AUGUST 2016
Table of Contents
Chapter No. Title No. of
Pages
Executive Summary 5
1.0 Introduction 03
2.0 Objective of the Comprehensive DPR 20
3.0 Inputs for preparation of Comprehensive DPR 02
4.0 Review of data 26
5.0 Cost, Schedule & Benefits 15
List of Tables
List of Annexure
Annexure No. Title No. of Pages
01 RLA &CAS Study of Boilers 1 and Boiler 2 15
02 Condition Assessment of Turbine Generators 1 05
and 2
Bibliography
Legend
Abbreviation Expansion
DPR Detailed Project Report
R&M Renovation & Modernization
KPCL Karnataka Power Corporation Ltd.
RTPS Raichur Thermal Power Station
LE Life Extension
RLAS Residual Life Assessment Study
CAS Condition Assessment Study
PLF Plant Load Factor
RH Re-heater
ST Station Transformer
ICT Interconnection Transformer
MU Million Units
GCV Gross Calorific Value
Kcal Kilo calories
kg Kilograms
Kcal / kg Kilo Calories per Kilogram
% Percent.
PAF Plant Availability Factor
APC Auxiliary Power Consumption
KL Kilo Liters
EES Energy Efficiency Study
HPT High Pressure Turbine
C&I Control and Instrumentation
BFP Boiler Feed Pumps
HFO Heavy Furnace Oil
LDO Light Diesel Oil
CEA Central Electricity Authority
HP High Pressure
APH Air Preheater
EA Energy Audit
GOI Government of India
BHEL Bharat Heavy Electricals Ltd.
BTG Boiler, Turbo Generator
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
IBR Indian Boiler Regulations
OEM Original Equipment Manufacturer.
O&M Operation and Maintenance
RPSH Radiant Platen Superheater
LTSH Low Temperature Superheater
RDSH Reheater desuperheater
TMCR Turbine Maximum Continuous Rating
BMCR Boiler Maximum Continuous Rating
ESP Electro Static precipitator
HT High Tension
HP High Pressure
Mg/Ncum Milligrams per Normal cubic meter
TG Turbo Generator set
H2 Hydrogen
CO2 Carbon Di oxide
AC Alternating current
LP Low pressure
IP Intermediate Pressure
DM Demineralized
SS Stainless Steel
ID Induced Draft
A/C Air conditioning
DG Diesel Generator
LT Low Tension
ATRS Automatic Turbine Running system
CPRI Central Power Research Institute
FD Forced Draft
PA Primary Air
PRDS Pressure Reducing and Desuperheating station
MPR Monthly Performance Report
TAR Trip Analysis Report
CRH Cold Reheat
CEP Condensate Extraction Pump
CWP Circulating water pump
BOP Balance of Plant
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
SCADA Supervisory control and Data Acquisition
EXECUTIVE SUMMARY
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
1. Power plants which are more than 25 years old are not operating at the design
capacity and efficiency. The existing generation capacity can be maximized by suitable
R&M works of existing plants which is one of the most cost effective options for
increasing the power availability due to short gestation period and lower investment
requirement.
2. RTPS is a coal fired power station located in the Raichur District of the state of
Karnataka, operated & maintained by KPCL. Units 1 & 2 of RTPS were commissioned
in 1985 &1986 respectively. These units have run more than two lakh hours each and
3. KPCL/RTPS have carried out RLA, CA and EA using the services of various agencies
such as BHEL and CPRI on the Boilers, TG units and auxiliaries of Unit 1 and 2. Based
on these studies, KPCL invited proposals for Consultancy Services for preparation of a
Comprehensive Detailed Project Report (DPR) for R&M Works to improve the
availability and residual life of these units. The Comprehensive DPR was also required
to cover the issue of whether to carry out R&M of Units 1 and 2 or go for a new higher
capacity unit as replacement for these Units. Various environmental issues such as
taking up R&M on the existing ESP’s of Units 1 and 2 in case of decision to go with
R&M of Units 1 and 2 were also to be addressed in the report. M/s. TUV SUD South
Asia Pvt. Ltd was the successful bidder for the above job.
4. Analysis of the various operating parameters of these units shows that the generation
levels of both units are well below the expected generation from similar plants. Trips
time, low availability and plant load factors. HFO, LDO and auxiliary power
consumption is high. Hence it is necessary to look into all the deficiencies in the
various equipment, system design features, account for the inferior grade of coal
presently being supplied to the plant and take a holistic approach in deciding the R&M
5. RLA study of Units 1&2 boilers was carried out by OEM BHEL during the year 2005 &
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
2010 respectively. RLA study of Unit-1 turbine was carried out during 2006 and that
of Unit-2 turbine was carried out during 2010. CA of Unit 1 Boiler was carried by BHEL
in July 2009. Baseline Energy Audit has been conducted by CPRI during the year
2011. All the above studies form the basis of this Comprehensive DPR. CA on ESP of
6. Ministry of Power, GOI guidelines allows R&M works for power stations where BHEL
are the OEM’s for the Boiler and TG (BTG) sets may be awarded to BHEL through
Phase 1: R&M works pertaining to BTG, BOP and Electrical including retrofitting
Phase 2: R&M works pertaining to fire alarm system & DM plant, ash handling
and other miscellaneous works like lighting etc. are required and may
7. M/s KPCL has discussed with M/s BHEL and consolidated all the works which need to
be taken up in Phase 1 and obtained the cost. For the Phase 2 works the cost including
supply, E&C, taxes etc. is estimated by M/s TUV- SUD. The total cost for Phase 1 and
2 Phase 2 9319.10
Total 78094.30
IDC 18115.00
8. The schedule for completion of R&M works under Phase 1 & 2 is estimated as 48
9. Replacing existing old units by a higher capacity new unit is an alternative to R&M.
However going in for a new larger capacity set will pose the following difficulties:
The cost for R&M works is around Rs 1.8 crores/MW as against Rs 6-7
Coal conveyers feeding Units 1&2 also feed Unit 3. For a new Unit his
existing 220KV switch yard affecting the evacuation from Unit 3 also.
