Sie sind auf Seite 1von 11

PEER-REVIEWED PAPER

IMPROVED SUBCONTRACTOR SELECTION EMPLOYING


PARTNERING PRINCIPLES

By Mohan M. Kumaraswamy,1 Member, ASCE, and Jason D. Matthews2


Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

ABSTRACT: Despite the increasing extent of subcontracting in construction, the importance


of subcontractor selection is frequently underestimated. While the subcontracting element needs
more attention in contractor selection itself, subcontractor selection techniques themselves need
considerable improvements. This paper examines how such techniques can beneficially draw
from improved multicriteria contractor selection methodologies in general, and specifically from
recent developments in client-contractor partnering. It is shown how partnering may be profit-
ably extended further into the supply chain, i.e., into subcontractor selection. A European case
study illustrates the development of a subcontractor selection process that incorporated partner-
ing principles. Despite the longer and costlier selection process, it was found that subcontractor
pricing levels were reduced by about 10% to account for anticipated efficiencies arising from
the proposed partnering. Markedly better time and cost control was achieved on the pilot project.
The relationships between all project participants were also found to have improved consider-
ably. Such observations confirm the value (1) of expanding the partnering ‘‘envelope’’ to en-
compass subcontractors in general; and more specifically, (2) of assessing the potential for such
extended partnering as an integral part of the subcontractor selection process.

INTRODUCTION AND BACKGROUND Jamieson et al. (1996) also attributed the increased use of
subcontractors to the increased complexity of both the
Importance of Improved Subcontracting construction of buildings and the organizational relation-
The contribution of specialist and trade subcontractors ships.
to the total construction process can account for as much However, this increase in complexity, the oversupply
as 90% of the total value of the project (Nobbs 1993), of specialist firms, and the declining construction output
while the incidence and importance of subcontracting in has cultivated an adversarial atmosphere, which has had
Hong Kong is similar (Matthews et al. 1997). Nobbs a negative effect on the main contractor-subcontractor re-
(1993) attributed the increased involvement of subcon- lationships. As main contractors have realized that the
tractors to the shift away from the traditional craft base, greatest potential for cost savings lies with subcontractors,
to a greater reliance on increasingly sophisticated tech- the extent of unfair contract conditions, ‘‘Dutch auction-
nology-based products. Matthews et al. (1996) believed ing,’’ and other onerous practices has increased (Corrup-
that the increase in sophisticated technology-based prod- tion 1992; Matthews et al. 1996; Jamieson et al. 1996).
ucts has required a high degree of design, manufacture, Subcontractors have also caused problems. With easy
installation and commissioning skills that have not been entry into the construction market place in the U.K., sub-
readily available to the industry’s clients, as the skill base contractor organizations have been established with very
has moved away from the main contractor’s organization. little capital investment. Many of these subcontractor
This has resulted in main contractors concentrating their companies do not have the necessary expertise to under-
efforts on managing site operations rather than employing take work satisfactorily and, as a consequence, are unable
direct labor to undertake construction work. By contrast, to give their clients the service they require. Moreover,
many of the bad traits common to the main contractor–
1
Assoc. Prof., Dept. of Civ. Engrg., Univ. of Hong Kong, Pokfulam subcontractor relationship are also common to the sub-
Rd., Hong Kong SAR, China.
2 contractor–sub-subcontractor relationship (Matthews
Res. Fellow, Dept. of Constr. and Real Estate, Univ. of Hong
Kong, Pokfulam Rd., Hong Kong SAR, China. 1996).
Note. Discussion open until November 1, 2000. To extend the clos-
ing date one month, a written request must be filed with the ASCE Importance of Improved Subcontractor
Manager of Journals. The manuscript for this paper was submitted for Relationships
review and possible publication on April 6, 1999. This paper is part
of the Journal of Management in Engineering, Vol. 16, No. 3, May/
Hinze and Tracey (1994) described the findings of ex-
June, 2000. 䉷ASCE, ISSN 0742-597X/00/0003-0047–0057/$8.00 ⫹ ploratory research undertaken in the United States in or-
$.50 per page. Paper No. 20666. der to identify how subcontracts were placed. They put
JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000 / 47

J. Manage. Eng. 2000.16:47-57.


forward a series of recommendations to improve the sub- sion makers who are (1) answerable to their sharehold-
contractor–main contractor relationship. They added that ers, their superiors, or the taxpayers; and (2) unable to
further in-depth research should pursue various critical see the product they are contracting to purchase. Clients
issues identified in their study. and their consultants often resort to simplifying assump-
In the U.K., the Latham Report (Latham 1994) pro- tions, for example that (1) their specifications clearly de-
vided a focus and motivation to explore improvements fined the product; and (2) all contractors are ‘‘the same’’
in main contractor–subcontractor relationships for the and will perform similarly (also under all circum-
benefit of the industry as a whole. Partnering was seen stances). It is now widely accepted that such assump-
as one way to achieve these improvements (Matthews tions were naive, if not fallacious. Bitter experiences
1996). have shown that the lowest tender may have originated
Latham also recommended that partnering should be from inaccurate estimating, inadequate risk provisions,
considered in the context of main contractor–subcon- deliberate decisions to use substandard resources, and/or
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

tractor relationships, commenting: even ‘‘smart’’ pricing strategies aimed at generating


