Beruflich Dokumente
Kultur Dokumente
m
t.co
spo
log
M V Pande
M.Tech.(HPE),DBM
Dy.Director, NPTI(WR)
z.b
NAGPUR.
h are
rees
allf
The steam turbine offers many advantages over other prime movers, both thermodynamically and
mechanically. From a thermodynamic point of view, the main advantage of the steam turbine over, say, a
reciprocating steam engine, is that in the turbine the steam can be expanded down to a lower back-
pressure, thereby making available a greater heat drop. In addition, the internal efficiency of the turbine is
high, so it is able to convert a high proportion of this relatively large heat drop into mechanical work.
From a mechanical point of view, the turbine is ideal, because the propelling force is applied
directly to the rotating elements of the machine and has not, as in the reciprocating engine, to be
transmitted through a system of connecting links, which are necessary to transform a reciprocating motion
into a rotary motion. Hence, since the steam turbine possesses rotary motion only, if the manufacture is
good and the machine is correctly designed, it ought to be free from out-of-balance forces.
If the load on a turbine is kept constant, the torque developed at the coupling remains constant. A
generator at a steady load offers a constant resisting torque. Therefore, a turbine is suitable for driving a
generator, particularly as they are both high-speed machines.
A further advantage of the turbine is that the exhaust steam is not contaminated with oil vapour
and can be condensed and fed back to the boilers without passing through filters. It also means that there
is considerable saving in lubricating oil when compared with a reciprocating steam engine of equal power.
Yet the steam turbine is not without disadvantages. It is non-reversible. Unlike the IC engine, it is
not a complete power plant, but must be associated with a steam generator. Steam rates are high unless
in condensing operation. The thermal (steam) power plant therefore was a duel phase cycle, i.e. vapour
and liquid. It is a closed cycle to enable the working fluid (water) to be used again and again. The cycle
used is "Rankine Cycle" modified to include superheating of steam, regenerative feed water heating and
reheating of steam.
In 1629, Giovanni Bianca (Italy) made drawings of simple impulse turbine, later developed by the
French Engineers, De Lavel and Rateau and others.
However, Parsons was the first to realize that successful turbine must rotate at very high speeds,
even in those early days. It was understood that a jet of steam could rotate a wheel with blades on its
circumference or that it could develop power when escaping tangentially from an orifice or nozzle in a
wheel by its own reaction. Either way, the problem confronting Parsons, was that of constructing a
practical turbine, using very high jet velocities of the order of 750 m/s of even L.P. steam exhausting to
atmosphere; or double that velocity of H.P. Steam exhausts via jets into a partial vacuum.
The utilization of these high velocities calls for the moving blades to travel at half these velocities,
i.e. velocities of the order of 375 m/s to 750 m/s. High linear speeds mean high rotational speeds and the
consequent centrifugal force of a severe nature. Blade speeds were reduced by sub-dividing the whole
expansion of steam into a number of stages so that moderate velocities have to be dealt with and this
forms the basis of the modern steam turbine as well. On this reaction principle, Parsons first commercial
turbine (1800 rpm) only generated 10 KW power in the year 1884.
Other inventors, i.e. C.G. Curtis (U.S.A.) and Prof. A. Rateau (France) preferred to use the
expansion of steam at each stage, by virtue of its velocity only, in fixed nozzles. Machines of this type,
where the steam drives the moving blading of each stage by virtue of its velocity only, are called impulse
turbines. Impulse turbines of fairly large size have been developed over the years, but it is recognized
that the reaction principle of Parsons Scores over the impulse, in having a higher efficiency.
Consequently, very large sets, which are nominally termed impulse, embody a certain amount of reaction.
Side-by-side with the introduction of the high-speed turbines, Parsons went on to invent the drum type of
generator stator (a.c.), to match the turbine.
Further contributions to the field of turbine power by Parsons were the steam jet air ejector and
regenerative feed heating, which was however first proposed by James W ier.
th
Shortly after the turn of the 19 Century, steam turbines began to replace reciprocating steam
engines in power plants. Rapid development ensued and by 1909 units of 12 MW capacity were installed
in Chicago. The turbine performance and efficiency exceeded those of the reciprocating engine and
allowed the use of superheated steam on large scale. This led to the use of cast steel rather than cast
iron in turbines. Capacity rose steadily. A 208 MW unit was installed in New York in 1929. The rise was
helped in 1937 by the use of hydrogen-cooled generator. By the late 1950s capacities reached 450 MW .
In the post-world war-II era, capacities rose beyond 500 MW .
b) Curved Blades
The blades are attached to the turbine rotor. The rapidly moving particles of steam issuing from the
nozzle enter the blades. As the blades are curved (Fig. 1.3), the direction of motion of these particles of
Finally when the steam comes out of the blades, the pressure and temperature of the steam are
reduced, i.e. the drop of the enthalpy at the exhaust of the turbine due to expansion of steam. The
processes of expansion and direction changing may occur once (single stage) as in the simple impulse
turbine, or a number of times (multi-stage) as in pressure compounded impulse or impulse-reaction
turbine.
In this turbine, the steam is expanded once only, the steam enters the nozzles at the steam chest
pressure and issues from the nozzles at condenser pressure. The heat drop is comparatively large and
as the increase in Kinetic energy is equal to the heat drop, the nozzle exit velocity of the steam is high.
For maximum blade efficiency, the blade velocity should be slightly less than one half the steam velocity,
so in this type of turbine the blade velocity is very high. As the rotor diameter is kept fairly small, the
rotational speed is also very high, being of the order of 30,000 rpm. W ith speeds of this order it is often
necessary to reduce the speed of the driven machine by gear-box, thus increasing the cost and
Fig.1.6 Pressure Compounded Impulse Turbine Fig.1.7 Velocity Compounded impulse Turbine
The leaving loss in the last stage as compared to simple impulse turbine is proportionately less,
still it is appreciable.
In a pressure-compounded impulse turbine the nozzles are usually fitted into partitions, called
"diaphragms", which separate one wheel chamber from the next. The wheels are mounted individually
on the shaft and carry the blades on their periphery. As expansion of the steam takes place wholly in the
nozzles, the space between any two diaphragms is filled with steam at a constant pressure, but the
pressure on either side of any diaphragm are different. The greatest difference occurs in the first few
stages. Hence, steam will tend to leak through the space between the bore of the diaphragm and the
surface of the shaft. Fitting of labyrinth glands usually minimizes such leakage. A.C.E. Rateau first
designed this type of turbine.
As in other type of impulse turbines, the steam is expanded wholly in the nozzles and the wheels
rotate in steam at constant pressure. The total pressure drop from steam chest to condenser being split-
Since in the reaction type machine a pressure drop also occurs across the moving blades it is
necessary to provide effective sealing at the blade tips. This must be done to prevent leakage of steam
past the shrouding of the wheel and consequent loss in efficiency particularly at the high-pressure end of
the machine. These turbines may be designed for radial flow or axial flow. However, radial flow
machines are absolute now a days and all modern turbine employ axial flow designs.
The axial-flow impulse-reaction turbine consists of a number of rows of moving blades attached to
the rotor and an equal number of rows of fixed blades attached to the casing as shown in Fig. 1.9.
The fixed blades compare to the nozzles used in the impulse turbine. Steam is admitted
over the whole circumference and in passing through the first row of fixed blades undergoes a small drop
in pressure and its velocity is increased. It then enters the first row of moving blades and as in the
impulse turbine, suffers a change in direction and hence momentum giving an impulse on the blades.
During the steam passage through the moving blades it undergoes a further small drop in pressure
resulting in increase in velocity, which gives rise to a reaction in the direction opposite to that of the added
velocity. It is in this way that the impulse-reaction turbine differs from the pure impulse turbine. Thus the
gross propelling force in the impulse-reaction turbine, or the "reaction" turbine, is the vector sum of the
impulse and the reaction effects.
Fig. 1.9 shows how the blade heights increase as the specific volume of the steam increases with
reduction in pressure. It also shows how the pressure falls gradually as the steam passes through the
groups of blades. There is a pressure drop across each row of blades both fixed and moving. This is of
considerable practical importance, especially at the high-pressure end of the turbine where the pressure
drops are greatest, because this difference of pressure tends to force some steam through the clearance
spaces between the moving blades and the casing, similarly between the fixed blades and rotor. These
clearances have to be carefully controlled by using axial and/or radial seals at the blade tips; otherwise
The steam velocities in this type of turbine are moderate, the velocity for maximum blade
efficiency being roughly equal to the blade velocity. The leaving loss is normally about the same as for
the multi-stage impulse turbine.
The impulse-reaction turbine was developed by Sir Charles A. Parsons and is widely used in
power stations.
The work done by the moving blade is reduced due to three most predominant losses, i.e. profile
loss, secondary loss and tip leakage loss, which are shown in Fig. 1.12.
The extent of the leakage depends on whether the turbine is of an impulse or reaction type.
Reaction turbines suffer a pressure drop across the moving blades, so encouraging flow through the
clearances. Consequently, it is more important for a reaction turbine to have good tip sealing than it is for
an impulse turbine. The sealing of impulse and reaction turbine stages is shown in Fig. 1.14.
Erosion occurs because the water droplets travel far slower than steam, consequently their
velocity relative to the blades is significantly different in direction as well as speed. The result is the
impact of condensation droplets on the blades, in particular at the tip where the blade rotational velocity is
highest.
In the past, the leading edge of the blade has been protected either by an edge-hardening
process or by the brazing on of stellite strips, which is a very hard material. Now a day, with better
understanding of the mechanism of droplet erosion, has produced means of alleviating much of the
problem. Higher last-stage heat drops are employed along with higher mass flow loading. The result is a
higher pressure at the inlet to the moving blades leading to the reduction in the size of droplets.
Fig. 1.17 shows a section of the condition line displaying one stage only. (H1 - H2) represents the
isentropic heat drop and (H1 - H3) the actual heat drop. Cylinder efficiency then is obtained for HP, IP and
LP turbines by considering the heat drop across all the stages of the cylinder.
It can be seen that though the pressure drop across the valves is at constant enthalpy, the
change in entropy affects the moving blade exit isentropic enthalpy so that :
H1 - H 2 H1 - H 2
η (internal) = x 100% and η (external) = x 100%
H1 - H 3 H1 - H 4
For HP and IP turbines, the kinetic energy effects at inlet and exhaust are small and usually ignored.
If the steam could be slowed down isentropically to zero kinetic energy, it would be at static
pressure and enthalpy. In practice the steam does slow down after leaving the last blade, but through the
conversion of its kinetic energy to flow friction losses. This is constant enthalpy process since the steam
cannot do work on blades that it has already left. Consequently steam comes to rest at the point "X" on
Fig. 1.18.
The heat loss between the total conditions at blade exit (H2) and the static pressure line (H4) is
known as the leaving loss.
W here, Ve is the velocity of steam leaving the last row of blades. For a 500 MW turbine, the
velocity Ve is typically 170 m/s. Generally the leaving loss is responsible for 2% reduction in LP Cylinder
efficiency.
-o0o-
One half of the cycle consists of the boiler (steam generator) and its auxiliaries. The other half,
the turbine cycle consists of turbine, generator, condenser, feed pump and feed water heaters.
Consider first the boiler plant involved in the cycle. Feed water is supplied to the boiler drum
through economizer, where water is boiled and converted into dry saturated steam. This dry steam is
further superheated in the superheater and then fed to the HP cylinder through main steam lines via
Emergency Stop Valves and Control Valves. The steam expands in the turbine giving up heat energy, a
high proportion of which is converted into work energy on the turbine shaft. The shaft turns an electrical
generator, which produces electric power. Steam leaving the HP cylinder returns to the boiler, where it is
reheated. The reheated steam is supplied to IP cylinder through hot reheat lines via Interceptor valves
and control valves. After doing the work on IP rotor, the steam exhausted from IP cylinder is directly fed
through cross-around or crossover pipes to L.P. Cylinder. Finally the steam exhausted by LP cylinder
In the condenser, which is a large surface-type heat exchanger, the steam is condensed by
transferring its latent heat of evaporation to the cooling water (KW ). The steam having been condensed in
the condenser is now in the form of condensate at very low pressure and saturation temperature. This
condensate is pumped by condenser extraction pump from condenser hot well and passed through the
low pressure regenerative feed heating system and deaerator (direct contact heat exchanger) to increase
the temperature of water and remove dissolved gases such as O2 and CO2 to form feed water suitable for
boiler. Boiler feed pump sucks feed water from deaerator and pumps to boiler drum via high pressure
regenerative feed heating system (HP Heater).
In modern regenerative cycle, some of the steam passing through the turbine cylinder is bled from
a series of extraction belts located after selected moving blade stages and fed to the condensate heater
(LP) and feed water heaters (HP), which are of surface type heat exchangers. The BFP increases the
feed water pressure to a level in excess of the drum pressure, to provide for the pressure loss in the boiler
circuit and HP feed heating train. The cycle is now completed.
Consider a simple Ranking Cycle for steam shown schematically in Fig. 2.2 and on T-S diagram
in Fig. 2.3. W ater is pumped into boiler by the feed pump (process A-B). In the ideal Rankine cycle, there
is no temperature rise across the pump and points A-B are coincident. The water is then heated to
produce dry saturated steam (Process B-C). The dry saturated steam is expanded through the turbine
isentropically, i.e. without loss. This process (C-D) produces work along the turbine shaft. Finally the wet
steam exhausted by the turbine gives up its balance latent heat in the condenser and returns to water
state (Process D-A).
The area “E-A-B-C-D-F” on the T-S diagram represents the heat input to the boiler. The area
within the polygon A-.B-C-D represents the work done by the cycle. The heat rejected to the condenser is
represented by the rectangle A-D-F-E.
The economic implication of cycle efficiency is a major factor behind the development of the
cycle, whilst maintaining or reducing capital cost per electrical unit produced. The other criteria are
changing cycle terminal conditions with following considerations.
• No saturated steam should enter the condenser, i.e., point D must be within the vapour boundary
(Ref. Fig. 2.3).
• The exhaust wetness in the last turbine stage must not exceed 12%, i.e., D-D’ must be less than 12%
of AD’.
In the superheat cycle, the saturated dry steam leaving the boiler drum is further heated in the
superheater coils before entering the turbine. For the same quality of steam entering the condenser (point
D of turbine exhaust as shown in T-S diagram for basic Rankine cycle, Fig. 2.3), the increase in work
done is shown by "area A" in Fig. 2.5. The quantity of the heat rejected to the condenser (area C) is the
same in both, basic Rankine cycle (Fig. 2.3) and superheat Rankine Cycle (Fig. 2.5). Hence, there is an
improvement in the cycle efficiency.
Work done
η Superheat =
Total Heat Added
Area A - B - C 1 - D
=
Area E - A - B - C 1 - D - F
Area (A + B)
=
Area (A + B + C)
Since W .D. Area (A+B) in above equation is greater than W .D. Area in basic Rankine Cycle (Fig.
2.3) and the heat rejected are in constant in both the cases, the efficiency of superheat cycle improves.
Another major advantage of superheating steam is that for increasing cycle temperature and
pressure, the exhaust wetness in the turbine can be maintained within 12% as mentioned earlier.
Alternatively, from Carnot Cycle, which is the ideal thermodynamics cycle, the efficiency is given by -
W here,
T1 = Highest temperature of heat addition
T2 = Lowest temperature of heat rejection
So from thermodynamic point of view there is upper limit for increasing temperature T1 and
T1
η Carnot Cycle = ( 1 - )
T2
o
achieving gain in cycle efficiency. But the limitation is mainly due to material consideration. Up to 400 C,
o o
plain carbon steels can be used and up to 480 C, low alloy steels can be used. Above 480 C and up to
o
600 C heat resistant ferrite steels can be used. It gives limiting value of initial steam temperature to be
o
565 C after leaving margin for temperature variations during operation. However, practical limit for initial
o
steam temperature is kept as 540 C to reduce the frequency of boiler outages.
In the reheat cycle, steam at a given initial conditions is partially expanded through the turbine
(Process C-D) doing some work, and then fed back to the boiler, where it is reheated to about original
temperature (Process D-D). The reheated steam is then fed through the remainder of the turbine
(Process E-F) before exhausting to condenser.
The reheat cycle incorporates an improvement in thermal efficiency over the superheat cycle.
The thermal efficiency from the T-S diagram is -
Among the most important disadvantages of the reheat cycle are the complication and high cost
of the piping and fittings. Due to increase in capital cost of the plant, the efficiency improvement
2
advantage is partly offset. Further there is a pressure drop of about 4-5 kg/cm of steam in reheater
piping. If the pressure drop in reheater is more than 12-15% almost all increase in efficiency is offset by it.
Steam after partial expansion is usually reheated to initial steam temperature at pressure 0.15 to
0.3 times initial pressure (M.S. Pressure). Absolute increase in thermal efficiency of thermal power plant
by reheating is approximately 1.5 to 2% respectively/
Fig. 2.8 illustrates the improvement in thermal efficiency for a simple Rankine cycle, by virtue of
addition of feed water heaters. There will be a small loss of work available from the bled-steam not
expanding in the turbine. However, this loss is out weighed by the gain in cycle efficiency. The
improvement in efficiency takes place due to reduction in heat rejection in the condenser per unit of work
done by the turbine as compared to cycle without regenerative feed water heating.
The greater the number of feed heaters installed, the greater the improvement in thermal
efficiency. However, the incremental gain for each additional feed heater reduces as the number of
heaters for a particular size of plant is calculated on viability basis.
The additional benefits of regenerative feed water heating can be listed as follows:
i) Increased steam flow in initial stages resulted in increased blade heights, which improves internal
efficiency of turbine.
ii) Reduced flow at turbine exhaust demand lesser exhaust area, resulting in smaller blades in last
stages, which is limiting factor in turbine design.
iii) The decrease in steam flow at turbine exhaust also reduces flow of working fluid in condenser,
condensate pumps, ejectors and low-pressure heaters, thereby reducing their sizes and saving in
capital investment.
However, the overall efficiency of the unit is a product of efficiencies of the boiler, turbine,
generator and thermal efficiency. The overall efficiency, therefore, will be reduced to 39 - 41% at rated
parameters. Various efficiencies are listed as follows:
The deviation of actual expansion line from isentropic expansion is due to losses or irreversibilites
corresponding to an increase in entropy. It can be seen from Mollier diagram (Fig. 2.11) that for an
expansion between two pressures, the greater the entropy rise (more losses), the less energy there is
available for work. Refinement in turbine design aims to reduce the losses and increases the available
energy.
Now consider the whole turbine expansion process through HP, IP & LP cylinders on a mollier diagrams,
as shown in Fig. 2.12.
The actual turbine expansion line includes the major losses encountered as follows:
i) HP throttling losses through the control valves and associated pipe work.
ii) Reheater pressure losses through pipe work (cold reheat, hot reheat pipe lines and reheater
coils).
iii) The leaving and hood losses at the last stage of the LP turbine.
H1 - H 2 H3 - H 4 H 4 - H5
HP Cylinder η = IP Cylinder η = LP Cylinder η =
H1 - H'2 H 3 - H'4 H 4 - H'5
On small advantage of the irreversibilites in the IP & LP turbines is the reduction in exhaust steam
wetness, causing less erosion on the final stages of blading. The condition of the plant can be monitored
by measuring the temperature and pressure of the steam at points between the cylinders, hence deriving
the steam enthalpy. It is then possible to compare cylinder efficiencies with the original design values.
Turbine blade erosion or steam leakage results in reduced cylinder efficiency. In practice, the LP cylinder
exhaust enthalpy is not directly measurable and it must be derived from an overall heat balance.
The heat rate is determined by measurement of various plant operating parameters. These include:
• Flow rate, using a differential pressure device
• Enthalpy, based on calibrated pressure and temperature measurement.
• Electric power, based on calibrated voltage and current measurements.
Consider a steam cycle with single reheat and regenerative feed heating shown in Fig. 2.13, using
measurements around the cycle, heat rate is calculated as follows:
M 1 (H 1 - H f ) + M 3 (H 3 - H 2 )
Heat Rate = KJ/KWh
Pg
W here,
M1 – Flow rate of superheated steam from boiler (Kg/h)
H1 – Enthalpy of superheated steam based upon pressure and temperature T1 (KJ/Kg)
H2 – Enthalpy of HPT exhaust steam (KJ/kg.)
H3 – Enthalpy of reheated steam (KJ/Kg)
M3 – Flow rate of reheated steam
Hf - Enthalpy of feed water to boiler.
Pg – Generator power output from generator terminals
3600 ( Kw)
η Thermal = x 100%
Heat Rate (KJ/s)
860 Kw
= x 100%
Heat Rate K Cal/hr
Heat rate is the means of monitoring turbine cycle performance by comparing the actual heat rate with the
design values provided by the manufacturers.
First consider the variation of the hourly heat consumed by the turbine generator with the load produced.
This characteristic is known as W illans line (fig. 2.14), which is based on turbine test runs at 100%, 80%,
60% and 40% load. This gives the linear relationship between load and heat consumption and
extrapolation below 40% load (dotted line) reveals a no-load heat consumption of about 3% of the full load
value.
output (100% load). The major contributory loss comes from the throttling loss across the turbine control
valves.
Operating the unit at part-load is one of the "external" factors preventing the achievement of the design
rate. The other major external factor, which increases average heat rate, is the need to re-start the unit as
required by the operating regime after trip out. During start-up, the unit is unloaded and additional
works/power is needed for start-up systems.
Plant operating losses cause the other major increase in design heat rate. In practice turbine heat rate
increases (deterioration of efficiency) due to:
- Deterioration of cylinder clearances
- Deterioration in feed heating efficiency
- Poor control of superheat and reheat temperature (particularly in older designs)
These factors are more prevalent as the plant ages.
In light of above considerations lower steam pressures are used for smaller turbines (resulting in simple
design and quicker start-ups) and higher initial steam pressure are used for larger turbines (resulting in
higher efficiency).
The following are typical recommended values of initial steam pressure for various rating turbines:
The effect of increase in initial steam pressure keeping the temperature constant is shown in Fig. 2.16.
The available energy increases with exhaust at higher wetness.
Fig. 2.18 shows the effect of increasing initial steam pressure and temperature both at constant
condenser exhaust pressure, which illustrates the significant advantage in achieving higher thermal
efficiency with normal wetness at exhaust.
Fig.2.17 Effect of Increasing Steam Temperature Fig.2.18 Effect of Increasing Steam Pressure
On Available Energy & Temperature Both on Available Energy
Although reducing LP exhaust wetness is desirable, too high a temperature could lead to some difficulties
with materials. The common practice has been to reheat the steam to the original superheat steam
o
condition i.e. 540 C.
Another important factor in the design of the reheater is the effect of pressure losses in the pipe work.
The pressure loss results from a throttling effect, which reduces the available energy for work. The
pressure at which steam is reheated is about 25% of the stop valve condition of main steam, representing
approximately a four-fold increase in volume. This necessitates the use of increased pipe sizes, which
Control valves at the inlet to the HP & IP turbines are used to regulate the inlet mass flow and hence the
load on the machine by a throttling process. Fig. 2.21 shows a Mollier diagram comparing the condition
lines of a reheat turbine at full load with all the valves wide open and one at part load, where the load has
been reduced by 40% by throttling on the inlet valves to the HP turbine, other pressure losses are
neglected. The throttling effect is to reduce the inlet pressure by a constant enthalpy process
(represented by horizontal line AB). The result is a increase in entropy and also a slight fall in
temperature with some reduction in the available heat drop. This accounts for a small loss of efficiency.
