
ping hairpin-shaped reinforcement that
concrete bandae
joint spliced projects from each of the wall panels
and cast-in-place concrete creating a

F-,
I
Sides of wail”—. Vertical reinforcement
monolithic joint of Type E, as shown
in Fig. 19.
A vertical steel bar was placed in
Precast concrete panels keyed typically lap spliced the space between the ends of the hair
wall panels and roughened above floor level pins prior to casting the concrete. De
Type A tails of the connection between the
wall and the foundation are shown in
Fig. 20(b). Holes were formed in the
Cast-in-place All horizontal shear bases of the panels so that horizontal
concrete bandagej,, reinforcement spliced reinforcing bars could be placed
Joint with 900 standard
I.e. through to resist the design horizontal

I Sides of we’II” Vertical reinforcement


shear forces and tension forces result
ing from overturning moments.

Precast concrete panels keyed typically lap spliced


wall panels and roughened above floor level Jointed Precast Concrete
Type B Structural Wall Systems
In jointed construction, the connec
tion of precast reinforced concrete
All horizontal shear
Cast-in-place tdh reinforcement spliced components is such that sections of
concrete band_ with 900 standard significantly reduced stiffness and
joint ,__—“hook lap bars.
4. _i.e.
strength exist at the interface between
adjacent precast concrete wall panels.
1•
,‘ \j5
of wall
This type of precast concrete wall con
struction is not common for high rise
Precast concrete Vertical reinforcement construction in New Zealand; how
wall panels panels keyed typically lap spliced
and roughened above floor level ever, it has been extensively used in
Type C the tilt-up construction of typically
one- to three-story apartment, office
and industrial buildings.
3
All horizontal shear
For tilt-up construction, relatively
Cast-in-place concrete large reinforced concrete wall panels
or grout filled joint Sealant reinforcement
hairpin spliced
/ are cast horizontally on top of con
crete floor slabs or casting beds adja
cent to final wall panel positions.
When the concrete has gained suffi
Precast
concrete
/
Sides of joint
‘Vertical reinforcement
typically lap spliced cient strength for the wall panels to re
wall panels roughened above or below main uncracked during lifting opera
floor level tions, the walls are tilted up and lifted
Type D
into their permanent positions. Gener
ally, tilt-up walls are secured to the
Cast-in-place All horizontal shear adjacent structural elements with
concrete bandage reinforcement jointed connections consisting of vari
Joint hairpin spliced
ous combinations of concrete inserts,
bolted or welded steel plates or angle
brackets, and lapped reinforcement
splices within cast-in-place joining
3 Vertical reinforcement
strips. Such walls are designed as
Precast concrete Sides of Joint typically lap spliced
wall panels keyed and above orbelow structural walls of limited ductility.
roughened floor level That is, the design seismic forces are
Type E on the order of twice those used in the
design of ductile walls.
Fig. 19. Some details of vertical joints in monolithic precast reinforced concrete Unfortunately, the revised New
wall construction (Ref. 3). Zealand concrete design standard,

May-June 1995 57
NZS 3lOl:l995, does not have de
sign recommendations covering all
aspects of tilt-up construction. How
ever, a research project is currently
in progress at the University of Can
23 with the objective of cata
terbury
loging currently used connection de
tails, assessing and testing them
where necessary, and recommending
appropriate details for tilt-up and
jointed construction.

TOLERANCES
Successful precast concrete con
struction relies on a full understanding
of the need for tolerances and the full
implications of variations in dimen
sions. This understanding must be de
veloped by designers, fabricators, and
constructors.
The New Zealand requirements for
tolerances for precast concrete con
struction are given in the construction
specification. More complete recom
8
mendations for tolerances for precast
concrete used can be found in PCI
24
publications.
The New Zealand Guidelines
3 sug
gest three different types of tolerances,
namely, product, erection, and inter
face tolerances, as defined below:
1. Product tolerances relate to the
dimensions of an individual precast
concrete component. They are set by
the designer to control production in
order to achieve the structural and ar
chitectural requirements.
2. Erection tolerances are the al
lowances needed between the actual
location of precast concrete compo
nents and the primary control surfaces,
(b) Detail of wall/foundation junction such as grids and datum levels.
3. Interface tolerances refer to the
allowances needed for the jointing or

I
Precast concrete attaching of material in contact with
wall
/J /012 at 200 the precast concrete components.
016 bar per hole Experience in New Zealand shows
in precast panels that designers should work together as
closely as possible with contractors
012 at
4-H32
when specifying tolerances so that ap
propriate allowances can be made,
4-H20 thereby reducing construction diffi
F
H
4 20
culties. When designing connections
that are sensitive to tolerances, the
sum of the maximum reasonable tol
Fig. 20. Construction of a two-story building incorporating full height precast erances can be used to define the
concrete wall panels (Ref. 3). worst design case.