claims for extra payments through contractual loopholes
‘‘Partnering arrangements are also beneficial between
firms. Some main contractors have developed long term (Kumaraswamy and Walker 1999).
relationships with subcontractors. That is welcome. Such Such problems initially led large clients: (1) to com-
arrangements should be the principle objective of im- pile lists of ‘‘registered’’ contractors who were perceived
proving performance and reducing costs for clients. to have the required minimal experience, track records,
They should not be ‘cosy.’ The construction process ex- and capabilities for certain types and values of construc-
ists to satisfy clients. Good relationships based on mu- tion; or (2) to prequalify tenderers for a specific project.
tual trust benefit clients’’ (Latham 1994). Such short-listing of eligible tenderers overcame some
of the deficiencies of selecting the lowest tenderer there-
Since the early 1990s many organizations in the Brit-
after. But further consideration of nonprice parameters
ish construction industry have employed partnering
after receiving tenders as well has been urged, for ex-
within their business practices and relationships. Walter
ample by Holt et al. (1996), who recommended combin-
(1998) showed that many of the large U.K.-based main
ing each ‘‘potential performance score’’ with the corre-
contractors were pursuing partnering relationships, with
sponding tender bid to yield an ‘‘overall score’’ for each
partnering ‘‘workloads’’ increasing over time. Similarly,
the Reading Construction Forum (The seven 1998) and tenderer.
Watson (1999) clearly show the attention major ‘‘blue- On the other hand, the ‘‘money value’’ of time savings
chip’’ clients are giving partnering. may also be factored into the final evaluation, for ex-
Research undertaken by Matthews (1996) pointed to ample if tenderers are permitted to propose alternative
the need to rationalize and improve the way subcontrac- project durations. For example, the Florida Department
tors are procured by main contractors, with the adoption of Transportation (Design-build 1996) cites a ‘‘dollar
of the ‘‘partnering philosophy’’ being the key to achiev- value per day saved’’ in the request for proposal package
ing these improvements. and tender price adjustments are accordingly incorpo-
The current partnering literature has largely concen- rated for any proffered time savings, before comparing
trated on the client–main contractor relationship, with prices (Palaneeswaran et al. 1999). Provision was also
little reference to the main contractor–subcontractor re- made to incorporate special considerations for proposals
lationship. Also, much of the partnering literature is con- that significantly reduced traffic disruptions during con-
cerned with discussing partnering from a general per- struction on the I-15 Corridor Reconstruction Project (I-
spective, with little attempt being made to detail the 15 1997).
‘‘mechanics’’ of how partnering relationships were This major shift of focus to the potential of prospec-
forged. This paper will overcome these two weaknesses tive contractors to meet multiple performance criteria
in not only discussing partnering between a main con- has spawned many proposed methodologies for evalu-
tractor and its subcontractors, but also detailing the se- ating contractors at registration/prequalification and
lection criteria used to procure subcontractors. tender stages. For example, Russell et al. (1990) devel-
The increasing size and importance of subcontracts also oped a knowledge-based system for contractor prequal-
make it worthwhile, if not necessary, to reexamine con- ification that involved the evaluation of the following
tractor selection methodologies from the viewpoints of (1) criteria: contractor’s reputation, past performance, finan-
adapting these to subcontractor selection where possible; cial stability, experience record, firm capacity, current
and (2) encouraging better subcontracting practices by workload, and technical expertise. Holt (1998) compared
drawing on lessons learned from contracting itself. different technologies for such evaluation, including, for
example, bespoke approaches (developed by large client
ADVANCES IN CONTRACTOR SELECTION organizations), multiattribute utility theory, cluster anal-
METHODOLOGIES ysis, and fuzzy set theory. A recent Hong Kong–based
Shifting from ‘‘Price Only’’ Single Criterion to survey of public clients also revealed the development
Multiple Performance Criteria of many innovative evaluation approaches that incor-
‘‘Price only/lowest tender wins’’ practices appear sim- porated a range of criteria and techniques (Palanees-
ple, straightforward and reasonable, especially to deci- waran et al. 1999).
48 / JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000

J. Manage. Eng. 2000.16:47-57.


Examples of Evolving Methodologies, Better prime contract work permissible at an any time, ‘‘work
Practices, and Critical Criteria class rating’’ being the maximum value within that class
The aforementioned survey included a review of rel- (Prequalification 1997); ‘‘available bidding capacity,’’
evant international journals and books, an Internet-based and ‘‘available work rating’’ (Rules 1997).
survey of contractor selection practices of public clients In Australia, general prequalification criteria recom-
in the United States and Australia with follow-up by mended by CIDA (the former Construction Industry De-
post, and e-mail with relevant procurement officers and velopment Agency) were classified under groupings of
fellow researchers. It also included case studies of con- technical capacity, financial capacity, quality assurance,
tractors’ evolving selection practices in Hong Kong pub- time performance, occupational health and safety, human
lic bodies. Only a few relevant examples will be cited resource management, and skill formation. These general
here, however, to illustrate the trend in the context of its criteria are incorporated in specific prequalification pro-
relevance to the principal theme of this paper—on im- cesses and indicators being developed by state govern-
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