However, the major flow reduction that results in the main reason for the reduction of work done in the
HP, IP and LP cylinders.
The efficiency of the cycle is strongly influenced by the LP turbine exhaust pressure. The back pressure
of the condenser sets the saturation temperature at which the expanded steam rejects its Latent heat of
vapourisation to the cooling water. Consequently, changes in back pressure affect the temperature of
cycle heat rejection. The effect of change in condenser saturation temperature on the cycle work done is
shown in a T-S diagram in Fig. 2.22. Generally, a low exhaust pressure is sought as it improves cycle
efficiency.
However, there are several plant constraints affecting the selection of design exhaust pressure consider
the effect of lowering the exhaust pressure on the turbine condition line on the Mollier diagram (Fig. 2.23).
Expansion to a lower pressure results in increased wetness and increased specific volume at the exhaust.
The increase in exhaust wetness tends to increase the erosion of the last-stage blades. However, more
significant is the effect of increased specific volume, implying the need for a higher volume flow rate. The
volume flow rate through the condenser is the product of the mean steam axial velocity and the annular
exhaust area. The annular exhaust area is limited by the maximum length of LP blade. At 3000 rpm, the
centrifugal forces on the long blades become very high and there is a limit to mechanical stresses which
blade roots can sustain. Hence, having established a maximum annular area, the increase in volume flow
rate must be accommodated by an increase in exit velocity. Steam leaving the last stage of the turbine
with high residual velocity represents a loss of Kinetic energy. This Kinetic energy performs no useful
work on the turbine blades and therefore is a loss of available energy, known as the "leaving loss", and
varies with the square of velocity. The other loss associated with the turbine exhaust is the "hood loss",
Finally, a major factor affecting the choice of exhaust pressure is the ambient temperature at which CW
can reject heat. This factor seasonally affects the thermal efficiency of the plant.
The variation of turbine heat rate with exhaust pressure (Fig. 2.24) is obtained from the basic turbine
design data relating to the turbine exhaust area, exhaust mass flows and the heat rejected. Fig. 2.25
shows the corresponding characteristics for the change in power output with change in condenser
exhaust pressure.
Keeping these characteristics in view, the turbine load should be reduced when the condensate back
pressure increases due to problems in condenser cooling water system or air ejection system to prevent
the overheating of condenser and LPT last stages.
-o0o-
In India the growth in utility power generation picked up after the independence. The machines of
capacity ranging from 10 MW – 67.5 MW were installed by 1960s in various parts of India. The G.E.
make 67.5 MW single cylinder turbogenerator, shown in Fig. 3.1, are still operational in many power
stations.
Then with the growth of industrialization, particularly process industry sector that is power
intensive, the need for higher capacity machines was experienced. The decade 1970-80
saw the enhancement of machine sizes from 100 MW to 140 MW of Polish, French, British and German
designs. Later on BHEL adopted the technology for manufacturing 210 MW steam turbines from LMW ,
USSR. The decade 1980-90 saw the tremendous growth in Fossil Fired Power Station with the
installation of C.E. design boiler and LMW design 210 MW turbines, solely supplied by BHEL. Almost
NTPC, TATA ELECTRIC CO., MSEB and few other electricity boards installed the 500 MW
machines in the last decade. But still in the national scenario, majority of the machined are of 210 – 250
MW capacity & are still preferred by power companies.
In the context of international picture of machine size, the highest size being installed is 1600
MW . The machines of 660 MW , 800 MW , 1000 MW and 1200 MW are already working in western
countries.
The high capacity machines working on high steam parameters require close monitoring and
precise control of turbine parameters, which has been made possible by computerized Data Acquisition
System and Distributed Digital Control System and state-of-the-art hydraulic actuation system.
Single Flow:
In case of single-flow turbine (Fig. 3.2(a)) the steam is admitted at the one end of the turbine in
the first stage blading. Steam flows axially through the radially-mounted blading and exhausts at the other
end after expansion (specific volume is increased). This is shown in Fig. 3.1. Single flow configuration
offers simplest arrangement of blading.
Double Flow:
In the double flow arrangement (fig.3.2 (b)) the steam is admitted at the centre of the cylinder and
is divided to flow in opposite axial directions towards the ends of the rotor. This arrangement is used to
avoid the excessively long blades, which would be required by a single-flow arrangement. Hence this
arrangement is invariably used for LP turbines and sometimes for IP turbines, where the steam pressure
is less and specific volume is high. For turbines of large output, it is normal to have several double flow
low-pressure cylinders to further divide the flow among LP cylinders so as to reduce the size of turbine.
The second benefit is that the double-flow cylinder effectively nullifies (self balancing) the axial
thrust caused by the steam forces on the moving blading (in reaction turbine).
Reversed Flow :
Above objectives can also be achieved in reversed –flow arrangement within the turbine cylinder.
However, thrust reduction is the main target for the reversed flow cylinder (Fig.3.3). In this case steam
flows in one direction through one group of stages and is then admitted through ducting (internally or
externally) to the second group of stages where steam flow in the opposite axial direction. In some cases,
the second group of stages may have several sections in parallel to accommodate the increasing
volumetric flow rate.
Axial Flow
Steam Inlet
Steam Outlet
In axial turbines, the steam is admitted to the cylinder and exhausted from it, by one or more
circular pipes in a radial or near-radial orientation. At the LP turbine exhaust, the connection flanges to
the condenser will however normally be rectangular, at an appropriate location and orientation to match
the condenser design. This is always-radial flow in one or more directions. The steam is therefore
required to turn through a right angle to enter the axial-flow blading and to exhaust from it, at the same
time redistributing itself around the circumference. The inlet and exhaust areas therefore require
sufficient space to allow an orderly flow without undue pressure loss or flow separation. In some cases,
particularly low pressure turbine exhaust, flow guides may be incorporated.
However, turbines may be sub-classified on the basis of cylinder arrangement, shaft connections and
other factors as follows:
1) Number of shafts and coupling methods
2) Number of cylinders
3) Type of exhausts (single exhaust, double exhaust)
4) Rotational speed (1500 rpm, 3000 rpm, 3600 rpm)
5) Use of reheat cycle (single reheat, double reheat)
6) Governing methods, ex. Nozzle Governed or Throttle Governed
Frequently, single cylinder turbines (industrial turbine) are designed and built on a modular basis,
with the inlet sections, blading sections selected from a range of standard designs to suit a range of
output powers, initial and exhaust conditions and special applications such as extraction steam for
process heating. The G.E. make single cylinder turbine generator unit of 67.5 MW installed in 1960s is
shown in Fig. 3.4.
For larger machines (above 100 MW ), multi-cylinder designs are used. Various configurations of
multi-cylinder designs are shown in Fig. 3.5. The number of cylinders depends on similar considerations
of terminal conditions and design aspects. A typical turbine of 500 – 1000 MW output in a Fossil Fired
Power Station would have one High Pressure Turbine, one Intermediate Pressure turbine and one to
three numbers of low-pressure turbines. A typical 210 – 500 MW units of KW U design adopted by BHEL
in India have three cylinder arrangement, one HP (single flow), one IP (single or double flow) and one LP
(double flow) cylinders connected in tandem arrangement as illustrated in Fig. 3.6 for KW U 210 MW unit.
In all the units single reheat cycle is used.
The rotational speed of the turbine depends on grid frequency. In India we have adopted 50 Hz
electrical frequency, which means the turbines connected directly to two poles generator rotate at 3000
rpm. In USA turbines are designed to rotate at 3600 rpm due to 60Hz grid frequency.
For large turbines, the IP & LP cylinders have double exhausts. Obviously, since the steam
expands considerably during its flow through the turbine, from inlet to exhaust, the blade annulus must
increase to cope with the larger volume of steam. As a result the blade lengths must increase towards the
Later on, therefore, the designers again preferred the use of under-slung condensers (below LP
turbine) with transverse tubes, using a connecting duct between the turbine outlet flange and the
condenser inlet flange. Because the condenser tubes are normally much longer than the width of the
turbine casing, this duct is trapezoidal in shape.
The best practical approach in this case to complete dynamic isolation results into mounting the
turbine-generator unit on springs buffered between concrete structures. Recently this technique has been
used by BHEL in 210 MW units 3 & 4 at Khaperkheda TPS. The view of front pedestal support is shown
in Fig. 3.9. Generally this practice uses springs of the helical-coil or plate type supporting a reinforced
concrete deck on which the turbine-generator is mounted. Springs mounted in rows on structural concrete
walls or in groups at the top of support columns have been used in some cases viscous dampers are
employed in conjunction with springs. Natural frequencies of about 3 Hz for movement in the vertical
direction are claimed for these systems. A hydraulic locking system is used to pre-load the springs to a
set deflection for construction and plant erection purposes. The same locking system can be used to
allow the insertion of packers, above a spring or spring group, to correct for foundation column settlement.
This also allows springs to be changed after erection if spring stiffness is noticed to be deteriorated.
The other important advantage is that because the sub-foundation is well isolated from dynamic
loads, it is possible to reduce the mass of the sub-foundation towards that necessary to support static load
only, or even to dispense with a mass concrete sub-foundation and install individual foundations for each
support column. The precise design, of course, depends on subsoil conditions at the particular site. The
foundations cost reductions of about 25% are claimed in normal circumstances.
Another design factor is imposed by the need for uniform heating of both the massive flange
metal (Parting plane joint) and rest of the cylinder.
The single casing design, which is practically obsolete, now, was adopted earlier for lower steam
parameters and medium to small capacity turbines. In this design the fixed blades, also called as
diaphragms, are housed directly in the grooves of casing. The rotor is centered axially and radially in side
the casing so as to maintain proper clearances during operation.
The design is complicated by the need of internal access, the casing being split along the
horizontal plane, allowing the rotor to be inserted as a complete assembly. Substantial thickness flanges
and bolting are required to withstand the pressure forces at the horizontal joint. The relatively massive
flanges compared to the casing wall thickness respond more slowly to temperature changes, particularly
during cold start-up of turbine, resulting in different rates of expansion and the setting-up of thermal
stresses and the distortion. This is explained in Fig. 3.11. This distortion is, however, minimized by
providing warm-up steam to flanges and studs during start-up and load-changes. Further stress
complexities are introduced by the gland housing located at the ends and also due to steam entry and exit
passages.
As with all pressure vessels, the integrity of the design is checked after manufacture with a
hydraulic pressure test at 15% of the highest working pressure.
W henever the steam conditions are high, the cylinder is generally of double shell design. The
inside shell serves as fixed blade carrier and encloses the rotor. The outer shell encovers the assembled
inner shell as shown in Fig. 3.12. The annular gap between inner shell and out-shell is filled up generally
by exhaust steam (in some cases inlet steam). This enables each shell to be designed for a relatively
small pressure differential as compared to single shell design (Fig. 3.12). Hence the reduced shell
thickness and flange thickness, together with the increase in area of contact with the steam, permits
quicker warming of turbine when starting without undue thermal stresses. Moreover casting becomes
simplified, resulting in sounder castings.
The modified form of double shell construction, using carrier rings, as shown in Fig. 3.13, is used
by some designers (LMW Design Turbine). In this case split carrier rings, which houses diaphragms, are
fitted in the grooves of the casing, this serves the job of partial double shell design.
Triple casings have been used on some modern turbines to further reduce the stresses on the hot
inner casing, and hence reduce thermal distortion.
The transition to an axial blading system was necessary for the increasing turbine capacities to
allow greater steam flow rates. In the course of further development, the packing gland parts with the
intricate radial gland rings were replaced by an axial design with a number of individual segments. The
sophisticated radial and axial centering of the blade carrier was reduced to a design with mounting
bracket on one plane with axial fitted keys. Also, instead of self-aligning rings fitted in grooves, V-rings
were developed that press on plane faces, after having been stressed, and can be removed easily. It
proved to be of great benefit to replace the shrunk-fitted coupling by an integrally forged coupling bolts.
This resulted in general barrel-type turbine design illustrated in Fig. 3.15 used as HP turbine in
turbine generator sets of upto 740 MW . In this design, the exhaust section is bolted to the barrel casing in
radial plane. In the meantime, the design changes to develop joint loss barrel type casing with
consideration being given particularly to fabrication and simple assembly and also top further improve the
operating behaviour has resulted into new design barrel type HP turbine as shown in Fig. 3.16.
Bolted Exhaust End
W hen the old barrel type casing (Fig. 3.15) is compared with the new design (Fig. 3.16), the
advantages of the new development stand out. The most striking change is missing radial flange to barrel
casing where the exhaust section was bolted together. Thus, mass accumulations are avoided thereby
and the wall thicknesses in all parts are approximately identical. This gives an advantage during
operation of reduced thermal stresses due to reduced mass accumulations. The new barrel type turbine
design, as viewed in Fig. 3.16, is resistant to deformation even during rapid temperature changes and at
high pressure. Inner casing (split type) and barrel are forged out of creep resistant alloy steel.
3.5.2.4 I P Casings
In reheat turbines, the design aspects for IP cylinders are similar to those for HP cylinders since the
reheat steam temperature is as high as main steam temperature. But the lower steam pressure permits
the IP casings to be thinner as compared to HP casings, which helps in minimizing the thermal stresses.
Mostly in modern turbines, the double casing design (both split) with double-flow arrangement is adopted
which allows faster start-up of axial thrust. Double flow casing design has an advantage eliminating the
rotor gland at high-pressure end and self-balancing of axial thrust.
Steam Exhaust
3.5.2.5 L P Casings
L P cylinders are generally of double-casing and double flow construction with an inner casing
containing diaphragm supports, bled steam and water extraction belts. Outer casing directs the exhaust
steam from the last stage to the condenser, which is located at bottom of LP turbine.
The large size of LP outer casings combined with their low-pressure loading favours a fabricated
(welded) structure rather than cast construction. Inner casings being more complicated may be of cast
construction. All casings have bolted horizontal flange joints.
Solid forged rotors are used in HP and IP turbines that employ impulse type blading and
sometimes for LP turbines when reaction type blading are used. The HP and IP turbines are subjected to
high temperature of steam. Under the high temperature and stress conditions, the phenomenon of creep
takes place after a large number of running hours. Hence other types of rotors, except integral or solid
forged rotor, may not withstand during the life of the turbine. Fig. 3.18 shows fully bladed integral type
rotor for HP turbine. However, the integral types of rotors are difficult to forge and due to high rejection
rate are expensive. Also a large amount of machining time and waste material is involved.
Reaction Stages
Disc
Drum rotors are used for large turbines using 50% reaction blading. These rotors may be further
classified as:
i) The hollow drum rotor (Fig. 3.19), which is designed with the same thickness of material
as the casing. This feature offers the advantage of even temperature distribution.
ii) The solid drum rotor (Fig. 3.20), which is suitable for cylinders where there are lower
temperatures but large diameter as in case of IP turbine without reheat.
The built-up rotor tends to be cheaper since the discs and shaft are relatively easy to forge and
inspection for flaws and the matching of these components can be carried out concurrently.
Built-up rotors cannot be used for high temperature applications. Such as HP and IP turbines due
to danger of loss of shrunk fitting and loosening of discs after a long hours of operation. However, these
can well be used for LP turbines where the steam temperatures are low.
This type of rotor offers the main advantage of lower stresses in the discs as in the case of LP
turbine. W ith regard to LP rotors, the main concern is one of centrifugal stress due to higher diameter.
Hence the last stage disc being most heavily stressed part of the turbine. The centrifugal load of large
rotating blades sets up a tensile stress in the rim of the disc and this stress increases with decreasing
radius. The maximum value of this tensile stress being at the bore of the hub. The larger the bore of the
hub, higher is the maximum stress. If the bore is exceedingly small, the hoop stresses throughout the
disc are halved. This aspect is made use of in certain welded LP rotors, which have no central hole;
hence it contains much lower stresses.
The other advantage of this rotor is that it obviates the need for large shaft forgings, which are
expensive and difficult to manufacture.
Creep can be restricted by proper geometry in critical areas, such as blade fastenings, in order to
control the stress concentration features. Rotor stresses are generally kept within limit for high
temperature working by employing creep resistant steels.
Thermal fatigue is caused due to cyclic reversals of thermal stresses resulting from transient
temperature gradients established during heating and cooling periods (start-up and shutdown). The
steam admission sections of HP & IP rotors are the critical areas for thermal fatigue, demanding careful
attention to design detail and operational practices. Modern turbines are equipped with "Turbine Stress
Evaluator/Controllers" package to control the speeding-up and loading gradients during machine
operation.
In addition there is a centrifugal force, caused by the speed at which the blade is rotating, trying to
throw the blade outwards. These two forces, the bending force and the throwing out force increases with
the increase in wheel diameter or blade height. Hence, these forces stresses in the blade are maximum
in the largest blade wheel at the LP turbine exhaust end (last two stages). Thus the stresses, which these
forces impose, limit the size of the blades and the diameter of the last wheel. Due to this limitation, the
blade height of last stages is restricted to maximum 1m by designing double flow in the LP cylinder and in
large turbines (above 500 MW ) two or three double flow LP cylinders.
The mechanical stresses as described above are smaller in HP turbine moving blades but on the
other hand, this blading is subject to very high temperature and material is subject to creep after long
running hours.
The HP moving blades for impulse type turbine are machined from solid bar and the spacers are
formed with the blade. Such construction avoids the use of distance pieces or packers when assembling
At the HP end of the turbine the diaphragms are of the built-up type. Each nozzle is machined
separately from a solid bar and on earlier design turbines, is attached by grooves and rivets to the
diaphragm plate. In most cases now the nozzles are welded together and to the plate. Fig. 3.26 shows
the manner in which the nozzles are built-up around the diaphragm plate.
Moving Blades
Fixed Blades
For the larger LP blades the side locking strips are not generally used and the blade roots are
parallelogram shaped for fitting into serrated grooves. On the very large LP blades, which are sometimes
of hollow construction to reduce weight, a side entry method of fixing is used (Fig. 3.30). For vibration
considerations lacing wires are passed through holes in the blades and either brazed in position or in
some designs the loose wire uses the centrifugal forces to restrain the blades.
The last stage is very important in turbine design. As the pressure of steam decreases during
expansion, the specific volume becomes very high. The volume flow of steam increases necessitating an
increased flow area consequently blade height and mean diameter increase with decrease of pressure.
Blades are held at one end with the rotor while the other end is free so they act as cantilevers with
distributed load of steam on them. They are subjected to bending stresses in addition to high centrifugal
stresses due to rotation. In the last stage of the LPT, both the bending stress and centrifugal stress reach
the maximum values. As per material considerations, the maximum blade velocity is also limited which is
about 350 – 400 m/s. Therefore, for 3000 rpm machine, the maximum diameter of the last stage comes
out to be 2.23 m. For straight blades, the maximum blade height is about 20% of the mean blade ring
diameter. W here it is necessary to exceed this ratio (Blade height/mean diameter) because of flow
requirements in large LP turbines, the blades may be tapered or twisted, thereby reducing both bending
and centrifugal stresses. W ith these modifications, the blade height may approach about 30% (0.7m) of
the mean blade ring diameter (2.23 m).
Serrated
Grooves
In Rotor
In the case of reaction type turbines, the HP blading is built up in packets of up to ten blades and
held in the rotor grooves with "inverted T" root.
For low-pressure stages with longer blades, "Inverted Fir Tree" types of roots are designed for
firm fixing and rigid construction.
3.5.4.5 Clearances
Massive rotors weighing up to 100 tons and 20 m long have to revolve without touching the
diaphragm glands and the casing glands, which may have clearances of about 0.6 to 0.7 mm only to the
Transient phenomena may be due to different heat losses from the top and the bottom half of
cylinders, after shutdown. This results into hogging of cylinders followed by rubbing. The phenomena
listed at (i) and (ii) above may largely be countered by effective lagging (insulation). The third type of
distortion can only be avoided by effective design.
Apart from radial, there are axial clearances. And in the case of 30 m long shaft axis, the differential
expansion between the rotor and the casing may produce about 25 mm movement at the output shaft
end, between extreme of operating conditions. Such movement may cause gland rubbing, if the gland
sealing is of labyrinth type, i.e. fins mounted alternatively on shaft and gland housing.
In all modern turbines labyrinth seals are employed. Generally the glands are of the radial
clearance variety and are fitted at all points where there is a pressure difference between the turbine
internals and the atmosphere or between stages (particularly reaction type stages).
The labyrinth gland provides a series of very fine annular clearances, in the gap between the
cylinder wall and the shaft. The steam is throttled through this gap and its pressure reduced step by step.
In expanding through each clearance, the steam develops kinetic energy at the expense of its pressure
energy. Ideally, the kinetic energy is converted by turbulence into heat with no recovery of pressure
energy. In this way, the pressure is progressively broken down as the steam is throttled at successive
restrictions. By keeping the clearance area sufficiently small, the quantity of energy lost may be kept low
and as turbine output increases, the gland leakage loss becomes proportionately less.
To reduce the clearance, glands are made with a diameter as small as possible. The diameter is
limited by considerations of shaft strength and radial clearance, by clearance within the bearing and by
the possibility of shaft distortion during transient conditions.
Glands must allow for axial expansion of the shaft and casing to take place without causing a rub.
On the other hand, if a rub does take place because of shaft vibration, it is desirable that the heat
generated is minimised to prevent serious distortion. A typical modern gland comprises of stationary fins
on spring-loaded segments, while the shaft is either smooth or having alternate fins. If a rub takes place,
the segments receive the generated heat and can be replaced readily if they are damaged.
Fig. 3.40 shows the labyrinth gland arrangement for typical turbine with HP, double flow IP and
double flow LP turbine cylinders. In the high pressure turbine glands there are three pockets, the gland
sealing steam being supplied at the centre pocket. The gland steam leaks-off from the outer pocket to the
The intermediate and low-pressure turbine glands have two pockets. The gland sealing steam is
applied at the inner pocket and the gland leak-off is from the outer pocket into the gland steam cooler.
Gland steam cooler sucks the air + steam mixture from the glands.
2
The steam supply header pressure is maintained generally at 0.01 kg/cm by the pressure
regulating valve and the steam is supplied from PRDS or Cold Reheat System.
The dummy piston diameter is so calculated that the steam pressure acting upon it in the opposite
direction to the steam flow, balances out the force on the rotor blades in the direction of steam flow. It is
preferable that the dimensions are so designed to keep a small but definite thrust towards the steam inlet
end of the turbine. In order to maintain this condition of thrust at all loads; a balance pipe is usually
connected from the casing, on the outer side of the balance piston, to some point at exhaust of the
cylinder.
Two bearings normally support each section of the turbine shaft. However, when rigid couplings
are used in some designs, only one bearing is used between cylinders in order to save length and bearing
losses. Plain white metal lined (babbit) journal bearings are invariably used because of their high loading
capacity, reliability and low wear due to hydro-dynamically generated films of lubricating oil. These films
are formed automatically due to wedge action of oil between the white metal and the shaft. The proper oil
film (by controlling inlet oil temperature and oil quality) ensures that no metal-to-metal contact is made.
The oil is continuously fed into the wedge by frictional drag and leaks away axially towards the edges of
the bearing.
A regulating valve or orifice is provided at the inlet of each bearing to adjust the oil supply, which
must not only lubricate but also cools the bearing by removing the frictional heat.