58 PCI JOURNAL
CONCLUSIONS achieving behavior equivalent to that simulated seismic loading of full-scale
of monolithic construction. subassemblies incorporating precast
Based on the preceding discussion,
the following conclusions can be 4. For moment resisting frames, the concrete elements, have been con
drawn: structural arrangements include precast ducted in New Zealand.
7 These tests
reinforced concrete beam elements give confidence in the design and con
1. Precast concrete floor systems, spanning between columns, precast re struction of a range of connections be
normally spanning one-way, have inforced concrete beam elements pass tween precast concrete members that,
been commonplace in New Zealand
ing through columns, and T-shaped and when first developed, went beyond the
since the 1960s. Also, non-structural cruciform-shaped precast reinforced codes of the time.
precast concrete has been widely used concrete elements. Structural continuity
for the cladding of buildings. between precast concrete elements is
2. The building boom in New generally achieved using cast-in-place ACKNOWLEDGMENTS
Zealand in the mid-1980s produced a reinforced concrete. A structural sys The author gratefully acknowledges
significant increase in the use of struc tem utilizing precast, prestressed con the helpful discussions of many mem
tural precast concrete, particularly for crete U-beams with a cast-in-place re bers of the design and construction pro
moment resisting frames, because of inforced concrete core is also in use. fession in New Zealand. Particularly
the advantages of high quality factory 5. Significant use of precast rein appreciated are the members of the
made units, speed of construction, and forced concrete wall elements is also Study Group of the New Zealand Con
the reduction of site formwork and being made for low rise structural wall crete Society and of the New Zealand
labor. This required developments in construction, particularly for tilt-up National Society for Earthquake Engi
all aspects of the use of structural pre walls. neering, which produced the “Guide
cast concrete as designers and contrac 6. The successful use of precast lines for the Use of Structural Precast
tors sought increasingly effective concrete requires close cooperation Concrete in Buildings,” published by
methods of design and construction. between designers, precasters and the Centre for Advanced Engineering
3. The design approach for moment contractors. of the University of Canterbury in Au
resisting frames incorporating precast 7. New Zealand design codes have gust 1991. Thanks are also due to R. G.
reinforced concrete elements in New traditionally contained extensive pro Wilkinson of the Holmes Consulting
Zealand is similar to that for totally visions for cast-in-place reinforced Group, and to A. I. O’Leary of
cast-in-place reinforced concrete concrete but are now being extended Kingston Morrison Ltd., for providing
structures. That is, the methods used to include design provisions for pre material. The efforts of graduate stu
for connecting the precast concrete el cast concrete. dents J. I. Restrepo and J. C. Mejia are
ements together are generally aimed at 8. Laboratory tests, involving the also gratefully acknowledged.