proving subcontractor selection. ment bodies, for example in Queensland and South Aus-
Palaneeswaran et al. (1999) highlighted some of the tralia (Palaneeswaran et al. 1999).
emerging ‘‘best practices’’ principles, such as
Human Resources Teamworking, Partnering, and
1. Seeking value for money, public accountability, Subcontractors
transparency, and open and fair competition; While the human resource itself and human resource
2. Incorporating indicators to evaluate responsive- management were commonly considered criteria in the
ness, responsibility, and competency of builders; contractor evaluation systems surveyed, only a few of the
and systems specifically invited attention (1) to the potential
3. Incorporating ‘‘performance ratings,’’ for example: for partnering; and (2) to subcontractor teams. For ex-
(a) the ‘‘prequalification rating,’’ formulated by the ample, ‘‘subcontractors and consultants’’ are briefly listed
West Virginia Department of Highways, based on as a factor under the ‘‘technical capacity’’ criterion group
past performance, net current assets, insurance, line recommended by CIDA in Australia, as mentioned in the
of credit, and equipment availability factors; and above paragraph. In an example from the United States,
(b) the PASS (Performance Assessment Scoring the Utah Department of Transportation (I-15 1997) doc-
System) of the Hong Kong Housing Authority that umented how (1) a requirement that prime contractors
involves detailed evaluation of the performance of perform at least 30% of the work was waived on the I-
registered contractors on their ongoing projects, 15 Corridor Reconstruction Project; (2) ‘‘partnering was
which is then fed into their PASS scores that would not only desirable, but a must for the project;’’ and (3)
in turn entitle contractors with higher scores to subcontracting opportunities for local contractors and
more bidding opportunities for future projects (by suppliers were encouraged/facilitated.
including the better-performing contractors in Baxendale and Greaves (1997) while recounting the
shortlists that exclude the poor performers). increasing popularity of client–main contractor partner-
ing, also showed how both subcontractors and main con-
Russell (1996) discussed the merits and methodolo- tractors would benefit from incorporating subcontractors
gies of contractor prequalification in greater detail, while within the partnering orbit and processes. Conversely, a
Hatush and Skitmore (1997) reported on a Delphic study case study of a partnered project in Hong Kong that did
that investigated perceived relationships between 20 not involve the many subcontractors revealed resulting
contractor selection criteria (CSC) currently in use in the inadequacies in the expected partnering, leading to the
U.K. and project success factors (PSFs) in terms of time, conclusion that ‘‘partnering begins at home’’ in team-
cost, and quality. Dominant CSCs perceived to affect all work within the contracting team itself (Dissanayaka and
three PSFs were found to include past failures, financial Kumaraswamy 1997).
status, financial stability, credit ratings, experience, abil- It appears that despite the significant extent of sub-
ity, management personnel, and management knowl- contracting in most construction industries, the evalua-
edge. tion of proposed subcontractors has not yet featured
These critical criteria/factors also need to be incor- prominently in contractor selection criteria and meth-
porated in measurable indicators/parameters, for exam- odologies. While some contractors require that subcon-
ple via transformed financial ratio models for improved tractors be approved by the client, this may not be an
contractor evaluation as demonstrated by Edum-Fotwe appropriate/adequate check in a pressurized operational
et al. (1995). On the other hand, contractors who are phase when delays in agreeing on a series of subcon-
‘‘registered’’ (for longer-term prequalification with large tractors may be counterproductive. It also may not be
client organizations) or prequalified (for specific jobs) possible to probe (at that stage) into the multiple layers
may be banded into groupings that would help determine of sub-subcontractors (and below) that eventually
the maximum dollar value of work for which such a emerge on Hong Kong construction sites, for example.
contractor may be allowed to bid. In the United States, Therefore, when evaluating potential contractors at
various states have developed their own rating systems tender stage (or even at registration/prequalification
with classified and well-defined limits such as ‘‘maxi- stages, if feasible) provision should be made to assess at
mum capacity rating’’ for the total value of uncompleted least (1) the proposed subcontractor selection method-
JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000 / 49

J. Manage. Eng. 2000.16:47-57.


ology/criteria; (2) any potential/short-listed subcontrac- standing of each other’s individual expectations and
tors; and (3) how well the main contractor/subcontractor values.’’
team may operate in a partnering mode with the client’s The vast majority of partnering commentators (Gaede
project management/design team. 1995; Trusting 1995; Matthews 1996) discuss partnering
in the context of either project partnering or strategic
PARTNERING partnering. Project partnering is partnering undertaken
on a single project. At the end of the project the part-
In order to appreciate the potential impact the part- nering relationship is terminated and another relationship
nering philosophy can have both on the main contractor/ may commence on the next project. Project partnering
subcontractor relationship and the subcontractor selec- was pioneered in the U.S. construction industry during
tion process, it is worth noting the development of the mid to late 1980s.
partnering as well as the main elements of a generic Strategic partnering takes place when two or more
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

partnering relationship. This section does not seek to be firms use partnering on a long-term basis to undertake
exhaustible in discussing these trends, as much work has more than one construction project, or some continuing
been undertaken in this respect by other commentators, construction activity (Trusting 1995). However, Kubal
such as the Reading Construction Forum (Trusting 1995; (1994) and, more recently, the Reading Construction Fo-
The seven 1998), the Construction Industry Institute (In rum (The seven 1998) discuss partnering at an industry-
search 1991), the National Economic Development Of- wide level. Kubal (1994) notes that although partnering
fice (Partnering: Contracting 1991), Crowley and Karim is practiced on fragmented projects, it required national
(1995), and the Associated General Contractors of Amer- lobbying in order for partnering to be used across in-
ica (Partnering: A concept 1991). However, the follow- dustry under the correct circumstances. In the U.K., the
ing will highlight the main relevant themes and points Reading Construction Forum (The seven 1998) develop
that were, and should be, borne in mind when develop- this point further by stating that new initatives in part-
ing partnering relationships and subcontractor selection nering have enabled ‘‘second- and third-generation part-
criteria. nering’’ to evolve. Watson (1999) reported that second-
The adoption of partnering into the construction in- generation partnering was underpinned by the ‘‘seven
dustries of the United States, Australia, and the U.K. can pillars’’ of partnering (The seven 1998), these being strat-
be attributed to the fact that relationships in these in- egy, membership, equity, integration, benchmarks, pro-
dustries were commonly lacking trust, respect, and hon- ject processes, and feedback. In the third generation of
esty between professionals, main contractors, and sub- partnering the construction firm should be building vir-
contractors. This had led to procurement problems, with tual organizations with its supply chain to provide a
claims, litigation, and unsatisfied clients being common. complete service that is efficient, creative, and innova-
The 1994 report on the U.K. construction industry by tive (Watson 1999).
Sir Michael Latham, entitled Constructing the Team (La- Table 1 compares four studies on partnering under-
tham 1994), provided an impetus to improve the rela- taken between 1991 and 1996 in the United States and
tionships between all parties involved in construction the U.K. It highlights the main elements of partnering
procurement. Partnering was seen by many as the key to as identified from these studies.
achieving this improvement. Sir John Egan advocated Such consideration of the main elements of both proj-
the use of partnering in his more recent review of the ect and strategic partnering has been commonplace
U.K. construction industry, Rethinking Construction within the partnering literature since its first implemen-
(Egan 1998). He wrote that partnering through the sup- tation in the late 1980s and early 1990s. Many com-
ply chain is a critical approach with which the U.K. con- mentators [for example, Cook and Hancher (1990), Part-
struction industry can drive innovation and sustain in- nering: A concept (1991), Mosley et al. (1991), Sanders
cremental improvement in performance. and Moore (1992), Harbuck et al. (1994), Larson (1995),
Walter (1998) reported that partnering has been pop- Trusting (1995), and Matthews (1996)] have discussed
ularly adopted in the U.K., with national contractors now partnering elements, but very few have discussed part-
prepared to work in a climate of cooperation fostered by nering in the context of the main contractor–subcon-
partnering arrangements. Walter found that many firms tractor relationship.
were expecting partnering contracts (whether formal or Baxendale and Greaves (1997) noted in their survey
informal) to account for over two-thirds of their work- of U.K. main contractors that several companies had
loads in the financial year 1998 to 1999. identified that they were adopting, or going to adopt,
One of the most commonly cited definitions for part- partnering relationships with their subcontractors in or-
nering is that of the Construction Industry Institute (In der to improve service and reduce costs. They also note
search 1991): ‘‘a long-term commitment between two or that many main contractors in the U.K. were at the time
more organisations for the purpose of achieving specific expressing their intentions (within the trade press) to
business objectives by maximising the effectiveness of partner with subcontractors, a view supported by Watson
each participant’s resources. This requires changing tra- (1999). Love (1997) points to an episode in the United
ditional relationships to a shared culture without regard States that clearly shows how partnering can facilitate
to organisational boundaries. The relationship is based project performance within the context of the main con-
on trust, dedication to common goals, and an under- tractor–subcontractor relationship. However, it can be
50 / JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000

