Sie sind auf Seite 1von 14

Arc Furnace Electrical Workshop 219

Fundamentals of the Electric Arc Furnace


by J. R. Bello

The electric arc furnace has its roots back in the


early 1900's as a practical device for melting metal. It
has, however, been traced to 1800 with the discovery of
the carbon arc. The first production electric arc furnace
for metals melting was successfully installed in France
in 1900. This furnace of rather primitive design was a
two-electrode, single-phase unit with manual electrode
positioning and rectangular carbon electrodes (Figure
1).
During the period between 1900 and 1940, furnaces in
sizes ranging to 15 feet or 50 tons capacity were built
and supplied to specialty steel users. The direct arc
furnace was first thought to be only applicable as a
specialty steel producing tool particularly useful in
stainless and alloy steels. Just prior to World War 11,
the arc furnace began to realize substantial acceptance
in the steel industry for the production of plain carbon
steels with a corresponding increase in size and power
ratinas. During this period the electrical suppliers rec-
ognizing an interest in the equipment involvements de- Fig. 1--One of the first electric arc furnaces.
veloped improvements in the electrical equipment to
meet this fast expanding industry.
Perhaps the most significant improvements in electric tories, and the arc flaring toward the refractories will
furnace design has taken place in the last ten years. cause rapid wear patterns.
During this time, ultra-high-powered equipments have The effect at the foot of the electrode is quite like a
been installed and power supplies extending beyond welding operation where a converter is used, either a
200,000 kva are now contemplated. These furnaces are transformer or M-G set, stepping the voltage down from
highly sophisticated in their electrical design, but still a typical supply of 460 volts, three-phase, 60 cycles to
retain the original circular shape with the cantilevered a low voltage required for weld metal fluidization. The
electrode positioning idea. electric arc furnace uses a transformer which in effect
An electric arc furnace can operate using direct cur- develops the low voltage required to create the electric
rent, single-phase alternating current, or three-phase arc.
alternating current. The most widely accepted service The three-phase electric arc furnace is the most prac-
is a three-phase electrical supply system connecting tical type due to its compatibility with typical three-
three electrodes mechanically displaced at 120". The phase utility transmission system. Single-phase furnaces
thermal energy produced in an arc furnace is radiation are built more for experimental purposes in rather
at the foot of each of the three electrodes. Any metal small sizes which will not disturb the utilities mains.
which will conduct electricity can be melted in an The amount of energy produced in the arc zone is a
electric arc furnace. Limitations must be applied to function of the rating of the equipment, and is basically
certain low melting point metals, which in effect must a volt-ampere consideration. In an alternating current
be treated very carefully in order to produce the de- profile, this volt-ampere relationship displaced by phase
sired results with some degree of economy. angle or power factor produces kilowatts in the arc zone,
In a three-phase supply system, the power which and these kilowatts can be directly related to energy in
occurs at the tip of each of the three electrodes is elec- the form of BTU, one kw-hr being equivalent to 3413
trically displaced 120". Domestic power supplies use a BTU. To explore this, let's consider a typical alternating
frequency of 60 cycles per second. At 60 cycles per sec- current circuit involving the three fundamental com-
ond or 60 Hertz, 120 bursts of energy will occur under ponents: voltage, current, and impedence. Ignoring for
each of the three electrodes each second. The tempera- the moment arc resistance and a small com~onentof
ture of these arc bursts is the boiling point of the ma- circuit resistance, the impedence element translates to
terial acting as the cathode during that period of igni- inductive reactance. So, essentially we have a voltage,
tion and energy flow. For example, when the graphite current, reactance consideration. The circuit reactance
electrode becomes the emittor or energy producing causes volt-ampere displacement, the vector sum of
source, the power is transmitted from the tip of the which is the energy or power that appears at the tip of
electrode to the scrap charge, leaving in its wake a each electrode. In its simplier form, we can say an
highly ionized resistance path. At this time the tempera- analogy of this might be an automobile being stopped
ture of the arc will range from say 6,500" to 19,000°F. from a sample speed of 60 mph. To stop the vehicle in-
During the opposite period, or interval when the arc volves a certain amount of reaction distance and brak-
energy flows from the metal back to the electrode, the ing distance, the sum of which then becomes the total.
arc temperature may be in the range of 6,000" to If we assume that the energy or kilowatts in the arc to
9,000°F. Arc ignition and energy flow follows a somewhat be the actual distance traveled during braking reaction
plastic path established by gases and vapors suspended time, that time required to apply braking or reactance
between the electrodes and the metal. The average or or kilovars of the circuit, the vector sum would then be
mean temperature may be in the range of 6,000" to kva. Unfortunately the values do not add arithmetically
9,000°F. Needless to say, this temperature is signifi- in the alternating current circuit but form a right tri-
cantly higher than the thermal resistance of the refrac- angle. The circuit power vector is obtained from the
resulting angle.
This operating power factor varies according to fur-
J. R. BELL0 is a Staff Engineer, Lectrornelt Corp., Pittsburgh, Pa. nace size. On small electric arc furnaces, satisfactory
operation occurs in power factor ranges of 75 to 80%. As
220 Electric Furnace Proceedings, 1971