10. Cost benefit analysis of R&M and break even period are given in the Table 2
Unit 1 Unit2
Sl. After After
Description Unit Existing Existing
No. R&M R&M
4 Cost of Coal per Unit Rs. / Kwh 2.68 2.52 2.78 2.52
5 Cost of Oil per year Rs. Crore 17.99 13.06 17.83 13.06
Revenue generated
9 per annum Rs. Crore 85.17 133.87 84.37 133.87
considering only
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
fixed charges
11. R&M works is expected to extend the life of the units by about 15 years provided the plant
12. KPCL/RTPS may go for internal funding partly and balance fund the may take from
International funding banks like World Bank / Asian Development Bank / KfW Development
Bank or Power Finance Corporation Ltd, India. It may be partly by equity and the rest by
Debt from banks or international funding agencies. The ratio of equity to debt for such
project work will generally be in the ratio of Equity to Debt as 20:80. Interest rates will vary
13. Time line for Phase III scope of works for Unit I & II R&M:
INTRODUCTION
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
1.1 There has been substantial increase in thermal power generation capacity addition in
each of the successive Five Year Plans of India; yet there exists a gap between
demand and supply of power. The new installations are highly capital intensive, and
1.2 Power plants which are more than 25 years old are not operating at the design
capacity and efficiency. Hence the existing generation capacity can be maximized by
suitable Renovation and Modernization (R&M) and such R&M works of existing plants
is one of the most cost effective options for increasing the power availability due to
short gestation period and lower investment requirement. The R&M projects supported
by World Bank focus on heat rate improvement in addition to life extension, capacity
1.3 Many thermal power stations in the country were designed for good quality coals.
However in actual practice the coal available for most plants is of inferior quality
compared to the design coal. The design unit heat rate/efficiency was also based on
the technologies prevailing at that time. These plants now require higher amount of
coal for producing steam for the rated capacity of power generation. Thus, the capacity
of the raw coal feeding system, pulverisers, primary air fan system, ash handling
system etc., for these power stations may have to be augmented during R&M to
generate steam at the rated capacity of the boiler, provided the furnace size is
1.4 For over four decades, the Karnataka Power Corporation Ltd (KPCL) has been a prime
mover behind power sector in the state. KPCL today has an installed capacity of 6498
MW in thermal, hydro, solar and wind with 2325 MW in the pipeline. The 1720 MW
Raichur Thermal power Station located in Raichur District is accredited with ISO
point, KPCL has raised the bar on the quality of deliverables and is working constantly
at lowering cost per MW- a commendable Cost-Value equation that has become a
1.5 The leverage point of KPCL initiatives are its resource management strengths- right
across planning, design, finance and project engineering towards achieving maximum
In order to bridge the gap between demand and supply, especially in the context of
limited financial resources available, it has become imperative to look for other options
which are not as capital intensive as new capacity addition and which could be
1.6 RTPS is a coal fired power station located in the Raichur District of the state of
Karnataka. It is operated by KPCL and was the first thermal power plant to be set up in
the State. The power station was commissioned during various periods from 1985 and
it accounts for a major part of the total electricity generated in Karnataka. The current
installed capacity of the station is 1720 MW. The station has 7 units each of capacity
1.7 Unit 1 of RTPS was commissioned in 1985 and Unit 2 was commissioned in 1986.
These units have served over 29 years, running for more than two lakh hours and have
high time to take up R&M works for enhancement of life of these old units. Frequent
failure of boiler tubes, turbine, excessive leakage in air pre-heaters, electrical flash
overs, reduced reliability of equipment, frequent tripping of units, higher specific fuel
consumption, etc. are the driving factors for considering R& M and LE of these Units.
1.8 KPCL/RTPS have carried out RLA & CA using the services of various agencies such
as BHEL and CPRI on the boilers, TG units and auxiliaries of Unit 1 and 2.
Based on these studies, KPCL invited proposals for Consultancy Services for
preparation of a Comprehensive DPR for R&M Works to improve the availability and
The Comprehensive DPR was also required to cover the issue of whether to carry out
R&M of Units 1 and 2 or go for a new higher capacity unit as replacement for these
Units. Various environmental issues such as taking up R&M on the existing ESP’s of
Units 1 and 2 in case of decision to go with R&M of Units 1 and 2 were also to be
M/s. TUV SUD South Asia Pvt Ltd was the successful bidder for the above job.
An order was issued by KPCL to M/s. TUV SUD South Asia Pvt Ltd, KPCL
preparation of the Comprehensive DPR for R&M works for these two units.
KPCL had carried out number of survey and had discussion with OEM for various
packages and also asked for quotation for various system / equipment. Based on above
In May 2016 KPCL asked TUV-SUD for proposal for comprehensive DPR. TUV- SUD
Under this order TUV – SUD have to undertake the followings scope of works:
1. R&M works of Ash handling system including modification work of ash slurry
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
disposal system, to suit the head requirement due to augmentation of Ash pond
No.2 – stage-1.
3. Any other civil works to be taken up along with the R&M of BTG, which
To include following works as part of R&M works - to be taken up as Phase -3 works (which
7. Retrofitting ESP
8. Electrical package:
b. Balance HT Switchgear to include station Bus A&B, AHP 1&2, Raw water
pump house.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
To study and recommend ways and means for enhancing the life of Units 1&2 with
a view to maximize the generation from these units with optimal utilization of
available resources. The effort to enhance the life of the equipment and improve
efficiency of the plant would involve replacement of existing worn out/ aged and
obsolete equipment/ component in operation with those with more efficient and
latest designs incorporating the state of the art technologies and improved
metallurgy. These Units were originally designed for a coal of GCV of 4700 Kcal/
Kg. This has deteriorated over the last 3 decades resulting in lower PLF compared
to rated value and the ash generation quantity has increased substantially over the
rated value leading to under capacity of the ash handling systems. The loss in PLF
can be partly compensated by improving the efficiency of boiler which may require
economizer coils etc. Ash handling plant capacity augmentation can be done by
More stringent environmental regulations which have come into force in the last 3
decades since the installation of these units call for refurbishment of the existing
pollution control systems to meet the present day standards and also address the
safety of the men, material, machinery and the health of flora & fauna.
Aging and deterioration in the condition of the units has resulted in more trips,
consumption and higher oil consumption due to more number of start-ups and
part load operations. The result of all these factors is higher operating and
generation cost.
Hence the study has to Identify the areas in Unit’s 1 and 2 which need renovation,
efficiency and life of these units based on various studies already carried out by
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
KPCL/RTPS.
ESP’s of Units 1 and 2 with a view to reduce the final emission levels from the
economic viability.
Based on the scope of services / scope ,TUV –SUD have to cover the followings
4. R&M works of Ash handling system including modification work of ash slurry
disposal system, to suit the head requirement due to augmentation of Ash pond
No.2 – stage-1.