J. Manage. Eng. 2000.16:47-57.


TABLE 1. Comparison of Identified Partnering Elements [Adapted from Matthews (1996)]

Associated General Contractors


of America (Partnering: Reading Construction Forum
A concept 1991) Sanders and Moore (1992) Matthews (1996) (Trusting 1995)
(1) (2) (3) (4)
Commitment Cooperative management team Goals and objectives Free and open communication
Continuous evaluation Cooperation Trust Open book costing
Equity Open communication Problem resolution Annual review of performance
Mutual objectives Group working Commitment Workshops
Timely responsiveness Common goals Continuous evaluation Continuous evaluation
Trust Problem solving Group working Mutual objectives
Implementation Win-win philosophy Problem resolution
Shared risk
Equity
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

Cooperation

concluded by a scan of the partnering literature that the contractors from the main contractor’s perspective in or-
impact of partnering on the main contractor–subcontrac- der to ascertain how the operations of each could be
tor relationships has largely been overlooked. This paper improved, and also at obtaining a holistic view on how
will seek, in part, to overcome this weakness and discuss practices and approaches, including those of subcontrac-
the impact of partnering on subcontractor selection. tor selection, between the main contractor and subcon-
tractors could be improved and what features of their
METHODOLOGY OF A U.K.-BASED relationships were perceived to be important or unim-
EUROPEAN CASE STUDY portant.
Introduction Examples of open-ended questions asked include
The main contractor who initiated this study believed
that in order to perform more productively it had to work • ‘‘What characteristics of a subcontract firm can
more closely with its subcontractors and also improve have a detrimental effect on the relationship be-
working relationships. The main contractor formulated a tween it and the main contractor?’’
research strategy aimed at identifying how to create an • ‘‘How do you think the precontract/contract/post-
environment on-site where it can be clearly demon- contract phases of the main contractor’s subcon-
strated that their subcontractors perform more cost-ef- tract process could change to make an improve-
fectively in meeting customer needs than they can when ment on the way the main contractor deals, selects,
working on sites of other main contractors. and communicates with subcontractors?’’

Background to Collaborating Contractor Stage 2: Assess Requirements of Main


The European main contractor has an annual turnover Contractors: Subcontractor’s View
in excess of £800 million (1999/2000) in the U.K. alone. The second stage of the research aimed at assessing
The contractor undertakes traditional, design/build, and the requirements of main contractors from the subcon-
negotiated projects. tractor’s perspective by undertaking a review of features
of a main contractor’s organization, including main con-
Case Study Methodology tractor selection procedures and criteria, that were per-
In order to formulate an alternative approach to project ceived to be important or unimportant.
partnering and subcontractor selection, a four-stage re- Examples of open-ended questions asked are
search methodology was developed by a team of 10 ex-
perts drawn from the main contractor and academia. The
experts agreed that this research methodology enabled • ‘‘When you receive an enquiry/tender for the same
identification of the main areas that had negative and contract from different main contractors, does the
positive impacts on the main contractor–subcontractor price that you quote differ for each contractor?’’
relationship. This approach elicited opinions on how • ‘‘What is the extent of the difference?’’
subcontractors could improve their dealings with both • ‘‘Would any preference be given to a particular
this main contractor and others; and how subcontractors main contractor?’’
believed that this main contractor and others could im-
prove their dealings with subcontractors and identify Stage 3: Compare Main Contractor Performance
those procedures and elements where a main contractor to That of Its Competitors
was ‘‘good’’ or ‘‘bad’’ as compared to their competitors. Stage 3 of the research aimed at identifying those
The aims of the four stages were as follows. practices and approaches used to procure and manage
subcontractors that were perceived by subcontractors to
Stage 1: Assess Requirements of Subcontractors be better or worse than the collaborating contractor’s
from Main Contractor’s Perspective competitors.
This stage aimed at assessing the requirements of sub- Examples of questions asked include
JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000 / 51