the furnace and power supplies become larger, lower


operating power factors are used due to the longer
overall electrical circuit length requiring higher secon-
dary voltages. This is necessary to obtain a desired arc
length which will not cause unusual refractory wear.
Arc radiation emission becomes a matter of equal dis-
tribution of energy at the tips of the three electrodes
with 1/3 of the measured kilowatts being supplied to
each electrode.
Since the average arc temperature of roughly 6500°F
never changes, in spite of energy input change, we con-
trol the thermal input by increasing and decreasing the
kilowatts thereby increasing or reducing the BTU in the
arc zone. For this reason, it is necessary to observe
caution in furnace operation at the end or the meltdown
period. At this time refractory wear can occur from a
high energy long arc sweeping across the metal surface
and bursting against the exposed refractories of the
sidewall and roof. In theory, no refractory damage can
occur during meltdown. The cold scrap has a high affin-
ity to absorb thermal radiation from the arc. In fact, the Fig. 3--Charging with a clam shell bi-parting type bucket.
hot face refractories actually dissipate latent or stored
heat into the scrap charge. The time of critical concern duced to essentially one half of the transformer name-
is the transition period between meltdown and the re- plate kva rating expressed in kilowatts. When the metal
fining energy levels. With cold scrap all around the is then totally fluidized in the furnace, samples are
slag line, no damage can occur from.the long meltdown
arc. However, if any area in the furnace becomes com- taken for metallurgical and chemical analysis and cor-
pletely melted away to the refractory surface during this responding adjustment made. The furnace may then be
period, the arc related to that particular electrode will slagged off by tilting backwards and then tilted forward
then impinge on the refractories. for tap out through the spout into a ladle to facilitate
In a typical electric arc furnace, the charge material a complete drain (Figures 4 and 5).
or scrap is vertically unloaded or drop charged into the During the finishing period, the power input is re-
refractory-lined steel jacketed vessel. This is done by duced by voltage adjustment of the furnace transformer,
clam shell or orange peel type charge bucket delivered creating an arc length which will drive the energy deep
to the furnace by overhead crane (Figures 2 and 3 ) . The into the liquid metal.
charge device is generally sized at about 80% of the vol-
ume metric holding capacity of the refractory lined ves-
sel interior. This provides a near uniform filling of the
furnace to the top flange. Due to scrap volume it is gen-
erally necessary to make a minimum of two charges in
order to get the proper heat size.
In o p e ~ t i o nduring meltdown, the electrodes drill
three throats through the scrap charge thereby reducing
approximately 15% of the total charge to fluid at the
hearth of the furnace. At this time, the liquid metal
begins to expand consuming the remaining scrap from
beneath and causing the metal to descend into the
liquid pool. During this descent, the scrap may tend to
tilt or come in contact with the electrodes requiring
rapid electrode withdrawal. When the first bucket
charge has been sufficiently reduced to accommodate the
second bucket, this charge is then dropped into the
furnace and the total scrap melted to fluid. During the
meltdown period, the furnace transformer operates at an
energy level consistent with its maximum rating. When
the metal is nearly fluid around the periphery of the Fig. &Tapping a 25-ton furnace.
slag line, the power input to the furnace should be re-

Fig. 2--Charging a furnace with an orange peel bucket. Fig. &Tapping a 200-ton furnace.
Arc Furnace Electrical Workshop 221