The view of the typical journal bearing is shown in Fig. 3.36. The bearing shell is split horizontally
and dowelled. The bearing rests on four pads fitted with shims. The bearing shell is made of cast iron
and the pads, which are bolted to it, are generally of spherical shape. The spherical seating feature
assures that on assembly, the bearing will automatically align to its correct axial tilt. This is necessary
because, when coupling faces are set and bolted flat together, the outer bearing on each shaft needs to
be higher than the inner bearing due to natural bending (sagging) catenary (shaft line) adopted by each
shaft under its self weight.
The inside surface of both the halves are lined with white metal (Tin & Lead alloy) which has very
low coefficient of friction. Modern bearings have a thin, uniform white-metal lining that adheres to the
shell by surface tinning.
High pressure jacking oil is admitted through small holes at the bottom of the bearing to lift the
journal (shaft) when starting from rest and upto about 540 rpm speed. This not only enables an oil film to
be established and so prevent wear when starting from rest, but it also reduces the starting torque on the
2
barring gear drive. The oil pipe is usually buried in the white metal so that the high pressure (120 kg/cm )
does not force the white metal away from the shell.
Typical large turbine bearings are upto 530 mm in diameter and have length to diameter (L/D)
ratio in the order of 0.5 to 0.7. Generator bearings tend to be rather longer, with L/D ratios of 0.6 to 1. In
this way, typical load on projected bearing area is kept below about 15 Kpa. The bearing clearance in
vertical direction is kept about 0.1 mm per 100 mm diameter while in horizontal direction it is 0.15 mm per
100 mm diameter of journal.
W ear of journal bearings mainly occurs with an oil film of very small thickness and mild local wear
taking place in a course of long running hours. However, severe wear is a symptom of trouble and can be
caused by following reasons.
• Contacting asperities on badly matched journal and bearing surfaces.
• Scoring by oil-borne solid particles
• Excessive local pressure or temperature
• Electrical pitting
Electrical erosion of bearings and journals occasionally occurs. Small shaft voltage is set up by
electromagnetic induction in the generator rotor. Higher voltages sometimes occur in the turbine,
produced electrostatically. Bearing erosion is prevented by effective insulation of the generator bearings
from earth and the application of an earthing brush to a suitable point on the turbine rotor system.
The thrust collar on the HP turbine shaft runs between two sets of white metal lined pivoted pads
located in holding rings. Each holding ring and its associated pads are located and secured in both top
and bottom halves of the inner housing by stop plates and combined washer and screws fitted at the
horizontal joint. Liners fitted between the holding ring halves and the inner housing can be adjusted to
give the desired oil clearance between the thrust pads and the shaft thrust collar. The axial alignment of
the thrust assembly can be adjusted by liners fitted to each end of the outer casing.
The purpose of turbine thrust bearing is to provide a positive axial location for the turbine rotors
assembly relative to the cylinders. To achieve this, it must be able to withstand the unbalanced thrusts
due to blade reaction and steam pressure acting on unbalanced areas. It must be free from maintenance,
except at major outages. Thrust bearing should normally be located close to the areas where
blade/cylinder clearances are minimum and operating temperatures are highest. Hence it is preferably
located between HP and IP turbine.
Although the net thrust on the white metal lined pads in the running condition (on-load) is always
in one direction, i.e. typically towards the generator (which is taken up by working pads), a second set of
pads, termed non-working or surge pads, are incorporated on the opposite side of the thrust collar,
integral with the shaft, to take the reversals of thrust loads during transient operation (load rejection and
turbine trip condition).
In operation, the pad faces are slightly inclined to the face of the thrust collar and the wedge
shaped cavity thus formed fills with oil. As thrust pressure is applied, the wedge narrows and oil is forced
in the restricted end. This ensures that metal-to-metal contact between thrust pads and thrust collar is
prevented. The pads are shaped and mounted so that each is able to pivot independently.
As seen in Fig. 3.37, the bearing has four supporting pads, two in vertical center plane and two in
the horizontal centre plane. These pads have steel and brass shims fitted to their bases to allow the
thrust assembly to be adjusted vertically or horizontally if it becomes necessary to correct the alignment of
the turbine shafts.
Thermocouples are embedded in the four thrust pads adjacent to the horizontal joint in the bottom
half of the thrust bearing. The leads from these thermocouples are carried from the thrust pads to the
bearing pedestals, through dovetail grooves cut in the horizontal joint face of the inner housing bottom
and sealed in position by strips of nylon packing.
The front pedestal, which is located at, exhaust or front end of the HP turbine, supports the
journal bearing No. 1 and exhaust side casing brackets. The M.O.P., speed measurement transmitters
and overspeed trip devices are also located inside the pedestal. Front pedestal can slide freely in axial
direction, which is located, by axial guide and radial keys in order to provide free expansion of turbine
cylinders. Typical front & rear pedestal view for KW U HP turbine is shown in Fig. 3.38.
The pedestals incorporate facilities for the attachment of lubricating and jacking oil supply pipeline
and the associated bearing oil drain pipe work. Also the turbovisory parameters monitoring
instrumentation (axial shift, vibration, differential expansion pick-ups) connections are mounted inside and
outside the pedestals.
Attention is paid in design of pedestals to ventilate around the pedestals, keeping them cool so
that any vertical thermal expansion effects, which might disturb the overall vertical alignment of the
turbine, are minimised.
3.5.8 Couplings
As seen earlier, there has been limit to the length of the individual cylinders making up the
complete turbine. Similarly, there is a limit to the length of turbine shaft that can economically be
manufactured. Also, depending upon the steam temperature and stress level in cylinders, the need for
use of different material, suitable to it, arises. Hence the multi-cylinder construction of large turbo-
generators necessitates the use of coupled shaft system. The coupling joins the different rotors together
to transmit the driving torque to each other and finally to the generator rotor.
Flexible Couplings:
Flexible couplings are capable of absorbing small amounts of angular misalignment, as well as
axial movement. Fig.3.39 shows some designs in common use. The claw coupling which may be single
or double is robust and slides easily when transmitting light load. At heavy loads, however, friction causes
it to be axially rigid.
The multi-tooth coupling transmits torque by internal and external gear teeth of involute form,
which are curved to accommodate angular misalignment. This type of coupling is used for coupling the
M.O.P. with H.P. turbine shaft in front pedestal.
The Bibby coupling is satisfactory upto medium sizes and provides, in addition to above, torsional
resilience, the torsional stiffness increasing with load.
All these couplings require continuous lubrication, normally provided with a jet of oil feeding into
an annular recess, from which it is fed centrifugally to the coupling teeth through drilled passageways.
Semi-flexible Couplings:
These types of couplings allow angular bending only. They require no lubrication and are
generally employed between LP turbine and generator (LMW turbine). It consists of a bellows piece
having one or more convolutions, as shown in Fig.3.40.
Rigid Couplings:
On turbines larger than 60 MW , the high torque to be transmitted generally renders the use of
flexible couplings impracticable. Consequently, it is now normal practice for rigid couplings to be
The long shaft that is formed naturally bends under its own weight (sagging) to form natural
catenary. Because of this, with the use of rigid couplings, the shaft alignment must be adjusted to ensure
that the coupling bending moment forces are minimised.
Rigid couplings may be integral with shaft forgings (monobloc) or are shrunk on to the shaft. It is
now common practice for the turbine rotors to have monobloc half couplings whereas shrunk on couplings
has been used on generator rotor.
Typical rigid coupling is shown in Fig. 3.41. Heating and shrinking them on to the shaft assemble
half couplings, which are forged separately from the shaft. Dowels are then inserted between the bore of
the coupling and the diameter of the shaft. An oil injection arrangement may be provided on the coupling
through which oil can be supplied under pressure to one or two annular grooves in the coupling. This
allows the coupling to be "floated" to ensure that it is seated correctly following the shrink-on procedure
and also assist easy removal.
The two halves of coupling have spigot fitting as shown in Fig. 3.41 couplings are designed to
withstand or close up three-phase fault or out-of-phase synchronizing without damage. The highest
torque under these conditions (typically 4-5 times full load torque) occurs at the generator/turbine
coupling.
Coupling halves are fitted together by standard coupling bolts, which fits in the reamed holes of
coupling and have cylindrical heads with an internal hexagon for tightening. Coupling bolts are recessed
into the coupling to cut down windage loss and noise.
To prevent the rotor distortion, turning gear mechanism is employed with the turbine to rotate the
turbine shaft at low speeds, as specified by design, during start-up and shutdown of turbine.
Manual control of the motor is provided in the control room and automatic stop and start facilities
based on the turbine speed are also included in the motor switchgear. LMW design turbines are equipped
with this type of arrangement (3-4 rpm speed).
The unstable shaft is likely to develop a 'bow' in service, producing out of balance forces and
consequential vibration.
Static Balance: This indicates that the weight is evenly disposed around the axis of the shaft. It can be
checked by rolling the rotor on horizontal knife-edge supports.
Dynamic Balance: This means that the moments of the out of balance weights along the axis about
either bearing nullifies to zero. This is checked by spinning the rotor on resilient bearings, detecting the
vibration. The correction is made by adding or subtracting weights until the vibration is negligible. HP &
IP rotors are normally balanced at low speed (400 rpm) in balancing tunnel. A modern balancing machine
enables balancing to be carried out with a high degree of accuracy and eliminates to a large extent the
trial and errors processes used earlier. The balancing weights, as calculated by machine, are adjusted in
two convenient planes, one at each end of the rotor. This adjustment may be by varying screwed plugs in
tapped holes, or by adding balance weights at specific circumferential positions. T-slots are machined
circumferentially in the periphery of the rotor front and rear half-coupling flanges to permit the weights to
be positioned and retained.
The purpose of balancing is to reduce the amplitude of vibration to a tolerable level, which can be
taken to be about 25 µm at the bearing pedestals.
The larger LP rotors and generator rotors having critical speeds below running speed are over-
speeded (above rated speed) and, if necessary, balanced in the fully bladed condition in a vacuum
chamber, where they can be run without being overheated due to windage.
This critical speed is either above or below running speed, depending on rotor construction. If the
critical speed is below, the shaft is regarded as flexible. On the other hand if critical speed is above the
running speed, the shaft is regarded as rigid. In case of flexible shaft rotors, care must be taken during
start-up to ensure that the critical speeds are passed as quickly as possible.
The other factor on which critical speed depends is the rotor length and rotor diameter. Critical
speeds decrease with increased rotor length and with reduction in rotor diameter. The present trend in
modern turbine designs is to provide a rigid rotor (critical speeds above running speed).
In case the rotor length is required to be increased for accommodating number of moving blade
stages in large units, rigidly is accomplished by increase in rotor diameter.
The rotors of large machines are joined by rigid coupling (tandem compounded arrangement), so
that the composite shaft joining four rotors including generator rotor, has to be treated as a whole
assembly. Each rotor is supported on two bearings, which are not simple supports. The calculated
critical speeds of a complete shaft line are the functions of bearing flexibility, expressed as the deflection
of an equivalent spring under the static load upon the bearing. In case of such rotor arrangement, some
critical speeds are below and some are above the running speed. However, care is taken while designing
that no critical speed should fall in the range of + 20% of normal running speed.
The insulation consists of upto 150 mm thickness of glass wool or mineral wool which is applied
either as fiber mattresses or sprayed on as loose fibers with a binder to set them in position. The
thickness is largely dependent on the temperature of the surface to be covered, enough insulation being
o
used to reduce the outside temperature to about 50 C. Asbestos was used extensively for sprayed
insulation in the past, but all modern insulation is asbestos-free, because of the health risk of inhaled
asbestos fibers.
The mineral wool is held in position firmly by wire mesh, which covers it and is attached to studs
welded to the outer casing and passing out through the mineral wool. If the mineral wool is thicker than
100 mm it is applied in two layers with an additional wire mesh support between them. The outside
surface wire mesh is finally covered with 6-8 mm of cement followed by a thin coat of oil proof and
waterproof sealant. A glass-reinforced plastic may be used as the sealant to provide suitable mechanical
strength and life.
It is essential that oil is not allowed to enter the lagging through gaps or damage to the covering,
as hot oil-soaked lagging has been responsible for some severe turbine fires.
In modern concept of steam turbine design the conventional properties such as tensile, creep-
rupture are not only important, but the properties like fracture toughness, rate of crack growth are also
very important for evaluation of life of the components for non-base load turbine operation.
Metallurgical considerations besides the design requirements are of utmost importance in the
selection of materials in order to have greater reliability and good service during operation. The
metallurgical considerations are alloying elements and their effect on structure, heat treatment, weldability
and creep resistance characteristics. The other metallurgical considerations at elevated temperature are
microstructure stability, inter-crystalline corrosion, and embrittlement phenomenon.
♦ Physical properties:
a) Thermal coefficient of expansion
b) Thermal conductivity
c) Modulus of elasticity
d) Poisons’ ratio
e) Density
♦ Mechanical Properties:
a) Hot yield (0.2% Proof Stress)
b) Creep and rupture
c) Relaxation properties
d) Cyclic loading behaviour
e) Fatigue behaviour
f) Fracture toughness
g) Rate of crack growth
h) Resistance to scaling
The physical properties are important for selection of material for the components working at
elevated temperature. The thermal conductivity is important for quick dissipation of heat in components in
order to minimise thermal stresses. Thermal coefficient of expansion and the modules of elasticity are
important because these play an important role in inducing thermal stresses and ensuring the design
clearance and the minimum values are favourable.
♦ Hot yield:
For components, which are working at moderately elevated temperatures but not in the creep
range, the hot yield is being taken into consideration for design. The hot yield is determined from the
o
stress-strains relationship at 650 C. The components are designed for stress occurring at 0.2% strain.
The hot yield of a steel decreases with an increase of temperature is as shown in Fig. 3.42.
The creep rupture data are generated for 100,000 hours. The stress required for causing 1%
creep is 100,000 hours and corresponding rupture stress are considered to evaluate material behaviour of
the steam turbine components.
The relaxation of stress in bolted joints may lead to loose joints and subsequent leakage. This
requires re-tightening of bolts. Similarly, due to stress relaxation, the shrunk fitted assemblies (e.g. disc
on rotor shaft) will become loose. Hence the material selected for above applications must have high
stress relaxation resistance. Also the stress relaxation data is required for the designing of bolts and
flanges, which is generated upto 30,000 hours at different temperatures.
♦ Fatigue Properties:
The fatigue behaviour of material is described under alternative cyclic stress and the fatigue curve
is drawn between stress Vs. number of cycles and this is known as S-N curves (Fig. 3.44).
Zone I is also referred as low cyclic fatigue zone and zone – III is termed as high cycle fatigue zone.
Low cyclic fatigue behaviour of material is determined to know the number of cycles to initiate a
crack in a material. This data is being used for estimation of life of the components. High cyclic fatigue
7
test is performed for determination of endurance limit for 10 cycles.
♦ Resistance to Scaling:
The components, which are working at elevated temperature, may be subject to scale formation.
It is very important factor because the excessive scaling of components (e.g. tubes) carrying high
pressure steam can significantly reduce the effective thickness, so that remaining metal is overstressed
and may burst. W hen oxide scales tightly adhere to the surface, they sometimes act as insulating film,
thereby reducing heat transfer rates. The scale can accumulate at loops and plug tubing and pipeline or
they can be carried into downstream equipments can cause damage to turbine blades. Notches may also
be developed due to preferential oxidation, which may cause steel to behave in a brittle manner.
♦ Blading Materials:
12% Cr. Stainless steels are used generally for LP turbine blading because of superior material
damping. Turbine blading alloys are chosen for their ability to provide properties peculiar to the
mechanical and environmental service, which they must endure. Some of the considerations for LPT
blading are –
- Corrosion and scaling resistance
- Adequate tensile strength to withstand steady centrifugal and bending stresses
- Impact strength to resist erosion and impact loading
- Material damping to cope up with vibratory stress developed in turbine blades.
The conventional 12% Cr steels have an ideal set of properties as described above for turbine
o
blading as long as temperature does not exceed about 480 C. Austenitic steels have been tried but, in
general, have not been satisfactory, except for the short blades of HP turbine where damping capacity is
not as crucial as it is for longer blades in the later stages of LP turbine.
For the shorter blades working at high temperature for HP turbine, the mechanical properties
have been improved by the addition of molybdenum and vanadium and suitable heat treatments to give
adequate creep resistance. Further the addition of nibolium to the 12% Cr MoV steels increases the
stress rupture strength and creep strength in the short term.
The other material, which is developed, is Titanium, which has high strength to weight ratio and
excellent corrosion resistance. Titanium is considered as an alternative to 12% Cr steel for low-pressure
turbine blading. Since the density of titanium is about 60% of the steel, a titanium blade nearly 40%
longer than the steel blade can be substituted, assuming comparable stress levels in the blade root.
The yield strength of a typical titanium alloy in the annealed condition is approximately 50% better
than standard 12% chromium stainless steel. However, the titanium alloy is not as readily forgeable as
12% Cr steel Further Titanium alloys are very active chemically at high temperatures, surface
contamination is another problem encountered when forging. Also further, this material has poor vibration
characteristics and higher cost as compared to 12% Cr steel. In view of these limitations, titanium is not
popularly used for blading but generally used for lacing wire and for cover banding and shrouding.
Though the best possible creep properties are required on both HP & IP rotor forgings, smaller
dimensions of HP rotor as compared to IP rotor simplify the HP problem. The IP rotor poses a serious
problem, especially in turbines employing a reheat cycle. Full steam temperature is encountered on discs
at the IP inlet stages, which have larger diameters and blades than equivalent stages on the HP rotor
exposed to steam at the same temperature. Both at the rim and the bore, the stresses are such that
steam cooling may be necessary, even with steels having best creep properties.
The reduced temperatures encountered at the last two stages of the IP turbine are offset by
increased bore stress due to the longer blade length, which demands an adequately high proof strength.
This is achieved by the use of 1 Cr – 1 Mo – 0.25 V alloy steel.
♦ LP Rotors:
LP rotors work in low temperature zone & have longer blades and diameter due to which they
encounter the impact of moisture in the last stages. Hence the main requirements of these rotors are high
tensile strength combined with high toughness.
The 3.5 Ni Cr MoV monobloc rotor forging is currently used as it avoids the complication of shrink
fits in the case of built-up rotors. The use of vacuum degassed ingots and the use of larger hydraulic
presses capable of such forging operations, have all contributed to a marked improvement in quality of
large LP rotor forgings. Vacuum degassing has eradicated the former problems of hydrogen
embrittlement cracking and gives good fracture toughness.
Ni Cr MoV steel containing upto 3.5% Ni has been used for both shafts and discs for built-up LP
rotors and is the first choice to achieve the tensile properties necessary for larger monobloc rotors.
High temperature bolts are made from low alloy steels designed specially for creep-resistant bolting. The
nickel alloys are more creep-resistant and stronger, allowing a more compact flange with better thermal
properties; however, they are subject to stress corrosion cracking, particularly if wet or contaminated with
sulphur compounds. Nickel alloy bolts are thus used mainly on inner cylinders where the compact flange
is most advantageous.
Low temperature bolts on LP casings are made from normal high tensile bolting steels.
-o0o-
The turbine is built on the well-proven design philosophy of "Modular Principle" in steam turbine
engineering field. The readily designed HP, IP & LP turbine modules are combined and sized to required
power output (120 MW , 210 MW , 250 MW and 500 MW capacity), as demanded by the customer. Steam
parameters and cycle configuration are designed to give most economical turbine set. This
maneuverability is achieved without imposing the reliability of the modules, which is governed by the
shape and configuration of rotors, cylinder and distance between the bearings.
For 210 MW design, the turbine comprises of modules H 30-25 for HP turbine, M30-20 for IP
turbine, and N 30- 2x5 for LP turbine. These modules incorporate the design and construction features,
which have proved their reliability in service and ensure trouble free operation over long operating periods
and at the same time ensuring high thermal efficiencies. All the materials used for manufacture of various
parts are most suitable for the duty required and have been selected after exhaustive research and long
experience.
Fig. 4.1 shows the sectional arrangement of 210 MW KW U Steam Turbine and Fig. 4.2 illustrates
the outline drawing with dimensions.
The turbine is of tandem compound design with separate HP, IP& LP cylinders. The HP turbine is
of single flow type while IP & LP turbines are of double flow type. Rigid couplings connect the individual
turbine rotors and the generator rotor.
The turbine is condensing type with single reheat. It is basically engineered on reaction principle
with throttle governing method. The fixed blade and moving blade stages are arranged in HP, IP & LP
turbines, driving the 210 MW AC generator.
The HP cylinder has throttle control valves. Steam admission circuit is shown in Fig. 4.3. The
main steam is admitted before the blading by two combined main steam stop and control valves. The
lines leading from the two HP exhaust branches to the reheater are provided with swing check non-return
valves (CRH NRVS), which prevent hot steam from the reheater flowing back into the HP turbine when
turbine is tripped.
The steam coming from the reheater is admitted to the IP turbine via two reheat stop and control
valves. The exhaust of IP turbine is connected to LP turbine via two cross-around pipes laid at floor level.
Penultimate stages of shaft gland seals are provided with steam at regulated pressure from gland
steam header whereas the last stages are connected to gland steam cooler.
LP Turbine
IPTurbine
Sectional Views from Fig.4.2
Although HP inner casing is with a horizontal split joint, yet it acts like a thin thermal membrane.
As the inner casing is not subjected to large pressure drops across the wall, the horizontal flange joint and
bolts are made of thin sections thus permitting large transverse temperature changes. Inner casing is
kinematically supported within the outer barrel.
The barrel type casing permits flexibility of operation in the form of short start-up times and a high
rate of change of load even at high initial steam conditions.
IP inner casing is kinematically supported within outer casing. IP inner and outer casings are
suspended from top halves so as to totally eliminate the effect of TG centre line with the heating of
flanges. Although the casings are of horizontal split design yet these do not impose any constraints in
start-up period and rapid load changes.
The reheated steam is admitted to the inner casing through the top and bottom centre of the
casing. The arrangement of an inner casing confines the high steam inlet conditions to the admission
branch of the casing, while the joint of the outer casing is only subjected to the lower pressure and lower
temperature at the exhaust of the inner casing.
The casing of the double flow LP cylinder is of three-shell design. The shells are axially split and
of rigid welded (fabricated) construction. The inner shell taking the first rows of guide blades is attached
kinematically in the middle shell. Independent of the outer shell, the middle shell is supported at four
points on longitudinal beams. Two rings carrying the last guide blade rows are also attached to the
middle shell.
Special design measures have been adopted to remove the moisture from last stages by reducing
the thickness of water film on guide blades. The axial clearances between guide blades. The axial
clearances between guide and moving blades have been so chosen so as to reduce the droplet sizes and
erosion of leading edges. Low-pressure extraction has been optimized not only from thermodynamic
considerations but to effectively drain out moisture also. Free standing blades (without lacing wire) have
been envisaged. The blades are designed to operate in the speed range corresponding to 47.5 to 51.5
Hz grid frequency.
After they have been fitted in the rotor groove, they are caulked into position with brass wire. The
blade roots are made of appropriate size to give the required blade spacing, and hence the designed
width of blade passage, and hence the necessity of spacer-pieces.
Fixed blades are of the same type as the moving blades with an inverted T-root and integral
shroud. In medium and low temperature regions, the fixed blades are made of solid drawn material with
brazed on or loose spacer pieces and have a hook-type root (Fig. 4.4(b)). In this case the shrouding is
separate and riveted in place.
b) LP Turbine Blades :
The fixed and rotor blades of the first few stages of the LP turbine are similar to the IP turbine
blades. However, the last three stages of the LP turbine have twisted blades as shown in Fig. 4.5 (a) &
(b). The difference between the circumferential velocity at the rotor blade root and tip is quite
considerable and is taken into account by twisting the blade along its length. The rotor blade fastening is
of the fir-tree type (Fig. 4.5(c),(d)), which engages in milled axial grooves in the rotor and is then secured.