J. Manage. Eng. 2000.16:47-57.


• ‘‘How do you rate the feedback you get from the • Stage 1: 141 questionnaires and 11 interviews
main contractor on your tender in comparison to • Stage 2: 76 questionnaires and 31 interviews
other main contractors: excellent, good, adequate, • Stage 3: 17 interviews
poor, or very poor?’’
• ‘‘If a limited number of subcontractors, say four, Method of Analysis
were used in tendering, how would this affect the The questionnaires contained closed (tick-the-box)
competitiveness of your bid?’’ and open-ended questions. Closed questions took the
form of a statement that had to be marked in terms of
Stage 4: Develop Alternative Project Partnering importance from 1 (no importance) to 6 (most impor-
Approach tant). All statements were given a percentage (%) score,
The aim of this stage was to develop an alternative which was either a positive or negative percentage of the
approach to partnering to suit the particular requirements total score that could be obtained [i.e., a higher positive
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

of this main contractor, and to improve subcontractor score (⫹%) indicated its relative importance, whereas a
relationships by taking into consideration the findings of negative score (⫺%) indicated its relative unimpor-
the first three stages. The particular requirements of the tance].
main contractor were as follows: Open-ended questions were analyzed by using a con-
tent analysis identification test. All responses to ques-
tions were recorded using, where possible, a tape re-
1. The main contractor did not want to commit to corder. Answers to questions were then incorporated into
long-term relationships without fully understanding a computerized database. The database allowed answers
the practicalities of what they were undertaking. to questions to be recorded in a systematic way that, in
They required, in the first instance, an approach of turn, facilitated the overall identification of those issues
developing relationships for a project-by-project that were found to be the most and least prevalent.
basis only.
2. The main contractor required an approach that pro-
vided both time and cost savings. Development of Questionnaires
3. The approach to partnering required an element of The designs of the questionnaires were based on es-
price competition. This competition was seen to tablished principles, for example derived from Sinclair
provide assurances that any price quoted by a sub- (1975) and Oppenheim (1966). All questionnaires and
contractor was representative of the current market interview instruments were developed by means of a test
price. and revision process. This process tested the content and
4. The new approach would allow the use of more understanding of the questionnaires.
than one tender subcontractor, as well as employ Basic subject areas were identified before questions
their specialist knowledge during all stages of the were formulated. Within all the research stages, the fol-
project. lowing were identified by industry experts as being im-
portant.

In this context it should be noted that the specific de-


tails of the overall partnering approach had been initially • Main contractor–subcontractor relationship;
developed by referring to the partnering literature, which • Main contractor–other main contractors relation-
included: Partnering: A concept (1991), In search ships;
(1991), Partnering: Contracting (1991), and Crowley • Other main contractors–subcontractor relation-
and Karim (1995). On reviewing the partnering literature ships;
it was concluded that the partnering approaches de- • Partnering;
scribed were primarily applicable to the U.S. construc- • Subcontracting practices and processes; and
tion industry and had limited application to the U.K. • Adversarial practices adopted by the main contrac-
Also, the models and methods advocated did not appear tor, other main contractors, and subcontractors.
to be adequately adaptable and did not allow for the
special needs of U.K. contractor tendering and estimat- Questions to be incorporated into questionnaires were
ing. Finally, the approaches developed were primarily in the first instance identified by referring to construction
concerned with the client–main contractor relationship. industry literature. Primary sources of literature used
were academic and trade journals. Further questions
Sample Size were identified by interviewing personnel from the main
In the first three stages of this research case study, 217 contractor and subcontractors.
questionnaires and 59 interviews were completed. Sub-
contractors surveyed ranged from sophisticated E&M or- Research Conclusions of Case Study
ganizations to small ‘‘labor-only’’ groups undertaking The above research elicited observations and general
bar-bending, for example. Personnel interviewed were conclusions that were beneficial within the overall con-
chosen from those in a hands-on management position. text of this study. For example, conclusions from stage
Sample sizes for each stage were 1 included the following:
52 / JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000

J. Manage. Eng. 2000.16:47-57.


1. Main contractor employees believe that there was General conclusions from stage 3 include the fol-
benefit in developing partnering arrangements with lowing:
key subcontractors.
2. Supervision and management characteristics were 1. Earlier involvement of subcontractors should take
the most important features of subcontractors from place at the precontract estimating stage.
the main contractor’s perspective. 2. Benefits of involving subcontractors earlier were
3. Little consensus was identified on how relation- identified as increasing knowledge and understand-
ships between the main contractor and its subcon- ing of the project, and that the main contractor and
tractors could be improved. However, two points subcontractor can share their specialist knowledge.
were identified as having possible significance: im- 3. The most important time for feedback to be given
proving communication, and more teamwork. to subcontractors was at the tender stage. Tender
4. Positive attitudes were demonstrated as having the feedback from the main contractor and other main
contractors was only established as being ‘‘ade-
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

most positive impact on the relationship between


the main contractor and its subcontractors. quate.’’
5. Compliance to commitments and the ability of the
subcontractor to respond quickly and correctly to In stage 4, an overall generic ‘‘project partnering’’ ap-
main contractor needs were confirmed as critical proach was selected based on an extensive literature re-
and important across all divisions of the main con- view and findings from the previous stages and parallel
tractor. research (Matthews 1996). The decision was based pri-
6. It was established within the research that main marily on the following factors:
contractor subcontracting process could be im-
1. As the main contractor did not want to commit to
proved by more feedback and review of subcon-
long-term relationships without fully understanding
tractors primarily within the pre- and postcontract
the practicalities and legal implications of what
stage. Other improvements identified included bet-
they were undertaking, it was concluded that proj-
ter evaluation of subcontractor bids, and allowing
ect partnering relationships were most appropriate.
the main contractor site team more involvement in
This approach would allow the main contractor to
the selection of subcontractors.
develop relationships on a project-by-project basis.
2. Although the main contractor understood that a
General conclusions from stage 2 can be summarized strategic partnering approach potentially offered
as follows: greater time and cost savings, it was aware of its
lack of experience in formal partnering and be-
lieved that successful project partnering relation-
1. Poor site management was identified as a charac-
ships could in time develop into longer-term rela-
teristic that particularly weakened the main con-
tionships.
tractor–subcontractor relationship. By contrast it
3. The main contractor concluded that it would be
was seen that good site management would have a
easier and useful, at least in the first instance, to
particularly positive impact on the subcontractor’s
incorporate an element of price competition into
ability to carry out their work.
project partnering.
2. A better attitude toward subcontractors and more
trust and fair dealing, especially when paying sub- The new approach would allow the use of the tenderers’/
contractors, were identified as being ways of im- subcontractors’ specialist knowledge during all stages of
proving main contractor–subcontractor relation- the project.
ships.
3. Subcontractors should be involved earlier within Partnering Subcontractor Selection Process
the building process to develop mutual understand- The selection process was designed by one of the writ-
ing of the project. ers of this paper, based on the research findings previ-
4. All subcontractors interviewed confirmed that they ously outlined, together with his extensive personal ex-
were willing to undertake partnering arrangements periences with partnering and subcontracting. Once the
in the future. process had been designed, validation took place via in-
5. Subcontractors gave certain main contractors pref- ternal approval by experienced main contractor person-
erential treatment. nel. It was then implemented in the main contractor’s
6. Main contractors placed too much importance on partnering projects throughout the U.K., and eventually
price to the detriment of quality. extended to Europe.
7. Subcontractors have a good understanding of what The main areas of the partnering approach related to
is important to main contractors when dealing with subcontractor identification, selection, and appoint-
subcontractors. ment are
8. Important issues in improving the main contractor–
subcontractor relationships were payment, com- • Package and company identification;
munication, feedback, selection, tendering, contract • First subcontractor interview;
management, and contract administration. • Second subcontractor interview;
JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000 / 53

