Beruflich Dokumente
Kultur Dokumente
Page 1
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
566 0% PCB x 2 Bases 1 day Thu 18/07/19 Thu 18/07/19 565
567 0% Disconnector x 2 Bases 1 day Fri 18/07/20 Fri 18/07/20 566
568 0% Yard Light Masts x 2 Bases 1 day Mon 18/07/23 Mon 18/07/23 567
569 0% Water Tank Base x 1 1 day Tue 18/07/24 Tue 18/07/24 568
570 0% Footing for Brickwork to Bunded area 3 days Wed 18/07/25 Fri 18/07/27 569
571 0% Aux Transformer 1 x Base; inside bunded area 0,5 days Mon 18/07/30 Mon 18/07/30 570
572 0% PCB Operator concrete platform 1 day Mon 18/07/30 Tue 18/07/31 571
573 0% Brickwork to pit and Sump 5 days Tue 18/07/31 Tue 18/08/07 572
574 0% Concrete floor slab to sump 1 day Tue 18/08/07 Wed 18/08/08 573
575 0% Diamond mesh fencing 1.2 and 1.8m 2 days Wed 18/08/08 Fri 18/08/10 574
576 0% Apply Herbecide 1 day Fri 18/08/10 Mon 18/08/13 575
577 0% Placing Yard stoning 2 days Mon 18/08/13 Wed 18/08/15 576
578 0% Angle iron frame and gate valve to sump/pit 1 day Wed 18/08/15 Thu 18/08/16 577
579 0% Cover to sump 0,5 days Thu 18/08/16 Thu 18/08/16 578
580 0% Fibreglass grid 0,5 days Fri 18/08/17 Fri 18/08/17 579
581 0% Tank and pipe connection 0,5 days Fri 18/08/17 Fri 18/08/17 580
582 0% Perimeter Fencing (Palisade) 20 days Wed 18/07/18 Tue 18/08/14 561
583 0% 3 kV DC SUBSTATION BUILDING 34 days Mon 18/05/28 Wed 18/07/11
584 0% Roofs and Doors 10 days Tue 18/06/05 Sun 18/06/17
585 0% Roof Replacement 10 days Tue 18/06/05 Sun 18/06/17 542
586 0% Roller Doors 10 days Tue 18/06/05 Sun 18/06/17 542
587 0% RECTIFIER & REACTOR ROOM 16 days Mon 18/05/28 Sun 18/06/17
588 0% Remove external door 0,25 days Mon 18/05/28 Mon 18/05/28 531
589 0% Cut out brickwork for 2 fans 0,5 days Mon 18/05/28 Mon 18/05/28 588
590 0% Remove middle pane glass bricks 0,5 days Mon 18/05/28 Tue 18/05/29 589
591 0% Brick up and plaster removed glass bricks and louvre ventilators 0,5 days Tue 18/05/29 Tue 18/05/29 590
592 0% Replace damaged glass bricks in the 2 side panes 0,5 days Tue 18/05/29 Wed 18/05/30 591
593 0% Fix external plaster frames and paint 0,5 days Wed 18/05/30 Wed 18/05/30 592
594 0% wash and patch walls 0,5 days Wed 18/05/30 Thu 18/05/31 593
595 0% patch around and paint external door 0,5 days Thu 18/05/31 Thu 18/05/31 594
596 0% repair and varnish 2 internal doors 0,5 days Thu 18/05/31 Fri 18/06/01 595
597 0% built new cable trench 2 days Fri 18/06/01 Tue 18/06/05 596
598 0% angle framing for new trench 1 day Tue 18/06/05 Wed 18/06/06 597
599 0% paint walls 0,5 days Fri 18/06/15 Fri 18/06/15 546;598
600 0% paint floor 0,5 days Fri 18/06/15 Fri 18/06/15 599
601 0% paint vastrap covers old and new 0,5 days Sun 18/06/17 Sun 18/06/17 600
602 0% repair and paint mesh partitions 0,5 days Sun 18/06/17 Sun 18/06/17 601
603 0% DC SWITCHGEAR ROOM 6,25 days Mon 18/06/18 Tue 18/06/26
604 0% Remove 2 external doors 0,25 days Mon 18/06/18 Mon 18/06/18 602
605 0% wash and patch walls incl. small room 0,5 days Mon 18/06/18 Mon 18/06/18 604
606 0% patch around and paint 2 external door 0,5 days Mon 18/06/18 Tue 18/06/19 605
607 0% repair and varnish 2 internal door 0,5 days Tue 18/06/19 Tue 18/06/19 606
608 0% paint walls incl. small room 0,5 days Tue 18/06/19 Wed 18/06/20 607
609 0% paint floor icl. Small room 0,5 days Wed 18/06/20 Wed 18/06/20 608
610 0% paint vastrap covers 0,5 days Wed 18/06/20 Thu 18/06/21 609
Page 2
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
611 0% Build in new 5 No 110 sleeves 1 day Thu 18/06/21 Fri 18/06/22 610
612 0% Break to enlarge cable trenche 1 day Fri 18/06/22 Mon 18/06/25 611
613 0% Angle framing to cable trench 0,5 days Mon 18/06/25 Mon 18/06/25 612
614 0% Screed floor 0,5 days Mon 18/06/25 Tue 18/06/26 613
615 0% WAVE FILTER ROOM 3 days Tue 18/06/26 Fri 18/06/29
616 0% wash and patch walls 1 day Tue 18/06/26 Wed 18/06/27 614
617 0% repair and paint external door 0,5 days Wed 18/06/27 Wed 18/06/27 616
618 0% repair and varnish wood structure 0,5 days Wed 18/06/27 Thu 18/06/28 617
619 0% paint walls 0,5 days Thu 18/06/28 Thu 18/06/28 618
620 0% paint floor 0,5 days Thu 18/06/28 Fri 18/06/29 619
621 0% BATTERY ROOM 3 days Fri 18/06/29 Wed 18/07/04
622 0% Cut out brickwork for fan and louvre 0,5 days Fri 18/06/29 Fri 18/06/29 620
623 0% Remove and replace sink and piping 0,5 days Fri 18/06/29 Mon 18/07/02 622
624 0% wash and patch walls 0,5 days Mon 18/07/02 Mon 18/07/02 623
625 0% repair and paint internal door 0,5 days Mon 18/07/02 Tue 18/07/03 624
626 0% paint walls 0,5 days Tue 18/07/03 Tue 18/07/03 625
627 0% paint floor 0,5 days Tue 18/07/03 Wed 18/07/04 626
628 0% REGENERATION ROOM 3,75 days Wed 18/07/04 Mon 18/07/09
629 0% Remove external door 0,25 days Wed 18/07/04 Wed 18/07/04 627
630 0% wash and patch walls 0,5 days Wed 18/07/04 Wed 18/07/04 629
631 0% patch around and paint external door 0,5 days Thu 18/07/05 Thu 18/07/05 630
632 0% repair and varnish internal door 0,5 days Thu 18/07/05 Thu 18/07/05 631
633 0% repair and paint mesh partitions 0,5 days Fri 18/07/06 Fri 18/07/06 632
634 0% paint walls 0,5 days Fri 18/07/06 Fri 18/07/06 633