The fixed blades of the last two stages are hollow. They are fabricated from sheet steel and slots
are provided in the blade surface through which any water passing over the surface of the blades may be
drawn away to the condenser. The trailing edge of the blades is very thin in order to avoid any patches
and the formation of streams of water. The axial distance between the final stages is kept at optimum
value to facilitate the break-up of any water droplets, which may still remain. This will reduce the relative
velocity between the droplets and the leading edges of the moving blades.
The leading edges of the final stage rotor blades are flame hardened to give protection against
erosion.
These blades are free-standing and have neither lacing wire nor shrouding. Great attention is
paid at the design stage to achieve a resonance free operation with long life.
The complete rings of shrouding on all rotor blades and on guide blades in high temperature
sections are built-up from the individual sections of shrouding which are machined integrally with each
blade and fitted to butt tightly together. In the case of guide blades for medium and low temperature
sections, the shrouding is riveted onto the blades. When the rotors and guide blade carriers have been
completely bladed, the blading is skinned on a lathe, the steps being machined on integral shrouding or
the rivet heads machined flush on riveted shrouding at the same time.
Various arrangements of tip sealing employing these rows of sealing strips, as shown in Fig. 4.6,
are used. The number of rows of sealing strips chosen depends on the stage pressure and the differential
axial expansion between the rotor and casing at the particular section of blading involved.
The sealing strips, which are caulked into the casing and shaft opposite the blade shrouding, are of
stainless steel. On one hand, they are strong enough to withstand the maximum pressure which will exist
across them on the other hand, the amount of heat generated by them and transmitted to the rotor or
casing in the event of their rubbing shall not be sufficient to cause deformation of the component.
The sealing strips are easy to replace. If the sealing strips wear out due to contact between fixed
and moving components (rubbing) at any time, then the worn out strips could be replaced with new one
within a short time to restore correct clearances at the next overhaul.
4.1.7 Valves
The HP turbine is fitted with two combined emergency stop and control valves. A stop and control
valve fitted in a common body with their spindles arranged at right angles to each other and in the same
plane. The stop valves are spring operated single-seat valves and similarly control valves also of single-
seat design having diffusers to reduce pressure losses. The two valves operate with two separate
servomotors independent of each other.
The IP turbine has also two combined reheat stop (IV) and control valves. The reheat stop valves
are spring-loaded single-seat valves. The control valves, also spring loaded and single seat design, have
diffusers. The control valves operate in parallel and are fully open in the upper load range. In the lower
load range, they control the steam flow to the IP turbine and ensure stable operation even when the
turboset is supplying only the station load.
Throttle governing method is adopted to regulate the turbine load. Both the emergency stop and
reheat stop and their control valves are supported kinematically on the foundation ceiling below the
machine floor before the turboset. Individual oil hydraulic servomotors actuate all valves.
The HP rotor is supported by two bearings, a double-wedge journal bearing at the front end of the
turbine and a combined journal and thrust bearing directly adjacent to the coupling with the IP rotor. The
IP and LP rotors have a journal bearing each at the end of the shaft. The combined journal and thrust
The front and rear bearing pedestals of the HP turbine are placed on base plates. The pedestals
of the LP turbine are fixed in position, whereas the front pedestal and the pedestal between the HP and IP
turbine are able to move in axial direction to permit free longitudinal expansion of HP and IP turbine
casings.
The brackets at the sides of the HP and IP cylinders are supported by the pedestals at the level of
the machine axis. In the axial direction the HP and IP casings are firmly connected with the pedestals by
means of casing guides, without restricting radial expansion. Since the casing guides do not yield in
response to axial displacement, the HP and IP casings as well as the associated bearing pedestals move
forward from the front LP bearing pedestal on thermal expansion.
The turbine gear assembly is located in the front bearing pedestal of LP cylinder and consists of
two rows of moving blades mounted on coupling flange IP turbine rotor, an inlet nozzle box with stationary
nozzles and guide blades. The turbine-generator shaft system is rotated by the double row wheel which
is driven by pressure oil supplied by the auxiliary oil pump. After passing through the blading, the oil
drains to the bearing pedestals and combines with the bearing lube oil returning to the main oil tank.
In addition, shaft system is equipped with facility for manual barring in the event of failure of
hydraulic turning gear.
As discussed above, high speed (160 rpm) hydraulic turning gear is envisaged to ensure uniform
and rapid heating and cooling of the casings and rotors during start-up and trip out respectively. The
turning gear is located on IP coupling flange, between IP and LP turbine coupling. As there is no
mechanical contact between the hydraulic turning gear and shat, the likelihood of a break-down is far less
than mechanical types employing disengaging gears, interlocks and checking devices.
An electric system measures and controls speed and output, and operates the control valves
hydraulically in conjunction with an electro-hydraulic converter. The electro-hydraulic governing system
permits run-up control of the turbine upto rated speed and keeps speed swings at low level following the
sudden load shedding.
The main oil pump located in the front pedestal and directly driven by HP turbine shaft draws oil
from the main oil tank via injector, during normal operation of turbine. However, during start-up and
shutdown, Auxiliary Oil Pump (AOP) driven by AC motor maintains the oil supply. Before starting the
2
turning gear, a jacking oil pump forces high pressure (120 kg/cm ) oil under the shaft journals to lift the
shaft. This is in order to prevent boundary layer lubrication and metal-to-metal contact. The lubricating
and cooling oil is passed through water-cooled oil coolers before being supplied to the bearings.
Two AOPs, one EOP (DC motor) and two JOPs are mounted on the main oil tank.
The installation of KW U design 210MW turbine is shown in Fig. 4.8. The fixed points of the
turbine are as follows:
i) The bearing pedestal between the IP and LP turbines. From this point the IP and HP casings
expand towards the front bearing pedestal of the HP turbine.
ii) The rear bearing housing of the LP turbine (LP/Generator bearing pedestal)
iii) The middle portion of each longitudinal girder of LP turbine. From these points the longitudinal
girders expand in both the directions (Turbine side and Generator side).
iv) The thrust bearing in rear bearing casing of HP turbine.
The outer casing of the LP turbine is located axially by fitted keys at the middle of their
longitudinal beam members. Free lateral expansion is allowed. The centre guides for these longitudinal
beams are recessed in the foundation. There is no restriction on axial movement of the casings. At the
front and rear supports of the longitudinal beam members the casing is free to expand horizontally in any
direction. Hence, when there is a temperature rise, the outer casing of the LP turbine expands from its
fixed point towards IP turbine and generator, as shown in Fig.4.9. Differences in expansion between the
outer casing and the fixed bearing pedestals to which the housings for the shaft glands are attached, are
taken by shaft seal compensators (expansion bellows).
The LP turbine rotor is displaced towards the generator by the expansion of the shafting system
from the thrust bearing. The magnitude of this displacement due to expansion, however, is reduced by
the amount by which the thrust bearing is moved in the opposite direction by the casing expansion of the
IP turbine.
Differential expansion between the rotor and casing of the LP turbine results from the difference
between the expansion of the shafting system originating from the thrust bearing and the casing
expansion originating from the fixed point of the LP turbine casing on the longitudinal girder.
-o0o-
• HP Turbine : 7t
• IP Turbine : 13.3 t
• LP Turbine : 43 t
c) Rotor Lengths
• HP Turbine : 3905 mm
• IP Turbine : 4145 mm
• LP Turbine : 6300 mm
d) Casing W eights
• HP Outer Casing : 25 t
• HP Inner Casing : 7.9 t
• IP Outer Casing : 24.8 t
• IP Inner Casing : 15.4 t
• LP Inner Casing : 9.85 t
• LP Inner-outer casing : 16.16 t
• LP Outer casing
i) Upper half : 17 t
m) Coupling
• HP – IP : Rigid
• IP – LP : Rigid
• LP – Generator : Rigid
o) Moments of Inertia
2
• HPT rotor : 316.94 kg m
2
• IPT rotor : 1155.59 kg m
2
• LPT rotor : 9794.13 kg m
• At HPT exhaust
2
100% load : 38.1 Kg/cm (abs)
2
80% load : 31.0 kg/cm (abs)
• At IPT exhaust
2
100% load : 7.05 Kg/cm (abs)
2
80% load : 6 kg/cm (abs)
2
• At LPT exhaust : 0.0911 Kg/cm (abs)
b) Steam Temperatures
o
• At inlet of ESV : 535 C
o
• At inlet of IV : 535 C
• At HPT exhaust
o
100% load : 334.8 C
o
80% load : 328.1 C
• At IPT exhaust
o
100% load : 314.5 C
o
80% load : 316 C
o
• At LPT Exhaust : 45 C (approx.)
• Vibration
Bearing Shaft
Nominal value for alarm : 35 µm 90 µm
Maximum value alarm : - 120 µm
Limit value for machine shutdown : 45 µm 200µm
• Bearing temperatures
o
Alarm at : 90 C
o
Machine must be shutdown at : 120 C
• Casing temperatures
o
HPT exhaust temperature alarm at : 480 C
o
Machine must be tripped at HPT exhaust temp: 500 C
o
LPT outer casing temperature alarm at : 90 C
o
Machine must be tripped at LPT exhaust temp : 110 C
Difference between upper & lower casing
o
sections at HPT middle : + 30 C
Difference between upper & lower casing
o
sections at IPT front & rear : + 30 C
b) Blades
Turbine Area First Stage Last Stage
i) HP Moving blades X 22 Cr Mo V 121 X 20 Cr 13
ii) HP stationary blades X 22 Cr Mo V 121 X 20 Cr 13/
X 20 Cr Mo 13
iii) IP moving blades X 22 Cr Mo V 121 X 20 Cr 13
iv) IP Stationary blades X 22Cr Mo V 121 X 20 Cr 13/
X 20 Cr Mo13
v) LP moving blades X 20 Cr 13 X 20 Cr 13
vi) LP Stationary blades 20 Cr 13/ 20 Mn 5/
X 20 Cr Mo 13 X 7 Cr AL 13
5.8 Emergency Main Stop Valves (ESV), Strainers & Control Valves
a) Number off : 2
b) Nominal diameter of ESV :φ 160 mm
c) Type : Single seated
2
d) Maximum pressure drop across the : Approx. 8 kg/cm (including
Valve assembly strainer, stop and control valve)
e) Material for construction
i) Valve body : GS-17 Cr Mo V 511
ii) Valve trim : Stellited
iii) Seats : Stellited
f) Mesh screen material for strainer : X 8 Cr Ni Nb 16 13
g) Maximum particles size, which will
Pass the screen : 1600 microns
h) Nominal diameter of HP control valve : φ125 mm
and type Single Rated
i) Sequence of opening control valves : Both control valves open together before
IP control valves.
j) Material of HPCV
i) Valve body : GS-17 Cr Mo V511
ii) Trip : Stelliited
iii) Stem : X 22 Cr Mo V 121 (Stellited)
-o0o-
HP TURBINE CONSTRUCTION
6.1 Design Features
The principal parts of the HP turbine are axially split type inner casing (guide blade carrier,
enclosing the rotor), and an outer casing of a barrel type construction. Sectional view of HP turbine is
shown in Fig. 6.1. As the barrel type casing has neither axial nor radial flanges, mass accumulations and
thus undue stresses are avoided. This result into almost complete rotational symmetry, also the wall
thickness can be kept moderate and equal in all parts. Thus, even with rapid temperature changes and at
high pressures, the barrel type casing has a stable shape, i.e. deformation is prevented.
By incorporating the steam admission side shaft seal portion into the inner casing, the number of
parts to be assembled and with them the efforts involved in assembly and alignment are reduced. Due to
The attachment of the inner casing allows the casing to expand radially in all directions
independently of the casing inlet section and axially from a fixed point. A threaded ring fixes the inner
casing in the axial direction. As the combined journal and thrust bearing on the inlet side is also the rotors
fixed point, the inner casing and rotor shaft expand in the same direction, which makes small axial
clearances inside the turbine possible. The radial centering of the inner casing on the inlet side is
accomplished in 4 inner casing projections, which engage with matching grooves in the casing inlet
section and are provided with sliding pieces (fitted keys). On the exhaust side, the inner casing is
supported accordingly and guided by two projections.
The space between inner casing and barrel casing is filled with inlet steam during operation,
allowing fast warming and start-up.
The above design features of barrel type turbine with an integral exhaust section results in
simplification in fabrication, assembly and inspection. Also it results in improved operational behaviour of
machine.
The supporting arrangement of HP cylinder is shown in Fig. 6.2. The casing (3) is supported on
two front brackets and two rear brackets in the plane of the machine axis on the bracket supports of the
bearing pedestals (2,4). This arrangement determines the height of the casing and also allows thermal
expansion to take place in the horizontal plane by the brackets sliding on the places (12) of the bearing
pedestals (2,4).
To prevent lifting of the turbine, casing (3), (Ref. Fig. 6.3) the brackets projecting into
corresponding recesses in the bearing pedestals are held by Cap (10). W hen the turbine is being
erected, a clearance "S" is kept between the disc (11) and bracket projection of the turbine casing (3).
6.2.2 Guides
The central location of the turbine casing at right angles to the machine axis is provided by the
guides shown in detail–A of Fig. 6.3. These guides allow the turbine casing to expand freely in the vertical
plane. In addition, the HP turbine casing guides join the casing and the bearing pedestal which follows
any axial expansion of the casing and slides on the base plate (1).
i) The inner casing, which is axially split in vertical plane which carries fixed blades and encloses
rotor. This is shown as part (4) in Fig.6.1.
ii) The outer casing designed as a barrel type without axial joint and with integral exhaust section.
The barrel casing (3) encloses the complete assembly of inner casing with rotor.
The guide blade carrier is almost cylindrical in shape as the horizontal joint flanges are relieved by
the higher pressure arising outside, and thus can be kept small.
On admission side, four projections of the guide blade carrier (4) and on the exhaust side two
projections fit into corresponding grooves in the barrel casing (3), as seen from Fig. 6.6 in section E-E and
section B-B respectively. In the horizontal plane these projections rest on fitted keys (12) as shown in
Section B-B and detail G. In the vertical plane they are guided by fitted keys (11) Section E-E. These
sliding contacts make it possible for the guide blade carrier to be exactly guided into the vertical and
horizontal planes.
As shown in Fig.6.7, the axial fixed point of the guide blade carrier is provided by a shoulder in the
barrel type casing (3) against which a collar of the guide blade carrier (4) rests. A ring (5) with a buttress
thread holds the guide blade carrier in the guide blade carrier in the barrel casing (4). As the combined
The axial thrust to which the guide blade carrier is subjected is transmitted to & absorbed by the
threaded ring (5) via spacer ring (16).
The moving and stationary blades are inserted into approximately shaped grooves in the shaft (8)
or inner casing (1) and are bottom caulked with caulking material (9). The insertion slot in the shaft (8) is
closed by a locking blade, which is fixed either by taper pins or grub screws. Special end blades, which
lock with the horizontal joint, are used at the horizontal joints of the inner casing. Grub screws, which are
inserted from the joint into the material, secure the stationary blades in the grooves.
The rear stages (Fig. 6.10) have stationary blades with hook-type roots, which are secured in
annular grooves in the inner casing by filler pieces (2). The shrouds of these stationary blades are riveted
to the blades in sections. The moving blades of these stages have the same design as those of the front
stages.
Fig. 6.11 shows the inner casing half complete with fixed blading and Fig. 6.12 shows the rotor
assembly inserted in half inner casing.
6.4.3 Connection of Bearing Pedestal & Base Plate (Ref. Fig. 6.16, 6.17)
The bearing pedestal (1) rests on four plates (15). By slightly lifting the bearing pedestal using
number of lifting devices and jack screws, these plates can be extracted and refinished or replaced if
necessary. This allows subsequent alignment of the bearing pedestal at any time. The bearing pedestal
(1) is connected to the base plate (18) by means of clamps (19) to permit free axial expansion. The centre
position of the bearing pedestal is guaranteed by two guide pieces (16) welded to the base plate (18) and
the fitted keys (17).
6.5.3 Connection of Bearing Pedestal & Base Plate (Ref. Fig. 6.19, 6.20)
The bearing pedestal (5) rests on four plates(13). By slightly lifting the bearing pedestal using
hydraulic lifting devices and jack screws, these plates can be taken out and refinished or replaced
6.6.2 Construction
The sectional view of combined journal and thrust bearing is shown in Fig. 6.21 and 6.22. It
consists of upper and lower bearing shells (4, 12), thrust pads (6), Cap (2), spherical blocks (14, 16) and
keys (10, 17). The upper and lower halves (4,12) of the bearing shell are bolted and doweled at the
horizontal joint by means of four taper pins and four socket-head screws.
The journal bearing is constructed as elliptical sleeve bearing. The bearing liners are provided
with a machined babbit face. Additional scraping of babbit lining is neither necessary nor allowable.
In order to prevent the bearing from exerting a bending moment on the shaft, it is pivot-mounted
on spherical seat (16). The spherical block (14), with shims (13, 15), is bolted to the lower bearing shell
(12). A transverse projection in the upper part of the cap (2) and the fitted keys (3) prevent the bearing
shells from rising.
The bearing shells are located laterally by keys (10), The bearing is supported axially against the
bearing pedestal (1,9) by means of keys (17, 18) (Section H-H). This fixing is of great importance for axial
clearance in the whole turbine.
At each end of the bearing shell, thrust bearing pads (6) (Section F-F) form two annular surfaces
on which the integrally machined shaft collars rotate. These collars and thrust pads permit equal loading
of the thrust bearing in either direction. As shown in Section N-N, the thrust pads are of the tilting type,
secured in place by pins (23) and flexibly mounted on split backing rings (21).
Oil leaving the journal bearing flows to the two annular grooves adjacent to the bearing surface
and then to the thrust pads (6). Through the two oil return cowlings (5), oil is discharged into the drain
area in the pedestal (9).
Passages are located at the lowest point in the lower bearing shell through which high pressure
jacking oil is supplied under the journal at low speed of the turbine rotor during start-up and shutdown.
Thus dry friction is prevented and the breakaway torque on start-up with turning gear is reduced.
As shown in Fig. 6.20 and detail-C, high pressure oil "a" flows under the journals via the oil line
and via openings in the lower bearing shell (12). O-rings (24) located between the bearing liner (17) and
the lower bearing shell (12) prevent any oil from penetrating between the two elements.
Any oil leakage passing the seal will drain off to the bearing pedestal through a groove in the
lower bearing shell. This arrangement ensures that no oil penetrates between the bearing liner and the
bearing shell.
In order to prevent the bearing from exerting a bending moment on the rotor (5), it is pivot-
mounted in the spherical seat (14). For this purpose, the spherical block (7) with shims (12,13) is bolted
to the bearing shell (6). A projection in cap (1) with shims (9) fits into a corresponding groove in the
bearing shell (3) and prevents vertical movement of the bearing shells. Centering of the bearing shells in
the vertical plane is achieved by means of keys (8) fitted on both sides of the projection.
The bearing shells are fitted laterally by the keys (11), which are bolted to each other. Each key
is held in position in the bearing pedestal (10) by two lateral collars. The temperature of the bearing
bodies is monitored by thermocouples (19) as shown in section C-C.
As shown in detail-B, a threaded nozzle (17) is arranged at the lowest point of the lower bearing
shell (6) through which high pressure oil is supplied under the journals at low speed of turbine rotor (on
The lift oil (jacking oil) flows into the above mentioned threaded nozzle (17) through passages in
the lower bearing shell (6). A seal (18) prevents high pressure oil from penetrating the space between
threaded nozzle and ring (16) and thus prevent lifting the babbit lining. Any leakage oil can drain through
passages in the bearing shell below the ring.
i) Preliminary assembly – comprises of fitter work for making individual components ready for
assembly.
ii) Radial and axial clearances determination – an assembly device accommodating the inner
casings and shaft is used for this purpose.
iii) Installation of rotor inside the inner casing and enclosing the inner casing with barrel casing and
final inspection of clearances.
(c) Aligning the Alignment Shaft in Inner Casing (d) Installation of Inner Casing in Barrel Casing
(a) Alignment of Inner Casing in Barrel Casing Fig.6.24 (b) Fitting-in of Fitted Keys
(b) Alignment of Halved Inner casing (c) Rotor Inserted in Top Half Inner Casing
(d) Alignment of Halved Inner Casing (e) Alignment of Halved Inner Casing
(a) Rotor Placed in Bottom Half Inner Casing (b) Placement of Top Half Inner Casing
(c) Heating of Casing Joint Bolts on Inner Casing (d) Test of Radial Clearances in Assembled
condition
A journal with turning bolt is connected to the shaft for the tilting procedure assuming the tilting
blocks supporting function (Fig. 6.29(d)) when the turbine shaft is lifted.
(a) Rotor Enclosed in Inner Casing (b) Mounting of Support for Inner Casing
(c) Mounting of Support Rings on Inlet Side (d) Turning of Turbine Shaft with Surrounding
Inner Casing
The turbine shaft enclosed in the inner casing is then moved over the casing inlet section and
lowered into the latter vertically (Fig. 6.30(d)). The inner casing is then aligned radially to the barrel
casing. This position is fixed by installing the fitted keys added during preliminary assembly.
Then the threaded ring is mounted in the barrel casing inlet side (Fig. 6.31(a)). It is, however,
necessary to overcome U-ring pre-stress to move the inner casing into its operating position. For this, two
compression beams are mounted on the casing inlet section of barrel casing and then the inner casing is
moved into the operating position by means of two hydraulic cylinders (Fig. 6.31(b)). The axial
dimensions are then checked and logged. The threaded ring is now tightened-up against the inner
casing sliding blocks until the marks added during preliminary assembly are matched. Hydraulic cylinders
are then depressurised and beams are removed. Three safety pieces are fitted in and placed into position
to fix the threaded ring (Fig. 6.31(c)). Finally the main steam inlet inserts and associated parallel pipes are
installed (Fig. 6.31 (d)).
HP turbine is brought in horizontal position (fig. 6.32(a)). Then the shaft seal exhaust outlet side
segments are installed next. As the two inner rings are still in the barrel casing, the sealing segments
have to be inserted. The barrel casing is therefore provided with an insertion opening into which
segments are placed with the aid of a device (Fig. 6.32(b)). Seal strip axial clearances are measured
through the mounting opening and logged. The closure segment is then mounted and secured against
turning. The installation opening is bolted closed by a closure segment, which is dowelled.
Subsequently, the one-piece casing ring, into which the shaft sealing segments are inserted,
placed into position and secured, according to the same method (Fig. 6.32(c)), is attached. The
installation opening is then similarly bolted by closure segment (Fig. 6.32(d)).
After the shaft sealing segments have been installed, the rotor is placed into its bearings at the
front and rear to allow the shaft and inner casing fixation to be dismantled. The halved support rings on
the inlet side are unbolted and removed. The four plates used for radial fixation at the exhaust end are
removed through the exit nozzles (Fig. 6.32(e)). The turbine shaft is then aligned radially and axially and
first the bottom halves of the shaft sealing covers are mounted, aligned and bolted on. Then, the radial
and axial clearances are checked in completely assembled condition (Fig. 6.32(f)).