J. Manage. Eng. 2000.16:47-57.


• Third interview tender clarification; and services or structural trades), project design manager,
• Final subcontractor selection. and in certain instances, the architect for those trades
with high aesthetical content/contributions, and a planner
Package and Company Identification for those trades with critical programming implications.
The objective of this stage was to identify all major The main contractor’s project manager chaired the
packages on the project that would benefit from the part- meeting. The criteria against which the subcontractors
nering approach. Trades and packages were examined were to be assessed was developed by the project team
under the following headings: facilitated by an independent party. The subcontractors
were informed at the meeting of the general nature of
• Design content; the criteria under which their submissions would be eval-
• Complexity of construction; uated. These criteria were
• High subcontract value;
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

• Long periods of construction; • Understanding of the partnership concept;


• Early commencement of construction; • Response to partnering;
• High level of aesthetics; • Alternative proposals put forward for their package
• Long procurement times; and (these included design innovation, alternative prod-
• Those trades that could ‘‘add value’’ with their uct specification, and value engineering);
early input. • Indicative price;
• Technical ability;
Key trades/packages that were identified included • Enthusiasm for the project;
structural steel frame, brickwork, mechanical and elec- • Past experience of similar work; and
trical engineering, ceilings, floors, partitions, stone clad- • Quality awareness.
ding, atrium glazing, and lifts.
Having identified all trades/packages, names of sub-
Assessment of the subcontractors during the meeting
contractors were put forward by all project team mem-
was facilitated by the use of a pro forma that was com-
bers during a team meeting. The team assessed each
pleted by the project team members at the meeting. The
company in order to shorten the list. Subcontractors were
pro forma was used during the final stages of the sub-
assessed primarily on past performance. Other criteria to
contractor selection process. Fig. 1 shows the structure
be employed include
and nature of the pro forma used. While arguably sub-
jective, these assessments, when combined and com-
• Ability to undertake this quantity of work;
pared across many subcontractors, were found to yield
• Ability to produce the required standard of work;
reasonable outcomes. Averages were taken if necessary
• Ability to undertake the work (not wanting to
(or agreement reached at the meeting) if the same sub-
‘‘overstretch’’ the subcontractors);
contractor received different ratings at the outset.
• Positive attitude (past experiences);
Information handed to all subcontractors at this inter-
• Firm financial background;
view included maximum cost plan prices, drawings of
• Good in-house design service (where applicable);
general arrangements and sections, specifications, and
• Good standards of management (site and head of-
approximate quantities. The structure and agenda for this
fice); and
meeting can be seen in Appendix I. Each interview was
• Main contractor’s desire (if any) to develop a long-
scheduled to last for one hour, with between three and
term relationship with the subcontractors.
six interviews taking place in any particular day. It was
common for all subcontractors concerned with a partic-
On conclusion of the team meeting, between 3 and 5
ular trade to be interviewed in one day.
short-listed subcontractors remained for each package.
In some situations, the first subcontractor interview
Each of the subcontractors was invited to the first sub-
was only used to evaluate subcontractors, as pricing in-
contractor interview, also informing them of the type of
formation was not available.
project, its location, programmed time, and other basic
data.
Second Subcontractor Interview: Project Briefing
First Subcontractor Interview In the scenario where the first interview acted as an
The first subcontractor interview had three aims: evaluation interview only, the second interview was used
firstly, to assess the subcontractor’s ability in terms of to hand over pricing documentation to the subcontractor,
attitude, proactiveness, design capability, honesty, back- as well as to offer another opportunity to the subcon-
ground, and workload; secondly, to introduce the project tractor to meet members of the project team if he/she
and the philosophy of partnering and the team to the had not fully understood the requirements of the project
subcontractors; and thirdly, to hand over pricing details from the first interview.
and other relevant information.
The project team was represented by the principal Tender Clarification
quantity surveyor, project estimator, project manager (for This interview was set for those instances where the
primarily construction trades), appropriate engineer (for first interview acted as an initial subcontractor evaluation
54 / JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000

