Republic of the Philippines

Department of Education
Region 02
Schools Division of Isabela
REGIONAL SCIENCE HIGH SCHOOL FOR REGION 02
Tumauini, Isabela

BILL OF MATERIALS AND COST ESTIMATE

Name of Project: Construction of Drainage at the back of Main Building and Administration Building
Location: Regional Science High School, Arcon, Tumauini, Isabela

I. Demolition
a. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman 1 10 400 4,000.00
Skilled 1 10 400 4,000.00
Laborer 5 10 350 17,500.00

II. Work Outlay


DESIGNATION NO. # of Days Rate/Day Total
Excavation 5 5 350 3,500.00

III. Massonry works


a. Materials
DESIGNATION NO. Unit Unit Cost Total
Cement 500 Bags 245.00 122,500.00
Gravel and Sand 10 Load 1,500.00 15,000.00
Reinforcement bar 40 Pcs 148.00 5,920.00

b. Labor
DESIGNATION NO. # of Days Rate/Day Total
Foreman 1 10 400 4,000.00
Skilled 1 10 400 4,000.00
Laborer 5 10 350 17,500.00

Rental
DESIGNATION NO. # of Days Rate/Day Total

Material Cost 143,420.00


Labor Cost 29,000.00
Total Estimated Product 172,420.00

Prepared by: Checked by:

GETULIO M. BULALA, JR. DANIEL P. BALACCUA


Physical Facility Coordinator Municipal Engineer

Approved:

EVELYN A. BUMANGLAG
Principal IV