6. Any other civil works to be taken up along with the R&M of BTG, which
To include following works as part of R&M works - to be taken up as Phase -3 works (which
d. Balance HT Switchgear to include station Bus A&B, AHP 1&2, Raw water
pump house.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
2.2 Following areas of Units 1&2 are covered by this Comprehensive DPR for carrying out R&M
studies:
Boilers
Bowl mills
C&I
ESP’s
Volumetric Feeders
RTPS is situated on the bank of river Krishna about 18 Kms north of Raichur town,
Karnataka state. The coordinates are 16°21′18″N & 77°20′31″E and the altitude is
passes adjacent to the project site. The nearest Railway station to RTPS is Krishna
Railway Station on SC Railway. The power station is also equipped with a railway
siding called RTPS Railway siding to which full wagon loads can be booked.
However to reach the site one has to detrain at Raichur Railway Station on the SC
Minimum - 06 degree C.
Relative Humidity :
Maximum - 85%
Minimum - 20%
Average - 65%
Wind Velocity :
Average - 29 Km/hr.
Brief details of the units in operation in the plant are given in the following
Table 2-1
a. Lingsugur
2 02.03.1986 1,2&3,
b. Raichur 1&2,
II 3 30.03.1991 290.09 c. Sedam 1&2,
d. Shahpur1&2.
RTPS uses coal for generation of electricity. Its daily requirement of coal is about
24,000 metric tons, delivered from Western Coalfields Ltd. and Mahanadi
Coalfields Ltd. RTPS generates about 2.73 million tons of total ash annually of
which fly ash is about 80% and the balance is bottom ash. Bottom ash which is in
the form of clinker is ground in clinker grinders mixed with water and pumped to the
ash bund. Fly-ash which is separated out from the flue gases in the ESP’s is
disposed off by converting it into wet slurry and dumping it in designated ash
ponds. A part of the fly ash is sold to cement manufacturing industries and other
small scale industries for manufacture of bricks and pavement tiles. The plant's
water requirement is met by pumping raw water from the Krishna River.
The run of mine coal is pulverized and fired into the boilers that convert water into
high pressure steam. This steam generated is used to drive the turbines coupled to
electric generators which generate electricity. The plant can produce 42 MU per
The power generated is evacuated through 220kV and 400kVpower lines from the
respective switchyards in the plant to the state grid. The 400kV yard is also
interconnected to 220kV yard by two ICT’s each of capacity 315MVA. Erection &
this station is taken from 220kV system by ST-1 for units 1 & 2, ST-2 for Units 3&4,
ST-3 for Units 5&6 and ST-4 for Units 7&8 with interlinking switchgear amongst
them.
The height of this chimney of Unit I & II is 130m as reported. The Chimney Shell is
made up of RCC with 0.5m thickness at the bottom. Internal and external
Natural Draft Cooling Tower is an important part of Unit –I & II of the entire project
and as reported was constructed by March 1985. The height of this cooling tower is
almost 130m.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
2.4.1 These Units have been in service for almost three decades since their commissioning.
2.4.2 The units were originally designed for a coal of a GCV of 4700 Kcal/ Kg. The
coal properties have deteriorated over the last 3 decades resulting in lower
PLF compared to rated value and the ash generation quantity has increased
substantially over the rated value leading to under capacity of the ash
handling systems. Aging and deterioration in the condition of the units has
higher auxiliary power consumption and higher oil consumption due to more
number of start-ups and part load operations. The result of all these factors is
higher operating and generation cost. Thus R&M of these units is necessary
2.4.3 Data on various performance parameters of these units including trips etc.
following paragraphs.
2.4.4 Power generated by Units 1 and 2 during the last six years: is indicated
in tabular and graphic form in the following Table 2-3 and in Figure 1
respectively.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
1500 1452.79
Unit-1 Unit-2
1400 1353.45
1300
1187.6 1244.13
1200 1229.838
1165.95
1171.53 1172.22
1100
1034.72
1000 1079.82
986.55
900
850.25
800
Figure – 1
2.4.5 PAF during last Six years in tabular and graphic form is given in the
Fig-2: PAF , %
88.66 Unit-1 Unit-2
88.71
90 88.24
84.98 85.55
82.24 78.77
80 76.32
78.22
70 67.13
59.63
69.23
60
50
U…
2009-10
2010-11
2011-12 U…
2012-13
2013-14
2014-15 (Feb)
2.4.6 PLF During last Six years in tabular and graphic form is given in the following Table 2-5 and
in Figure 3 respectively.
Fig-3:PLF (%)
Unit-1 Unit-2
78.97
80
73.37
67.63 73.06
70 64.56 63.21
63.68 69.64
60 56.25 53.63
58.7
46.22
50
40
U…
2009-10
2010-11
2011-12 U…
2012-13
2013-14
2014-15(feb)
2.4.10 Station APC: during last Six years in tabular and graphic form is given in the
Year APC
2009-10 8.78
2010-11 9.67
2011-12 9.42
2012-13 9.79
2013-14 10.18
2014-15(Feb) 9.12
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
10.18
10.5
9.79
9.67
10
9.42
9.12
9.5
8.78
8.5
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15(Feb) Station
2.4.7 Number of Trips during Last Six Years along with major reasons thereof is
tabulated in Table 2-7 below
Table-2.7: Incidents of Unit Trips & Major cause of Trip
Unit-1 Unit-2
No. Major cause of Trip No. Major cause of Trip
Year
of of
trips trips
Bottom ash seal trough BTF 3 times, Elect. Fault in
2009-1 leakage, reverse power one of the unit buses,
9 23
0
relay operation, etc.
Turbine axial shift, Coal shortage, BTF, Flame
bunker choking due to 42 failures (15 times)
2010-1
29
1 wet coal, No load
demand
BTF 2 times, Flame Non availability of mills,
2011-1
22 18
2 failures BAH leakage,
HPT vibration, Wet coal, BTF 9 times, Flame failure
2012-1
21 29
3 BTF
Turbine capital No load demand, PA-2A
2013-1
34 24
4 overhaul, DG supply motor cable fault, BTF (Re
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
40
35 34
29 29
30
25 22 24
23 24
21
20
20 18
15
10 9
0
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 (Feb)
2.4.8 Unit outages During Last Six Years: Outages in a utility power station
can be a planned outage or a forced outage due to plant and equipment
failures. The outages both planned and forced for units 1 and 2 are listed in
Table 2-8 below.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
2014-15 till
650 1745 541
28-2-15
1095 616 1157
3000 2879
2500
2158
2000 1865
1707
2.4.9 HFO Consumption during Last Six Years is tabulated in following Table
2-9 and diagrammatically shown in Figure 8.