(c) U-ring Inserted in the Groove at Inlet Side (d) Vertical Installation Turbine Shaft in the
Barrel
(c) Mounting of Safety Pieces for Threaded Ring (d) Mounting 0f an MS Inlet Pipe
(c) Mounting of Shaft Sealing Segments (d) Insertion Opening for Shaft Sealing Segments
closed
(e) Support of Turbine Shaft to inner Casing & (f) Radial & Axial Clearance Check in Completely
Centering of Inner Casing Assembled Condition
Inlet
Exhaust
Thrust Collar
th
25 Stage
Base Plate
Axial Guide Key
Front Journal Bearing Bottom Shell Mounting Combined Journal & Thrust Bearing Mounting
Stop Valve
Control Valve
Valve Seats
-o0o-
In addition, the bracket and bearing areas are not affected by the high temperature of the steam,
2
which enters at the centre, and leaves at the exhaust ends at low pressure and temperature (7 kg/cm ,
o
314 C). High temperatures occur only at the admission branches of the inner casing, while the flange
joint of the outer casing is subjected to the pressure and temperature of the steam leaving the blading (the
annular gap between inner and outer casing is filled with exhaust steam). This feature permits the flange
thickness to be designed relatively small with no need for over dimensioning the cylinder in this
particular area unlike old turbines. This has eliminated most of the operational problems encountered due
to deformation of the casing under non-steady state condition (start-up and shutdown).
The differing temperatures of the inner and outer casing require the inner casing to be located at
one point only and in all directions radially, while maintaining concentricity of the inner casing with respect
to the shaft. In order to fulfill this requirement, the inner casing, with four brackets on its upper part, rests
on the joint of the lower outer casing and carries its own lower part, which is bolted to it. Thus the casing
can freely expand in radial directions while maintaining concentricity relative to the shaft in this plane. To
locate the inner casing axially, shims are placed on both sides of front brackets (HP turbine side) of the
lower inner casing from where expansion in the axial direction originates. This does not affect radial
expansion since the brackets are allowed to move in the recesses of the lower outer casing.
This IP turbine design by KW U has been in use since 1972 for power plants and has proved extremely
successful in respect of operational behaviour and ease of maintenance.
To prevent lifting of the turbine casing (3) the brackets projecting into recesses in the bearing
pedestals are held by Cap (5) (Ref. Fig. 7.3 Section AA). W hen the turbine is being erected, a clearance
"S" is kept between the disc (6) and bracket projection of the turbine casing (3).
7.2.2 Guides
The central location of the turbine casing at right angles to the machine axis is provided by the
guides shown in details – B of Fig. 7.3. These guides allow the turbine casing to expand freely in the
vertical plane. In addition, the IP turbine casing guides join the casing and bearing pedestals into a single
unit in the axial direction by means of the keys (13). Due to this, the axial expansion of the turbine casing
initiates from the rear bearing pedestal (anchor point of IPT) (Part 4 in Fig. 7.2) and is transmitted to the
bearing pedestal (2) causing this to slide on the base plate (1).
7.3 Construction
7.3.1 Double Shell Construction
As discussed earlier, the IP turbine is split horizontally and is of double shell construction. The
construction of IP turbine is illustrated in Fig.7.4. A double flow inner casing (4,5) is supported in the outer
casing (2,3). Steam from HP turbine after reheating enters the inner casing from above and below
through two inlet nozzles (7) flanged to the mid section of the outer casing. This arrangement provides
opposed double flow in the two blade sections and compensates axial thrust. The centre flow prevents the
steams inlet temperature from affecting the support brackets and bearing sections.
In this arrangement the steam inlet conditions are limited to the inlet section of the inner casing
whereas the joint of the outer casing is only subjected to the lower pressure and lower temperature
prevailing at the outlet of the inner casing. The joint flange can thus be kept small and material
accumulations reduced to a minimum in the area of the flange. In this way difficulties arising from
deformation of a casing with flange joint due to non-uniform temperature rises, e.g. on start-up and shut-
down, are avoided.
W hile providing a tight seal, this arrangement permits the inner casing to move freely in all
directions The inlet nozzle (7) and the extraction nozzles (6) are bolted to the outer casing (2,3) (Fig. 7.5).
Inlet
Exhaust
Branches
The support bracket provided at the inner casing, lower half (5) (section H-H), project into the
recesses of the outer casing, lower half (3) and have clearance on all sides. Located on top of each
bracket is a spacer disc (11), whose upper surface has a clearance "S" to the flange face of the outer
casing, upper half (2). This clearance thus determines the lift of the inner casing.
As shown in detail "D", the inner casing is located axially by the fitted keys (10) arranged on both
sides (front side) of the supports brackets of the inner casing, lower half (5). Thermal expansion in the
axial direction originates from these points and so the inner casing expands axially in the rear direction.
Radial expansion is not prevented by these fitted keys as they can slide in the recesses of the outer
casing, lower part.
In the vertical plane, as shown in detail "B" (Fig. 7.4, 7.7), two centering pins (14) each are fitted
in the upper and lower half of the outer casing and in bushings (15) and are anchored in T-blocks (16)
The moving and stationary blades are inserted into approximately shaped grooves in the shaft (8)
or inner casing (1) and are bottom caulked with caulking material (9), the insertion slot in the shaft (8) is
closed by a locking blade, which is fixed either by taper pins or grub screws. Special blades, which lock
with the horizontal joint, are used at the horizontal joints of the inner casing. Grub screws, which are
inserted from the joint, secure the stationary blades in the grooves.
The rear stages (Fig. 7.9) have stationary blades with hook-type root, which are secured in
annular grooves in the inner casing by filler pieces (2). The shrouds of these stationary blades are riveted
to the blades in sections. The moving blades of these stages have the same design as those of the front
stages.
The sealing between the rotating and stationary elements of the turbine is achieved by means of
seal strips (6), which are caulked into the individual sealing rings (3) and into the shaft (4) (Detail "D").
The prevailing pressure is reduced by converting the pressure energy into velocity energy, which then
passes the large number of strips. The steam space are connected as follows:
2
P: It is connected to seal steam hender maintained at 0.011g/cm pressure by seal leak off steam
Valve.
R: It is connected to the header of gland steam cooler maintained under vacuum.
Sealing Rings :
The sealing rings (3) (Fig.7.10), the number of which depends on the pressure drop required, are
divided into several segments as shown in section A-A (Fig.7.11). These segments are mounted in T-
grooves in the inner steam seal casing (2) and outer steam seal casing (5), respectively; to allow radial
movement. Each segment is held in position against a shoulder by two coil springs (8) so that a fixed
reference for the clearance of the shaft is provided. Should the shaft come into contact with the strips in
the segments, the affected segments will move away radially. A possible slight contact between the shaft
and the thin strips (6), which generate only a small, amount of heat which cannot lead to deformation of
the shaft (4). During a cold start or warm start, the sealing rings naturally heat-up more quickly than the
casing. The outer sealing strips are arranged in easily removable casing (5) to enable the labyrinths of
these rings to be checked without the turbine casing being opened.
Hydraulic turning gear is located in bearing pedestal between IPT & LPT (Fig 7.12). The manual
turning gear is also provided that enable turning af the shaft by hand. It may be operated to start the
turbine rolling or to rotate the shaft assembly through a specific angle.
During turning gear operation, the shaft system is rotated by a double-row blade, which is driven
by oil supplied by the auxiliary oil pump (AOP). However, to overcome the breakaway torque during start-
up and to prevent dry friction, the shaft is lifted off the bearings by means of jacking oil (from JOP) which
is introduced from the bottom of the bearing.
As said earlier, the oil passes via a check valve into the nozzle box (3) (Fig 7.14) and then into the
nozzles (6) which guides the oil jet in front of the blading (7,8). In order to reduce the gap leakage losses
at the moving blades (8), sealing strips (11) are caulked into the nozzle boxes (3). After passing the
blading, the oil drains into the bearing pedestal and flows along with the bearing oil into the return flow
piping.
This mechanism consists of a gear machined on the rim of the turning gear wheel (10) and pawl
(6) as shown in Fig. 7.15. This pawl engages the ring gear & turns the shaft system when operated by
means of a bar attached to the lever (1). The pawl (6) is shown disengaged and the lever (1) resting
against a stop. The lever (1) is held in position by latch (7).
Manual turning gear is operated by first removing cover (2), unlatching at (7) and by attaching a
bar to the lever (1).Barring of lever(1)will rotate the combined turbine generator rotor.
After barring has been completed, return lever (1) and pawl (6) to the position shown in Fig. 7.15.
Then secure the lever (1) by means of latch (7) and replace cover (2). The barring gear may only be
operated after the shaft system has been lifted with a jacking oil pressure.
During the first stage of assembly, the individual casing sections must be prepared for assembly
in a preliminary stage involving nearly all the necessary touching.
The inner casing alignment with the outer casing is illustrated in Fig. 7.16(a,b,c,d). As a first step,
the individual casing sections must be prepared for assembly in a preliminary stage involving almost all
the required matching-up and fine fitting work, also installing the shaft seal retaining rings in the outer
casing and inserting the casing bolts.
• Fig. 7.16 (a) shows the setting of the bottom half outer casing down on four preponed trestles and
aligning it using a water level (Fig. 7.16(b)).
• Insertion of the eccentric bushings and centering pins in the outer casings and the sliding pads in
the bottom half inner casing.
• Installation of the bottom half inner casing (Fig. 7.16(c)) engaging its lugs in the recesses in the
outer casing (Fig. 7.16 (d)).
• Dummy shaft is placed for the alignment of casings as shown in Fig. 7.17(a). The dummy shaft is
set down on alignment pedestals, which can be shifted vertically and horizontally (Fig. 7.17(b)).
Inductive position sensors are fitted to the shaft to measure the concentricity of shaft at several
• Mount the top-half inner casing (Fig. 7.17(c)), taking care to ensure that the increased load on the
substructure does not cater the alignment of the turbine. Once the position becomes correct,
align the inner casing. For this purpose, two centering measurement relative to the outer casings
and three centering measurements relative to inner casings along the length of the inner casing
are taken (Fig. 7.17(d)).
• Having completed radial alignment using provisional spaces, establish the final thickness of the
shims required to establish the horizontal location of the inner casing.
• Before mounting the top-half outer casing, install the sliding pads in the casing guide (Fig.
7.18(a)) and secure them from sliding out by means of a set screw (Fig. 7.18 (b)).
• Place the top-half outer casing, as shown in Fig. 7.18(c). Check the horizontal alignment once
again with the water level and ensure the concentricity of the inner casing by means of the
inductive sensors.
• Insert the eccentric bushings and centering pins for the inner casing guide (Fig. 7.18(d)), and
adjust the eccentric bushings and pins for proper concentricity (Fig. 7.19(a)).
• Having corrected the concentricity, attach the shaft seal cover (Fig. 7.19(b)). The position of the
holes has already been checked at the preliminary assembly stage.
• Using the inductive sensors mounted on the dummy shaft, align the shaft seal cover to a
concentric position (Fig. 7.19(c)), and bolt it in place.
• Align the shaft in the radial plane and adjust it to the desired position in the axial plane (Fig.
7.20(b). Then check the axial clearance in the blading using block gauges (Fig. 7.20(c)).
• Check the radial clearances in the blading between shaft and bottom-half inner casing with a
feeler gauge (Fig. 7.21(a)).
• Then measure axial & radial clearances at the shaft seal (Fig.7.20 (d), 7.21(b)).
• Check the radial clearances in the top-half inner casing using lead wire. For this purpose slightly
lower the shaft and lay the wire on the blades and shaft seal strips (Fig. 7.21(c).
• Then carefully set down the top half inner casing. Check the clearances between inner and outer
casing by attaching plasticine to the casing contour and the cap nuts of the inner casing joint bolts
(Fig. 7.22(a)).
• Then mount the top –half outer casing briefly, raises the shaft into its operating position and then
lowers it again.
• If the clearances measured fall within the limits specified in the blading protocol, the final position
of the casing is established. In the event of deviation from the specified clearances, the relative
positions of the casing may be shifted as appropriate to the anticipated expansion of the turbine
components. Take the dimensions for the axial positioning pads and insert shims of appropriate
thickness (Fig. 7.22(d)).
(a) Bottom-half Outer Casing Placed (b) Aligning the Outer Casing with a Water Level
(c) Installing the Bottom-half Inner Casing (d) Bottom-half Inner Casing Installed in Bottom-half
Outer Casing
(c) Mounting the Top-half Inner Casing (d) Adjusting the Inductive Sensors
(c) Setting Down the Top-half Outer Casing (d) Inserting the Centering Pins for the Inner
Casing Guide
Fig.7.18 Placement of Top-half Inner Casing & Inserting the Centering Pins
(c) Axial Clearance Check on Blading (d) Axial Clearance Check at Shaft Seal
(c) Checking the Radial Clearances in the Top- (d) Inserting the Axial Shims & Measuring
half Inner Casing with Wire Calipers their Clearance to the Inner Casing
• Before final assembly, mount the angle section rings to the inlet and extraction pipe units. The
angle section rings were fitted into the inlet and extraction pipe units at the preliminary assembly
stage (Fig. 7.24(a)). Check the concentricity of the inlet and extraction openings in the inner and
outer casings prior to installation of the angle section ring. Recheck the clearance between angle
section ring, threaded ring and the inner casing (Fig. 7.24 (b)).
• Having meticulously cleaned the casings and the turbine shaft, proceed with assembly. Following
the adjustments previously made, the positions of the shaft and the inner casing are now
definitely established (Fig. 7.24(c)).
• Recheck the radial clearances at the blading and the shaft seal in the course of assembly.
Expand the casing joint bolts using a gas fired bolt heater (Fig. 7.25(a)) and tighten the cap nuts
to the specified torque angle.
• W hen the bolts have cooled, measure and record the degree of elongation. Then install the
extraction units (Fig. 7.25 (b)).
• W hen the turbine is fully assembled, carry out the final radial and axial clearance check. W hile
turning the shaft, shift it horizontally, vertically and axially until rubbing is observed (Fig. 7.25(c),
(d)). This concludes the final assembly (box-up) of IP turbine, and then it becomes ready for
shipment as shown in Fig. 7.26.
Inlet
Ext.No. -5
Inlet Chamber
Stationary Blades
Support Lugs
Sealing Rings
Exhaust
Branches
Thermocouple
Flange
Inlet
th
45 Stage Turning Gear Wheel
-o0o-
LP TURBINE CONSTRUCTION
The outer casing consisting of the front and rear end walls, two longitudinal girders and a top
cover encloses two inner casings. The twin shell inner casing is supported kinematically at each end by
two support arms resting on the longitudinal girder of the outer casing.
The inner shell of inner casing acts as a guide blade carrier for the initial stages. Together with
the welded structure of the inner casing, these carriers form the ducts required for steam admission and
extraction.
In addition the condenser vacuum monitoring, which act on to trip the Turbine and the LP bypass
control station, so that the condenser & LP outer casing are protected against excessive pressure &
temperature by bursting diaphragms (4 Nos.) located at the top LP turbine.
The shaft is forged form solid ingot and is supported on only one bearing at the rear of the casing
(front side bearing is shared by IPT & LPT). The last three stages of the LP rotor have twisted blades.
The difference between the circumferential velocity at the rotor blade root and tip is quite considerable
and is taken into account by twisting the blade along its length.
The fixed blades of last two stages are hollow. They are fabricated from sheet steel and slots are
provided in the blade surface through which any water passing over the surface of the blades may be
drawn away to the condenser. Also the trailing edges of the blades are very thin in order to avoid any stall
patches and the formation of streams of water. Another important design feature of final stages is that the
distance between them is kept at optimum value to facilitate the break-up of any water droplets, which
may still remain.
Above blade design features reduces the relative velocity between the droplets and the leading
edges of the moving blades resulting into less wear and tear. However, the leading edges of the final
stage rotor blades are flame hardened to give protection against erosion. These blades are free standing
and have neither lacing wire nor shrouding.
8.2 Construction
8.2.1. Steam Admission
The vertical sectional view of LP Turbine is shown in Fig. 8.2. The exhaust steam from IP Turbine
o
(7kg/cm2, 314 C) is admitted into LP turbine inner casing (3,4) from both sides through steam inlet
nozzles at the center section before the LP blading. Expansion joints are installed in the steam piping to
prevent any undesirable deformation of the casing due to thermal expansion of the steam piping. The
steam flows through the blading in two opposite streams and finally exhausted to condenser from the
diffuser sections (6) attached at the ends of last stages.
casing lower part (7) below the center inlet as shown in detail–F (Ref. Fig. 8.3, 8.4) to prevent axial
displacement of the outer casing. The outer casing (1,7) expands axially in both directions from this point
with the longitudinal beams. The keys (12) in the casing guides allow radial expansion.
The vertical center plane guides for the casing are at the lowest point of circular box beam which
stiffen the front and rear end walls (see Detail – A, Fig. 8.2, 8.5). This location allows for radial and axial
expansion of the casing.
Two rectangular plates (16) are welded at right angles to the inner surface of each box beam. A
guide block (15) rigidly attached to foundation, fits between these plates to locate the casing. Keys (14)
are provided between the block (15) and the plates (16) to facilitate accurate vertical alignment of the
casing.
Detail-X
Casing Guide
The spacer bolts (23) prevent lifting of the inner casing. Spacer bolt hole clearance is provided to
permit the inner casing to expand horizontally on shims (19) of the fixed support in the transverse
direction relative to the axis of the machine and on the shims of the non-fixed support in the transverse
and longitudinal direction relative to the machine axis. Since vertical thermal expansion originates at the
level of the horizontal joint, concentricity of the inner casing with the shaft is ensured in this plane.
As shown in Fig. 8.6, two casing guides are located at the lower half (5) of the outer shell to
prevent any transverse displacement of the inner casing from the centerline of the turbine. Radial and
axial expansion is permitted by fitted keys (18) in these casing guides (Also refer Fig.8.2 & 8.3).
Fig.8.8 Arrangement of Inner Shell in Outer Shell Fig.8.9 Top View of Joint-face
Fig.8.10 Inner Casing Fixed Support Fig.8.11 Inner Shell Non-fixed Support
In the vertical plane, there are four centering pins (31) (Ref. Fig. 8.12), which are guided in
bushings (30). The ends of the centering pins are fitted in Keys (32), which slide in axial grooves of the
inner shell. This arrangement permits axial displacement along the axis of the centering pins (31).
However, the keys prevent transverse displacement relative to the axis of the turbine. Transverse thermal
expansion relative to the axis of the turbine originates from these keys, so that concentricity of the inner
shell with the shaft is also maintained in this plane. Bushings (30) have an eccentric bore and by turning
them during erection, transverse alignment of the inner casing is adjusted. After the alignment is
completed, the bushings are locked in place by grub screws.
The diaphragm consists of a thin rolled lead plate. To ensure that the blow-off steam does not carry the
remnants of the diaphragm and rupturing disc along, a cage with brackets (5) is provided. As long as
there is a vacuum in the condenser, the atmospheric pressure forces the breakable diaphragm and the
rupturing disc against the supporting flange (3). The assembled atmospheric relief diaphragm housing is
shown in Fig. 8.14.
The stationary blades (6) of the first stage have T-roots. They are fitted in the inner casing (1) in
grooves of corresponding design where they are secured by caulking material. The remaining stationary
The moving blades (4) have T-roots, which are inserted into grooves of corresponding design in
the LP turbine shaft (8) and secured by caulking material (9). The insertion slot is closed by means of a
locking blade, which is attached to the adjacent blade by means of taper pins.
All T-root blades have integral shrouds, which, upon installation, form a continuous shroud. The
blades with hook-type roots have riveted shrouds. In order to kip the blade tip losses low, replaceable
sealing strips (3) are caulked into the inner casing (1) and the turbine shaft (8).
In order to minimise blade-tip losses at the stationary blades (4,8,11), sealing strips (1) are
caulked into the turbine shaft (10). Opposite the sealing strips, shroud rings of the stationary blades have
cylindrically turned surfaces. This arrangement permits favourable radial clearances to be attained.
In order to prevent the bearing from exerting a bending moment on the rotor (5), it is pivot-
mounted in the cylindrical shell (14). For this purpose, the spherical block (7) with shims (12,13) is firmly
bolted to the bearing shell (6). A projection in Cap (1) with shims (9) fits into a corresponding groove in
the bearing shell (3) and prevents vertical movement of the bearing shells. Centering of the bearing shells
in the vertical plane is thus maintained.
The bearing shells are fixed laterally by the keys (10), which are bolted to each other. Each key is
held in position in the bearing pedestal (1) by two lateral collars. The temperature of the bearing babbit
metal is monitored by the thermocouples (15) as shown in Section C-C (Fig. 8.20).
Lubrication oil is admitted to the bearing shells from both sides, from where it flows to the oil
spaces milled into the upper and lower shells at the horizontal joint that are open to the rotor end. Oil from
the oil space machined in the Babbitting is carried through the rotor (5) and emerges from the bearing
shell from where it is collected in the oil return cowling (4) and drained into the bearing pedestal (11).
As shown in Section B-B (Fig. 8.20), two threaded nozzles (17) are arranged at the bottom side of
the lower bearing shell (6) through which high pressure oil is supplied during start-up. The high-pressure
oil relieves the bearing to overcome breakaway torque and prevent dry friction, thus reducing the torque
requirement of the hydraulic turning gear.
The jacking oil flows into the above mentioned threaded nozzles (17) through passages in the
lower bearing shell (6). A seal (18) prevents high-pressure oil from penetrating the space between
threaded nozzle and the ring (16) and thus from lifting the babbit. Any leakage oil can drain though
passages in the bearing shell below the ring.
As discussed earlier, the outer casing of the turbine is carried on the side members, which rest on
plates grouted into the foundation alongside the turbine. These end supports are provided with sliding
arrangement. The LP turbine is anchored below the center steam inlet as shown in Fig. 8.21, (also refer
Fig.8.3 & 8.4). The outer casing expands axial in both directions (IPT side and Generator side) from this
point with the longitudinal beams. The casing is guided at the bottom most centerline of the casing by the
fitting keys, which allow free radial expansion.
The supports of longitudinal beams are matched to ensure specified clearances in non-fixed
supports at the ends. Similarly fitted keys of center guide are matched. Then the outer casing is placed in
position.
Before installation of the turbine shaft, the matching spigots and recesses must be measured and
compared to ensure that the coupling heads can be connected up (Fig. 8.24). Then the turbine shaft is
installed in the inner casing.
The bottom half outer shell of inner casing with the complete bottom half inner casing has been
adjusted axially and aligned radially. By mounting the top halves, the clearances achieved during
alignment using the alignment shaft are to be checked with the actual shaft installed. W hen the
prescribed checks have been performed, the top halves are assumed ready for operation and the casing
joints are drawn together by tightening the bolts to the prescribed torque. The steps for clearance
checking are as follows.
• Before proceeding for assembly, remove all traces of protective agents from the casing joints of the
inner casing.
• Screw in the guide bolts required for mounting the top half at the prescribed locations (Fig. 8.25).
• Hook up the top-half of the inner shell of the inner casing to perfectly horizontal position using ropes
and shackles. Clean the blading and casing joint of all traces of protective agents. Carefully lower the
top half inner shell of the inner casing (Fig. 8.29).
• W hen the top half has been lowered until the casing joint is limited on all sides by the screwed-in
guide bolts, align the top half in both planes using a spirit level. W hile lowering when the gap between
the casings joint approaches 10 mm, insert the taper pins smeared with a corrosion inhibiting paste
(Molykote paste G) into the holes and install the support plates for the brackets. Then lower the top
half to close the casing joint and hammer in the taper pins.
