PRODUCT : Piping Installation
OP DESCRIPTION OF PROCESS AND RESP. CONTROL ACCEPTANCE CRITERIA CERTIFY – VERIFY PT.TTN INSPECTOR ITEM /
EPITERMA DRAWING
No. INSPECTION ACTIVITY DOCUMENT DOCUMENT
REFEREN
MDR ACT SIGN ACT SIGN CE
1.1 E Transmittal Drawing Approved Drawing / Last Rev. Drawing List/Nominate check - M R
Check design drawing
sheet ( Where Apllycable )
1.2 Check Piping GA Drawing E Transmittal Drawing Approved Drawing / Last Rev Drawing List/Nominate check - M R
sheet ( Where Apllycable )
1.3 Check Isometric drawing E Transmittal Drawing Approved Drawing / Last Rev Drawing List/Nominate check - M R
sheet ( Where Apllycable )
1.4 Pressure test (Hydro test) SF, Hydro test Procedure 1981-000-PISPC-0002 Hydro test report Yes SM R
QA/QC
1.6 Surface Treatment, check DFT of painting QA/QC Painting Procedure 1981-000-MESPC-0001 Painting report Yes SM R
ACTIONS H= HOLD I = INSPECT M = MONITOR W = WITNESS R = REVIEW R/A = REVIEW AND APPROVE SM = SUBMIT
RESPONSBILITY QC = QUALITY CONTROL E = ENGINEERING SP = SUPERVISOR MC = MATERIAL CONTROL SPT = SUPERINTENDENT F = FOREMAN SF= SAFETY
INSPECTION AND TEST PLAN FM 427 Rev. 1
PRODUCT : Piping Installation
OP DESCRIPTION OF PROCESS AND RESP. CONTROL ACCEPTANCE CRITERIA CERTIFY – VERIFY PT.TTN INSPECTOR ITEM /
EPITERMA DRAWING
No. INSPECTION ACTIVITY DOCUMENT DOCUMENT
REFEREN
MDR ACT SIGN ACT SIGN CE
4.1 Check the place for crane SF Epiterma’s HSE PTTTN Job Safety Analysis Preparation Check List - I R
Management Project Plan
4.2 Prepare for all crane support equipment F Epiterma’s HSE PTTTN Job Safety Analysis Preparation Check List - I R
Management Project Plan
AWS D1.1/ASME
Check the pipe line with the actual
5.1 E Piping Design Drawing B31.Series/1981-0000-PISPC- Piping Installation Check List. - M M
situations
0002
AWS D1.1/ASME
Make sure pipe not cross steel structure and
5.3 E Piping Design Drawing B31.Series/1981-0000-PISPC- Piping Installation Check List. - M M
mechanical or electrical.
0002
AWS D1.1/ASME
Make sure pipe support already installed
5.4 F Piping Design Drawing B31.Series/1981-0000-PISPC- Piping Installation Check List. - I M
properly.
0002
ACTIONS H= HOLD I = INSPECT M = MONITOR W = WITNESS R = REVIEW R/A = REVIEW AND APPROVE SM = SUBMIT
RESPONSBILITY QC = QUALITY CONTROL E = ENGINEERING SP = SUPERVISOR MC = MATERIAL CONTROL SPT = SUPERINTENDENT F = FOREMAN SF= SAFETY
INSPECTION AND TEST PLAN FM 427 Rev. 1
PRODUCT : Piping Installation
OP DESCRIPTION OF PROCESS AND RESP. CONTROL ACCEPTANCE CRITERIA CERTIFY – VERIFY PT.TTN INSPECTOR ITEM /
EPITERMA DRAWING
No. INSPECTION ACTIVITY DOCUMENT DOCUMENT
REFEREN
MDR ACT SIGN ACT SIGN CE
Make sure all pipe free from contaminant Piping Design Drawing AWS D1.1, /ASME B31.Series