Table 2.9 HFO Consumption, KL/year
Unit-1 Unit-2
10000 9404
9000
8000
7115
7000
5926 5842
6000
5206
5000 4609
3866 3802
4000
3097 3244
2864
3000
1764
2000
1000
0
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15(Feb)
Unit-1 Unit-2
250
200.88
200 182.61
164.18
150
83.39
100
52.62
44.41
50
0
2009-10 2010-11 2011-12
generation of Unit 1 was about 73.5% in 2011-12 which has reduced during the
subsequent years and even in the current year 2014-15 it is not expected to cross
70%. In the case Unit 2 the highest generation was about 79% in 2009-2010 which has
dropped in the subsequent years and the figure is expected to be about 73% in the
It is understood that dip in generation during 2010-11 was due to frequent trips, 2383
hours of outage of Unit-1 and 3536 hours of outage of Unit-2. During this period, some
of the need based R&M works such as replacement of bends, DMW joints for PLSH
and Final SH coils and CW pumps for Unit-1, replacement of HPT module, Boiler C&I
Carrying out these need based R&M works resulted in reduction of outage hours of
Dip in generation of Unit-2 during 2012-13 was due to 29 trips (9 trips due to Boiler
Tube Leakage) resulting in 2855 hours of outage. During 2013, need based R&M
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
works like replacement of RH coils, Boiler and Station C&I etc., were carried out for
AF
Unit 1: During 2010-11, the axial shift problem in Turbine rotor, coal shortage, bunker
choking due to wet coal, No load demand and during 2013-14, Need based R&M (capital
OH) of Turbine and GT failure during Feb’15, Frequent flame failure trips has resulted in
Unit 2: During 2010 to 2013, most of the time the unit availability was less than 70%. This
was mainly due to frequent flame failure in boiler (15 times), Boiler tube failures (BTF: 13
times), electrical fault in unit bus, Bottom ash hopper leakage, coal shortage,
PLF
PLF of units 1 and 2 is around 60% during last six years except for unit-1 during 2009-10
and for unit-2 during 2011-12.The major causes are - lesser availability of critical
non-availability of mills, coal feeding problems, ash evacuation problems, more stringent
emission norms coming into force, turbine related problems, electrical and instrumentation
faults, poor performances of condensate/ feed water heaters, condenser, etc. This is in
addition to the problems like, coal shortage, poor quality coal, bunker/ feeder choking,
APC
APC of the Units has been on the rise due to following reasons:
It is understood that 45% of total station HFO consumption is by units 1&2 during
2010-11, HFO consumption of unit 1 & 2 rose to 5926KL and 4609 KL respectively.
desired value of less than 2 ml/KWH. During 2012-13 & 2013-14, HFO is used for
start-up of the units also. Hence, Specific Oil consumption during 2012-13 has risen to
8.03ml/KWH for unit-1 and 7.21ml/KWH for unit-2. These values are very high.
The above analysis of the various operating parameters of Units 1 and 2 shows that
the generation levels of both units are well below the expected generation from similar
plants. The trips due to failures of components and equipment is frequent leading to
increased down time and consequent low availability and plant load factors. The
consumption of HFO and LDO is high due to frequent trips and repeated start-ups. The
such as condenser cooling water pumps for supply of only auxiliary cooling water,
The need based R&M works being carried out at present are having only a temporary
effect and is not the ultimate solution to improve the generation, reduce the operating
system design features, and account for the inferior grade of coal presently being
supplied to the plant and take a holistic approach in deciding the R&M for
Units 1 and 2.
To improve the performance parameters viz. PLF, PAF, APC etc., of Units 1 and 2
R&M works are envisaged. The R&M work is required for Unit 1&2 BTG package
because most of the equipment is subjected to fatigue stresses and creep due to high
temperatures. Equipment such as turbine rotor and casings, HP piping, boiler headers,
boiler drum, main steam piping and valves, feed discharge lines etc. are designed for a
may encounter premature metallurgical failure due to various operational stresses like
frequent temperature and pressure excursions, full load tripping, frequent starts and
stops etc.
CEA guidelines issued in the year 2009 mandates that the following studies be
conducted on the major plant and equipment through agencies of repute to determine
respectively. RLA study of Unit-1 turbine was carried out during 2006 and that of Unit-2
turbine was carried out during 2010. CA of Unit 1 Boiler was carried out by BHEL in
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
July 2006. Baseline Energy Audit has been conducted by CPRI during the year 2011.
letter date 8.1.2004. It is stated that power stations where BHEL has supplied the main
plant, e.g. BTG sets, the R&M works may be awarded through negotiations to BHEL. It
is also stated that utilities may stipulate only performance related guarantees such as
plant capacities, heat rates, boiler efficiency and stabilized operations for 1-2 years.
As per IBR 1950, utility boilers used for generation of power or process steam has to
operation for safe and reliable further operation of boilers. IBR-391A table 1 & 2 covers
the type of tests to be carried out on each component of boiler pressure parts. The
non-destructive tests are useful in assessing the present condition of the individual
component and calculating their remaining life especially where sampling is not
feasible for components like drum, headers, critical piping, control valves etc.
Destructive tests are used for accurate mechanical & metallurgical properties for
DPR
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
3.1 The Comprehensive DPR for R&M works is to be prepared based on the CAS, RLAS
3.2 The following documents and reports prepared by various agencies received from
CAS carried out by BHEL on Boiler 1 of Unit 1 in July 2009. This report is enclosed
as Appendix 2.
2013.
2010.
Appendix 4.
Brief Report prepared by the office of Chief Engineer Thermal Designs giving data
on plant performance and scope of work and cost for R&M works as discussed with
BHEL.
Performance parameters and data on trips as furnished by RTPS during the last
Some photographs taken during the various RLAS conducted on major equipment.
Summary of brief report for the retrofitting of volumetric feeders with the existing
volumetric feeders.
3.3 TUV SUD also visited RTPS site between 29th October and 31st October 2014 and
had discussions with RTPS engineers and O&M groups regarding the current status
meetings was held at RTPS site between RTPS and TUV SUD on 23rd and 24th
February 2015 to obtain data/details which could not be fully gathered during the first
meeting. The information collected during the above discussions has also been used
Discussions were also held with KPCL at Bangalore on the 1st and 2nd of June 2015.