635 0% paint floor 0,5 days Mon 18/07/09 Mon 18/07/09 634
636 0% paint vastrap covers 0,5 days Mon 18/07/09 Mon 18/07/09 635
637 0% ESKOM METRING ROOM 2 days Tue 18/07/10 Wed 18/07/11
638 0% wash and patch walls 0,5 days Tue 18/07/10 Tue 18/07/10 636
639 0% repair and paint external door 0,5 days Tue 18/07/10 Tue 18/07/10 638
640 0% paint walls 0,5 days Wed 18/07/11 Wed 18/07/11 639
641 0% paint floor 0,5 days Wed 18/07/11 Wed 18/07/11 640
642 0% Building Electrics, lighting and Ventilation 11,5 days Mon 18/06/18 Wed 18/07/04
643 0% AC & DC Building DB 1 day Mon 18/06/18 Tue 18/06/19 605
644 0% Conduit 2 days Tue 18/06/19 Thu 18/06/21 643
645 0% Plugs & Switches & Photo Cell 1 day Thu 18/06/21 Fri 18/06/22 644
646 0% Light Fittings 3 days Fri 18/06/22 Wed 18/06/27 645
647 0% Fans & Louvres & Temp Control 2 days Wed 18/06/27 Fri 18/06/29 646
648 0% Wiring 2 days Fri 18/06/29 Tue 18/07/03 647
649 0% Obtain a COC Certificate 0,5 days Tue 18/07/03 Wed 18/07/04 648
650 0% BUILDINGS EXTERNAL 3 days Wed 18/07/04 Mon 18/07/09
651 0% Repair paint and burglar frames 3 days Wed 18/07/04 Mon 18/07/09 649
652 0% 3 kV DC INDOOR EQUIPMENT 28 days Thu 18/07/12 Mon 18/08/20
653 0% 3 kV DC EQUIPMENT 3 days Thu 18/07/12 Mon 18/07/16
654 0% Wave Filter Room Equipment (Complete) 1 day Thu 18/07/12 Thu 18/07/12 585;586;641
655 0% 3kV DC Switchgear Panels x 4 1 day Fri 18/07/13 Fri 18/07/13 654
Page 3
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
656 0% Busbar Earth Switch x 1 0,25 days Mon 18/07/16 Mon 18/07/16 655
657 0% Possitive Isolator x 1 0,25 days Mon 18/07/16 Mon 18/07/16 656
658 0% Reactor Coil x 1, CW 4 x Small PI's 0,25 days Mon 18/07/16 Mon 18/07/16 657
659 0% Rectifier x 1 0,25 days Mon 18/07/16 Mon 18/07/16 658
660 0% CONTROL & SECONDARY PLANT 25 days Tue 18/07/17 Mon 18/08/20
661 0% PCB Control Panel 1 day Tue 18/07/17 Tue 18/07/17 659
662 0% ACDC DB 1 day Wed 18/07/18 Wed 18/07/18 661
663 0% Isolation Transformer 1 day Thu 18/07/19 Thu 18/07/19 662
664 0% Battery Charger 1 day Fri 18/07/20 Fri 18/07/20 663
665 0% Batteries & Stand 1 day Mon 18/07/23 Mon 18/07/23 664
666 0% DC Earth Leakage Relay 1 day Tue 18/07/24 Tue 18/07/24 665
667 0% Negative Cut Monitor 1 day Wed 18/07/25 Wed 18/07/25
668 0% Install Negative Cut Relay 0,2 days Wed 18/07/25 Wed 18/07/25 666
669 0% Trenching and Exposing Existing Neg Cables to Manhole 0,2 days Wed 18/07/25 Wed 18/07/25 668
670 0% Installing FO on top of Neg Cables 0,2 days Wed 18/07/25 Wed 18/07/25 669
671 0% Backfill Trench 0,2 days Wed 18/07/25 Wed 18/07/25 670
672 0% Terminate FO Cable 0,2 days Wed 18/07/25 Wed 18/07/25 671
673 0% Telecontrol Panel + Transducer 1 day Thu 18/07/26 Thu 18/07/26 672
674 0% Interlocks (Complete) 1 day Fri 18/07/27 Fri 18/07/27 673
675 0% INDOOR BALANCE OF PLANT 16 days Mon 18/07/30 Mon 18/08/20
676 0% Alu Bus Bars Through Wall Bushing to Rectifier to Reactor Coil to Positive0,5
Isolator
days Wed 18/08/15 Wed 18/08/15 659;717;718
677 0% Install DC Indoor Earthing; Equipment and Steel Frames 1 day Mon 18/07/30 Mon 18/07/30 674
678 0% Control Cables; lndoor; Install and Terminate 1 day Tue 18/07/31 Tue 18/07/31 677
679 0% Install 3 kV DC Power Cables ; Pos & Neg, for Complete Rectifier Unit 1 day Thu 18/08/16 Thu 18/08/16 676;678
680 0% Terminate 3 kV DC Power Cables ; Pos & Neg, for Complete Rectifier Unit2 days Fri 18/08/17 Mon 18/08/20 679
681 0% 6.6 kV AC SUBSTATION BUILDING 16 days Fri 18/06/01 Thu 18/06/21
682 0% Remove 2 external doors 1 day Fri 18/06/01 Fri 18/06/01 540
683 0% Roof Repair works 3 days Mon 18/06/04 Wed 18/06/06 682
684 0% Install Roller Doors 2 days Mon 18/06/18 Tue 18/06/19 586;683
685 0% wash and patch walls 1 day Wed 18/06/20 Wed 18/06/20 684
686 0% Repair and paint external fascial 1 day Thu 18/06/21 Thu 18/06/21 685
687 0% 3 kV DC FEEDER CABLE INSTALLATION 8 days Mon 18/05/28 Wed 18/06/06
688 0% Identify Existing cable routes 1 day Mon 18/05/28 Mon 18/05/28 531
689 0% Recover Existing Cables 1 day Tue 18/05/29 Tue 18/05/29 688
690 0% Install Sleeve Pipes 0,5 days Wed 18/05/30 Wed 18/05/30 689
691 0% Excavate Trenches 0,5 days Wed 18/05/30 Wed 18/05/30 690
692 0% Install Power Cables 1 day Thu 18/05/31 Thu 18/05/31 691
693 0% Terminate Cables 2 days Fri 18/06/01 Mon 18/06/04 692
694 0% Backfill & Compact Trenches 1 day Tue 18/06/05 Tue 18/06/05 693
695 0% Cable Testing 1 day Wed 18/06/06 Wed 18/06/06 694
696 0% YARD STEELWORK 8 days Mon 18/07/30 Thu 18/08/09
697 0% Sec SA Bracket on New Transformer 1 day Tue 18/08/07 Tue 18/08/07 707
698 0% CT's x3 Support Steel; Insulated from Plinth 1 day Mon 18/07/30 Tue 18/07/31 571
699 0% PCB x 2 Legs; Support Steel; Insulated from Plinth 1 day Tue 18/07/31 Wed 18/08/01 698
700 0% Disconnector x 1 Support Steel 1 day Wed 18/08/01 Thu 18/08/02 699
Page 4
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
701 0% Prim SA Bracket; on Disconnector 1 day Thu 18/08/02 Fri 18/08/03 700
702 0% Yard Light Masts x 2 1 day Fri 18/08/03 Mon 18/08/06 701
703 0% Aux Transformer Steel Support, Insulated from Plinth 1 day Mon 18/08/06 Tue 18/08/07 702
704 0% Metal stand for water tank 1 day Tue 18/08/07 Wed 18/08/08 703