• The casing joints may now be bolted together. Smear the threads of the stud bolts and the contact
surfaces of the cap tighten up on both sides in parallel proceeding from the center (Fig.8.30).
• Tighten the casing joint with the aid of a bolt heater (Fig. 8.31). Finally remove the guide bolts and
alignment screws from the bottom half.
• Attach fine lead wires of the required thickness to the last stages moving blades and to the seal strips
on the stationary blades (Fig. 8.32).
• Mount the top-half outer shell of the inner casing (Fig. 8.33) in the same manner.
• Observing the measures already discussed, tighten the bolts from the center outwards. Check using
feeder gauges to ensure that the casing joint surfaces make contact (Fig. 8.34).
• Remove the taper pins and casing joint bolts. Lift the outer casing by leveling with sprit level. Measure
the thickness of lead wires attached on the moving blades and scaling strips to ascertain the radial
clearances as specified.
• Apart from the above lead wire procedure, the axial (Fig. 8.27) and radial clearances (Fig. 8.26) can
be measured in the bottom half casing by using appropriate feeler gauges.
• The turbine shaft must be axially aligned as specified in drawing prior to measurement of the radial
clearances. The feeler gauge blades shall be long enough to be able to enable measurement at all
points of the lower half between the individual moving and guide blade stages.
• After the clearance check, the top inner casings are mounted again and bolts are hot tightened as
described before (Fig. 8.34).
Fig.8.24 Checking the Centering Fit Before Installation Fig.8.25 Screwing in the Guide Bolts
Fig.8.26 Measuring Radial Blade Clearances Fig.8.27 Checking Axial Clearances Using Feeler
Using Feeler Gauges Gauges
Fig.8.30 Inner Shell in Assembled Condition Fig.8.31 Heating the Casing Joint Bolts
Fig.8.32 Fixing Lead Wires for Tip Clearances Check Fig.8.33 Setting Down the Top-half Outer Shell
Fig.8.35 (a) LPT Rotor with Expansion Joint Fig.8.35 (b) Expansion Joint as Installed
Front View
Side View
Fig.8.36 LP Turbine Outermost Top Casing
Side View
Front View
Side View
-o0o-
These systems are described briefly in further sections to understand their functioning.
The exhaust of HP turbine is passed to the reheater by left and right cold reheat lines via CRH
2 o
non-return valves. The reheated steam at pressure 34.5 kg/cm and temperature 535 C is admitted to IP
turbine through hot reheat pipelines (left and right), strainers and combined reheat stop and control valves
(2 Nos.).
2 o
The exhaust of IP turbine (7 kg/cm , 314 C) is directly admitted to LP turbine via cross-around
pipes laid at the floor level. The exhaust steam from LP turbine finally goes to condenser, which is
maintained under vacuum. This completes the steam admission and exhaust system.
The elements of strainer are shown in Fig. 9.2. The strainer screen (2) is made of corrugated
strip wound on a frame. This design offers a high degree of resistance, even to particles impinging at high
velocity. The frame consists of two rings (1, 6) and a number of rods (5) welded between the rings. The
rods are additionally held by reinforcing rings (4) welded inside them. The strainer is designed for a single
direction of flow from the outside inwards. For longer strainers, the screen is made up of several parts.
The end turns of the corrugated strip are then tacked to the T-section intermediate rings (3). The
maximum mesh size of the strainer, which is determined by the height of the corrugations, is 1.6 mm. The
effective area is made at least three times the cross sectional area of the pipe. The strainer is used for
both initial commissioning of the turbine and for regular operation.
The control valves, on the other hand, regulate the flow of steam to the turbine according to the
prevailing load.
One stop valve and one control valve share a common body in which stems are perpendicular to
each other (Fig. 9.3) and are placed in front of turbine. The two valves operate with two separate
servomotors independent of each other.
The steam is above the valve disc when the stop valve is in the closed position. The main valve
disc incorporates a pilot disc formed from the end of the valve stem to give relieving effect and thus
reduce the force necessary to open the valve. The stem is sealed by means of metallic packing rings. The
valve disc has got back seating arrangement to provide sealing when the valves are fully open.
This feature allows the working clearance between the stem and the rings to be relatively large
without allowing excessive steam leakage, with the result that the operating reliability of the valve is
improved. The valve body cover, which carries the packing rings, is held in the body by a screwed ring.
The gasket between the cover and the body is of "U" cross section and steam pressure presses the two
legs of the "U" against the sealing faces to give a tight joint. The stop valve is opened hydraulically and
closed by spring force (closing time 0.25 sec.).
The stem and disc of the control valve are in one piece. The valve disc, which is guided in a bush
is of the plug type and has balancing holes to reduce the opening force required. The guiding and sealing
of the valve stem in the cover and the design and jointing of the cover are similar to those employed on
the stop valve. The valve disc also has a back seat, which provides sealing when the valve is fully open.
The position of the servomotor, which operates the control valve, is subjected to disc spring force
in the closed direction and hydraulic pressure in the open direction. The position of the valve is
determined by the oil pressure under the piston, which in turn is controlled by the turbine governor through
a pilot valve and the secondary oil system.
The stems of the stop valve and control valve are armoured by plasmare process and the guide
bushes for the stem and valve disc are manufactured from solid stellite material to achieve optimum
rubbing compatibility (low wear and tear property).
9.2.4 Combined Reheat Stop and Control Valve (IV & IPCV)
Reheat stop valves are protective devices triggered by protection system to speedily close down
in the event of a dangerous condition to interrupt the flow of steam from the reheater system. The reheat
control valves are operative only in the lower load range (less than 20% load). Above this range they
remain fully open in order to avoid throttling losses.
One stop valve and one control valve are combined in a single unit (Fig. 9.4) and share a
common body with the stems perpendicular to each other. However, the two valves operate with two
separate servomotors independent of each other.
The stop valve is a single seat valve with a pilot disc for pressure equalization when opening.
The stem is sealed by means of metallic packing rings and there is also a raised seat on back of the valve
disc, which comes into contact with a neck bush when the valve is fully open and so provides additional
sealing at this point. The stop valve is opened hydraulically and close by spring force.
The control valve has a hollow plug type disc, which is guided and protected from side
impingement by the valve body cover. There are relief holes in the valve disc to reduce force, which must
The control valve is operated by a servomotor containing a piston subjected to hydraulic pressure
in the opening direction and disc spring force in the closing direction. The position assumed by the valve
is determined by the oil pressure under the piston, which is controlled by a pilot valve linked to the turbine
governor through the secondary oil system.
W hen an emergency trip is initiated, pressure in the secondary oil system, which is supplied from
the trip oil circuit, also collapses to cause the control valve to shut very quickly with the stop valve.
The stems of the stop valve and control valve are armoured by the plasmare processes and guide
bushes for the stems and valve discs are made of solid stellite material in order to achieve optimum
rubbing compatibility.
As a general rule drain valves must be open before charging of any steam line in order to avoid
hammering and for proper warming of pipe lines/main valves. After proper warming & removal of moisture
from pipelines, valves & other equipments drain valves are kept closed. The drainage steam or water
returns to condenser via flash boxes.
5) Extraction line drains MAL 55, 54, If Extraction Valves closed Open
(A2, A3, A4, A5) 51, 47
209
The function of this system is to ensure the sealing of glands in HP, IP & LP turbine under various
conditions. The turbine glands are self-seal type. Up to approximately 40% load, steam from auxiliary
source through valve AS-2 (Supply valve) is taken to seal off the entire HP, IP & LP glands. During this
period the valve AS-1 (Leak-off Valve) connecting this header to condenser is kept closed. After
approximately 40% load, valve AS-2 is closed and valve AS-1 is opened. Piping are so sized that the
leak-off steam from front and rear end of HP turbine goes to condenser through valve AS-1 while steam
from the IP front and rear glands is utilized for sealing the LP glands, thus ensuring proper temperature of
sealing steam. The leak-off steam and air from the last chambers of each rotor is sucked into gland
steam cooler.
Building up of vacuum in the condenser is the first step during turbine start-up. For this purpose it
is necessary to seal the turbine gland by supplying steam to the turbine shaft through valve AS-2 (from
PRDS). The control system opens the gland steam supply valve AS-2 until the pressure in the header
2
acquires a preset value [0.01 kg/cm (g)]. W hen the turbine picks-up load, the pressure of steam inside
HP & IP turbine builds-up resulting in the leakage of steam from the turbine gland steam supply header,
which in turn would result in increase of pressure. However, the gland steam pressure controller
gradually closes the gland steam supply valve AS-2 and opens gland leak off valve AS-1, if required.
The actuators of the two control valves are continuously under the control commands from the
electric controller through two electro-hydraulic converters. The positive voltage output opens the gland
steam supply valve (AS-2) while the negative voltage output opens the gland leak-off valve (AS-1). Each
hydraulic actuator has its own motor-driven oil pump supplied from station AC system. In the event of
pump failure, the valve remains in stay-put position. Subsequent operation of valve can be carried out
locally through a hand-pump.
The pressure in the header is measured by means of an inductive pressure transducer. This
measurement is used for control as well as display purposes. The measurement range is –100 to +
300mm water column.
The pressure controller has PI characteristics its output is fed to electro-hydraulic actuators via a
PID position controller. The function of this controller is to set the position of the valve as determined by
the pressure controller as quickly and accurately as possible.
In order to ensure stable control characteristics during the transition period of AS-2 closer to AS-1
opening or vice-versa, the valve travel of both the valves has got slight overlap.
The valves can be controlled manually from the control desk after switching of the auto control.
Feed heating system for KW U turbine cycle is shown in Fig. 9.6. It consists of three low-pressure
heaters, gland steam condenser, drain cooler, deaerator and two high-pressure heaters. In addition to
this the condensate passes through inter-coolers of main ejectors used for extraction of non-condensable
gases from the condenser.
The condensate extraction pumps (2x100%) take suction from condenser hot well and deliversthe
condensate to deaerator through the tube systems of main ejector, gland steam cooler, drain cooler and
low pressure heaters. Boiler feed pumps (3 x 50%) take suction from deaerator and pump the feed water
to boiler through high-pressure heaters. The condensate/feed water gets heated up progressively by bled
steam from turbine extractions together with gland leak-off steam.
Also the LP heater No. 2 & 3 are provided each with drain control valves (2 Nos.), one for
maintaining heater level at normal value and second control valve provides alternate path to condenser
through flash box by maintaining heater level at higher set point. No level is maintained in LP heater 1.
Its drain is connected through a siphon to condenser.
W henever level in LP heater Nos. 1, 2 & 3 reaches very high set point, the respective motorised
block valve in extraction line closes along with the opening of drip valve in extraction line (drip valves only
in LPH-2 & 3). Drip from next higher pressure heater is diverted to condenser through flash box b y
alternate drip control valve. Affected LP heater is isolated by closing condensate line isolating valves and
opening bypass valves across it.
9.5.3 H P Heaters
Two horizontal HP heaters No. 5 & 7 are provided in the system. HP heater No. 5 gets heating
steam from IP turbine and HP heater No. 6 from cold reheat line (after CRH NRV). Hydraulically operated
non-return valve is provided in extraction line to HPH-5 and motorised block valves near heater ends of
HPH 5 & 6.
HP heaters shall be automatically isolated on feed water and steam side under heater very high-
level condition. Quick opening group protection valves (FD16 & 17) are also provided for bypassing HP
heaters during very high heater level condition.
Normal level of HP heater No. 6 is controlled through control valves cascading the drip to HP
heater 5 and another valve cascading to deaerator and alternate drain control valve is provided to
condenser through flash box operating on high level.
9.5.4 Deaerator
Deaerator is designed to operate under variable pressure between 55% to 100% load on turbine
and during this range, steam is drawn from turbine extraction, i.e. IPT exhaust. During start-up of turbine,
deaerator is provided with steam supply from cold reheats line as well as external steam source, i.e.
auxiliary PRDS header.
During initial start-up, pegging of deaerator is done through a control valve connected to auxiliary
steam header at a pressure of 3.5 ata. till about 15-20% boiler MCR load, depending upon the type of
start-up (viz. cold, warm or hot).
After this, the steam supply to deaerator is switched over to cold reheat line through a control
valve and pegging is maintained at 3.5 ata. up to about 55% turbine load. Thereafter the steam supply to
deaerator is automatically switched over to turbine extraction and this is in service up to full load. During
HP/LP bypass operation also, the deaerator is pegged from cold reheat line at a pressure of 3.5 ata.
The minimum flow requirements of ejector, condensate pump and gland steam condenser is
approximately 210 T/hr. and the same is achieved by condensate recirculation control valve (CD-19).
This valve is a regulating type and remains open during start-up when main condensate valve (CD-14) is
closed. As the load on the turbine increases, main condensate control valve opens and the minimum
recirculation control valve closes proportionately to maintain minimum flow of 210 T/hr.
The HP bypass valve is a combined type of pressure reducing and desuperheating station with
spray water being tapped off from BFP discharge and is supplied to HP bypass downstream chamber via
spray control valve (BPE1, 2).
The HP bypass valve dumps the depressurised and desuperheated steam with suitable
parameters into cold reheat lines.
The HP bypass station while operating with a LP bypass station enables boiler operation by
establishing steam flow from main steam line to cold reheat line and from hot reheat line to condenser
without co-ordination with turbine. This allows quick raising of steam parameters to a level acceptable to
turbine for roll-off during start-up. This also facilitates holding of stable firing rate from the starting of
turbine roll-off till the entire flow from the bypass station is transferred to the turbine.
• 2 Nos. combined pressure reducing and desuperheating valves complete with valve mounted
electro-hydraulic actuators. Each valve has been sized to pass 210 T/hr of steam at inlet steam
2 o
condition of 150 kg/cm , 540 C.
• 2 Nos. throttling device, one after each HP bypass valve
• 1 No. Spray water pressure control valve complete with valve mounted electro-hydraulic actuator.
• 2 Nos. spray water pressure control valve complete with valve mounted electro-hydraulic
actuators for temperature control.
• 1 No. automatic pressure control loop consisting of the elements:
- Pressure master controller (PI characteristics)
The control system is designed to maintain the steam pressure ahead of bypass valves to the
given set value. The pressure set point can be adjusted from control desk manually. The steam
temperature at downstream of the valves is automatically controlled to the given set value. The
temperature set point can also be adjusted from control desk manually. Therefore, the operation of the
HP bypass station is manipulated by the pressure and temperature set points and is independent of LP
bypass operation. Depending upon the initial pressure condition at the time of boiler firing, the pressure
set point is to be adjusted to a value equal to steam pressure ahead of bypass valves plus a bias
pressure. This would result in opening of the valves. The pressure controller would then try to maintain
the set pressure by allowing a flow matching with firing rate. As the firing rate increases the set point
needs to be manipulated in the same manner to allow matching flows. This, however, shall be possible till
the maximum flow capability of the valves is reached (210 T/hr per valve). Upon reaching the steam
parameter for turbine roll-off, the boiler firing rate can be maintained at that level.
Consequent upon steam admission in the turbine, the pressure ahead of bypass valves shall tend
to fall in view of constant firing rate. This shall result in closing of bypass valves due to pressure controller
action. This process continues till the HP bypass valves are completely closed. After this, further loading
of TG set can be achieved by increasing the firing rate and the bypass pressure set point can be
2
increased to rated turbine throttle pressure plus pressure bias (5-6 kg/cm higher). This maximum limit of
set point should be below the safety valves set pressure for superheater. W ith this pressure set point, the
HP bypass station shall automatically open to balance the discrepancy between steam generation and
consumption arising out of load rejection under constant pressure operation.
The control loop for the steam temperature at the down steam of HP bypass valves can be
operated by modulation of set point as required for different mode of start-ups governed by boiler/turbine
characteristics as well as warm-up requirements of steam piping. During normal turbine operation, the set
point is set at a value closer to the turbine exhaust temperature.
Interlocks:
The following safety interlocks have been envisaged.
i) If HP bypass valve opening below 2%, the spray water isolating valve (BD Valve) shall
automatically close.
ii) If HP bypass valve opening is above 2%, the control of spray water isolating valve (BD valve)
opens and the spray water control valves (BPE Valve) shall be changed to "Auto" mode
notwithstanding their initial conditions.
iii) If the downstream steam temperature of HP bypass valve (BP valves) becomes high (3800C),
the valve will close on priority. This is accomplished with an alarm.
LP bypass controls are energised to dump the excess steam present in the reheater circuit due to
its large "Time Constant" during transient non-steady state. LP bypass valves get opened and dump
steam to condenser to such an extent as to maintain the reheater pressure at a value desired from criteria
representing the HP turbine flow conditions at any given instant during load changes. This control
criterion ensures that only the requisite flow is maintained through he IP & LP turbines. The control of LP
bypass system is hooked-up by same control oil which is envisaged for the turbine governing system.
LP bypass, though has an independent control system, works in conjunction with HP bypass
system as and when necessitated by system requirements such as warming-up stage or dumping of large
quantity of steam following a heavy load rejection.
Under certain operating conditions, such as start-up the variable set point (sliding set point) is
replaced by a fixed set point value. The controls of LP bypass system are essentially a combination of
electrical and well-proven hydraulic system. Electro-hydraulic converter provides the necessary link
between electrical system and hydraulic actuation system.
The electronic controller acts as a pressure controller and regulates the reheater pressure either
to the fixed set value or suitable desired set value. If the reheater pressure exceeds this set value, the
controller causes the electro-hydraulic converter to operate and initiate bypass operations.
Emergency stop and control valves of the LP bypass are combined in a common body. The
double shut-off arrangement separates the condenser from the reheater during normal operations.
The electro-hydraulic LP bypass control system includes the necessary safety device for the
protection of the condenser. These devices prevent the dumping of the steam into condenser if the water
injection pressure is too low or if pressure inside condenser is too high. In case, flow of bypass steam is
too large, the bypass control valve closes proportionately. As a measure of additional protections, LP
bypass station closes in following eventualities.
-o0o-
The oil system consists of (Fig. 10.1, 10.2) 1 x 100% Main oil pump coupled to the HP turbine; 2 x
100% Auxiliary oil pump mounted on the MOT and driven by AC motor; 1 x 100% Emergency oil pump
mounted on MOT and driven by DC motor; 2 x 100% Jacking oil pump mounted on MOT and driven by
AC motor (now a days one JOP with DC motor).
The Jacking Oil Pump is mounted on the oil tank and discharges oil into a header whose pressure
2
(120 kg/cm ) is maintained by a pressure limit valve. As shown in Fig.10.4, the jacking oil pressure
required for each bearing is adjusted by its regulating globe valve.
In case main and auxiliary oil pumps cease to operate simultaneously, a pressure switch in the
lube oil line starts D.C. emergency oil pump. It bypasses the oil coolers and discharges oil directly into
the lubricating oil lines thereby ensuring oil supply to bearings during rundown of the TG set.
The double flow impeller is mounted on the pump shaft by means of a feather key. The impeller
is located axially by means of the bearing bush and the spacer sleeve. The delivery and suction
chambers are sealed off against each other by sealing rings, which are split and secured against turning
the joint. The pump shaft is supported by journal bearing at coupling end and combined journal and thrust
bearing at free end. Bearing are lubricated by oil drawn from the delivery chamber of the M.O.P. the oil
lines. During testing of emergency governor by testing device, pressure oil at "a" is passed through the oil
tube fitted in the pump shaft. The oil is carried to the bottom of eccentric strikers to lift them at rated
speed for testing the operation of overspeed trip 1 & 2.
The pump shaft also carries the hydraulic speed transmitter, which also runs, in the bearing and
in the rings. The speed transmitter operates on the principal of pump impeller developing the pressure
signal (primary oil pressure) in proportion to speed, which actuates the hydraulic governor. The hydraulic
speed transmitter is supplied with the governing oil coming from the hydraulic governing rack. Besides
the hydraulic speed transmitter electric speed transducer, a hall probe is fitted on the shaft to convert the
speed signal into electrical pulses, which forms the actual speed signal feedback to speed controller of
electric governor module.
The space above the maximum oil level in the tank is sufficient to accommodate the oil, which is
in the circuit and will flow back into the tank in the event of tripping of the set. The tank is divided
longitudinally by a partition; oil returning to the tank from the system enters through a submerged inlet to
the riser section of the tank where the first stage of deaeration takes place as the oil rises to the top of the
tank. Oil overflows from the riser section through a basket type strainer into the adjacent section of the
tank. After circulating around the longitudinal partition of the tank, the oil is drawn-off by the pumps,
mounted on the top of the tank. The tank is made as air tight as possible oil vapour extractor is mounted
on the tank, which produces a slight vacuum in the tank, bearing pedestals and drain lines oil vapour is
therefore exhausted in the controlled manner.
10.4.6 Data
1. Pumps :
Sr. Name No. Power Capacity Discharge
No. Pressure
3 2
1 Main Oil Pump (MOP) 1 x 100% 115 KW 500 m /hr 8.2 kg/cm
3 2
2 Auxiliary Oil Pump (AOP) 2 x 100% 75 KW 267 m /hr. 6.11 kg/cm
3 2
3 Emergency Oil Pump 1 x 100% 7.5 KW 169 m /hr. 1.53 kg/cm
(EOP, DC Motor)
3 2
4 Jacking Oil Pump (JOP) 2 x 100% 3 KW 4.54 m /hr 120 kg/cm
-o0o-
The main control system, i.e. electro-hydraulic governing system, facilitates the operation of the
turbo-set in an interconnected grid system. The electrical measuring and processing of signals, after the
advantages such as flexibility, dynamic stability and simple representation of complicated functional
relationship. The salient features are listed below:
The types of governor used are electro-hydraulic backed-up by hydraulic speed governor.
Throttle governing method is adopted to control the turbine load
Hydraulic governor always tracks the EHC during normal operation through tracking device
Electro-hydraulic control system has three control loops:
• Speed control loop
• Load control loop
• Pressure control loop
The signals for speed, load and M.S. Pressure are acquired by electrical transducers, processed in
electronic circuit cards and then converted in to hydraulic pressure signal in electro-hydraulic
converter. Hydraulic signal is further amplified for actuation of control valves. Speed, load and
pressure control loops provide flexible operation of turbine in various modes of operation & are
designed to encounter emergencies.
Regulation range of electro-hydraulic speed controller can be adjusted from 2.5 – 8%, even while the
machine is in operation, in steps of 0.5%. The normal regulation setting is 5%.
Precise load frequency droop (in load controller) with high sensitivity.
Hydraulic speed governor regulation is set at 5%
Control valves open in proportion to signal of secondary oil pressure and actuated by constant control
oil pressure.
Transient speed rise (TSR), i.e. maximum speed rise above rated speed when the turbine trips at full
load:
i) W hen control valves are mounted near turbine casing : 8%
ii) W hen control valves are mounted away from the turbine casing : 8.5%
Oil required for governing system : 100 lit/min.
Dead Band (No response speed in %) :
i) Electro-hydraulic governor : 0.01%
ii) Hydraulic governor : 0.1%
Closing time of valves
i) Emergency stop valve (ESV) : 0.26 sec.
ii) H P Control Valve (HPCV) : 0.4 sec.
All types of turbine starts-ups are performed through HP control valves and they control the load from
0-100%. However, IP control valves have a controlling function alongwith HPCV upto 20% load.
Above 20% load IP control valves remain open 100% and load control is performed by HP control
valves 1 & 2.
The Trimming Device provided for the IP control valves, is used for controlling the HP exhaust
pressure to prevent churning in HP turbine in case following conditions occur.