Details discussed and collected during this meeting have also been used as required
The information furnished in the various CA, RLA and Energy Audit reports have been
reviewed in detail along with the data/details collected during TUV-SUD site visits and discussions
with RTPS engineers at the plant and the data provided in the brief report prepared by M/s KPCL,
4.1.1 Brief design details of the boilers and auxiliaries are furnished in Table 4-1
Make BHEL
mills.
Unit 2 – 1986
4.1.2 The Steam Generators are radiant reheat, natural circulation, single drum, semi-outdoor
The complete furnace section is of welded wall type, arranged as a gas and pressure- tight
envelope. The extended side wall section (where the re heaters are located) is also
covered with water-cooled section. The circulation system is complete with the necessary
The superheated steam system has mainly three sections. The low temperature super
heater section (arranged in the second-pass of the Unit) the RPSH (arranged at the outlet
section of the furnace) and the final super heater (arranged after the Reheater).
Desuperheater have been provided in between the LTSH and the platen super heaters (in
the connection links L&R) for controlling the superheated steam temperature over control
load range. The complete second pass of the boiler (up to the economizer) has been
The complete reheater has been arranged in one section in the horizontal pass of the
Boiler in between the RPSH and the final super heater section. Two numbers RDSH have
also been provided in the cold reheat steam piping at the inlet of the reheater for
emergency use.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
The location and selection of the super heater and the reheater sections have been so
chosen that the rated temperatures of superheat and reheat are anticipated to be achieved
The boiler includes a bare tube economizer made of seamless steel tubes arranged in
The Boiler has two numbers regenerative APH of tri-sector type, as the last stage of heat
recovery. The tri-sector APH have separate sections for heating the primary air required for
The fuel preparation section has primarily six numbers bowl mills arranged for pressurized
operation. Each mill is provided with a raw-coal volumetric feeder. The pulverized fuel
from the mill is taken through pulverized fuel piping to the four corners of the furnace.
Each mill serves one fuel nozzle elevation. The burner wind box section is located in the
four corners of the furnace and arranged for tilting tangential firing.
The complete boiler is of the top-supported type and is provided with the required structural
The Boiler has two cold primary air fans to supply the primary air and two numbers forced
draught fans for supplying the required total combustion air. The boiler is equipped with two
number of ID fans, arranged after the dust collecting system. The complete air and gas
ESP’s are located after the air heater to collect the fly-ash from the flue gas.
The boiler has necessary lining and insulation along with fixing material to limit the outside
The complete integral piping, valves and fittings, all air and gas ducting with dampers/
The CA of Boiler 1 of Unit 1 was done by BHEL in 2009. Summary of the findings and
enclosed at Appendix 2.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
RLAS on Boiler 2 of Unit 2 was done by BHEL in August 2010. Summary of the RLAS and
recommendation of the agency is also enclosed at Annexure 1. The RLAS report of BHEL
is enclosed at Appendix 3.
4.1.3 The following are major recommendations of CA carried out by BHEL on Unit-1 Boiler 1
during 2009:
replaced.
Ducts are punctured & Expansion joints heavily rusted & needs replacement.
FD fans to be replaced
4.1.4 The following are major recommendations of RLA studies made on Unit-2 Boiler
The damaged spray nozzles (LHS) in CRH line are to be replaced in the next
earliest opportunity.
4.1.5 Based on the findings of the various RLA and CA reports, discussions with RTPS
engineers and the discussions which RTPS have had with BHEL regarding the Scope of
R&M works for Boilers 1 and 2, the following are the major works to be taken up for R&M in
Boilers 1 and 2
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
a) APH: Air-preheater leakage in RHS is 53.45% for Boiler 1 and 51.15% for Boiler 2.
Corresponding figure for LHS are 44% for Boiler 1 and 45.10 for Boiler 2 as against
design value of 13.11%. Leakages result in higher loading of ID fan and reduction
of performance of boiler. Hence the APH of both Boilers 1 and 2 need replacement.
Replacement of APH will reduce APH outlet flue gas temperature from present
Action has been taken by RTPS separately for Unit 1&2, for replacement of the
existing APH by a double seal arrangement, drive mechanism with three input gear
b) RH, LTSH, PLSH and Economiser coils: The root cause of deterioration of RH coils
of tubes due to phosphate deposition/ foreign material entrapment etc. In LTSH and
economiser zones, boiler tube failure occurs mainly due to fly ash erosion and cold
end corrosion. The factors influencing fly ash erosion are velocity of flue gas, mineral
content such as alfa quartz in coal, change in direction of flue gas, misalignment of
tube assembly, and temperature of flue gas. It is opined that tube banks replacement
is the need of the hour to minimize these tube bank failures. Hence these coils need
c) Ducts and Dampers: Originally supplied ducts, dampers, gates and expansion joints
are still in service. All the expansion joints are in heavily rusted condition. Hot air
ducts are found in rusted/punctured condition. Flue gas inlet damper of APH is found
in fully eroded condition. Hence, it is proposed to replace the entire hot and flue gas
ducting system along with dampers, gates, flow measuring elements and expansion
joints for gas leak proof and air leak/ingress proof operation of boiler. This has to be
d) All HT Motors of Units 1 and 2 are old and have been rewound a number of times.
e) HP drains and Vent valves: HP drain valves in boiler &turbine area need replacement
4.1.6 KPCL/RTPS have discussed with BHEL the R&M to be carried out on Boilers 1 and 2and
details of the work to be carried out on Boiler 1 and 2 are briefly summarized in following
Table
Scope Of R&M
sss S.No. Description
Unit 1 Unit 2
pieces
5. WW Burner panel
To be Replaced To be Replaced
TDV’s
dampers/gates and
supports.
expansion joints,
12.
dampers/ gates and
supports
Exp Joints,
Chimney inlet)
and supports
ducting.
below
replaced.
For BOP R&M to be carried out for Unit 1 & 2 as per Extended Comprehensive DPR
There are 12 bowl mills, 6 each for each boiler, BHEL make, Type XRP 803. The
All the above replacements are included in the R&M works proposed by BHEL.