It is the furnace operator's judgment a t refining as to


power and arc length which will prevent rapid refrac-
tory wear and also establish a power input situation
consistent with raising temperature and meeting final
suecifications. The modern electric arc furnace provides
instrumentation to aid the furnace operator in-making
this determination. For example, in a typical steel- or
ironmaking operation, the equation for determining
when to add the second bucket charge or reduce the
power input for refining is a function of the scrap
weight charged into the furnace. It is a power-time
equation where the number of tons charged is multi-
plied by approximately 320 kilowatt-hours. This total,
when registered on the kilowatt-hour meter, should
represent the approximate time for recharge. After re-
charging, following the same procedure of measuring
the total tons charged by 320 kilowatt-hours, will give
an indication when to reduce the power for the refining
or finishing period. There are three basic factors which
affect the overall performance of the electric arc furnace
as related to refractories, electrodes, and power con- Fig. 7-Furnoce transformer installation.
sumption.
connection in delta for attachment to the conductors
1. The power input distribution to each of the three going to the electrodes. Tap changing or ratio adjust-
electrodes must be symmetric. ment is always done in the primary winding where the
2. The furnace should be mechanically in good repair current or ampere flow is significantly lower than in the
and maintenance with the electrodes truly vertical and secondary. Off-load transformer tap changers are gen-
equally spaced. erally arranged to make available four or six tap posi-
3. Distribution of scrap, where the scrap should be tions at the operator's control panel. On small furnace
graded from the heaviest material at the bottom of the applications, generally up to 10,000 kva, four tap posi-
furnace to the lightest at the top. The furnace should be tions are selected from twelve available voltages in the
uniformly filled and all zones properly covered with furnace transformer. Six of these voltages are in pri-
scrap. The charge buckets should be opened quickly so mary delta-secondary delta, the other six in the primary
that the metal, if properly located in the charge box, wye, secondary delta profile. The latter six represent
wili then relocate in the furnace with the heaviest at reduced capacity or low energy levels of voltages useful
the bottom and the lighter, fluffy scrap at the top. Fol- for final finishing and holding metal temperature await-
lowing this procedure, refractory erosion adjacent to ing the ladle. Above 10 mva with off-load tap changers,
the three electrodes should be relatively uniform. six taps are selected again from the twelve total taps as
If, at any time, unusual wear occurs in any one of the outlined above.
arc zones, this could be attributed to non-compliance in In nearly all cases the secondary or low voltage
any one of the three areas outlined above. winding of the furnace transformer is connected in
The electrical equipment in the electric arc furnace delta. In the early days of electric furnace operation,
involves a utility transmission system, generally at sub- furnace transformer secondaries were connected in wye.
transmission voltages delivered to the furnace trans- The neutral leg of this wye was brought out and at-
former primary windings (Figure 6 ) . The furnace trans- tached to the bottom center of the furnace shell. Un-
former and power equipment is generally located in a fortunately, in such an arrangement, if nonconductive
vaulted enclosure designed to accommodate the ~ h v s i c a l material-such as wood, cloth or brake shoes, should
equipment size (Figure 7 ) . Furnace transformers are insulate two electrodes-the third, having an electrical
made up in on-load as well as off-load tap changing connection to the furnace transformer, could melt
equipment. Tap changers are ratio adjusting mechanisms through the bottom of the furnace since insufficient
necessary to secure the voltages required to accommo- metal would be delivered to the basin during meltdown.
date the varying power input requirements for melting With the advent of the delta-connected furnace trans-
and finishing. The furnace transformer is not unlike a former secondary, the possibility of electrically melting
utility power transformer in that it has an iron care and through the hearth has been eliminated, but unfortu-
uses copper or aluminum windings separated with an nately there are occasional run-outs and burn throughs
insulating barrier. In the case of the furnace trans- due to lining problems.
former, however, the high voltage coils are wound next The electric arc furnace operating switch or circuit
to the iron core, an insulating barrier, and the low breaker has for many years been a very difficult prob-
voltage heavy copper or aluminum bus sections wound lem for electrical manufacturers as well as furnace
on the outside. The bus bars representing the coil ends builders. The arc furnace imposes the most stringent
are brought up through the tank cover arranged for switching duty of any power electrical equipment. The
earliest switches were oil circuit breakers with their
related maintenance due to oil contamination. These
were superceded by air magnetic circuit breakers which
did a fine job electrically, but again were simply ham-
mered to pieces mechanically. In order to provide good
switching performance, the air magnetic unit had to
function extremely fast. This meant high inertia on the
moving parts and usual stresses on the linkages or con-
necting pins. These linkages and other mechanical parts
would fail and require frequent maintenance. The main-
tenance, however, on this switch type was far less fre-
quent than on the old oil circuit breakers. Recently,
hybrid switching devices have become available, and a t
this time perhaps the most desirable switching device
for the arc furnace is the vacuum interruptor. This
method involves tungsten conductor rods impregnated
with a low melting point ionizing alloy in a glass-vac-
Fig, 6-Electrical line diagram of a typical orc furnace. uum evacuated envelope (Figure 8). The complete
222 Electric Furnace Proceedings, 1971