705 0% Torque and Mark of All Bolts & Nuts on Steel Structures 1 day Wed 18/08/08 Thu 18/08/09 704
706 0% YARD EQUIPMENT 6 days Mon 18/08/06 Mon 18/08/13
707 0% Traction Transformer; Deliver and Install 1 day Mon 18/08/06 Mon 18/08/06 564FS+3 wks
708 0% 88 kV Secondary Surge Arrester x3 0,2 days Thu 18/08/09 Thu 18/08/09 705
709 0% 88 kV CT's x3 0,2 days Thu 18/08/09 Thu 18/08/09 708
710 0% 88 kV PCB x1 0,5 days Thu 18/08/09 Fri 18/08/10 709
711 0% 88 kV Disconnector CW E/S x1 0,4 days Fri 18/08/10 Fri 18/08/10 710
712 0% 88 kV Primary Surge Arresters x3 0,2 days Fri 18/08/10 Fri 18/08/10 711
713 0% AC REF CT CW Box x 1 0,5 days Mon 18/08/13 Mon 18/08/13 712
714 0% Aux Transformer x 1 0,5 days Mon 18/08/13 Mon 18/08/13 713
715 0% YARD BALANCE OF PLANT 8 days Tue 18/08/14 Thu 18/08/23
716 0% Anode Wall Plate x 2 + 2 0,25 days Tue 18/08/14 Tue 18/08/14 714
717 0% Through Wall Bushings x 6 0,25 days Tue 18/08/14 Tue 18/08/14 716
718 0% Alu Bus Bars Trfr LV to Through Wall Bushings & Aux Trfr 1 day Tue 18/08/14 Wed 18/08/15 717
719 0% Clamps and Conductors (HV Side) 1 day Wed 18/08/15 Thu 18/08/16 707;718
720 0% Yard Flood Lights x2 0,25 days Thu 18/08/16 Thu 18/08/16 719
721 0% Cable racking & Supports / Gland Plates 0,25 days Thu 18/08/16 Thu 18/08/16 720
722 0% Connection to Earth Mat of Equipment & Steel Supports & Fence & Building Structure
0,5 days& Gutters Fri 18/08/17 Fri 18/08/17 721
723 0% Connection between Earth Mat and Eskom Earth Mat; at 2 x corners 0,5 days Fri 18/08/17 Fri 18/08/17 722
724 0% Install Earth Spikes for inspection Boxes; ground level; x 2 0,5 days Mon 18/08/20 Mon 18/08/20 723
725 0% Install Earth Inspection Box x 2 0,5 days Mon 18/08/20 Mon 18/08/20 724
726 0% Connection to Earth Leakage of Equipment & Steel Supports 1 day Tue 18/08/21 Tue 18/08/21 725
727 0% Spark Gap and Door Switch Assembly 0,5 days Wed 18/08/22 Wed 18/08/22 726
728 0% Control Cables; Outdoor; Install and Terminate 1 day Wed 18/08/22 Thu 18/08/23 727
729 0% Yard Signs & Labels 0,5 days Thu 18/08/23 Thu 18/08/23 728
730 0% DISPOSAL 4 days Fri 18/08/24 Wed 18/08/29
731 0% Remove old stone Cart Away 2 days Fri 18/08/24 Mon 18/08/27 729
732 0% Remove concrete rubble -Cart Away 2 days Tue 18/08/28 Wed 18/08/29 731
733 0% TEST, COMMISSION & HANDOVER 36 days Wed 18/08/08 Tue 18/09/25
734 0% Roshqott Testing 23 days Wed 18/08/08 Fri 18/09/07
735 0% Traction Transformer; Test and Cold Commission 5 days Wed 18/08/08 Tue 18/08/14 697
736 0% PCB Speed Testing 1 day Fri 18/08/10 Mon 18/08/13 710
737 0% Functional Test on Complete Substation 1 day Thu 18/08/30 Thu 18/08/30 581;582;651;680;686;695;732;735;736
738 0% Eskom Metering Department to Test and Commission 1 day Thu 18/08/30 Thu 18/08/30 737SS
739 0% Eskom To Re-Connect the 88 kV Jumpers 1 day Fri 18/08/31 Fri 18/08/31 738
740 0% Testing By Roshqott's Test Officer (On Transnet Documentation) 2 days Mon 18/09/03 Tue 18/09/04 739
741 0% Transnet Telecontrol Test Officer 1 day Mon 18/09/03 Mon 18/09/03 739
742 0% Roshqott walk around and compile butt list 1 day Wed 18/09/05 Wed 18/09/05 740;741
743 0% Roshqott Clear Snag list Items 2 days Thu 18/09/06 Fri 18/09/07 742
744 0% Handover to Transnet 13 days Mon 18/09/10 Tue 18/09/25
745 0% Pre Inspection by Trsnnet -Project Team walk around and compile butt list 1 day Mon 18/09/10 Mon 18/09/10 743
Page 5
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
746 0% Clear Snag list Items 5 days Tue 18/09/11 Sun 18/09/16 745
747 0% Transnet Testing 1 day Mon 18/09/17 Mon 18/09/17 746
748 0% Energise 88 kV Yard with 3 kV DC Track Switched racked out and Isolated 1 day Tue 18/09/18 Tue 18/09/18 747
749 0% Substation Soak / Energised only prior to Taking Load 4 days Wed 18/09/19 Mon 18/09/24 748
750 0% Substation Ready for Load, pending next Double Line Occupation 0 days Mon 18/09/24 Mon 18/09/24 749
751 0% Double Line Occupation - Transnet Re-Connect 3 kV DC Feeder 1 day Tue 18/09/25 Tue 18/09/25 750
752 0% Cables
Partial Project Hand Over 0 days Tue 18/09/25 Tue 18/09/25 751
753 2% SUB-25 SPRUCEWELL SUBSTATION 87 days Mon 18/06/18 Sun 18/10/14
754 100% SITE ESTABLISHMENT 5 days Mon 18/06/18 Fri 18/06/22
755 100% Site Camps and Facilities 5 days Mon 18/06/18 Fri 18/06/22
756 100% KEY DATE - Transnet Provides Full Access to site 0 days Fri 18/06/22 Fri 18/06/22 755
757 100% Transnet Issue a Permit To Work, Substation Isolated From Eskom 0 days Fri 18/06/22 Fri 18/06/22 756
758 0% REMOVE OLD EQUIPMENT 14 days Mon 18/06/25 Thu 18/07/12
759 0% DECOMMISSION 1,5 days Mon 18/06/25 Tue 18/06/26
760 0% De-Commission all Secondary and control gear - de-energis all Control Panels 1 day Mon 18/06/25 Mon 18/06/25 757
761 0% Disconnect Negative Rail Cable in Neg Manhole, Bond Yard AC Earth,AC Earth0,5 days
Leakage, DCTue
EarthLeakage
18/06/26 andTue
Negative
18/06/26
inside
760Reactor room together
762 0% OUTDOOR EQUIPMENT 2,5 days Tue 18/06/26 Thu 18/06/28
763 0% Disconnect all de-commissioned LV Control Cables 0,5 days Tue 18/06/26 Tue 18/06/26 761
764 0% Dismantle Outdoor yard Equipment and transport to Germiston via Heidelberg Depot
