Sie sind auf Seite 1von 5

NASHPA GAS PROCESSING AND LPG RECOVERY

PLANT PROC-FC-CB/NASHPA/PROJ-1247/2015

DOCUMENT NO.: MS FOR INSTRUMENT & UTILITY AIR


Page 1 of 5
NGP-000-ELE-15.71-0004-A SYSTEM TEST

METHOD STATEMENT
FOR
INSTRUMENT & UTILITY AIR SYSTEM TEST

Zealcon HBP/HH ZEL OGDCL


(Representative) (EPC contractor) (Consultant) (Owner representative)
Date: Date: Date: Date:

Signature: Signature: Signature: Signature:


NASHPA GAS PROCESSING AND LPG RECOVERY PLANT
PROC-FC-CB/NASHPA/PROJ-1247/2015
DOC. NO. NGP-000-ELE-15.71-0004-A
DESCRIPTION MS FOR INSTRUMENT & UTILITY AIR SYSTEM TEST
PAGE 2 OF 5

1. SCOPE

Main purpose of this method statement is to describe the INSTRUMENT & UTILITY AIR SYSTEM

test including activities to be carried out according to required specifications.

2. PURPOSE

To ensure INSTRUMENT & UTILITY AIR SYSTEM test.

3. INSTRUMENT & UTILITY AIR SYSTEM TEST PROCEDURE

According to the overall schedule, HBP/HH is planning to INSTRUMENT & UTILITY AIR SYSTEM

at: 9:30 on 20 August 2017, details are given as below:

1) To start diesel generator Y4 as basic power source and to supply power to MDB system;

Note: external power supply is to be of alternative option.

2) After MDB receive power, close BC1-01 switchgear (PANEL AA12) ;

3) After MDB bus bar receive power, close AA17-6/12M switchgear, it is to supply power to

INSTRUMENT & UTILITY AIR system;


NASHPA GAS PROCESSING AND LPG RECOVERY PLANT
PROC-FC-CB/NASHPA/PROJ-1247/2015
DOC. NO. NGP-000-QAC-15.71-0003-A
DESCRIPTION MS FOR Y4 Diesel GENERATOR Trial Run TEST
PAGE 3 OF 5

4. INSTRUMENT & UTILITY AIR SYSTEM TEST FLOW CHART


NASHPA GAS PROCESSING AND LPG RECOVERY PLANT
PROC-FC-CB/NASHPA/PROJ-1247/2015
DOC. NO. NGP-000-ELE-15.71-0004-A
DESCRIPTION MS FOR INSTRUMENT & UTILITY AIR SYSTEM TEST
PAGE 4 OF 5

5. Electrical isolation scheme


NASHPA GAS PROCESSING AND LPG RECOVERY PLANT
PROC-FC-CB/NASHPA/PROJ-1247/2015
DOC. NO. NGP-000-ELE-15.71-0004-A
DESCRIPTION MS FOR INSTRUMENT & UTILITY AIR SYSTEM TEST
PAGE 5 OF 5

6. SAFETY PRE-CAUTIONS AND MEASURES

1). Procedural: Approved Standard Operating Procedure should be prepared / developed and

Operating staff by Commissioning Team

2). Procedural: Shift Inspection Checklist to be developed by commissioning team (including

leakages, dozing details, and as per Vendor recommended checklist)

3). Procedural: Work instructions for operator shall be installed

4). Equipment Safety: Direction or indication of live piping should be done to aware all workforce

about live lines

5). Equipment Safety: Leakages of gas/diesel should be rectified and Missing bolts and screws

shall be installed

6). Equipment Safety: CO2 Fire extinguishers shall be placed

7). Personnel Safety: Work area should be well barricaded to avoid unauthorized entry

8). Personnel Safety: Proper grounding / earthling of equipment should be ensured and checked

as per standard

9). Personnel Safety: Warning sign/instruction sign shall be installed for graphical communication

10). Personnel Safety: Trained and competent personnel should be deployed

11). Personnel Safety: Proper illumination should be ensured within the facility as per standard

guidelines

12). Personnel Safety: entrance slope should be prepared properly to avoid tripping hazards

13). Personnel Safety: Tagging of all valves should be done as per Standards

14). Environmental Compliance: Drainage/leakage should be checked before start up.

Das könnte Ihnen auch gefallen