PVP2015
July 19-23, 2015, Boston, Massachusetts, USA
PVP2015-45938
Joseph Akanni
Senior Inspection Engineer
Shell Nigeria Exploration and Production Co,
Nigeria
Oladipo Alonge
Materials, Corrosion and Inspection Engineer
Shell Petroleum Development Company of Nigeria Ltd.
NOMENCLATURE
• Inspector;
• Asset operator; Figure 1: RBI Assessment Workshop Workflow
• Maintenance engineer
Asset Integrity Data
• Process engineer/Technologist
• Materials & Corrosion engineer The RBI process starts with a precise definition of its
• Representatives of local legislative body boundaries and identifying all static equipment to be
included. The next step is to compile and check all
The RBI team may be supplemented by additional relevant asset integrity data such as:
expertise including production chemist and IT support • Process data and drawings
engineer on an ad hoc basis. • Engineering design data
• Description and evaluation of degradation
It is essential to bring together all relevant information mechanisms
including asset integrity data in preparation for the RBI • Compilation of inspection history
assessment. After completion of the preparation, the
workshop which is preferably off-site can be organised. It The RBI is a live process and must include update of the
is best practise to schedule the RBI workshop as full week asset integrity database with results of inspections,
or 2 week session depending on the asset and equipment monitoring and process/asset changes. This will
to be assessed. progressively eliminate uncertainties in assessments and
calculations, and result in an effective inspection
The RBI assessment workflow is represented in Figure 1 programme.
and also stated below:
Corrosion Loop Definition
• Review of asset integrity data
• Identification of corrosion loops All facilities are subjected to several potential degradation
• Marking of the loops on PEFS mechanisms, which need to be carefully controlled to
The susceptibility to failure is subdivided into 4 classes: For non-age related (random) failure characteristics, the
negligible, low, medium and high. It is assessed using remnant life cannot be assessed because the onset and
questionnaires based on relevant information regarding rate of degradation cannot be predicted. These failure
process conditions, degradation mechanisms and also the characteristics require a separate approach based on
materials, corrosion and inspection knowledge. control of internal and/or external operating conditions. A
proper monitoring scheme for the integrity operating
Three consequence categories are considered for a window should be agreed for such cases.
failure mode: economic, health/safety and environment.