"bottle," as it is termed, is located in a porcelain en- flexible conductors. Inside the wall, the bus connections
closure and requires very little mechanical force for are made at various elevations so the secondary bus
operation. As a result, it has been most successfully bars may pass each other in closing the delta vector. The
applied to eIectric furnace applications. Its overall phys- bars are then rigidly emplaced in the transformer room
ical size makes it ideal for location adjacent to the wall and insulated to prevent current flow between the
furnace transformer in the transformer room vault phase sections. On medium and large furnaces the total
(Figure 8 ) . secondary system is arranged in a triangular form. The
Capacitors are sometimes used for power factor cor- reason for this "triangulation" as it is called is an effort
rection on electric arc furnace installations, particu- to balance the power input between each of the three
larly in large electric furnace operations where melt- phases by equidistant mechanical centers between the
down power factors are in the 70% range (Figure 9 ) . three phases. This provides a situation where each of
Utility power contracts imply that some power factor the electrodes will deliver the same amount of energy.
improvement is necessary in order to reduce the kvar Water-cooled or air-cooled cables are used as a
load on step-down transformers and transmission sys- method of carrying the current from the terminal head
tems. This sometimes appears as a "penalty" in the bill- connection point at the transformer room wall to the
ing contract. We have found that the use of capacitors terminal head at the furnace side (Figures 10 and 11).
requires consideration from the standpoint of over volt- Flexibility in this area is necessary to permit the fur-
ages and switching. The capacitors should be rated for nace to rock or tilt for slagging and emptying, and also
the highest system voltage excursion, and should take to provide flexibility in roof swing for vertical charging
into account harmonic penetration from furnace opera- of scrap.
tion. If possible, the capacitors should be located at a On the furnace, the water-cooled bus tubes, located
position in the system where it will not be necessary to above the electrode arms, are also arranged in a tri-
switch them frequently. This is particularly true on angular profile. With electrical triangulation resulting
large capacitor bank installations. from the mechanical arrangement of secondary flexible
The arc furnace electrical circuit toward tlhe furnace cables and bus tubes and the obvious 120" displace-
from the furnace transformer is designed to reduce ment of the electrodes, an effort should be made to keep
inductive effects in such high current applications. This the electrode arms at the same relative elevation. This
means transposing the winding ends of the furnace can be done by slipping the electrodes just prior to
transformer to minimize the inductance and also make meltdown, or during the early phase of meltdown, such
greater use of the copper or aluminum bus sections. that the arms do become essentially level, thereby en-
The delta closure at the furnace transformer, either hancing the possibility of getting good uniform electri-
made up by air-cooled or water-cooled bus connections cal energy distribution at the tips of the electrodes.
from the furnace transformer secondary terminals, goes On small arc furnaces, generally below 5,000 kva tri-
through the transformer room wall for connection to the angulation of the secondary conductors is not done since

--
Fig. &Vacuum interruptor rated 15 kv 600 amps.
Fig. l&Furnace equipped with air-cooled cables.

Fig. 9-Capocitor bank instollation adjacent to step-down trans-


former. Fig. 11-Furnace equipped with water-cooled cables.
Arc Furnace Electrical Workshop 223

a sizable reactor acting as a symmetric impedence is


included in the furnace transformer.
Graphite electrodes act as the conductor material for
the energy flow to the arc. Graphite, incidentally, is an
excellent material to produce a high temperature arc
since it has a extremely high boiling point. It also pro-
duces high levels of ionization or vaporization which
then causes a quick return reaction or circuit connec-
tion from the metal back to the electrode to provide
continuous arcing.
There are a number of methods of electrode control
applicable to the electric arc furnace: electrical, me-
chanical, hydraulic, and combinations of hydraulic and
pneumatic (Figures 12-16).
There are two salient entities in the operation of the
arc furnace. These are power circuit stability and ac-
curate electrode positioning control. We will deal with Fig. 1 L A s s e m b l y of magnetic variable (flux clutch) drive.
the power circuit consideration a little later. As regards

Fig. 16-Control module for one phase of magnetic variable coupling.