2
• HP exhaust pressure > 32 kg/cm and
• Load less than 20% of rated load
The solenoid valves fitted on IP secondary oil and auxiliary secondary oil lines operate through
energisation of load shedding (rejection) relay if following conditions occur.
• Load throw off > 50% &
• Balance load < 20% &
• Grid frequency > 49 Hz
W hen solenoid valve opens, it drain IP secondary oil and auxiliary secondary oil & de-pressurizes it
resulting in to closure of HP & IP control valves for 1.3 sec. This prevents over speeding of turbine.
Afterwards governing system controls the turbine load with proportionate opening of HP & IP control
valves.
One contact of load shedding relay operate the fast opening device of HP bypass valves to open it
quickly to prevent the abrupt rise of pressure in M.S. lines.
Automatic turbine tester (ATT) is provided to check the operation of protective devices and normal
closing of ESV, IV, HPCV & IPCV while the machine is running on load.
Automatic Turbine Run-up System (ATRS) is integrated with electro-hydraulic controller for automatic
turbine start-up upto block load.
Isolated grid operation facility with reliable operation of turbine at block load.
Turbine Stress Evaluator/Controller (TSE, TSC) influence to prevent overstressing of turbine parts, is
incorporated in speed controller and load controller of E.H.G. This ensures safe operation at all loads
and steam conditions.
Interfacing of Coordinated Master Control with electro-hydraulic governing system and boiler master
fuel controller for controlling the unit with single set point, i.e. unit target load set point.
Fig. 11.1 shows the structure of turbine control system, comprising of electro-hydraulic controller
and mechanical hydraulic controller. In case of EHC, the processed governing signal in the electrical
voltage form is converted into hydraulic signal, which is further amplified to derive secondary oil pressures
for operation of control valves. Similarly, the hydraulic speed signal (primary oil pressure) or the speeder
Fig11.2 Action of Protection & Governing System on Turbine Stop & Control Valves
The load of the turbine is controlled by throttling the main steam pressure upto full load range by
HP control valves (2 Nos.) and by throttling the hot reheat pressure upto about 20% load range after
2
which IP control valves remain full open. The secondary oil pressure signal varying from 2.5 – 5 kg/cm
opens the control valves from 0 – 100% in both the cases.
2
The protection oil circuit which generates trip oil pressure (6- 7.5 kg/cm ) acts on the servomotors
of Emergency stop valves and Interceptor valves to open it fully. Hence in the absence of trip oil
pressure, stop valves close rapidly due to spring force. The protection devices drain the trip oil in the
event of electrical or mechanical tripping signal from protection logic.
Fig. 11.2 shows the action of governing and protection system on turbine control stop valves &
Fig.11.5 elaborates the governing & protection oil circuit.
In the normal course, trip oil is passed through the main trip valves connected in series. W hen
main trip valves are in lifted condition, trip oil is supplied at normal pressure (6 – 7.5 kg/cm2) through
changeover valve to turbine stop valves (ESV & IV) and governing system for generation of secondary oil
to regulate control valves position. The main trip valves are held in lifted position in turbine running
condition by the auxiliary trip oil pressure. The auxiliary trip oil is connected to hydraulic protective devices
viz. overspeed trip, thrust bearing trip and low vacuum trip.
The changeover valve is employed in the trip oil circuit (Fig. 11.3) to change over the trip oil
supply from protection circuit to test oil supply from solenoid valves during the automatic turbine tester
(ATT) procedure. This permits the testing of the operation of protective devices without tripping the
turbine on load.
Since the secondary oil generated by electro-hydraulic converter and hydraulic converter are
connected in parallel to respective HP Secondary oil and IP secondary oil circuits, the governor with
minimum position controls the process by generating required secondary oil pressure, i.e. the hydraulic
minimum is achieved.
Electro-hydraulic Governing:
The electro-hydraulic converter receives the governing signal in the form of electrical voltage from
electrical governor. Electrical governor has three control loops as follows :
Speed Control : Used for rolling the turbine upto rated speed and loading to block load
The selection circuit employed in the electric governor logic automatically selects the appropriate
controller depending upon turbine control requirement. The output from selection circuit is passed to
the valve position controller which checks the error between actual valve position and control signal
and accordingly generates the output, which is finally supplied to electro-hydraulic converter.
Electro-hydraulic converter converts the electrical signal into HP & IP secondary oil pressure signals
for the actuation of control valves to control the turbine speed/load.
Hydraulic Governing:
The hydraulic governor receives turbine speed signal in the form of primary oil pressure and
reference speeder gear position. Accordingly the equilibrium is achieved and it generates auxiliary
secondary oil pressure. Auxiliary secondary oil pressure signal operates the follow-up pistons of hydraulic
converter, which in turn generate HP & IP secondary oil pressure signals.
In normal course of turbine operation, speeder gear of hydraulic governor is positioned at 100%
so that E.H.C. can assume the turbine control throughout the loading range since it remains at minimum
position. The tracking device, which constantly adjust the position of starting and load limiting device with
respect to EHC position ensures that turbine load does not rise abruptly in the event of failure of EHC
(which goes to 100% in case of coil failure). S.L.L.D. locks the position of hydraulic governor bellow
position for limiting the load.
The speed control loop is formed by a speed reference limiter, speed reference & speed
controller. The speed controller compares the speed reference generated by the speed reference limiter
circuit with the actual speed of the turbine and accordingly provides an output for valve position controller.
The actual turbine speed (nact) is acquired by three digital speed pick-ups based on the hall probe
principle. The output of each pick-up is processed in three different channels. The output from only one
channel is used and other channel provides redundancy.
The speed reference is generated by the speed reference limiter loop. The desired reference
speed value is set with the help of potentiometer remotely from control desk or manually from the panel.
In the speed reference limiter the reference speed signal is juxtaposed with the output from the turbine
stress evaluator and a time dependent limited speed reference is generated corresponding to the highest
permissible rate of speed increase, which is consistent with the safe operation of the turbine (max. rate
600 rpm/min, minimum rate 108 rpm/min). After attaining the target reference speed the output of the
speed reference speed limiter is held constant.
The output of speed reference limiter is automatically blocked in the event of a fault in T.S.E. and
the speed of the set cannot be changed (speed reference blocked) until and unless TSE influence is
made off.
The reference load is set by a motor operated potentiometer, which is transmitted to the load
reference limiter. The load reference set value and output signal from turbine stress evaluator are
juxtaposed in the time dependent limited reference load setting depending upon the influence of the TSE
at the highest permissible rate consistent with the thermal stresses of the turbine both during load
increase and decrease. After attaining the target load reference, the reference limiter output is held
constant. The turbine stress evaluator influence is rendered ineffective upon failure of TSE and the load
reference limiter is held constant (blocked). It is possible to increase or decrease the load when turbine
stress evaluator is disconnected. The load gradient setter also influences the time dependent load
reference signal but the actual maximum permissible load rate is governed by the turbine stress evaluator.
The grid controller can also be activated to exercise control on the load reference setter, which in
turn is effective via the load reference limiter and TSE. This facilitates loading of the set from load
dispatch centres.
The load controller receives the reference load signal from the load reference limiter and also
from the frequency controller depending on the frequency of the grid. These two signals are summed in
the load controller and net value derived for controlling the valve position. The droop characteristics of the
frequency controller can be varied from 2.5 to 8% in steps of 0.5%.
To limit the total power delivered by the turbine, the system is equipped with maximum load
reference limit, Pmax, which has priority over all other influences acting directly or indirectly on the valve
position controller.
The actual active load value is acquired in three independent channels and transmitted to the load
controller. In case of a deviation of more than 5% in between the measurement channels, an alarm
"actual load signal faulty" is initiated.
The load controller exhibits a proportional-integral action and has an excellent dynamic response.
The load controller comes into operation only when the turbine is synchronized and the block loading has
been achieved. This controller and the speed controller signals are transmitted to valve position controller
through maximum and minimum selection circuits.
In case the sudden loss of export load, the output of the load controller is immediately reduced
below the output of the speed controller, which is set at station load (10% of rated load). Due to maximum
selection speed controller assumes control and returns the turbine fact to almost the rated speed. Hence
this provision prevents the over speeding of the turbine.
On the other hand in the limit pressure mode, the pressure controller does not come into picture
2
unless the main steam pressure drops by preset limit (generally 10 kg/cm ) with respect to the M.S.
pressure setpoint. In this case pressure controller takes over the load controller and closes the control
valves to restore the pressure. During this period, load controller tracks the actual load value of generator
and takes over the control as soon as pressure becomes normal and pressure controller output become
more than the load controller output. The load controller/speed controller output and the pressure
controller output are passed through the minimum gate. In normal course, pressure controller output is
maximum so that load controller is always active.
The feed back signal representing the valve lift is derived from position of electro-hydraulic
converter plunger as an analogue value from the differential transformer type transducer. There are two
transducers (Collins) continuously scanning the position of the plunger. The characteristics of valve
position (lift) controller are Proportional-Integral and differential type, which ensures high overall sensitivity
and improves transient response.
The outputs from the speed control loop and load control loop are juxtaposed and tied to each
other by means of a maximum selection circuit. In a separate circuit the output of speed control loop is
summed with load reference valve. This signal is compared with the signal from maximum selection
circuit of speed and load controller and minimum of the two juxtaposed with the output signal from
pressure control loop in yet another minimum selection circuit. The output of this minimum selection
circuit is fed to valve position controller.
To latch the protective devices and HP/IP stop valves (ESV, IV) when SLLD is brought to bottom most
position (0%). In this position SLLD generates auxiliary start-up oil, which latches protective devices
and also generates start-up oil to latch stop valves servomotor (ready for opening).
To compress the governor bellows at the beginning of start-up so that control valves opening is
prevented till ESVs and IVs are opened fully at 56% SLLD position. Further raising of SLLD causes
control valves to open (when EHG is out of service) the speed of the turbine is raised to 2400 rpm
(approx. 80% of rated speed). At this speed hydraulic governor takes over the control.
To provide the load limiting function in case of hydraulic governor operation or when EHC fails.
The LRR measures the electrical load rejection at generator. Any load rejection of the turbo-set,
i.e. a bulk negative load change, is therefore acquired instantaneously by the LRR and is then
transformed into an electrical pulse, the duration of which is related to the magnitude of load rejection.
This pulse energizes two solenoid valves:
One solenoid valve connects the auxiliary secondary oil (hydraulic output signal of hydraulic speed
governor) supply line to a drain, causing a rapid drop of the pressure of that fluid and therefore closing
of the HPCVs and IPCVs.
The second solenoid valve connects the secondary oil of IPCVs to a drain causing IP control valves to
close rapidly than the action of first solenoid valve (due to its hydraulic characteristics).
According to above arrangement, all the control valves close at a maximum speed. The fast
response of the LRR is caused by measuring the change of generator load before the turbine speed rising
starts. The LRR acts therefore earlier on the hydraulic control system, i.e. before the hydraulic control
takes action due to speed increase.
After the electrical pulse issued by the LRR has ended, the solenoid valves will close again.
Auxiliary secondary and secondary oil pressures will build-up again, corresponding to balance load on the
turbine since by this time hydraulic governor will resume normal control of the turbine.
To prevent any response of LRR at frequencies below rated one, a frequency lock is employed. If
the transmission system is operating below rated frequency while a load rejection occurs, without this
lock-out, the LRR will issue its signal and cause the control valves to close immediately. After its signal
has disappeared, however, the hydraulic speed governor will find a big mismatch between the actual
speed and the hydraulic speed set point causing the turbine control valves to open rapidly and in turn
accelerate the turbine that it most likely will run into an overspeed trip. Therefore, the frequency relay
blocks the LRR signal below an adjustable value 49 Hz and releases it when this frequency is exceeded
again.
The contact of LRR is also provided to fast opening device of HP bypass system to open HP/LP
bypass valves rapidly during load throw-off to prevent abrupt rise of steam pressures.
The comprehensive turbine protection scheme is explained in Fig. 11.7. The design of the
mechanical-hydraulic protection devices are in accordance with the hydraulic break-current principle and
consists of :
Two tripping devices, i.e. Main trip valves with integral manual trip arrangement
Two remote trip solenoid valves operated by electrical protection system to cut-off trip oil supply
Two channels of Electrical protection logic and turbine trip relays
Two overspeed trip devices operated at 11% overspeed.
One thrust bearing trip device (high axial shift due to thrust bearing wearing)
One mechanical low vacuum trip device, which is a back up to electrical vacuum trip.
Operation:
The operation of trip system close all stop and control valves of turbine rapidly. The main trip
valves draw oil from pressure oil circuit cascaded through remote trip solenoid valves (ref. Fig.11.3). The
oil coming out of main trip valves is supplied via changeover valve to ESV, IV, Secondary oil circuit and
auxiliary secondary oil circuit of governing system as trip oil. The main trip valve remains in lifted
condition (normal position) against the spring force by the auxiliary trip oil pressure acting below the spool.
W hen the auxiliary trip oil pressure under the differential piston in the main trip valve falls below a
certain adjustable value, due to the response of some protective device, the spring moves the piston
downwards, opening the drain for the trip oil and closing the pressure oil inlet from remote trip solenoid
valves. This in turn totally blocks oil to control circuits and causes closure of ESV, IV, Control Valves and
extraction swing check valves. W hen the pressure in the trip oil circuit falls below a certain value, the
upper piston and lower piston of the ESV & IV servomotors are separated by springs and valves are
instantaneously closed.
The turbine can be tripped manually by pressing the lever of the main trip valves or by pressing
the "Emergency Trip" knob from the control room.
The turbine protection system can be tested during operation. A device to initiate turbine trip
during protective device testing is provided with the automatic turbine testing system so that the turbine is
protected continuously during the period the protective devices are being tested.
-o0o-
The aim of the monitoring of these parameters is early detection of malfunction due to wear,
thermal stresses and the effect of external forces so as to save the possible damage. The operation of
the highly stressed machine, i.e. turboset, operating at high temperatures and pressures is affected by
expansion and vibrations encountered.
This special measurement system includes all necessary sensors mounted on the turbine with
flexible leads for connection to junction boxes, circuits for processing the sensors signal along with power
supply monitoring, signal level monitors, test circuits etc., in a cabinet to generate information about the
following parameters.
Other important parameter like speed is measured electrically by Hall Probe & signals are
provided to Electro-hydraulic governor & for display in unit control room after conditioning.
For measurement of absolute shaft vibrations, the seismic mass type pick-ups are mounted on
the pedestal cover. The bearing vibrations are transmitted directly to the seismic device.
The device operates on the plunger coil principle. The mechanical vibrations are converted to an
electrical signal, which is proportional to velocity of vibration. In seismic device (Fig. 12.1), a coil is
suspended in an air gap in a resilient way by a spring. The magnetic flux in an air gap is constant. The
permanent magnet is firmly connected to the housing and to the magnetic return path. Above the natural
frequency, the plunger coil is steady in space due to its mass inertia. Thus a fixed point in space is
created and vibrations can be referred to this point. The relative motion between the coil and magnet
generates a voltage, which is proportional to the rate of vibration.
The measurement of relative shaft vibration is carried out by a contactless pick-up according to
the eddy current method. An oscillating circuit consisting of the disc-shaped coil of the sensor and the
cable capacitance of the feed line receives a high frequency alternating current from the adaptor mounted
on the bearing cover, corresponding to the resonant frequency of this oscillating circuit. The
electromagnetic alternating field generated in the process includes eddy currents on the shaft opposite to
the coil. The smaller the distance between coil and the shaft larger is the current. The eddy current feed
back to the coil is felt as an increasing effective load, so that the a.c. voltage at the coil is proportional to
the distance between the sensor and the shaft.
This signal is filtered in a band-pass filter, then rectified and smoothened. A linerisation circuit
corrects the output of the sensor, which is a measure of relative shaft vibrations.
The vibration signals from the absolute bearing vibration measuring unit and relative shaft
vibration measuring unit are added in a computing unit for obtaining the absolute shaft vibration. The
measuring range is 0 – 400 microns peak-to-peak.
The measuring principle is based on the fact that the impedance of a coil with iron core depends
upon the size of the gaps in the magnetic circuit as shown in Fig. 12.2. There are two such coils
(Fig.12.3) mounted on either side of the measuring disc and connected to form a measuring bridge. A
high frequency voltage is fed to the bridge, the output of which changes proportionally to the change in air
gap (Fig.12.4). The bridge output voltage is rectified by phase selection and amplified. On load test
facility of the measuring attachment is provided. The range of measurement is –0.5 to +0.5 mm.
Fig.12.3 Inductive Type Axial Shaft Position & Differential Expansion Pick-up
Differential expansions of HP, IP and LP turbines are monitored in the same way as described
earlier for axial shaft position measurement by inductive type of sensors.
Fig. 12.5(b) elaborates the location of sensors for the measurement of differential expansion of
HP, IP and LP turbine, which are fitted in front pedestal, pedestal No.3 and pedestal No.4 respectively.
The difference lies in the size of the measuring discs and the sensors arrangements. For the large range
of relative expansion in LP turbine, the measuring disc is in the form of a double cone to produce less
change in expansion.
As the bridge output for a larger air gap changes non-linearly a linearising network is employed.
The ranges of measurement are –
For HP turbine - 5 to + 16 mm
For IP turbine - 5 to + 16 mm
For LP turbine - 10 to + 32 mm
Fig.12.5 (b) Location of Differential Expansion Sensors for HP, IP & LP Turbines
The difference between permissible temperature difference and the actual difference between
surface & middle wall temperatures is known as available temperature margin. The margins are
evaluated in an analogue computing circuit and displayed in the instruments as upper and lower
temperature margins upto the stage of synchronization and as load margins during subsequent loading.
The display also indicates the component, which is critical at any given time.
12.2.2 Arrangement
The scheme of TSE consists of following five computing channels as shown in Fig. 12.7 :
Channels 1 & 5 (ESV & HPCV) form the steam admission area and channels 2, 3 & 4 form the
turbine area. The indicator (TSE Display) is shown in Fig. 12.8.
The input to turbine stress evaluator is supplied by thermo-couples mounted on stop valve, high
pressure turbine and intermediate pressure turbine. Ni Cr-Ni thermocouples (W T Sensors), as shown in
The actual load of the turbine generator set Pact is measured separately and a current signal of
4-20 mA is available for load indication and computation of load margins. The speed is also measured
separately and 4 – 20 mA signal is available for display in TSE indicator.
12.2.3 Computation
The permissible temperature margins are converted into permissible load margins with the help of
mechanical stress calculations for on load operation of the TG set. The available temperature margins are
converted into corresponding load margins by TSE circuitry with the help of mathematical algorithms.
These load margins are the guiding factors to further load or unload the TG set on both manual and
automatic mode.
During no load and start-up and shutdown operations the temperature margins are indicated for
admission (or for the turbine area whichever is lower or as selected), together with the instantaneous
speed. During on load operation the upper and lower load margins ∆Pu and ∆PL are computed from
available minimum temperature margins and are displayed together with instantaneous load value.
During speeding up and upto synchronization, the markings on the white scale indicate the actual
speed of the set. The operature formed by the red discs indicates the safe temperature margin (in degree
Kelvin) in which components remain stressed within the permissible level only.
These indicated margins along with the actual metal temperature help to assess the matching
steam temperature requirement prior to rolling. Correcting action has to be taken when the margin
narrows down or become zero.
During the loading operation the display indicates the load range in which the output can be
altered without any restriction on rate offload load change. The margin is a step change in load permitted
on the turbine at that moment. The actual load is indicated in the white scale. It is possible to switch back
to the variable speed range in order to check the instantaneous temperature margins at admission area or
turbine area.
Two 12-point recorders of Kompensograph model are provided for recording of absolute
temperature, temperature margins actual speed, actual load and load margins.
For checking the proper functioning of the computing circuit from the input section upto display, a
known input can be applied to get a predetermined reading in the indicator for each channel. It is
advisable to test the circuits periodically. If there are deviations the TSE should not be used till the fault is
cleared.
The basic philosophy for computing the margin remains the same. For example, as shown in Fig.
o
12.10, the margins with respect to θm of 250 C are computed as follows :
o
Steam Temperature θi = 280 C
o
Midwall temperature θm = 250 C
∴ ∆θact = (θi - θm)
o
= (280 – 250) = 30 C
Fig.12.11 Effect of TSE Influence on Speeding Rate Fig.12.12 Effect of TSE Influence on Loading Rate
The inference of the above computation of upper and lower temperature margins is that the steam
o o
temperature θi can be increased by 30 C (to the level of 310 C) safely. This is known as upper margin.
o
Similarly θi can be decreased by 110 C safely and this is known as lower margins.
The temperature margins for all the five channels are calculated in the similar way and the
minimum upper margin and minimum lower margin among them is selected separately for display
purpose as well as fed to Electro-hydraulic controller for controlling the rate of rise of speed and rate of
rise/fall of load. However, the rate of fall of speed can not be controlled as it will come down on its own
after trip out or closing of valves.
The influence of margin during rolling is such that the rate of rise of speed is directly proportional
o
to TSE margins between 0 – 30 K as shown in Fig. 12.11.
o
If margin is more than 30 K, then the speed increases at a constant maximum rate of 600
rpm/min.
During loaded condition, the rate of rise of load depends upon upper margin and rate of decrease
of load depends upon lower margin as follows:
o o
TSE Margin 0 – 30 K = 0 – 25 MW /min. If the margin is more than 30 K load will
o
increase/decrease at a constant maximum rate of 25 MW /min. As shown in Fig.12.12, between 0 – 30 K
of margin, the rate of rise of load is directly proportional to margin
o
Hence operator should maintain TSE margins well above 30 K while rolling & loading the set by
proper control of MS & HRH steam temperatures.
-o0o-
TURBINE OPERATION
13.1 General Operation Philosophy
The objective of starting-up the turbogenerator is to bring a unit on load and raise it to the rated
output within the optimum time but without undue stresses on the turbine components. The proper
procedure gives a logical sequence of start-up, ensuring that no part of the system is overlooked and
gives the confidence to the operating personnel that each step is completed as specified. For this
purpose, the essential requirement of any pre-start check sheet is that it is complete in itself and includes
very simple to most serious checkpoints in the logical sequence. The parameter values, or the sequence
of operation may change from one type of design to other but the operation philosophy remains same in
the broad sense.
The unit operation is an integrated exercise of boiler, turbine and generator operation with proper
coordination so that operating parameters are maintained as recommended by manufacturer. Frequent
crossing of high or low limits of critical parameters may lead to serious damage to the equipment. Hence
operating personnel should observe following points during normal operation –
In short by observing proper procedure number of trippings / outages can be brought to minimum.
The long shut-downs lead to cold start-ups which cause plant equipments, particularly working at high
temperatures, to undergo stress cycle. This deteriorates the plant life besides huge power generation
loss coupled with shut-down and start-up losses.
Efforts should be made during shutdown to keep the equipments hot and reduction of shutdown
period so that hot start-up can be performed saving time, power generation loss and reducing the stress
level in the components.
i) Steam parameters suitability viz. pressure and temperature & its raising rates.
ii) Soaking time for turbine and main valves
iii) Turbine speed raising, loading rates
iv) Total time required reaching the full load.
M.S. H.R.H.
2 2
Pressure 30- 35 kg/cm 10-12 kc/cm
o o o o
Temperature 320 – 350 C 320 – 350 C
Flow 95 –100 t/hr.
o
10. W arm-up of turbine stop valves (ESV & IV) to get the TSE margins >30 K & fulfillment of steam
pressure and temperature criteria (X1, X2,X3)
11. Turbine trip resetting by bringing S.L.L.D. to zero position.
12. Opening of stop valves (ESV & IV) by raising the SLLD (starting device) to 42% and 56%
respectively.