J. Manage. Eng. 2000.16:47-57.


Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

FIG. 1. Pro Forma Employed for Subcontractor Interview (Each Subcontractor Is Marked from Total Score of 10 for Each Cri-
terion. Also, Each Criterion Could Be Weighted Depending on Its Relative Importance, if Required)

whilst the second was used to hand over pricing docu- they had consciously reduced their pricing levels by an
mentation. The aim of this interview is to give both the average of around 10% (varying only within a close
main contractor and the subcontractor the opportunity to range), in recognition of savings that they anticipated
discuss the tender and check for compliance and accu- from the improved working relationships and arrange-
racy following the return of the tender documentation. ments. These enhanced operational efficiencies were ex-
pected to arise from the partnering arrangements. Con-
Subcontractor Selection fidence in such direct and tangible benefits from
The final decision on what subcontractor was to be partnering was perhaps inspired by (1) acceptance of the
employed was left primarily to the main contractor, al- main contractor’s philosophy that industry needed a rad-
though the client’s quantity surveyor had the opportunity ically changed approach to doing business; (2) increased
to raise any relevant issues. acceptance of partnering principles in the industry in
The selection was made on the criteria communicated general; (3) benefits that were seen to have emerged
to the subcontractor during the first interview. The se- from such client–main contractor partnering; and (3)
lected subcontractor was informed by the project esti- commitment to main contractor–subcontractor partner-
mator that the main contractor wished to work with him/ ing demonstrated by this main contractor in the prelim-
her on the project. An indicative price and budget rates inary meetings and throughout the entire selection pro-
were agreed upon based on the clients’ cost plan. cess.
Follow-up interviews with over 40 project participants
CONCLUSIONS
(30 were formal, while about 12 were informal) also
Twenty separate debriefing interviews with both suc- elicited a general consensus of much better working re-
cessful and unsuccessful subcontractors revealed that lationships between and within teams having been gen-
JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000 / 55

J. Manage. Eng. 2000.16:47-57.


erated in this pilot project. It was also found much easier c. Final tenant
to control time and cost performance levels and achieve d. Other projects on development
higher quality levels given the close cooperation and e. Design philosophy
openness/transparency that facilitated earlier anticipation f. Future awards
and minimization of potential problems. However, it was 2. Main contractor perspective
also noted during the follow-up interviews that the a. Previous development tendering
tender costs during this partnering approach were greater b. Negotiated design and construct through presen-
than those found on competitively tendered projects. tation
The foregoing observations from the case study con- c. Present flip charts of presentation
firmed the value of integrating subcontractors into part- (1) Client concerns
nering arrangements. This also complemented observa- (2) Client needs
tions in Hong Kong on the deficiencies of project (3) How main contractor addressed concerns and
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

partnering arrangements that did not include subcontrac- needs


tors. It is also consistent with the general philosophy of d. What main contractor wants from subcontractors
partnering, in integrating all key participants and incul- e. Go away and think about project
cating a common sense of project purpose, commitment, (1) Achieve cost efficiency
teamwork, and problem-solving. 3. Technical/design details
This established need for main contractor–subcontrac- a. Technical details
tor partnering must therefore be incorporated in the sub- b. Who will supply what (attendance)
contractor selection criteria and reflected in the selection c. What main contractor needs from subcontractor
process itself. The case study described in this paper (cost efficient with design input)
demonstrates a successful application in this respect. The d. Use subcontractor knowledge/experience
needs to incorporate other nonprice criteria in selecting e. Examine information from main contractor in or-
subcontractors can also be addressed by drawing on ap- der to build up price from
propriate approaches from innovative and ‘‘better prac- (1) Drawings
tice’’ contractor selection methodologies that are also (2) Specifications
scanned in this paper. Examples include the incorpora- (3) Details
tion of (1) indicators of responsiveness, responsibility, (4) Form of subcontract
and competency; (2) performance ratings derived from (5) Prelims
previous projects; and (3) capacity ratings of potential f. What subcontractor can use in terms of plant
participants (including subcontractors). g. Performance details of system
Conversely, it is also concluded that main contractor
selection itself should incorporate considerations of the
APPENDIX II. REFERENCES
type of subcontractors, subcontracting arrangements,
and/or subcontractor selection systems that are envisaged Baxendale, T., and Greaves, D. (1997). ‘‘Competitive partnering—a
by the various potential main contractors (i.e., at pre- link between contractor and subcontractor.’’ Proc., CIB W92 Symp.
qualification or bid stages). on ‘‘Procurement: A key to innovation,’’ 21–28.
Cook, E. L., and Hancher, D. E. (1990). ‘‘Partnering: Contracting for
The increasing importance of construction subcon- the future.’’ J. Mgmt. in Engrg., ASCE, 6(4), 431–446.
tracting thus reinforces the criticality of comprehensive Corruption of the commercial process. (1992). Confederation of Con-
selection methodologies that draw on experiences from struction Specialists Services Ltd., London.
other parts of the supply chain, while developing appro- Crowley, L. G., and Karim, M. A. (1995). ‘‘Conceptual model of
priate arrangements that would enhance the overall ef- partnering.’’ J. Mgmt. in Engrg., ASCE, 11(5), 33–39.
Design-build procurement and administration. (1996). Florida De-
fectiveness and efficiency of the total construction proj- partment of Transportation, Tallahassee, Fla.
ect team. Dissanayaka, S. M., and Kumaraswamy, M. M. (1997). ‘‘Partnering
begins at home.’’ Proc., 1st Int. Conf. on Constr. Industry Devel.,
APPENDIX I. FIRST STAGE National University of Singapore, Vol. 1, 340–346.
Edum-Fotwe, F. E., Price, A. D. F., and Thorpe, A. (1995). ‘‘Trans-
SUBCONTRACTOR INTERVIEW AGENDA formed financial ratio models for improved contractor evaluation.’’
Proc., 1st Int. Conf. on Constr. Proj. Mgmt., Nanyang Technological
The structure of each interview is divided into three
University, Singapore, 559–567.
main stages: Egan, J. (1998). Rethinking construction. Department of the Environ-
ment, Transport and the Regions, London, U.K.
1. Introduction to project (15 min) Gaede, A. H. (1995). ‘‘Partnering: A common sense approach to pre-
venting and managing claims.’’ Int. Constr. Law Rev., 72(12), 72–
2. Technical/design details (15 min)
83.
3. Questions and answers where subcontractor takes Harbuck, H. F., Basham, D. L., and Buhts, R. E. (1994). ‘‘Partnering
the lead (10 min) paradigm.’’ J. Mgmt. in Engrg., ASCE, 10(1), 23–27.
Hatush, Z., and Skitmore, M. (1997). ‘‘Evaluating contractor pre-
Agenda for Interview qualification data: Selection criteria and project success factors.’’
Constr. Mgmt. and Economics, London, 15, 129–147.
1. Introduction to project Hinze, J., and Tracey, A. (1994). ‘‘The contractor-subcontractor rela-
a. Location (land surrounding site, access) tionship: The subcontractors view.’’ J. Constr. Engrg. and Mgmt.,
b. Introduction to client ASCE, 120(2), 254–287.