In addition 12 no. new feeders are to be installed in the coal feed lines. These will be taken
ESPs provided for Units 1&2 are in operation for more than 29 years since commissioning
of these units in 1985/86. The existing ESPs are designed for emission at ESP outlet of
150mg/Ncum based on the coal quality such as ash content and GCV specified at the time
of procurement of the boilers. Over the years the quality of coal supplied to the power
station has deteriorated both in terms of its GCV as well as ash content. This has resulted
in higher fly ash loads to be handled by the ESP’s. Further, because of deterioration due to
emission levels are higher than the design values. Pollution control board has now made
norms more stringent and accordingly the emissions at ESP outlet has to be maintained
below 50mg/Nm3. Hence for better performance, the present ESPs of Units 1&2 need to be
ESPs with modified design to reduce the emission levels to 50mg/Nm 3 along with
proposed R&M works of boilers of Units1&2. It is preferable to entrust the work to BHEL
who are the original ESP suppliers. Accordingly RTPS has discussed and finalized the
The existing ESP’s casing will be modified to accommodate taller electrodes of latest
design after dismantling the complete internals, retaining the existing support structures,
hoppers & casing. Providing of additional series fields at inlet and outlet as per available
site conditions, rerouting of existing ash handling pipelines and any other equipment if
installed in this area, available front for civil works etc. is also considered.
It is proposed to change the internals of existing ESPs with new design. Existing six field
internals are replaced with five field new improved design internals by increasing casing
height to 14m, bigger field with 750mm wide collecting electrode, 400mm pitch design and
latest design tumbling hammer type rapping mechanism. Also existing ESP casing will be
extended horizontally to have one series field each at inlet and outlet. Thus ESP will have
seven fields in series. Due to fouling in existing intermediate storage hopper at ESP inlet
side between Units 1&2, one field at inlet side Unit-1(D pass) and one field at Unit-2(A pass)
is not feasible and hence not provided. Therefore there will be 27 Electrical fields for one
Two Nos. existing LT main switch board feeding power to auxiliary control panels will be
modified. One set of PC based precipitator integrated operating system (IOS) to enable
UCB operator to access the ESP controls for control monitoring and data acquisition
50mg/Nm3 with all fields in service corresponding to the precipitator collection efficiency of
99.904% considering the gas temperature and dust concentration at ESP inlet as shown
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
in Table-4.3.
design, proposed
Design
deg.C
h
Emission at ESP Outlet 150 50 Emission reduction by 66%.
e
mg/Nm3
above data for refurbishment of ESP’s is based on the analysis of coal as indicated in
2 Ash % 46.8 -
Augmentation of existing ash handling system for modified ESPs /Ash handling system for
Germany
Rating 210 MW
inlet
CA on this turbine was carried out by BHEL in March 2006. The summary of the BHEL
BHEL had not observed any major issues and had recommended running the machine
a) IP stud (PP) No. 155, which was found to have damaged threads, to be repaired /
replaced.
b) Bearing No. 3 (top and bottom) to be monitored for edge de-bonding which was
noticed in DPT in UT during every overall to ensure safe operation of the unit.
c) The cracked blade numbers 414 (G – 23) and 585 (G-48) of 8th stage (generator
next overall to assess the then prevailing material condition for further continuous
Rating 210 MW
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
Superheated steam pressure at 148 Kg/cm2
turbine inlet
turbine inlet
metal debris which might have come from the boiler tubes. RTPS was advised to
replace existing HP rotor and inner casing with the spare one and go for a set of new
spares. Lot of scaling was observed in the condenser tubes during the testing and it
was suggested to remove the scaling fully or replace with new tubes to enhance the
efficiency of the condenser. All the other components subjected to NDT were good for
continued service.
requirements. As such no immediate action was recommended and all the tested
components were cleared for continued service for another 5 years. Last stage LP
blades on both sides i.e. 2L, 3L and 2R & 3R were advised for replacement at the
Make THW
Rating 210 MW
September 2013. BHEL had not observed any major issues and had recommended
For the purpose of this report no major rework is assumed for this generator.
Make THW
cooled
Rating 210 MW
October 2010.
Electrical tests conducted on rotor and stator windings showed that the condition of
insulation in both cases is satisfactory. BHEL had not observed any major issues and
BHEL had suggested that the electrical tests be repeated during the next major
overhaul to rule out any major deterioration in the condition of the insulation.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
sets and based on the discussions with RTPS operating personal the following are the
Turbine Unit 1
the CA report has been carried out as part of regular maintenance of the plant.
LPH-3, HPH-5&6 for Unit 1 have extensive leakages leading to very low feed water
replacement to improve the boiler inlet water temperature which will lead to
Condenser Vacuum drop needs prime attention to improve turbine heat rate. The
reduce back pressure on the turbine. This in turn will increase efficiency and
reduce the heat rate of the unit. Condenser tube replacement is necessary.
All major valves, piping and accessories including valves in the LP and HP heater
and by pass lines, turbine drain valves, oil supply unit etc. to be replaced.
Generator Unit 1
H2 and Co2 gas systems to be completely replaced along with manifolds etc.
AC seal oil pump and Vacuum pump along with motors, piping, valves and
instruments to be replaced.
Turbine Unit 2
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
the CA report has been carried out as part of regular maintenance of the plant.
In the case of Unit 2, the performance of all the heaters is very poor. This has
design value of 2410 C), high flue gas temperature at boiler outlet,high spray
requirement.et, high coal consumption, low boiler load and reduction in creep life of
super heater and re-heater tubes. Hence replacement of all the heaters of Unit 2 is
essential.
Condenser Vacuum drop needs prime attention to improve turbine heat rate. The
reduce back pressure on the turbine. This in turn will increase efficiency and
reduce the heat rate of the unit. Condenser tube replacement is necessary.
All major valves, piping and accessories including valves in the LP and HP heater
and by pass lines, turbine drain valves, oil supply unit etc. to be replaced.
Generator Unit 2
H2 and Co2 gas systems to be completely replaced along with manifolds etc.
AC seal oil pump and Vacuum pump along with motors, piping, valves and
instruments to be replaced.
Based on discussions with Ash Handling Plant personal at RTPS it is found that there
are problems in the following areas of the existing ash handling system for Units 1 and
Boiler bottom ash collection system has heavy leakage and the existing feed
gates, clinker grinders, hydro ejectors and ash piping need extensive
Economizer and air preheater ash handling system as existing is a wet system
with ash slurry pumps and pipelines. These are giving problems due to severe
Dry ash piping at various locations especially at bends is posing severe erosion
The existing compressors for fly ash handling are reciprocating type which
needs lot of maintenance and have lived their useful life. These are proposed
The boilers are designed to use coal with ash content of 28%. However over
the years there has been an increase in the ash content of the coal and
presently the ash content is as high as 52%. Hence the ash generated has also
increased and the bottom ash slurry pumps have become grossly undersized
and inadequate. All the ash slurry pumps have to be replaced with suitable
Ash disposal lines to ash pond needs resizing for the additional ash quantity.
The ash slurry lines and all valves in these lines need replacement.