1 day Wed 18/06/27 Wed 18/06/27 763
765 0% Remove 88 kV PCB, store in Roshqott Yard 1 day Thu 18/06/28 Thu 18/06/28 764
766 0% Remove existing Traction Transformer to Germiston via Heielberg & Re-Assemble
2 days Wed 18/06/27 Thu 18/06/28 763
767 0% INDOOR EQUIPMENT 10 days Fri 18/06/29 Thu 18/07/12
768 0% Dismantle rectifier and associated Indoor Equipment and transport to Germiston
2 days
via Heidelberg
FriDepot
18/06/29 Mon 18/07/02 765
769 0% Dismantle Protection and Control Equipment and transport to Germiston via Heidelberg
2 days DepotTue 18/07/03 Wed 18/07/04 768
770 0% Dismantle 3 kV DC Switchgear Equipment and transport to Germiston via Heidelberg
2 days Depot Thu 18/07/05 Fri 18/07/06 769
771 0% Dismantle Wave Filter Equipment and transport to Germiston via Heidelberg Depot
2 days Mon 18/07/09 Tue 18/07/10 770
772 0% Dismantle Old Room Ventilators and associated Equipment and transport to Germiston
2 days via Wed
Heidelberg
18/07/11
Depot Thu 18/07/12 771
773 0% OUTDOOR YARD 50 days Fri 18/06/29 Thu 18/09/06
774 0% YARD CIVIL WORKS 50 days Fri 18/06/29 Thu 18/09/06
775 0% Earthworks 21 days Fri 18/06/29 Fri 18/07/27
776 0% Remove Fences as required for access 2 days Fri 18/06/29 Mon 18/07/02 765;766
777 0% Remove Yard Stone 4 days Tue 18/07/03 Fri 18/07/06 776
778 0% Demolish all existing Plinths and Bases 10 days Mon 18/07/09 Fri 18/07/20 777
779 0% Fill and compact Old Transformer Off-Loading Pit 3 days Mon 18/07/23 Wed 18/07/25 778
780 0% Level and Compact Yard Platform 2 days Thu 18/07/26 Fri 18/07/27 779
781 0% Install AC Yard Earh Mat / Electrode 6 days Mon 18/07/30 Mon 18/08/06
782 0% Trenching 2 days Mon 18/07/30 Tue 18/07/31 780
783 0% Install Earthing Copper Conductor in Trench 0,5 days Wed 18/08/01 Wed 18/08/01 782
784 0% Install Earth Spikes inside open trench x 8 0,5 days Wed 18/08/01 Wed 18/08/01 783
785 0% Brazing of All earth Connections 1 day Thu 18/08/02 Thu 18/08/02 784
786 0% Backfill & Compact Trench 2 days Fri 18/08/03 Mon 18/08/06 785
787 0% Plinths & Foundations 29 days Mon 18/07/30 Thu 18/09/06
788 0% New Transformer Plinth 2 days Mon 18/07/30 Tue 18/07/31 780
789 0% Surface bed to old Transformer Off-Loading Pit 2 days Wed 18/08/01 Thu 18/08/02 788
790 0% CT's x 3 Bases 1 day Tue 18/08/07 Tue 18/08/07 786;789
Page 6
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
791 0% PCB x 2 Bases 1 day Wed 18/08/08 Wed 18/08/08 790
792 0% Disconnector x 2 Bases 1 day Thu 18/08/09 Thu 18/08/09 791
793 0% Yard Light Masts x 2 Bases 1 day Fri 18/08/10 Fri 18/08/10 792
794 0% Water Tank Base x 1 1 day Mon 18/08/13 Mon 18/08/13 793
795 0% Footing for Brickwork to Bunded area 3 days Tue 18/08/14 Thu 18/08/16 794
796 0% Aux Transformer 1 x Base; inside bunded area 0,5 days Fri 18/08/17 Fri 18/08/17 795
797 0% PCB Operator concrete platform 1 day Fri 18/08/17 Mon 18/08/20 796
798 0% Brickwork to pit and Sump 5 days Mon 18/08/20 Mon 18/08/27 797
799 0% Concrete floor slab to sump 1 day Mon 18/08/27 Tue 18/08/28 798
800 0% Diamond mesh fencing 1.2 and 1.8m 2 days Tue 18/08/28 Thu 18/08/30 799
801 0% Apply Herbecide 1 day Thu 18/08/30 Fri 18/08/31 800
802 0% Placing Yard stoning 2 days Fri 18/08/31 Tue 18/09/04 801
803 0% Angle iron frame and gate valve to sump/pit 1 day Tue 18/09/04 Wed 18/09/05 802
804 0% Cover to sump 0,5 days Wed 18/09/05 Wed 18/09/05 803
805 0% Fibreglass grid 0,5 days Thu 18/09/06 Thu 18/09/06 804
806 0% Tank and pipe connection 0,5 days Thu 18/09/06 Thu 18/09/06 805
807 0% Perimeter Fencing (Palisade) 20 days Tue 18/08/07 Mon 18/09/03 786
808 0% 3 kV DC SUBSTATION BUILDING 34 days Mon 18/06/25 Thu 18/08/09
809 0% Roofs and Doors 10 days Tue 18/07/03 Mon 18/07/16
810 0% Roof Replacement 10 days Tue 18/07/03 Mon 18/07/16 768
811 0% Roller Doors 10 days Tue 18/07/03 Mon 18/07/16 768
812 0% RECTIFIER & REACTOR ROOM 16 days Mon 18/06/25 Mon 18/07/16
813 0% Remove external door 0,25 days Mon 18/06/25 Mon 18/06/25 757
814 0% Cut out brickwork for 2 fans 0,5 days Mon 18/06/25 Mon 18/06/25 813
815 0% Remove middle pane glass bricks 0,5 days Mon 18/06/25 Tue 18/06/26 814
816 0% Brick up and plaster removed glass bricks and louvre ventilators 0,5 days Tue 18/06/26 Tue 18/06/26 815
817 0% Replace damaged glass bricks in the 2 side panes 0,5 days Tue 18/06/26 Wed 18/06/27 816
818 0% Fix external plaster frames and paint 0,5 days Wed 18/06/27 Wed 18/06/27 817
819 0% wash and patch walls 0,5 days Wed 18/06/27 Thu 18/06/28 818
820 0% patch around and paint external door 0,5 days Thu 18/06/28 Thu 18/06/28 819
821 0% repair and varnish 2 internal doors 0,5 days Thu 18/06/28 Fri 18/06/29 820
822 0% built new cable trench 2 days Fri 18/06/29 Tue 18/07/03 821
823 0% angle framing for new trench 1 day Tue 18/07/03 Wed 18/07/04 822
824 0% paint walls 0,5 days Fri 18/07/13 Fri 18/07/13 772;823
825 0% paint floor 0,5 days Fri 18/07/13 Fri 18/07/13 824
826 0% paint vastrap covers old and new 0,5 days Mon 18/07/16 Mon 18/07/16 825
827 0% repair and paint mesh partitions 0,5 days Mon 18/07/16 Mon 18/07/16 826
828 0% DC SWITCHGEAR ROOM 6,25 days Tue 18/07/17 Wed 18/07/25