56 / JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000

J. Manage. Eng. 2000.16:47-57.


Holt, G. D. (1998). ‘‘Which contractor selection methodology?’’ Int. in the construction industry: Win-win strategic management in ac-
J. Proj. Mgmt., 16(3), 153–164. tion.’’ Nat. Productivity Rev., Summer, 319–325.
Holt, G. D., Olomololaiye, P., and Harris, F. C. (1996). ‘‘Tendering Nobbs, H. (1993). Future role of construction specialists. The Busi-
procedures, contractual arrangements and Latham: The contractors’ ness Round Table, London.
view.’’ Engrg., Constr. and Arch. Mgmt., Oxford, U.K., 3(1,2), 97– Oppenheim, A. N. (1966). Questionnaire design and attitude mea-
115. surement. Heinmann, London.
I-15 corridor reconstruction project design/build contracting—initial Palaneeswaran, E., Kumaraswamy, M. M., and Tam, P. W. M. (1999).
report, (1997). Utah Department of Transportation, Salt Lake City, ‘‘Identifying best practices in contractor selection for enhanced har-
Utah. mony and profit.’’ Proc., ‘‘Profitable Partnering in Constr. Pro-
In search of partnering excellence. (1991). Construction Industry In- curement’’ Symp., S. Ogunlana, ed., Chiang Mai, Asian Inst. of
Technology, Bangkok, Thailand, 637–647.
stitute, Austin, Tex., Special Publication 17-1.
Partnering: A concept for success. (1991). Associated General Con-
Jamieson, M. J., Thorpe, A., and Tyler, A. (1996). ‘‘Refocusing col-
tractors of America, Washington, D.C.
laboration technologies in the construction value system.’’ Proc.,
Partnering: Contracting without conflict. (1991). National Economic
CIB W78 Conf. Constr. on the Information Superhighway, 279–289.
Development Office, London.
Kubal, M. T. (1994). Engineering quality in construction: Partnering
Downloaded from ascelibrary.org by New York University on 05/01/15. Copyright ASCE. For personal use only; all rights reserved.

Prequalification of contractors, chapter 468-16 WAC. (1997). Wash-


and TQM, McGraw-Hill, New York. ington State Department of Transportation, Olympia, Wash.
Kumaraswamy, M. M., and Walker, D. H. T. (1999). ‘‘Multiple per- Rules for prequalification of contractors and issuance of plans and
formance criteria for evaluating construction contractors (chapter proposals. (1997). Illinois Department of Transportation, Spring-
10),’’ Procurement systems; a guide to best practice in construction, field, Ill.
S. Rowlinson and P. McDermott, eds., CIB W92, Routledge and Russell, J. S. (1996). Constructor prequalification—choosing the best
E & FN Spon, London, U.K., 228–251. constructor and avoiding constructor failure. ASCE, New York.
Larson, E. (1995). ‘‘Project partnering: Results of study of 280 con- Russell, J. S., Skibniewski, M. J., and Cozier, D. R. (1990). ‘‘Quali-
struction projects.’’ J. Mgmt. in Engrg., ASCE, 11(2), 30–35. fier-2: Knowledge based system for contractor prequalification.’’ J.
Latham, M. (1994). Constructing the team. Her Majesty’s Stationery Constr. Engrg. and Mgmt., ASCE, 116(1), 157–171.
Office, London. Sanders, S. R., and Moore, M. M. (1992). ‘‘Perceptions of partnering
Love, S. (1997). ‘‘Subcontractor partnering: I’ll believe it when I see in the public sector.’’ Proj. Mgmt. J., XXII(4), 13–19.
it.’’ J. Mgmt. in Engrg., ASCE, 13(5), 29–31. The seven pillars of partnering: A guide to second generation part-
nering. (1998). Reading Construction Forum, Center for Strategic
Matthews, J. (1996). ‘‘A project partnering approach to the main con-
Studies in Construction, Reading, U.K.
tractor-subcontractor relationship.’’ PhD thesis, Loughborough Uni-
Sinclair, M. A. (1975). ‘‘Questionnaire design.’’ Applied Ergonomics,
versity, Loughborough, U.K.
6(2), 73–80.
Matthews, J., Thorpe, A., and Tyler, A. (1997). ‘‘A comparative study Trusting the team: The best practice guide to partnering in construc-
of subcontracting in Hong Kong.’’ Campus Construction Papers tion. (1995). Reading Construction Forum, Center for Strategic
(CIOB), Ascot, U.K., May, 13–16. Studies in Construction, Reading, U.K.
Matthews, J., Tyler, A., and Thorpe, A. (1996). ‘‘Pre-construction proj- Walter, M. (1998). ‘‘The essential accessory.’’ Constr. Mgr., 4(1), 16–
ect partnering: Developing the Process.’’ Engrg., Constr. and Arch. 17.
Mgmt., Oxford, U.K., 3(1 & 2), 117–131. Watson, K. (1999). ‘‘Is partnering starting to mean all things to all
Mosley, D., Moore, C., Slale, M., and Burns, D. (1991). ‘‘Partnering people.’’ Contract J., 397(6212), 14–16.

JOURNAL OF MANAGEMENT IN ENGINEERING / MAY/JUNE 2000 / 57

J. Manage. Eng. 2000.16:47-57.

Das könnte Ihnen auch gefallen