All the LP and HP pumps in the ash handling plant are not of adequate capacity
LP, HP and seal water lines need replacement as these are worn out due to
aging.
Instrument air piping in the complete ash handling plant is worn out due to
The fluidizing system in the ash silos of the ESP’s is not working for a long time.
To cater the requirements of wet ash disposal from all the units, Ash Pond I & 2
were constructed. Ash pond I is completely filled and abandoned since 2002.
At present entire quantity of bottom ash and un- lifted portion of fly ash is
disposed off into the ash pond II in slurry form. Owing to the continuous
dumping of the bottom ash & un- lifted portion of the fly ash, the level of the ash
Under the present conditions, if the height of the ash bund is increased, the
Replacing with higher efficiency five vane impeller retaining with same motor
and New Pump with New Motor is considered to be the better option due to
management.
Visual Inspection of Cooling Tower - 1 was carried out with thorough exercise
externally as well as internally. Internal inspection was possible since this unit
was under shutdown for annual maintenance during our progress of inspection
works.
dispositions of the defects conspicuous and clear on the structure and also
spread across the structure and helps to analyze and device strategies for
leakage; bulging, spalling etc. following discussions provides the details on the
wise and various parts of the structure and provide clear idea about the
from external faces. The whole structure for its full height was inspected by
direct and close inspections whereas for distant locations binoculars have been
used.
and also their extents of spread. Photographs shows condition of the defects
on the chimney structure and help to analyze and device strategies for repairs
required.
structure. Details explained are distinct and segment wise by various parts and
A) Shell.
B) Platforms and Railings.
C) Monkey Ladder.
Based on discussions with RTPS, it is found that there are problems in the various
water systems including the DM water plant. The following need attention in these
systems
Clarifier 1 - Traction rail on top of the clarifier, platform at the top around the
clarifier tank, bridge including the drive mechanism, flash mixers, flow meters,
River water system – All butterfly valves, along with electrical actuators, rubber
Condenser cooling water system – All butterfly valves, rubber expansion joints,
DM water lines from the DM water plant to the Boilers. These lines are to be
Two DM water pumps of required capacity and head with motors and power
Following items need replacement as these are worn out due to usage for over 29 years:
Supply and return piping including tracing, insulation and cladding where ever
required.
Valves in the entire fuel oil system where ever these are found damaged and
unusable.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
Replacement of worn out low pressure cooling water lines to hydrogen coolers.
Retrofitting of centralised A/C system of unit control room as this system is very
Following items in the outdoor 220KV switch yard are very old and of outdated design.
These have frequent failures and spares are not available in many cases. Some of the
transformers have been rewound many times and the internal losses are very high.
DG sets 2x500KVA
The following HT drive motors are in poor working condition and are also of outdated
design. These motors have failed many times and have been rewound on numerous
occasions. Spares such as bearings for these motors are not available. These need to
The following HT switch gear and relays are of very old design and availability of
Amps Nos
Balance in Phase 2
The existing HT cables are paper insulated lead sheathed type which is causing
frequent cable faults and failures. Hence these cables have to be replaced by XLP
It is understood that R&M has been carried out on the C&I systems of the boilers by
BHEL and on the station C&I by Yokogawa. R&M on turbine ATRS has been done by
BHEL.
However the C&I system architecture for all the plant auxiliaries is not current digital
system and there are problems in control in a number areas of the plant such as the
A new DCS system for the main plant of Units 1 and 2 is under implementation and it is
understood that the system is already functional for Unit 1 and for Unit 2 the system will
be fully implemented as soon as they are able to get a plant shut down.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
It is desirable to have current state of the art DCS system for the auxiliaries such as
CPRI, Bangalore has conducted energy audit of all seven Units and also the various
auxiliary systems in 2011. The audit was carried out to study the possibility of reduction
in the heat rate and auxiliary power consumption of the Units. The main observations
R&M.
& material. Replacement of baskets and seals reduce the air ingress in flue gas
ducts and reduces the energy consumption of ID fans, FD fans & PA fans.
The overall efficiency of BFP, CEP, ID fan, FD fan & PA fan are on lower side
The auxiliary power used by BFP & CEPs slightly higher than other units.
test.
KPCL has envisaged that the R&M works as discussed in Section 4.0 may be
Phase 1: R&M works pertaining to BTG, BOP and Electrical including retrofitting
of ESP for which scope of work have been discussed and finalized and
offers received from BHEL. Some of these R&M works have already
disposal system.
DG sets 2x500KVA
Retrofitting ESP
Electrical Package:-
1. Replacement of cable for Transformers
2. Balance HT switchgears to include station Bus A&B, AHP
1&2, Raw water pump house.
5.2.1 KPCL has discussed with BHEL and consolidated all the works which need to be taken up
for comprehensive R&M (Phase 1) of Unit 1&2 and ensure that the work is done
simultaneously in one shutdown period. Accordingly, the scope of work pertaining to Boiler
& Auxiliaries, T.G & Auxiliaries, BOP, Electrical and ESP retrofitting has been finalized.
BHEL has submitted their techno-commercial offer covering supply, erection, testing &
commissioning including civil works of BTG package and also for retrofitting of ESP as
Phase 1 work:
No. Rs lakhs
A Fans 2609.00
vapour extractors.
B Boiler Feed Pumps (Pump Assembly- 3 nos.) & R.C. Valves (6), 943.00
C H. P. Heaters. 1078.00
water plant (pipe line to unit 2), LP piping along with valves,
etc.
motors), Cables
Phase III?????)
A SUPPLY: ESP (Rs. 4230 lakhs), Ash Handling System of new 5045.00
Illumination for the new fields and extended height (Rs. 135
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
B E&C 3000.00
C CIVIL 1575.00
Service Tax at 14% on E&C cost + Civil works i.e. Rs 12082 1691.48
C Lakhs
15 Less cost of 3 no’s BFP R/C valves already placed (-) 131
5.2.2 For the Phase 2 works the estimated cost including supply, E&C, taxes etc. is estimated as
follows based on costs given by original OEM’s and indicated in Table 5.2– Estimated
gravimetric.
provided on 15.06.16)
headers
10 Bunker gates and feeder gates, feeder inlet pipes, feeder 300
system etc.