829 0% Remove 2 external doors 0,25 days Tue 18/07/17 Tue 18/07/17 827
830 0% wash and patch walls incl. small room 0,5 days Tue 18/07/17 Tue 18/07/17 829
831 0% patch around and paint 2 external door 0,5 days Tue 18/07/17 Wed 18/07/18 830
832 0% repair and varnish 2 internal door 0,5 days Wed 18/07/18 Wed 18/07/18 831
833 0% paint walls incl. small room 0,5 days Wed 18/07/18 Thu 18/07/19 832
834 0% paint floor icl. Small room 0,5 days Thu 18/07/19 Thu 18/07/19 833
835 0% paint vastrap covers 0,5 days Thu 18/07/19 Fri 18/07/20 834
Page 7
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
836 0% Build in new 5 No 110 sleeves 1 day Fri 18/07/20 Mon 18/07/23 835
837 0% Break to enlarge cable trenche 1 day Mon 18/07/23 Tue 18/07/24 836
838 0% Angle framing to cable trench 0,5 days Tue 18/07/24 Tue 18/07/24 837
839 0% Screed floor 0,5 days Tue 18/07/24 Wed 18/07/25 838
840 0% WAVE FILTER ROOM 3 days Wed 18/07/25 Mon 18/07/30
841 0% wash and patch walls 1 day Wed 18/07/25 Thu 18/07/26 839
842 0% repair and paint external door 0,5 days Thu 18/07/26 Thu 18/07/26 841
843 0% repair and varnish wood structure 0,5 days Thu 18/07/26 Fri 18/07/27 842
844 0% paint walls 0,5 days Fri 18/07/27 Fri 18/07/27 843
845 0% paint floor 0,5 days Fri 18/07/27 Mon 18/07/30 844
846 0% BATTERY ROOM 3 days Mon 18/07/30 Thu 18/08/02
847 0% Cut out brickwork for fan and louvre 0,5 days Mon 18/07/30 Mon 18/07/30 845
848 0% Remove and replace sink and piping 0,5 days Mon 18/07/30 Tue 18/07/31 847
849 0% wash and patch walls 0,5 days Tue 18/07/31 Tue 18/07/31 848
850 0% repair and paint internal door 0,5 days Tue 18/07/31 Wed 18/08/01 849
851 0% paint walls 0,5 days Wed 18/08/01 Wed 18/08/01 850
852 0% paint floor 0,5 days Wed 18/08/01 Thu 18/08/02 851
853 0% REGENERATION ROOM 3,75 days Thu 18/08/02 Tue 18/08/07
854 0% Remove external door 0,25 days Thu 18/08/02 Thu 18/08/02 852
855 0% wash and patch walls 0,5 days Thu 18/08/02 Thu 18/08/02 854
856 0% patch around and paint external door 0,5 days Fri 18/08/03 Fri 18/08/03 855
857 0% repair and varnish internal door 0,5 days Fri 18/08/03 Fri 18/08/03 856
858 0% repair and paint mesh partitions 0,5 days Mon 18/08/06 Mon 18/08/06 857
859 0% paint walls 0,5 days Mon 18/08/06 Mon 18/08/06 858
860 0% paint floor 0,5 days Tue 18/08/07 Tue 18/08/07 859
861 0% paint vastrap covers 0,5 days Tue 18/08/07 Tue 18/08/07 860
862 0% ESKOM METRING ROOM 2 days Wed 18/08/08 Thu 18/08/09
863 0% wash and patch walls 0,5 days Wed 18/08/08 Wed 18/08/08 861
864 0% repair and paint external door 0,5 days Wed 18/08/08 Wed 18/08/08 863
865 0% paint walls 0,5 days Thu 18/08/09 Thu 18/08/09 864
866 0% paint floor 0,5 days Thu 18/08/09 Thu 18/08/09 865
867 0% Building Electrics, lighting and Ventilation 11,5 days Tue 18/07/17 Thu 18/08/02
868 0% AC & DC Building DB 1 day Tue 18/07/17 Wed 18/07/18 830
869 0% Conduit 2 days Wed 18/07/18 Fri 18/07/20 868
870 0% Plugs & Switches & Photo Cell 1 day Fri 18/07/20 Mon 18/07/23 869
871 0% Light Fittings 3 days Mon 18/07/23 Thu 18/07/26 870
872 0% Fans & Louvres & Temp Control 2 days Thu 18/07/26 Mon 18/07/30 871
873 0% Wiring 2 days Mon 18/07/30 Wed 18/08/01 872
874 0% Obtain a COC Certificate 0,5 days Wed 18/08/01 Thu 18/08/02 873
875 0% BUILDINGS EXTERNAL 3 days Thu 18/08/02 Tue 18/08/07
876 0% Repair paint and burglar frames 3 days Thu 18/08/02 Tue 18/08/07 874
877 0% 3 kV DC INDOOR EQUIPMENT 21 days Fri 18/08/10 Fri 18/09/07
878 0% 3 kV DC EQUIPMENT 3 days Fri 18/08/10 Tue 18/08/14
879 0% Wave Filter Room Equipment (Complete) 1 day Fri 18/08/10 Fri 18/08/10 810;811;866
880 0% 3kV DC Switchgear Panels x 4 1 day Mon 18/08/13 Mon 18/08/13 879
Page 8
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
881 0% Busbar Earth Switch x 1 0,25 days Tue 18/08/14 Tue 18/08/14 880
882 0% Possitive Isolator x 1 0,25 days Tue 18/08/14 Tue 18/08/14 881
883 0% Reactor Coil x 1, CW 4 x Small PI's 0,25 days Tue 18/08/14 Tue 18/08/14 882
884 0% Rectifier x 1 0,25 days Tue 18/08/14 Tue 18/08/14 883
885 0% CONTROL & SECONDARY PLANT 18 days Wed 18/08/15 Fri 18/09/07
886 0% PCB Control Panel 1 day Wed 18/08/15 Wed 18/08/15 884
887 0% ACDC DB 1 day Thu 18/08/16 Thu 18/08/16 886
888 0% Isolation Transformer 1 day Fri 18/08/17 Fri 18/08/17 887
889 0% Battery Charger 1 day Mon 18/08/20 Mon 18/08/20 888
890 0% Batteries & Stand 1 day Tue 18/08/21 Tue 18/08/21 889
891 0% DC Earth Leakage Relay 1 day Wed 18/08/22 Wed 18/08/22 890
892 0% Negative Cut Monitor 1 day Thu 18/08/23 Thu 18/08/23
893 0% Install Negative Cut Relay 0,2 days Thu 18/08/23 Thu 18/08/23 891
894 0% Trenching and Exposing Existing Neg Cables to Manhole 0,2 days Thu 18/08/23 Thu 18/08/23 893
895 0% Installing FO on top of Neg Cables 0,2 days Thu 18/08/23 Thu 18/08/23 894
896 0% Backfill Trench 0,2 days Thu 18/08/23 Thu 18/08/23 895
897 0% Terminate FO Cable 0,2 days Thu 18/08/23 Thu 18/08/23 896
898 0% Telecontrol Panel + Transducer 1 day Fri 18/08/24 Fri 18/08/24 897
899 0% Interlocks (Complete) 1 day Mon 18/08/27 Mon 18/08/27 898
900 0% INDOOR BALANCE OF PLANT 9 days Tue 18/08/28 Fri 18/09/07