13. W arming of HP control valves by opening warm-up control drains valves through warm-up
controller.
14. Fulfillment of steam temperature criteria with respect to mid wall temperature of turbine metal to
ensure that main steam temperature is greater than turbine metal temperature & degree of
o
superheat is > 50 C as recommended by criteria curves X4 and X5 respectively. TSE margins are
o
ensured greater than 35 K.
15. Preparing the electro-hydraulic governing system ready for operation by setting the speed & load
controller reference values & keeping hydraulic governor as back-up by raising speeder gear
position to 100%.
16. Turbine rolling to 600 rpm through speed controller.
17. Soaking of turbine at 600 rpm to fulfilled X6 criterion (approx. 1 hr), which ensures the proper
warming of HP turbine with respect to main steam temperature. Turbine parameters monitoring.
18. Speed raising to 3000 rpm by setting speed reference value at 3000 rpm without stopping in
between.
19. Soaking of turbine at 3000 rpm to fulfilled X7 criterion (approx. 45 min.), which ensures proper
warming of IP turbine with respect to HRH temperature. Monitoring turbine expansion and
shaft/bearing vibration trend.
o
20. Ensuring TSE upper temperature margin of turbine greater than 35 K.
21. Synchronization of generator to grid.
22. Load raising to 10% (20MW) through speed reference setter.
23. Closing of all manual operated drains
24. Ensuring closure of HP-LP bypass valves by increasing pressure set point above M.S. pressure.
25. Check that load controller becomes active at about 20 MW .
2
26. Raising the M.S. pr. to 50 kg/cm by taking coal mill into service and load is raised to 40 MW .
27. Charging of LP heaters from steam side and putting the level controllers of LPH 2 & 3 on auto.
• First of all bring all the electrical equipments to a state of readiness i.e., switch-on the necessary
switchgear for motors, valve actuators, controls protections and monitoring system.
• After this, carry out the necessary interlocks and protection checks feasible under stationary
condition of turbine. Certain tests and checks require bypassing of certain interlocks. All such
deliberate bypassing of interlocks must be prominently displayed in the control room during the
test. After the test, all interlocks and protections should be brought to normal state.
• Various valves as per the scheme are to be kept in open or close position. It must be ensured
that these valves are kept up in the required position. The isolating valves for all measuring
control and protective device should be kept in fully open position.
• Turbine oil quality should be checked for viscosity, neutralization number, sludges etc. If
required, the oil should be drained from MOT and topped up with fresh oil in order to restore the
quality.
• Condenser tube leakage should be checked by charging the CW system and watching the
increase in hot well level. If good amount of leakage is noticed, then action must be taken to plug
the leaking tubes.
Operation :
AOP and JOP can be started manually from PCR or on auto through “SLC-ON” or through SGC
"Auto-ON"
Take the standby trial of AOP, EOP and JOP
W hen the turbine is running, check the bearing drain oil temperature and babbit temperatures :
o
Bearing drain oil temperature : < 60 C
o
Journal bearing babbit temperature : < 90 C
o
Thrust bearing babbit temperature : < 110 C
Turning gear can be started by opening gate valve either manually or through SLC. Observe that
turbine speed on turning gear is as follows :
i) W hen no vacuum in condenser : 110 – 120 rpm
ii) At normal vacuum condition : 150 – 160 rpm
After turning gear is ON, AOP amperes will increase to 125A from 105A.
AOP, JOP and turning gear trip and pick-up speeds are as follows :
Trip Speed rpm Pick-up Speed rpm
i) Turning gear 240 210
ii) J.O.P. 540 510
iii) A.O.P. 2850 2800
2
W hen MOP takes over, the discharge oil pressure will be 8.5 – 9.5 kg/cm depending on turbine
speed.
Interlocks of AOP, EOP & JOP
2
- The standby AOP (SLC ON) will pick-up if discharge oil pressure < 4.8 kg/cm OR
- The running AOP is OFF
2
- DC Emergency Oil Pump will pick-up when SLC is ON and if lube oil pressure is < 1.1 kg/cm
- The standby JOP (SLC ON) will pick-up if running JOP trips.
Operation :
- Charge the M.S. line by opening the boiler outlet bypass valves (MS 301A/302A)
- Ensure that there is no hammering in M.S. pipeline.
- W atch the temperature rise of ESV mid wall
o o
- Rate of heating of steam pipelines should not exceed 25 to 30 C/5 min.
- During heating of M.S. & R.H. steam pipelines; the temperature difference between LHS &
o o
RHS pipelines should not exceed 15 C. But this difference should not exceed 10 C when the
set is on load.
Operation :
2
- Set the fixed pressure set point of LPBP at 3 kg/cm
- Put the LP Bypass controller on “Auto”
- Make the automatic control interface "ON"
- Ensure drain valves of CRH, HRH and W arm-up valves are open
In addition to limiting temperature changes, the relative expansion of shaft and casing must also
be taken into account. The axial and radial clearances between the rotating and stationary parts are
sufficient to accommodate any normal expansion, which may occur within the permitted range of
temperature change. In the event of abnormal conditions, however, factors other than temperature, such
as differential expansion, vibration, casing deformation etc. also have to be considered.
The TSE temperature margins also influences the speed or loading rate of the turbine if the
margins are not adequate to sustain loading.
The raising of pressure at the turbine admission during cold start-ups must be done slowly, in
order to prevent any condensation of steam. The raising of the pressure in the steam line is carried out by
establishing flow through HP-LP bypass system. W arming up of pipe line upto emergency stop valve is
done by steam flow through the drain before ESV. W arming of control valves body is carried out by
establishing flow through the drain between ESV and Control valve. Opening of this drain valve is
controlled by the TSE margins.
The criteria curves from X1 to X7, as described below, are to be fulfilled during the start-up of
turbine to rated speed and synchronization of generator thereafter.
i) Minimum main steam temperature with respect to Steam Pressure: This criterion ensures that
o
degree of superheat in the main steam at the applicable steam pressure is greater than 50 C, as
shown in Fig. 13.3.
o
∴ TMS > Ts + 50 C
ii) Minimum and maximum values of main steam temperature with respect to HP control valve body
temperature at 50% wall thickness (criteria X1 & X3): As shown in Fig. 13.1, these criteria ensure
that the main steam temperature before HP bypass is always more than curve A. W ith respect to
midwall (50% depth) temperature of HPCV, but should be less than curve B with respect to
midwall HPCV temperature. So the recommended zone for main steam temperature before HP
bypass is only between curve A and Curve B (X1 & X3 criteria). This ensures the proper steam
temperature for warming-up operation.
Criteria X1 & X3
Recommended minimum
(curve A) & maximum (curve B)
main steam temperature ahead
of HP turbine when opening
the main stop valves (ESVs)
iii) Maximum main steam pressure ahead of the turbine with respect to mid wall temperature of
HPCV (criterion X2): This criterion (X2) is shown in Fig. 13.2 which illustrates that if the steam
pressure selected is too high (i.e. high saturation temperature), the surface metal will be heated
up to saturation steam temperature due to which the temperature difference between surface and
midwall will increase beyond permissible limit. Hence steam pressure selected for rolling should
be within the reasonable limit (below the curve).
Note : However, if the control valve temperature at 50% thickness (Tmid HPCV) exceed the
temperature of the saturated steam belonging to the main steam pressure, the pressure criterion
must not be observed.
b) Criteria for opening HP control valves, i.e., raising the speed to 600 rpm (X4 & X5):
Before opening the main control valves (HPCVs), the main steam and reheat steam temperature
should fulfill the following conditions.
Main steam temperature (TMS) ahead of the turbine should be greater than Middle wall
temperature of HP casing or simulated middle phase shaft temperature (Tmid HP shaft or casing) as
shown in Fig. 13.4.
Similarly the hot reheat temperature ahead of IP turbine (THRH) should be greater than middle
phase temperature of IPT shaft (Tmid IP shaft), as shown in Fig. 13.5.
The X5 criterion ensures that inlet steam temperature is greater than turbine metal temperature so
that cooling of turbine & thereby contraction is prohibited, particularly in hot rolling.
c) Criterion for raising the speed from 600rpm to 3000rpm rated speed (X6):
This criterion, called as X6, should be fulfilled before raising the speed to rated speed, i.e. 3000
rpm. This ensures the proper warming of HP turbine rotor and casing which is a function of time
(about 1 Hr.). X6 criterion is shown in Fig. 13.6 in which the recommended zone is below the
curve. W hen the turbine is brought to 600 rpm, the middle phase HP shaft temperature will be in
the not recommended zone, but after soaking for about 1 hr. the mid-shaft temperature will be in
the recommended zone.
d) Criterion for loading the turbine (synchronization of generator) after soaking at 3000 rpm (X7):
This criterion, called as X7, should be fulfilled before synchronization of generator and loading the
turbine. As shown in Fig. 13.7, this criterion exhibits the relationship between hot reheat
temperature and the simulated middle phase temperature of IP shaft. The recommended zone is
below the curve, which ensures proper warming of IP turbine components during soaking period
(approx. 45 min.) at 3000 rpm speed.
Criterion X7
13.5.2 General
After above checks have been completed, steam can be admitted to the turbine. Typical cold-
start-up curves for 210 MW KW U steam turbine are depicted in Fig.13.8. It must be ensured that steam
parameters at the turbine inlet are matching with turbine metal temperature as discussed before. W hile
increasing the speed to 600 rpm, first the gate valve gearing (turning gear) is closed at 240 rpm and then
JOP is tripped at 540 rpm. The turbine speed during warming-up period should be preferably kept
constant. The duration of soaking period (first soaking at 600 rpm and then at 3000 rpm) depends on
casing temperature and steam pressure and temperature, as determined by TSE.
After holding the set at warm-up speed for soaking purposes, the speed can be raised to the rated
value provided the following parameters are within permissible limit.
o
- Adequate temperature margin available on TSE (greater than 35 K)
- The differential expansion of the turbine are within limits
o
- The top and bottom temperature difference of the casing within permissible limits (less than 30 C)
- Sufficient steam generation in the boiler to meet the requirement of the turbine for loading to block
load after synchronization ( > 96 t/hr ).
The speeding-up of the turbine is carried out with the help of speed-controller. The speed should
be raised quickly in the range of critical speed. The MOP takes over the supply of oil to the oil system at
about 2850 rpm and at this speed AOP is switched-off automatically.
During speeding up, bearing temperatures should be monitored closely and also the rubbing
sound in the glands.
If the turbine is to run for a long period at no load, before it is synchronized (as the case in
improving the I.R. value of generator, proper care must be taken to ensure that the exhaust-hood
o
temperature of LPT does not increase more than the permissible value (90 C), otherwise the exhaust-
hood spray valves get opened when on auto.
Before synchronization all the turbovisory parameters are checked and ensured that they are well
within the limits. After the second soaking of turbine at rated speed in case of cold start and as per the
requirements of TSE, proceed to synchronize the generator with the grid and immediately take a block
load (10% of rated load). W hen the frequency, voltage and phase angles are as per the desired
conditions, the generator circuit breaker is closed and the loading of the turbine begins. The amount of
load, which may be placed on the turbine after synchronization, and thereafter permissible rate of load,
depends on the margins indicated by TSE.
After the 5% load has been taken on the set, the cylinder drains are closed. The load controller
takes over the speed controller at about 10% loading (21MW ) and thereafter load is raised through load
reference setter.
2
- Control oil pressure = 6 – 6.5 kg/cm
2
- Trip oil pressure = 5.5 – 6 kg/cm
2
- Start-up oil pressure = 5.5 – 6 kg/cm
2
- Aux. Start-up oil pressure= 5.5 – 6 kg/cm
2
- Aux. trip oil pressure = 5.5 – 6 kg/cm
Note : If control oil pressure is less, rotate the filters in governing and ATT oil circuit.
Note : Before opening the IVs, wait till the temperature of the ESVs, HPCVs at 50% depth
increase and stabilize (normally a time period of 45 min. is required).
• AOP starts at 2800 rpm , JOP at 510 rpm & turning gear
at 210 rpm
Note : Check that HP / IP stop valves and control valves are closed.
Note : Soaking at 600 rpm is completed when the above parameters stabilize and TSE
o
upper margin (admission mode) is achieved @ 35 K. During soaking period ensure
Ensure Soaking of turbine at 3000 rpm (about 45 min) till X7 criterion for raising IP mid shaft
temperature is fulfilled.
Note 1) Control valves open in proportion to secondary oil pressure for HPCV and IPCV.
2
Control valves starts opening at 2.5 kg/cm sec. oil pressure and opens 100% at 5
2
kg/cm sec. oil pressure signal.
o
2) The rate of rise of speed is controlled by TSE margin, i.e., 0 - 30 K of TSE margin
o
gives 0 - 600 rpm/min speeding rate. However, if the margin is more than 30 C,
the speed increases at constant rate of 600 rpm/min. If TSE is faulted, it blocks
the further raising of speed or load. If the speeding rate is < 108 rpm/min then
dn/dt protection relay operates and brings down the speed set point to 600 rpm to
safeguard the turbine in critical speed zone. To get rid of this situation, operator
o
should ensure that TSE margin is > 35 K before rasing the speed and the speed
reference should be raised to 3000 rpm without stopping in between.
Note : 1) Hydraulic governor takes over at about 90% of rated speed i.e. at 2700 rpm.
Hence further raising of speed is done through raising the speeder gear.
2) TSE influence is not provided in Hydraulic governing system. Hence operator
o
should ensure TSE margins > 35 K before raising the speed to 3000 rpm.
Operation : Raise the speeder gear position so that turbine speed increases to 3000 rpm.
Observe : Turbine speed stabilizes at 3000 rpm.
Note : 1) Turbine soaking should be performed at 3000 rpm till X7 criterion is fulfilled
before synchronization and loading of turbine.
2) W atch all the turbine parameters as mentioned in 13.5.4.
Observe : • TSE disc changes over to load side and starts showing load margins
• CRH NRVs open fully
• TSE load margins shows increasing trend
• LP Bypass sliding set point comes into service
Operation : After soaking the turbine at 5 – 7 MW for about 15 minutes, raise the load on the
turbine to 20 MW by increasing speed reference.
Note : The load on the turbine should be increased through load reference by ensuring
following conditions:
1) Steam pressure shows rising trend and observe arbitrarily the difference
between M.S. pressure & turbine load about 10 till 60% load. Then up to 80%
2
load M.S. pr. Can be raised to 140 kg/cm .
2) TSE upper load margins are improved adequately by soaking at intermediate
loads 40 MW , 80 MW , and 100 MW etc.
3) After 80% load, rated values of M.S. Pressure can be achieved.
4) HP heaters can be taken into service after 100 MW load.
5) After about 40% load, gland seal steam supply valve closes and leak-off valve
2
starts opening to maintain gland steam header pressure at 0.01 – 0.015 kg/cm .
6) At about 55% load A4 NRV of Extraction-4 to deaerator is released.
Changeover the deaerator pegging steam supply from CRH to Extraction-4
(by opening Ex-301 valve).
7) Put HP bypass pressure master set point on 'Auto' in order to maintain 6 – 8
2
kg/cm positive bias with respect to M.S. Pressure as per load. This ensures
the HP bypass valves remain closed during normal operation of turbine.
8) CMC can be taken into service after 80% load on turbine and further raising of
load to rated value can be achieved by raising the unit target load set point.
Turbovisory Parameters :
Levels :
- Deaerator level : 2375 mm
- HPH-6 level : 250 mm
- HPH-5 level : 250 mm
- LPH-3 level : 410 mm
- LPH-2 level : 350 mm
Changeover Procedure
1) Switch 'OFF' tracking Device
2) Reduce speeder gear till HP secondary oil pressure drops slightly thereby load drops
3) Observe that EHC position automatically goes to 100%
4) Raise the load reference set point to 100% (so that hydraulic governor can function in
entire load range).
5) Raise the SLLD position to 100%.
6) The turbine load now can be changed by the operation of speeder gear.
Note : TSE influence is not incorporated in Hydraulic Governor, hence operator should follow TSE
Now the load on the turbine can be changed with load reference in full range with TSE influence
included in it.
1) Gradually reduce the load on the turbogenerator through lowering the unit target load set point of
CMC. Operator should observe the lower load margin of TSE so that the step change of load
should not be below this margin. The rate of reduction of steam parameters and metal
temperatures should not exceed prescribed limits and there should not be sharp changes.
2) W ith the reduction of turbogenerator load, the firing rate of the boiler should be reduced
proportionately so that HP-LP bypass valves should not open.
3) W hen the load on the machine has gradually reduced to 160 MW and all the parameters are
stabilized, HP heaters 5 & 6 are withdrawn from steam side and feed water side. Also CMC
should be taken out of service.
4) At load about 150 MW observe that steam supply to deaerator pegging changes from extraction
No.4 to CRH on interlock or change manually if needed.
5) Further bring down the turbine load to 90 MW . The M.S. pressure is brought to the level of about
2 o
100 – 110 kg/cm and M.S. temperature about 510 C by adjusting the firing rate. Out of two, one
of the BFPs can be stopped and also one air cycle may be taken out of service. W atch should be
kept on turbovisory parameters,
6) Reduce the load on the turbine further to 50 MW . At this load changeover the feed water supply
line from 100% to 30% low load line (FD 20 line). At this point only two coal mills are in service
with respective oil elevation.
7) W hen the load on the machine is reduced to 40 MW and even below, change over the auxiliary
supply from UAT to station transformer. W ithdraw L.P. Heaters 1, 2 and 3 from steam side.
2
8) Ensure that HP bypass pressure set point is adjusted to 8-10 kg/cm higher than actual M.S.
pressure.
9) Reduce the load to 30 MW and stabilize the parameters. Trip the turbine manually or through the
protection trial.
10) W hen the turbine is tripped, ensure that generator trips on Reverse Power Protection.
Note : If due to some reasons, the turbine speed is to be dropped quickly, open the vacuum
breaker to break the vacuum in the condenser immediately.
o
12) If the turbine oil temperature is dropping below 40 C, isolate the oil cooler from water side.
13) Take the HP bypass valves on manual and slowly close the valves after reducing the boiler firing.
Trip the boiler.
14) Charge the PRDS header from adjacent unit and close boiler outlet valves (MS 301,302).
15) After maintaining the hot well and drum level, CEP &BFP should be stopped.
o
16) Turning gear can be stopped when the HPT (T/B) casing and shaft temperature are below 100 C.
In case of severe emergency, generally the turbine is tripped abruptly either through lockout relay
or manually.
Following are the emergency conditions under which the set should be tripped irrespective of the
protection systems to act.
Measures to be taken :
o o
i) So in case of sharp temperature drop from 535 C to 520 C, start unloading the set by 3 MW /min.
o
and the set should be unloaded to 100 MW corresponding to 480 C. Below this temperature
turbine should be tripped immediately.
ii) To avoid thermal shocks, load or unload the set as per the recommended curves of the
manufacturer.
iii) Avoid priming of superheater in boiler as it sharply drops the temperature.
iv) Avoid mismatch of temperature beyond recommended limits during rolling the turbine.
v) In case of boiler trip, turbine should be tripped immediately.
vi) Increase the excess air percentage to increase the final superheater outlet temperature.
i) Start DC lube oil pump (EOP) to save the bearings if it is not started on auto.
ii) Remove main ejectors and gland steam cooler from service and kill the condenser vacuum by
opening vacuum breaker valves or air valve of starting ejector. Stop gland sealing when machine
comes to rest.
iii) If the turbine emergency board is charged through the starting of DG set, start AOP and put the
machine on turning gear. If hydraulic turning gear cannot be established, rotate the rotor by
manual barring.
iv) See that all the extraction NRVs have closed.
v) Monitor bearings babbit metal temperature and bearings drain oil temperature.
The rapidity of fall of vacuum due to cause (a) to (e) depend on severity of cause, whereas, in
case of (f) the fall of vacuum is very gradual over a period of time. In case the vacuum drop rate is fast,
reduce the load on turbine at the first instant. Then find out the cause of vacuum deterioration and rectify
the same.
High bearing vibrations may be due to many reasons. Most probable causes are :
Operator should control the steam parameters as per the load on the turbine and should maintain
the lube oil temperature, pressure and oil quality as specified. Also, proper and adequate soaking of
turbine should be performed during start-up so as to reduce the thermal stresses on turbine parts, normal
o
differential expansion and top/bottom casing temperature difference (< 30 C).
Increase in differential expansion may be caused due to, too fast a change in the inlet steam
temperature or due to too rapid change in the steam flow to the turbines. Hence in normal running
conditions, maintaining the steam temperatures as close as possible to the metal temperatures and
controlling the rate of change of temperature to the minimum will help in maintaining the differential
expansion within the limit. Operator should load the turbine as directed by Turbine Stress Evaluator
particularly during cold start-up and should follow the start-up curves while raising the steam parameters
with recommended rates.
During cold start-up when the steam temperature is much higher than the metal temperature the
expansion tends to go towards +ve, i.e. the rotor expands more than the casing, even though provisions
are made for warming up the turbine prior to rolling in many designs. Hence, the recommended start-up
procedure regarding the inlet parameters is to raise the inlet steam parameters, turbine speed at normal
rates and give adequate time for soaking at recommended speeds. Similarly, during a hot start, when the
rotor tends to contract, the steam temperature should be high enough and rate of rise of load should be
controlled to maintain the differential expansion in +ve side.
Further the wet steam due to priming in boiler or fall in boiler outlet pressure abruptly may cause
flashing and decrease in turbine load coupled with severe vibration and noise in the turbine. Hence boiler
outlet steam parameters should be maintained as per requirement of turbine condition.
Plant Response :
Turbines trip initiates closing of ESVs, IVs and all control valves through protection and governing
oil circuit. Simultaneously generator trip is initiated with some time-delay. However, if HP-LP bypass
valves do not open, boiler also trips on reheater protection.
If the cause of trip is such that unit can be brought on line shortly, it is not needed to break the
vacuum. However, in some cases (fire hazard, abnormal sound, very high vibration etc.), it is necessary
to bring rotor to a quick stop, in that case open the condenser vacuum breaker valve and starting ejector
air valve. This will quickly bring down the turbine at rest.
The ATT is subdivided into functional groups for each device. Each group contains the device
itself and all necessary signal transmission elements for initiation of a normal trip. The automatic turbine
tester has following two subgroups.
The complete testing of all components, which must operate when an automatic trip becomes
necessary, is assumed. The main trip valves which store the trip signal by mechanical/hydraulic means
are operated together with each protective device and the subsequent satisfactory drop in the trip oil pr.
after the valves is monitored, which initiates turbine trip alarm along with the protective device signal.
During testing of stop valve and control valves, the closing time is monitored to assure the
satisfactory operation.It is recommended to carry out the A.T.T. once in a week by bringing down the load
on the machine to about 80% (during slack hours).
-o0o-
5. C.E.G.B.
Turbine Operator Course
Lesson 13, Turbine Plant Efficiency
6. C.E.G.B.
Principles and Operation of Power Plant - Part I,
Lesson 14, Steam Turbine
7. C.E.G.B.
Principles and Operation of Power Plant - Part II
Lesson 19, Plant Performance and Optimisation
8. Gill A.B.
Power Plant Performance, (Year 2003).
9. P.K. Nag
Power Plant Engineering, Second Edition
10. J. Arogyaswam y
Power Station Practice