Total 9319.10
5.2.3 For the Phase 3 works the estimated cost including supply, E&C, taxes etc. is estimated as
follows based on costs given by original OEM’s and indicated in Table 5.3– Estimated
=135
5.2.4 The total cost for Phase 1 and Phase 2 works is as given in Table 5-3
Total 78094.30
Say 78100.00
IDC 18115.00
Total 96215.00
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
The schedule for completion of R&M works under Phase 1 for both Units 1 and 2 from
the Zero date, which corresponds to the contract finalization date by KPCL on BHEL, is
indicated as 48 months. The schedule has been prepared in such a way that only one
Unit is taken out of service at a time in order to minimize the loss of power supply from
RTPS to the grid.
The schedule shall be broadly as follows corresponding to a Zero date of
1st September 2015. Assuming RTPS can provide the required shut down of Units 1
and 2 as per schedule envisaged it should be feasible to complete the Phase 1 R&M
works by August 2019.
Engineering: 6 Months from zero date i.e. by end of February 2016.
Manufacture and supply of boiler parts: 10 Months after completion of engineering
i.e. by December 2016.
Manufacture and supply of turbine parts: 12 Months after completion of engineering
i.e. by end February 2017.
Manufacture and supply of ESP parts of first unit: 10 Months after completion of
engineering i.e. by end December 2016.
Manufacture and supply of ESP parts of second unit: 10 Months, after completion of
engineering i.e. by end April 2017.
Erection of Unit-1 BTG and ESP one pass (out of four) components and systems
which do not need plant shut down including any new civil works etc. 6 months from
September 2016 to February 2017.
Shut down of Unit 1 BTG and ESP, 4 months for completion of balance works i.e.
from March 2017 to End June 2017.
Commissioning and stabilization of Unit 1 BTG with ESP one pass (out of four), 2
months July & August 2017.
Erection of Unit-2 BTG and ESP one pass (out of four) Component systems which
do not need plant shutdown including new civil works etc., 7 months from October
2017 to April 2018.
Shut down of Unit 2 BTG & ESP 4 months for completion of balance works i.e. May
2018 to August 2018.
Commissioning and stabilization of Unit 2 with ESP one pass (out of four),
2 months September & October 2018.
Erection of Unit-1 ESP 3 passes (out of 4), 6 months from October 2018 to March
2019.
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
Shut down of Unit-1 for isolation and normalisation of BTG with ESP
3 passes (out of 4), 45 days from 1st April to mid of May 2019.
Commissioning and stabilization of unit-1 (after normalization of ESP
3 passes out of 4), one month and end by mid June 2019.
Unit-2 Erection of ESP balance 3 passes (out 4), 7 months from
December 2018 to May 2019.
Shut down of Unit-2 for isolation and normalization of ESP balance 3 passes, (out
of4) 45 days from Mid June 2019 to July 2019.
Commissioning and Stabilization of Unit-2 (after normalization of ESP
3 passes out of 4), one month by August 2019.
Replacing existing old units 1&2 by a higher capacity new unit is an alternative available to
R&M of old units 1&2. During R&M of existing Units, KPCL/RTPS can also look into the
possibility of uprating the existing units. This has to be discussed with the OEM BHEL at
the time of finalization of R&M works. However any major uprating in generation capacity
may not be possible considering the life of these units, type of design which is almost 3
decades old and the restrictions in the capacities of various auxiliary systems.
However R&M of existing Units is a more favorable option due to the following reasons:
The cost for R&M works as indicated in Table 5.3 above is around
Rs 1.8 crores/MW as against installing a new unit which at current rates will
be Rs 6-7 crores/MW.
The book value of existing units 1&2 is nullified if we go for new unit.
PPA.
five to six years including getting all statutory clearances. During this period
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
the grid will lose the entire power available from the existing 2 units
(2x210MW).
Units 1 and 2 and clearing of debris for accommodating the new unit and
preparation of site for erection of new unit is a major job both in terms of
additional cost and time. Existing works like cooling tower, TG building, boiler
and other foundations, chimney etc. of units 1 and 2 are to be dismantled and
Erection of new units will need larger space in the existing area where Units 1
and 2 are located. Providing additional space may be difficult as many of the
common utilities like coal conveyers, DM plant, water systems etc. are
situated on one side and Station Transformers, DG plant, CW pipe lines and
220KV switch yard catering to remaining units of RTPS are located on the
layout for the new unit and locating construction yard for new unit will also be
a problem.
The coal feeding conveyers feeding the bunkers of Units 1&2 are also
conveyor feeding Units 4 to 8 may also need shifting to make space for higher
capacity unit.
At present power generated by Units 1, 2 & 3 are fed to 220KV Bus. In case
yard which is serving Units 1&2 along with Unit 3. This will affect the
evacuation from Unit 3 also. All lines emanating from 220 KV switch yard
(Lingsugur 3 lines, Shahabad 2 lines, Raichur 2 lines and Sedam 2 lines) and
affect the state grid because of loss of 630 MW generations from the three
units.
The ash evacuation pipe lines for a distance of about 6 Km from plant to ash
Existing road network leading to the different locations of the main plant and
transformer yard has to be redesigned and re-laid and many existing service
and maintenance buildings may have to be relocated to make space for new
Many other issues and problems may arise which will surface only when the
Comprehensive DPR for the new higher capacity unit is taken up and which
The Phasing of fund requirement to meet the schedule as per Para 5.3 above is given in
Half year No 1 2 3 4
Fund Required as 5 15 20 20
% of total
estimated cost
Half year No 5 6 7 8
Fund Required as 15 10 10 5
% of total
estimated cost
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
An analysis of the generation costs before and after R&M and the benefits have been
analyzed and simple break even period calculated. Details are given in the following Table
5-5
and Cash flow statement are enclosed as Annexure-3: Financial Calculations. Payback
As indicated by BHEL who will carry out the R&M works for the BTG package
carrying out the listed R&M works will lead to an extension in life of Units 1 and
2 by 15 years provided the plant and equipment are operated and maintained as
KPCL/RTPS will be funding the R&M works partly from internal sources (Equity)
funding agencies. The ratio of equity to debt for such project work will generally
be in the ratio of Equity to Debt as 20:80. Interest rates will vary based on the
KARNATAKA POWER CORPORATION LTD
RAICHUR THERMAL POWER STATION UNITS 1 & 2 (2X210MW)
DETAILED PROJECT REPORT FOR RENOVATION & MODERNIZATION
out a study for R&M on Units 1 and 2 of Chandrapur Super Thermal Power
RTPS Units 1 and 2. The estimated cost for R&M for these units was around Rs
5.10 Time lines for Phase III scope of works for Unit I & II R&M:
5.11 Conclusion
In view of above and with reference to the entire Comprehensive DPR, we are
recommending for R&M of Unit 1 & Unit 2, instead of going for new higher
capacity plant.