901 0% Alu Bus Bars Through Wall Bushing to Rectifier to Reactor Coil to Positive0,5
Isolator
days Tue 18/09/04 Tue 18/09/04 884;942;943
902 0% Install DC Indoor Earthing; Equipment and Steel Frames 1 day Tue 18/08/28 Tue 18/08/28 899
903 0% Control Cables; lndoor; Install and Terminate 1 day Wed 18/08/29 Wed 18/08/29 902
904 0% Install 3 kV DC Power Cables ; Pos & Neg, for Complete Rectifier Unit 1 day Wed 18/09/05 Wed 18/09/05 901;903
905 0% Terminate 3 kV DC Power Cables ; Pos & Neg, for Complete Rectifier Unit2 days Thu 18/09/06 Fri 18/09/07 904
906 0% 6.6 kV AC SUBSTATION BUILDING 16 days Fri 18/06/29 Fri 18/07/20
907 0% Remove 2 external doors 1 day Fri 18/06/29 Fri 18/06/29 766
908 0% Roof Repair works 3 days Mon 18/07/02 Wed 18/07/04 907
909 0% Install Roller Doors 2 days Tue 18/07/17 Wed 18/07/18 811;908
910 0% wash and patch walls 1 day Thu 18/07/19 Thu 18/07/19 909
911 0% Repair and paint external fascial 1 day Fri 18/07/20 Fri 18/07/20 910
912 0% 3 kV DC FEEDER CABLE INSTALLATION 8 days Mon 18/06/25 Wed 18/07/04
913 0% Identify Existing cable routes 1 day Mon 18/06/25 Mon 18/06/25 757
914 0% Recover Existing Cables 1 day Tue 18/06/26 Tue 18/06/26 913
915 0% Install Sleeve Pipes 0,5 days Wed 18/06/27 Wed 18/06/27 914
916 0% Excavate Trenches 0,5 days Wed 18/06/27 Wed 18/06/27 915
917 0% Install Power Cables 1 day Thu 18/06/28 Thu 18/06/28 916
918 0% Terminate Cables 2 days Fri 18/06/29 Mon 18/07/02 917
919 0% Backfill & Compact Trenches 1 day Tue 18/07/03 Tue 18/07/03 918
920 0% Cable Testing 1 day Wed 18/07/04 Wed 18/07/04 919
921 0% YARD STEELWORK 8 days Fri 18/08/17 Wed 18/08/29
922 0% Sec SA Bracket on New Transformer 1 day Mon 18/08/27 Mon 18/08/27 932
923 0% CT's x3 Support Steel; Insulated from Plinth 1 day Fri 18/08/17 Mon 18/08/20 796
924 0% PCB x 2 Legs; Support Steel; Insulated from Plinth 1 day Mon 18/08/20 Tue 18/08/21 923
925 0% Disconnector x 1 Support Steel 1 day Tue 18/08/21 Wed 18/08/22 924
Page 9
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
926 0% Prim SA Bracket; on Disconnector 1 day Wed 18/08/22 Thu 18/08/23 925
927 0% Yard Light Masts x 2 1 day Thu 18/08/23 Fri 18/08/24 926
928 0% Aux Transformer Steel Support, Insulated from Plinth 1 day Fri 18/08/24 Mon 18/08/27 927
929 0% Metal stand for water tank 1 day Mon 18/08/27 Tue 18/08/28 928
930 0% Torque and Mark of All Bolts & Nuts on Steel Structures 1 day Tue 18/08/28 Wed 18/08/29 929
931 0% YARD EQUIPMENT 6 days Fri 18/08/24 Fri 18/08/31
932 0% Traction Transformer; Deliver and Install 1 day Fri 18/08/24 Fri 18/08/24 789FS+3 wks
933 0% 88 kV Secondary Surge Arrester x3 0,2 days Wed 18/08/29 Wed 18/08/29 930
934 0% 88 kV CT's x3 0,2 days Wed 18/08/29 Wed 18/08/29 933
935 0% 88 kV PCB x1 0,5 days Wed 18/08/29 Thu 18/08/30 934
936 0% 88 kV Disconnector CW E/S x1 0,4 days Thu 18/08/30 Thu 18/08/30 935
937 0% 88 kV Primary Surge Arresters x3 0,2 days Thu 18/08/30 Thu 18/08/30 936
938 0% AC REF CT CW Box x 1 0,5 days Fri 18/08/31 Fri 18/08/31 937
939 0% Aux Transformer x 1 0,5 days Fri 18/08/31 Fri 18/08/31 938
940 0% YARD BALANCE OF PLANT 8 days Mon 18/09/03 Wed 18/09/12
941 0% Anode Wall Plate x 2 + 2 0,25 days Mon 18/09/03 Mon 18/09/03 939
942 0% Through Wall Bushings x 6 0,25 days Mon 18/09/03 Mon 18/09/03 941
943 0% Alu Bus Bars Trfr LV to Through Wall Bushings & Aux Trfr 1 day Mon 18/09/03 Tue 18/09/04 942
944 0% Clamps and Conductors (HV Side) 1 day Tue 18/09/04 Wed 18/09/05 932;943
945 0% Yard Flood Lights x2 0,25 days Wed 18/09/05 Wed 18/09/05 944
946 0% Cable racking & Supports / Gland Plates 0,25 days Wed 18/09/05 Wed 18/09/05 945
947 0% Connection to Earth Mat of Equipment & Steel Supports & Fence & Building Structure
0,5 days& GuttersThu 18/09/06 Thu 18/09/06 946
948 0% Connection between Earth Mat and Eskom Earth Mat; at 2 x corners 0,5 days Thu 18/09/06 Thu 18/09/06 947
949 0% Install Earth Spikes for inspection Boxes; ground level; x 2 0,5 days Fri 18/09/07 Fri 18/09/07 948
950 0% Install Earth Inspection Box x 2 0,5 days Fri 18/09/07 Fri 18/09/07 949
951 0% Connection to Earth Leakage of Equipment & Steel Supports 1 day Mon 18/09/10 Mon 18/09/10 950
952 0% Spark Gap and Door Switch Assembly 0,5 days Tue 18/09/11 Tue 18/09/11 951
953 0% Control Cables; Outdoor; Install and Terminate 1 day Tue 18/09/11 Wed 18/09/12 952
954 0% Yard Signs & Labels 0,5 days Wed 18/09/12 Wed 18/09/12 953
955 0% DISPOSAL 4 days Thu 18/09/13 Mon 18/09/17
956 0% Remove old stone Cart Away 2 days Thu 18/09/13 Fri 18/09/14 954
957 0% Remove concrete rubble -Cart Away 2 days Sun 18/09/16 Mon 18/09/17 956
958 0% TEST, COMMISSION & HANDOVER 36 days Tue 18/08/28 Sun 18/10/14
959 0% Roshqott Testing 23 days Tue 18/08/28 Wed 18/09/26
960 0% Traction Transformer; Test and Cold Commission 5 days Tue 18/08/28 Mon 18/09/03 922
961 0% PCB Speed Testing 1 day Thu 18/08/30 Fri 18/08/31 935
962 0% Functional Test on Complete Substation 1 day Tue 18/09/18 Tue 18/09/18 806;807;876;905;911;920;957;960;961
963 0% Eskom Metering Department to Test and Commission 1 day Tue 18/09/18 Tue 18/09/18 962SS
964 0% Eskom To Re-Connect the 88 kV Jumpers 1 day Wed 18/09/19 Wed 18/09/19 963