May-June 1995 59
REFERENCES
1. Code of Practice for the Design of 10. ACI-ASCE Committee 550, “Design 18. Poole, R. A., and Clendon, J. E., “Mid
Concrete Structures, NZS 3101:1982, Recommendations for Precast Con City Towers — An Efficient Precast
Standards Association of New Zealand, crete Structures,” ACI Structural Concrete Framed Building,” Proceed
Wellington, New Zealand, 1982. Journal, V. 90, No. 1, January-Febru ings, Pacific Concrete Conference,
ary 1993, pp. 115-121. V. 1, Auckland, New Zealand,
2. Uniform Building Code, UBC:1991,
November 1988, pp. 319-332.
International Conference of Building 11. Buettner, D., and Becker, R. J., PCI
Officials, ‘Whittier, CA, 1991. Manual for the Design of Hollow-Core 19. Silvester, D. B., and Dickson, A. R.,
Slabs, Precast/Prestressed Concrete In “Fanshawe Street Building A Pre
3. “Guidelines for the Use of Structural cast Concrete Study,” Proceedings,
stitute, Chicago, IL, 1985, 120 pp.
Precast Concrete in Buildings,” Re Pacific Concrete Conference, V. 1,
port of a Study Group of the New 12. Fédération Internationale de Ia Pré Auckland, New Zealand, November
Zealand Concrete Society and the contrainte, Precast Hollow- Core 1988, pp. 333-344.
New Zealand National Society for Floors, Thomas Telford, London,
Earthquake Engineering, Centre for 1988,31 pp. 20. O’Grady, C. R., “Precast Cruciform
Advanced Engineering, University of Columns, H Frames and Precast
13. Mejia, J. C., and Park, R., “Tests on Concrete Shear Walls in Building
Canterbury, Christchurch, New Zea
Special Reinforcement for the End Construction,” Proceedings, Pacific
land, 1991, T74pp.
Support of Hollow-Core Precast Con Concrete Conference, V. 1, Auckland,
4. Design of Concrete Structures, NZS crete Floor Units,” PCI JOURNAL, New Zealand, November 1988,
3101:1995, Standards Association of V. 39, No. 5, September-October pp. 345-354.
New Zealand, Wellington, New 1994, pp. 90-105.
21. Raymond, W., “Efficient Use of
Zealand, 1995.
14. Park, R., “Seismic Design Considera Structural Precast Concrete in High
5. Code of Practice for General Struc tions for Precast Concrete Construc Rise Buildings — A Case Study,”
tural Design and Design Loadings for tion in Seismic Zones,” Seminar on Transactions, Institution of Profes
Buildings, NZS 4203: 1992, Standards Precast Concrete Construction in Seis sional Engineers New Zealand, V. 19,
Association of New Zealand, mic Zones, V. 1, Japan Society for the No. 1/CE, November 1992, pp. 21-27.
Wellington, New Zealand, 1992. Promotion of Science-United States 22. Park, R., and Bull, D. K., “Seismic
6. Park, R., and Paulay, T., Reinforced National Science Foundation, Tokyo, Resistance of Frames Incorporating
Concrete Structures, John Wiley & Japan, 1986, pp. 1-38. Precast Prestressed Concrete Beam
Sons, New York, NY, 1975, 769 pp. 15. Park, R., “Precast Concrete in Seismic Shells,” PCI JOURNAL, V. 31, No. 4,
7. Restrepo, J. I., Park, R., and Buchanan, Resisting Building Frames in New July-August 1986, pp. 54-93.
A. H., “The Seismic Behaviour of Zealand,” Concrete International, V. 23. Restrepo, J. I., and Park, R., “Review
Connections Between Precast Concrete 12, No. 11, November 1990, pp. 43-51. of Tilt-Up Construction Details,” Pro
Elements,” Research Report No. 93-3, 16. O’Leary, A. J., Monastra, D. P., and ceedings, Annual Technical Confer
Department of Civil Engineering, Uni Mason, J. E., “A Precast Concrete Mo ence of New Zealand Concrete Soci
versity of Canterbury, Christchurch, ment Resisting Framing System,” Pro ety, Auckland, New Zealand, October
New Zealand, April 1993. ceedings, Pacific Concrete Confer 1993, pp. 38-43.
8. Specification for Concrete Construc ence, V. 1, Auckland, New Zealand, 24. PCI Committee on Tolerances, “Toler
tion, NZS 3109:1987, Standards Asso November 1988, pp. 287-298. ances for Precast and Prestressed Con
ciation of New Zealand, Wellington, 17. Billings, I. J., and Thom, G. W., “NZI crete,” PCI JOURNAL, V. 30, No. 1,
New Zealand, 1987. Centre — Design of Multi-Story January-February 1985, pp. 26-112.
9. ACI Committee 318, “Building Code Towers,” Proceedings, Pacific Con 25. Recommended Practice for Erection
Requirements for Reinforced Con crete Conference, V. 1, Auckland, of Precast Concrete, Precast/Pre
crete (ACI 3 18-89),” American Con New Zealand, November 1988, stressed Concrete Institute, Chicago,
crete Institute, Detroit, MI, 1989. pp. 309-3 18. IL, 1985, 87 pp.

60 PCI JOURNAL

Das könnte Ihnen auch gefallen