Beruflich Dokumente
Kultur Dokumente
2015
CONTRACT
PREAMBLE
Whereas Energypac Power Generation Ltd. (Hereinafter referred to as “Employer”) has entered into a
contract with the Sylhet Gas fields Limited for “Design, Engineering, HAZOP Study, Procurement, Supply,
Construction, Installation, Testing, Pre-Commissioning, Commissioning, Start-up and Handover of One
Skid-Mounted 4000 Bbl/Day Capacity Condensate Fractionation Plant with Associated Facilities at
Rashidpur, Bahubol, Habiganj, Bangladesh on Turn-key basis” as per Contract No. SGFL/4000
CFP/EPC/C-1 dated 27-04-2015 and;
Whereas for successful accomplishment of the EPC contractual obligations, Energypac Power
Generation Ltd has expressed its desire to appoint a Consultant for Civil design and related
Consultancy work.
Therefore in consideration of the aforesaid, both parties wish to enter into an agreement to carry out
wants of the Energypac Power Generation Ltd. as mentioned above in accordance with the terms and
conditions set out below.
1. DEFINITIONS
For the purpose of the Contract Documents the words and expressions below shall have the
following meanings:
b) "Consultant" means Structural Design Associates whose quotation/offer has been accepted
and with whom the Contract has been entered into.
d) "Engineer" means the person whose services have been engaged by the Employer to
administer the Contract as well as supervise the whole work as provided therein, as will be
notified to the Consultant.
e) "Contract" means the written agreement between the Employer and the Consultant.
f) "The Work" means the works to be executed and completed under the Contract.
h) "Bill of Materials" is the document in which the Consultant submitted the Works, on the basis of
the foreseen quantities of items of work.
1
i) "Contract Price" means the sum agreed in the Contract as payable to the Consultant for the
execution and completion of the Works and for remedying of any defects therein in accordance
with the Contract.
j) "Site" means the land and other places on, under, in or through which the Works or Temporary
Works are to be constructed.
Payment will be through L/C on sight. 10% advances, 90% of the payment will be made after
successful completion of work ,
4. SCOPE OF WORK
2
Design and drawing will be release progressively. Total work completion time will be 13 weeks.
No extension of time shall be allowed without written consent from the employer.
6. Extra work:
For smooth continuation of the work flow, Employer shall provide preliminary approval to
Consultant. Upon getting the approval from end user, Employer shall provide the final approval.
Any rework after this finalapproval of design, drawing will be considered as an extra work. Any
extra work shall be paid extra over the quoted rate and this will be agreed and approved by the
employer. But in such cases contactor shall not hold the job pending and will continue working to
match the timeline, provided the employer provide approval for the extra amount within Ten
working days.
7. SITE VISITS
Eight visits will be in consultant’s scope for coordination. Any extra visit will charge extra BDT at
10000 per day+ local travel will be provided by employer.
The Consultant warrants that no official of the Employer has been or shall be admitted by the
Consultant to any direct or indirect benefit arising from this Contract or the award thereof. The
Consultant agrees that breach of this provision is a breach of an essential term of the Contract.
The Consultant shall on the written order of the Employer suspend the progress of the Works or
any part thereof for such time or times and in such manner as the Employer may consider
necessary and shall, during such suspension, properly protect and secure the Works so far as it
is necessary in the opinion of the Employer. In no circumstances the Consultantshall suspend the
work without prior written approval of the employer.
Either party can terminate the contract if any major clause of this contract is violated or timeline is
not maintained properly. In that case intending party has to provide one month advance notice.
Employer can terminate the contract if LD reaches at its maximum limit as set forth in section
13B.
Employer will not employ directly or indirectly any of the consultant person from the team who is
involved in the project work till the contract is live and for next six months after work is completed,
terminated.
12. CONFIDENTIALITY
Alldrawings, photographs, plans, reports, recommendations, estimates, documents and all other
data compiled by or received by the Consultant under the work order shall be the property of the
Employer, shall be treated as confidential and shall be delivered only to the duly authorized
representative of the Employer on completion of the Works; their contents shall not be made
known by the Consultant to any person other than the personnel of the Consultant performing
services under this work order without the prior written consent of the Employer.
3
13. LIQUIDATED DAMAGES:
It is understood and agreed that time is the essence of the Contract. Should the Consultant fail to
complete the specified work and portions of the Work within the periods of time stipulated in the
Contract, after due allowance for any extension of time which may be granted under the
provisions set forth hereinafter, the Consultant shall pay to the Employer, Liquidated Damages for
“each” day of default or fraction thereof. Liquidated damage shall be 1% (One percent) of total
contract value for each calendar day.In no event shall the aggregate sum of liquidated damages
exceed 10% of the CONTRACT PRICE.
Contractor shall also be liable for any damages to arise because of the faulty design under the
scope mentioned herein.
14. CONFIDENTIALITY:
Except with the consent in writing of Employer, the Contractor shall not disclose technical
specification or any other proprietary information supplied while executing the Work and
subsequently.
a) War and other hostilities (whether war be declared or not), invasion, mobilization,
requisition or embargo; (b) rebellion, revolution, insurrection, military or usurped power and
civil war; (c) riot, civil commotion, terrorism or public disorder except where solely restricted to
employees of Supplier or any subcontractor (d) flood, lightning, cyclone, typhoon, earthquake,
fire, explosion, shipwrecks, transportation accident or other accidents or act of God.
16. ARBITRATION:
Arbitration Rules: Any arbitration proceedings or award rendered hereunder and the validity,
effect and interpretation of this Clause shall be governed by arbitration rules of BANGLADESH
CHAMBER OF COMMERCE (BCC). Each arbitration shall be conducted in accordance with
BANGLADESH CHAMBER OF COMMERCE (BCC) Arbitration Rules as in effect on the date of this
Contract.
Number of Arbitrators: The arbitral tribunal shall consist of three arbitrators appointed one
each by Employer and Contractor and one neutral.
Contract shall be effective from 22nd August, 2015 (0 date) and shall remain valid until the
fulfillment of the obligations as per this contract and the attached time schedule.
The respective authorized representative of both Parties hereto sign the Contract.
4
(Authorized Signature) (Authorized Signature)
Date : Date :
Witnesses
1.Name : 1.Name :
Address: Address:
2.Name : 2. Name :
Address : Address :