965 0% Testing By Roshqott's Test Officer (On Transnet Documentation) 2 days Thu 18/09/20 Fri 18/09/21 964
966 0% Transnet Telecontrol Test Officer 1 day Thu 18/09/20 Thu 18/09/20 964
967 0% Roshqott walk around and compile butt list 1 day Mon 18/09/24 Mon 18/09/24 965;966
968 0% Roshqott Clear Snag list Items 2 days Tue 18/09/25 Wed 18/09/26 967
969 0% Handover to Transnet 13 days Thu 18/09/27 Sun 18/10/14
970 0% Pre Inspection by Trsnnet -Project Team walk around and compile butt list 1 day Thu 18/09/27 Thu 18/09/27 968
Page 10
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID % Task Name Duration Start Finish Predecessors
Complete
'15 Jan 18 '15 Jun 07 '15 Oct 25 '16 Mar 13 '16 Jul 31
971 0% Clear Snag list Items 5 days Fri 18/09/28 Thu 18/10/04 970
972 0% Transnet Testing 1 day Fri 18/10/05 Fri 18/10/05 971
973 0% Energise 88 kV Yard with 3 kV DC Track Switched racked out and Isolated 1 day Mon 18/10/08 Mon 18/10/08 972
974 0% Substation Soak / Energised only prior to Taking Load 4 days Tue 18/10/09 Fri 18/10/12 973
975 0% Substation Ready for Load, pending next Double Line Occupation 0 days Fri 18/10/12 Fri 18/10/12 974
976 0% Double Line Occupation - Transnet Re-Connect 3 kV DC Feeder 1 day Sun 18/10/14 Sun 18/10/14 975
977 0% Cables
Partial Project Hand Over 0 days Sun 18/10/14 Sun 18/10/14 976
978 0% SUB-24 SPRYSTRUS SUBSTATION 93 days Wed 18/09/26 Tue 19/02/26 527
1203 0% SUB-27 TEAKWORTH SUBSTATION 93 days Mon 18/10/15 Sun 19/03/17 753
Page 11
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
1 82%
2 100%
77 100%
80 100%
83 100%
308 100%
527 15%
528 100%
529 100% 05/21 05/25
530 100% 05/25
531 100% 05/25
532 100%
533 100%
534 100% 05/28 05/28
535 100% 05/29 05/29
536 100%
537 100% 05/29 05/29
538 100% 05/30 05/30
539 100% 05/31 05/31
540 100% 05/30 05/31
541 100%
542 100% 06/01 06/04
543 100% 06/05 06/06
544 100% 06/07 06/08
545 100% 06/11 06/12
546 100% 06/13 06/14
547 21%
548 21%
549 62%
550 100% 06/01 06/04
551 100% 06/05 06/08
552 100% 06/11 06/21
553 25% 06/22 06/28
554 0% 06/29 07/05
555 0% 07/06 07/09
556 0%
557 0% 07/10 07/11
558 0% 07/12 07/12
559 0% 07/12 07/12
560 0% 07/13 07/13
561 0% 07/16 07/17
562 0%
563 0% 07/10 07/11
564 0% 07/12 07/13
565 0% 07/18 07/18
Page 12
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
566 0% 07/19 07/19
567 0% 07/20 07/20
568 0% 07/23 07/23
569 0% 07/24 07/24
570 0% 07/25 07/27
571 0% 07/30 07/30
572 0% 07/30 07/31
573 0% 07/31 08/07
574 0% 08/07 08/08
575 0% 08/08 08/10
576 0% 08/10 08/13
577 0% 08/13 08/15
578 0% 08/15 08/16
579 0% 08/16 08/16
580 0% 08/17 08/17
581 0% 08/17 08/17
582 0% 07/18 08/14
583 0%
584 0%
585 0% 06/05 06/17
586 0% 06/05 06/17
587 0%
588 0% 05/28 05/28
589 0% 05/28 05/28
590 0% 05/28 05/29
591 0% 05/29 05/29
592 0% 05/29 05/30
593 0% 05/30 05/30
594 0% 05/30 05/31
595 0% 05/31 05/31
596 0% 05/31 06/01
597 0% 06/01 06/05
598 0% 06/05 06/06
599 0% 06/15 06/15
600 0% 06/15 06/15
601 0% 06/17 06/17
602 0% 06/17 06/17
603 0%
604 0% 06/18 06/18
605 0% 06/18 06/18
606 0% 06/18 06/19
607 0% 06/19 06/19
608 0% 06/19 06/20
609 0% 06/20 06/20
610 0% 06/20 06/21
Page 13
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
611 0% 06/21 06/22
612 0% 06/22 06/25
613 0% 06/25 06/25
614 0% 06/25 06/26
615 0%
616 0% 06/26 06/27
617 0% 06/27 06/27
618 0% 06/27 06/28
619 0% 06/28 06/28
620 0% 06/28 06/29
621 0%
622 0% 06/29 06/29
623 0% 06/29 07/02
624 0% 07/02 07/02
625 0% 07/02 07/03
626 0% 07/03 07/03
627 0% 07/03 07/04
628 0%
629 0% 07/04 07/04
630 0% 07/04 07/04
631 0% 07/05 07/05
632 0% 07/05 07/05
633 0% 07/06 07/06
634 0% 07/06 07/06
635 0% 07/09 07/09
636 0% 07/09 07/09
637 0%
638 0% 07/10 07/10
639 0% 07/10 07/10
640 0% 07/11 07/11
641 0% 07/11 07/11
642 0%
643 0% 06/18 06/19
644 0% 06/19 06/21
645 0% 06/21 06/22
646 0% 06/22 06/27
647 0% 06/27 06/29
648 0% 06/29 07/03
649 0% 07/03 07/04
650 0%
651 0% 07/04 07/09
652 0%
653 0%
654 0% 07/12 07/12
655 0% 07/13 07/13
Page 14
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
656 0% 07/16 07/16
657 0% 07/16 07/16
658 0% 07/16 07/16
659 0% 07/16 07/16
660 0%
661 0% 07/17 07/17
662 0% 07/18 07/18
663 0% 07/19 07/19
664 0% 07/20 07/20
665 0% 07/23 07/23
666 0% 07/24 07/24
667 0%
668 0% 07/25 07/25
669 0% 07/25 07/25
670 0% 07/25 07/25
671 0% 07/25 07/25
672 0% 07/25 07/25
673 0% 07/26 07/26
674 0% 07/27 07/27
675 0%
676 0% 08/15 08/15
677 0% 07/30 07/30
678 0% 07/31 07/31
679 0% 08/16 08/16
680 0% 08/17 08/20
681 0%
682 0% 06/01 06/01
683 0% 06/04 06/06
684 0% 06/18 06/19
685 0% 06/20 06/20
686 0% 06/21 06/21
687 0%
688 0% 05/28 05/28
689 0% 05/29 05/29
690 0% 05/30 05/30
691 0% 05/30 05/30
692 0% 05/31 05/31
693 0% 06/01 06/04
694 0% 06/05 06/05
695 0% 06/06 06/06
696 0%
697 0% 08/07 08/07
698 0% 07/30 07/31
699 0% 07/31 08/01
700 0% 08/01 08/02
Page 15
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
701 0% 08/02 08/03
702 0% 08/03 08/06
703 0% 08/06 08/07
704 0% 08/07 08/08
705 0% 08/08 08/09
706 0%
707 0% 08/06 08/06
708 0% 08/09 08/09
709 0% 08/09 08/09
710 0% 08/09 08/10
711 0% 08/10 08/10
712 0% 08/10 08/10
713 0% 08/13 08/13
714 0% 08/13 08/13