Fig. 12-Wiring diagram of contactor regulator using d.c. motors.


the electrode positioning control system it should be
fast, accurate, and responsive to the error signals, this
error being developed as a product of the phase to
P --! neutral voltage and line current reference. Such an
"Impedence" control permits operation at a constant
power factor and arc length in spite of line voltage
variation consistent with good operation. The electrode
travel speed should permit fast electrode movement
especially when the scrap topples against the electrodes
and the controller must then elevate the electrodes at
high speed to reduce the stresses of such a short circuit
on the utility system's supply and furnace electrical
equipment.
The electrode speed, particularly during cave-ins, and
the period when electrodes are being raised to swing the
roof, should on small furnaces be in the range of 13
feet per minute to the largest furnaces up to 20 feet per
Fig. 13-Assembly of rotating amplifiers tor electrode control. minute. During automatic normal electrode control
electrode speeds of about 8 feet per minute down and 8
feet per minute raise serves the melting needs quite ef-
fectively providing the maximum available ascent travel
speed automatically occurs on scrap cave-in short cir-
cuits.
The electrode control should provide a uniform power
input control in maintaining a very narrow kilowatt
envelope (Figure 17).
High response in the electrode drive system is de-
sirable in order to minimize the disturbances to the
power system while the electrodes are in arcing opera-
tion. A high speed system will also reduce the fre-
quency of furnace circuit breaker operations. This high
speed can only be available if the electrode drive sys-
tem has very low inertia. In an electromechanical sys-
tem, the drive motor therefore should have a high
torque to inertia ratio. The drive system should be
capable of forcing the arm-column-electrode assembly
into its natural frequency. This natural or resonant
frequency on large electric arc furnaces is in the neigh-
borhood of four cycles per second. This means that a
Fig. 1 k A s s e m b l y of static (S.C.R.) regulating system. responsible electrode control system or one being able