6.2 F Piping Installation Check List.
carbon material Isometric & drawing P&ID / 1981-000-PISPC-0002/001
For the weld connection make sure to have Piping Design Drawing AWS D1.1, /ASME B31.Series
6.3 F Piping Installation Check List. - I M
the place for weld or tie up. Isometric & drawing P&ID / 1981-000-PISPC-0002/001
Make sure all connected pipe already tie up Piping Design Drawing AWS D1.1, /ASME B31.Series
6.4 F Piping Installation Check List. - I M
or full weld Isometric & drawing P&ID / 1981-000-PISPC-0002/001
Check internal cleaness for pipie Piping Design Drawing AWS D1.1, /ASME B31.Series
6.5 F Piping Installation Check List. - I I
Debris,letfover tool material Isometric & drawing P&ID / 1981-000-PISPC-0002/001
7.0 WELDING
ACTIONS H= HOLD I = INSPECT M = MONITOR W = WITNESS R = REVIEW R/A = REVIEW AND APPROVE SM = SUBMIT
RESPONSBILITY QC = QUALITY CONTROL E = ENGINEERING SP = SUPERVISOR MC = MATERIAL CONTROL SPT = SUPERINTENDENT F = FOREMAN SF= SAFETY
INSPECTION AND TEST PLAN FM 427 Rev. 1
PRODUCT : Piping Installation
OP DESCRIPTION OF PROCESS AND RESP. CONTROL ACCEPTANCE CRITERIA CERTIFY – VERIFY PT.TTN INSPECTOR ITEM /
EPITERMA DRAWING
No. INSPECTION ACTIVITY DOCUMENT DOCUMENT
REFEREN
MDR ACT SIGN ACT SIGN CE
AWS D1.1/ASME
-Spool traceability check QA/QC,
8.1 Piping Design Drawing B31.Series/1981-0000-PISPC- Piping Installation Check List. Yes I I
-Dimension check F
0002
10.1 Make sure all pipes already finish SP Design Dwg 1981-000-PISPC-0002/0001 Pre-commissioning and Yes M W/R
connected. Inspection Check List
ACTIONS H= HOLD I = INSPECT M = MONITOR W = WITNESS R = REVIEW R/A = REVIEW AND APPROVE SM = SUBMIT
RESPONSBILITY QC = QUALITY CONTROL E = ENGINEERING SP = SUPERVISOR MC = MATERIAL CONTROL SPT = SUPERINTENDENT F = FOREMAN SF= SAFETY
INSPECTION AND TEST PLAN FM 427 Rev. 1
PRODUCT : Piping Installation
OP DESCRIPTION OF PROCESS AND RESP. CONTROL ACCEPTANCE CRITERIA CERTIFY – VERIFY PT.TTN INSPECTOR ITEM /
EPITERMA DRAWING
No. INSPECTION ACTIVITY DOCUMENT DOCUMENT
REFEREN
MDR ACT SIGN ACT SIGN CE
10.2 Installed blinds and blanks to isolated F Design Dwg 1981-000-PISPC-0002/0001 Pre-commissioning and - M W/R
facilities from pressure test. Inspection Check List
10.3 Increased pressure slowly and allowed to SP Design Dw 1981-000-PISPC-0002/0001 Pre-commissioning and - M W/R
stabilize to monitor for leakage. Inspection Check List
10.4 1 hours pressure recorders as required. SP Design Dwg 1981-000-PISPC-0002/0001 Pre-commissioning and Yes M W/R
Pressure drop >5% Inspection Check List
10.5 Flushing and blowing SP Design Dwg 1981-000-PISPC-0002/0001 Pre-commissioning and - M W/R
Inspection Check List
ACTIONS H= HOLD I = INSPECT M = MONITOR W = WITNESS R = REVIEW R/A = REVIEW AND APPROVE SM = SUBMIT
RESPONSBILITY QC = QUALITY CONTROL E = ENGINEERING SP = SUPERVISOR MC = MATERIAL CONTROL SPT = SUPERINTENDENT F = FOREMAN SF= SAFETY