715 0%
716 0% 08/14 08/14
717 0% 08/14 08/14
718 0% 08/14 08/15
719 0% 08/15 08/16
720 0% 08/16 08/16
721 0% 08/16 08/16
722 0% 08/17 08/17
723 0% 08/17 08/17
724 0% 08/20 08/20
725 0% 08/20 08/20
726 0% 08/21 08/21
727 0% 08/22 08/22
728 0% 08/22 08/23
729 0% 08/23 08/23
730 0%
731 0% 08/24 08/27
732 0% 08/28 08/29
733 0%
734 0%
735 0% 08/08 08/14
736 0% 08/10 08/13
737 0% 08/30 08/30
738 0% 08/30 08/30
739 0% 08/31 08/31
740 0% 09/03 09/04
741 0% 09/03 09/03
742 0% 09/05 09/05
743 0% 09/06 09/07
744 0%
745 0% 09/10 09/10
Page 16
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
746 0% 09/11 09/16
747 0% 09/17 09/17
748 0% 09/18 09/18
749 0% 09/19 09/24
750 0% 09/24
751 0% 09/25 09/25
752 0% 09/25
753 2%
754 100%
755 100% 06/18 06/22
756 100% 06/22
757 100% 06/22
758 0%
759 0%
760 0% 06/25 06/25
761 0% 06/26 06/26
762 0%
763 0% 06/26 06/26
764 0% 06/27 06/27
765 0% 06/28 06/28
766 0% 06/27 06/28
767 0%
768 0% 06/29 07/02
769 0% 07/03 07/04
770 0% 07/05 07/06
771 0% 07/09 07/10
772 0% 07/11 07/12
773 0%
774 0%
775 0%
776 0% 06/29 07/02
777 0% 07/03 07/06
778 0% 07/09 07/20
779 0% 07/23 07/25
780 0% 07/26 07/27
781 0%
782 0% 07/30 07/31
783 0% 08/01 08/01
784 0% 08/01 08/01
785 0% 08/02 08/02
786 0% 08/03 08/06
787 0%
788 0% 07/30 07/31
789 0% 08/01 08/02
790 0% 08/07 08/07
Page 17
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
791 0% 08/08 08/08
792 0% 08/09 08/09
793 0% 08/10 08/10
794 0% 08/13 08/13
795 0% 08/14 08/16
796 0% 08/17 08/17
797 0% 08/17 08/20
798 0% 08/20 08/27
799 0% 08/27 08/28
800 0% 08/28 08/30
801 0% 08/30 08/31
802 0% 08/31 09/04
803 0% 09/04 09/05
804 0% 09/05 09/05
805 0% 09/06 09/06
806 0% 09/06 09/06
807 0% 08/07 09/03
808 0%
809 0%
810 0% 07/03 07/16
811 0% 07/03 07/16
812 0%
813 0% 06/25 06/25
814 0% 06/25 06/25
815 0% 06/25 06/26
816 0% 06/26 06/26
817 0% 06/26 06/27
818 0% 06/27 06/27
819 0% 06/27 06/28
820 0% 06/28 06/28
821 0% 06/28 06/29
822 0% 06/29 07/03
823 0% 07/03 07/04
824 0% 07/13 07/13
825 0% 07/13 07/13
826 0% 07/16 07/16
827 0% 07/16 07/16
828 0%
829 0% 07/17 07/17
830 0% 07/17 07/17
831 0% 07/17 07/18
832 0% 07/18 07/18
833 0% 07/18 07/19
834 0% 07/19 07/19
835 0% 07/19 07/20
Page 18
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
836 0% 07/20 07/23
837 0% 07/23 07/24
838 0% 07/24 07/24
839 0% 07/24 07/25
840 0%
841 0% 07/25 07/26
842 0% 07/26 07/26
843 0% 07/26 07/27
844 0% 07/27 07/27
845 0% 07/27 07/30
846 0%
847 0% 07/30 07/30
848 0% 07/30 07/31
849 0% 07/31 07/31
850 0% 07/31 08/01
851 0% 08/01 08/01
852 0% 08/01 08/02
853 0%
854 0% 08/02 08/02
855 0% 08/02 08/02
856 0% 08/03 08/03
857 0% 08/03 08/03
858 0% 08/06 08/06
859 0% 08/06 08/06
860 0% 08/07 08/07
861 0% 08/07 08/07
862 0%
863 0% 08/08 08/08
864 0% 08/08 08/08
865 0% 08/09 08/09
866 0% 08/09 08/09
867 0%
868 0% 07/17 07/18
869 0% 07/18 07/20
870 0% 07/20 07/23
871 0% 07/23 07/26
872 0% 07/26 07/30
873 0% 07/30 08/01
874 0% 08/01 08/02
875 0%
876 0% 08/02 08/07
877 0%
878 0%
879 0% 08/10 08/10
880 0% 08/13 08/13
Page 19
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
881 0% 08/14 08/14
882 0% 08/14 08/14
883 0% 08/14 08/14
884 0% 08/14 08/14
885 0%
886 0% 08/15 08/15
887 0% 08/16 08/16
888 0% 08/17 08/17
889 0% 08/20 08/20
890 0% 08/21 08/21
891 0% 08/22 08/22
892 0%
893 0% 08/23 08/23
894 0% 08/23 08/23
895 0% 08/23 08/23
896 0% 08/23 08/23
897 0% 08/23 08/23
898 0% 08/24 08/24
899 0% 08/27 08/27
900 0%
901 0% 09/04 09/04
902 0% 08/28 08/28
903 0% 08/29 08/29
904 0% 09/05 09/05
905 0% 09/06 09/07
906 0%
907 0% 06/29 06/29
908 0% 07/02 07/04
909 0% 07/17 07/18
910 0% 07/19 07/19
911 0% 07/20 07/20
912 0%
913 0% 06/25 06/25
914 0% 06/26 06/26
915 0% 06/27 06/27
916 0% 06/27 06/27
917 0% 06/28 06/28
918 0% 06/29 07/02
919 0% 07/03 07/03
920 0% 07/04 07/04
921 0%
922 0% 08/27 08/27
923 0% 08/17 08/20
924 0% 08/20 08/21
925 0% 08/21 08/22
Page 20
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
926 0% 08/22 08/23
927 0% 08/23 08/24
928 0% 08/24 08/27
929 0% 08/27 08/28
930 0% 08/28 08/29
931 0%
932 0% 08/24 08/24
933 0% 08/29 08/29
934 0% 08/29 08/29
935 0% 08/29 08/30
936 0% 08/30 08/30
937 0% 08/30 08/30
938 0% 08/31 08/31
939 0% 08/31 08/31
940 0%
941 0% 09/03 09/03
942 0% 09/03 09/03
943 0% 09/03 09/04
944 0% 09/04 09/05
945 0% 09/05 09/05
946 0% 09/05 09/05
947 0% 09/06 09/06
948 0% 09/06 09/06
949 0% 09/07 09/07
950 0% 09/07 09/07
951 0% 09/10 09/10
952 0% 09/11 09/11
953 0% 09/11 09/12
954 0% 09/12 09/12
955 0%
956 0% 09/13 09/14
957 0% 09/16 09/17
958 0%
959 0%
960 0% 08/28 09/03
961 0% 08/30 08/31
962 0% 09/18 09/18
963 0% 09/18 09/18
964 0% 09/19 09/19
965 0% 09/20 09/21
966 0% 09/20 09/20
967 0% 09/24 09/24
968 0% 09/25 09/26
969 0%
970 0% 09/27 09/27
Page 21
E0532- Transnet Rrooikop to Newcastle Project Schedule - Rev19 - 25-06-2018
ID %
Complete
'16 Jul 31 '16 Dec 18 '17 May 07 '17 Sep 24 '18 Feb 11 '18 Jul 01 '18 Nov 18 '19 Apr 07 '19 Aug 25 '20 Jan 12 '20 May 31 '20 Oct 18 '21 Mar 07 '21 Jul 25 '21 Dec 12 '22 May 01
971 0% 09/28 10/04
972 0% 10/05 10/05
973 0% 10/08 10/08
974 0% 10/09 10/12
975 0% 10/12
976 0% 10/14 10/14
977 0% 10/14
978 0%
1203 0%
Page 22