I
224 Electric Furnace Proceedings, 1971

begin to melt, and when a third electrode contacts,


three-phase power contact occurs.
Electrodes are added at the top and this is done by
adding a nipple to a machined socket in the top end of
the electrode, and then adding a new electrode to this
insert. The electrodes are tightened with a chain wrench
and then adjusted in the electrode holder. Electrodes
should never be clamped in a joint. Normally, the
graphite producers of electrodes use a narrow white
band painted on the electrode as the space within which
the electrode must not be clamped. Slipping the elec-
trode can be done shortly after a new charge is dropped
into the furnace. The melter will meltdown until he
creates a socket in each of the three electrode zones. At
this point, the furnace circuit breaker is tripped. The
electrodes can then be lowered into this socket, the
power clamp released, the electrode arms raised to the
Fig. 17-Typical power input (kw) recording of a furnace heat. new elevation, and the electrodes clamped again. This
method does not involve the overhead crane.
Typical commercial arc furnaces range in size from 4
to position at the rate of 15 cycles per second would foot ID rated 1200 pounds and powered with about 500
reach the natural node of a conventionally designed kva to 32 foot rated 400 tons, and powered in excess of
electric arc furnace mechanical system (Figure 18). 150,000 kva. A 32-foot furnace is now in operation at
Beyond this, resonance would precipitate hunting and Northwest Steel and Wire Company at Sterling, Illinois.
require reduced gain in order to produce uniform con- Modern foundry furnaces range in size from 8 foot to
trol. In all cases where electromechanical systems are 12' 6" with holding capacities of 5 to 30 tons and
involved, a gear box is necessary to act as a speed re- powered with transformers ranging from 3,500 to 15,000
ducer between the electrode drive and the drum capstan kva. Nominal transformer primary voltages range from
for rope positioning. The load in this case is overhauling 13.8 kv to 34% kv.
in the down direction, and since you cannot push a rope, One of the most important matters in good furnace
the electrodes always descend by gravity. A number of performance is a good ground connection between the
variations of hydraulic systems have been used, these furnace shell bottom and the electrode control equip-
are both hydraulic cylinder piston arrangements for ment. The ground connection should be a flexible con-
raising and lowering of electrodes as well as hydraulic ductor attached precisely at the bottom center of the
motors acting directly on gear boxes with rope drums. furnace shell, and brought directly to the electrode con-
In operation, the electrodes are raised to full height trol system, then tied to the common ground of the
and the roof swung around for charging. This is done by earthing system in the building.
appropriate control actuators. With the roof swung, the When the refractories are cool in the furnace, or after
batch charge can be added to the furnace. The furnace a new lining has been installed, the refractories mate-
operator then returns the furnace roof onto the fur- rial does not conduct well. This means that a good con-
nace usually from a separate control stand which posi- duction path between the metal and the furnace shell
tions the roof. The remote location of the roof lift and is not available. To assist regulation at this time, a pipe
swing apparatus is used in order to permit the furnace should be laid across the furnace hearth under the
operator good visual access to this area when this func- charge and this pipe then jammed aaginst the furnace
tion is being performed. After the charge has been added door to provide a ground connection until the refrac-
to the furnace and the roof returned and lowered, the tories become hot and conductive. When the refractories
furnace operator closes the furnace circuit breaker, are hot they will conduct properly. Magnesium oxide
turns the furnace control into its automatic mode oi and aluminum oxide both act as good conductors be-
operation. At this time the electrodes descend and begin tween the furnace basin to ground. Silica refractories,
the meltdown procedure. The electrodes randomly con- however, do not have this resource. In cases where elec-
tact the scrap which means that one electrode will tric arc furnaces are lined with acid material, ground
usually touch before the other two. When this first rods must be located in the bottom of the furnace
electrode contacts the scrap, it stops. It stops because its brought up through the refractories material and then
descent signal resulting from the phase to neutral volt- flattened out over the surface of the refractories. This
age is reduced to zero. In other words, the control ele- is necessary to provide a good ground circuit connection
ment which causes the electrode to descend is taken during operation, since acid refractories tends to sur-
directly from the electrode to the bottom grounded face sinter and remain in power form several inches
center of the hearth. When the second electrode con- under the glazed hot face. With acid bottoms, ground
tacts the metal, a single phase situation is developed straps should be attached to the shell of the furnace di-
and energy flows between the two electrodes. They then rectly beneath each of the three electrodes and a fourth
strap in the bottom center of the furnace. These straps
should be %" thick, 1%" wide, and say 42" long, welded
in the zones required and brought up through the re-
fractories. The brick or ramming material should be
laid around these straps so they can project up through
the final impacked refractories. They can then be bent
over against the outer face of the hearth. This ground-
ing is a vital part of good acid electric arc furnace per-
formance.
In order to determine if the ground of the furnace is
effective, you can proceed as follows. With liquid metal
in the furnace, insert a pipe into the liquid with the fur-
nace in operation at a low tap, and bring this pipe into
contact with the furnace shell at the door. If sparking
occurs, this means that the ground connection at the
bottom center of the furnace is not effective. I n this
case, it would be desirable to keep a pipe connection
under the charge against the door of the furnace in each
Fig. 18-Electrode travel speed oscillograrn. of the consecutive heats until the sparking disappears.
Arc Furnace Electrical Workshop 225

If acid refractories are used in the furnace, it may be put was concerned. The kilowatts were there, the volt-
necessary to drill up through the bottom and drive a amp relationship was there, but the electrodes were
rod into the hearth in order to create a ground connec- certainly not melting. This extreme condition was cre-
tion. When sparking does occur with the metal fluid in ated by the high level of zinc in the furnace which pro-
the furnace, you can almost expect excessive electrode duced a super ionization situation between the electrodee
breakage during meltdown and extremely erratic fur- where all the input energy was being transmitted from
nace operation. It could also cause unusual refractories electrode to electrode rather than from electrode to
wear, simply because the electrode control system is scrap. In varying degrees this type of ionization prob-
not truly neutral at the bottom center of the furnace. lem occurs in all operating electric arc furnaces. A cer-
This is a point at the precise center of the delta vector tain amount of energy is bled from electrode to electrode
formed by the secondary circuit of the furnace trans- during operation. It increases as the arc length increases,
former. however, and if the arc length then becomes greater
Since small electric arc furnaces seem to operate bet- from electrode to metal than it is from electrode to elec-
ter at power factors generally higher than large fur- trode, the electrodes will retract possibly to full height
naces, regulation of small furnaces is more difficult. with no appreciable change in power input.
The very large furnaces seemingly require very little Most new furnace installations are equipped with
electrode control where the scrap is literally blasted smoke and fume collection apparatus which tend to
out from under the electrode. In order to sustain and ventilate the furnace and can reduce this problem.
follow and arc near its threshold of stability, as is the However, there still remains a problem with certain
case in the small electric furnaces, the control must be low melting point residual metals which can get into
extremely reliable. With a related longer arc on the the scrap and cause unusual power input consumption.
small furnaces, less latitude for control over-shoot oc- In fact the super ionization situation can very easily be
curs and the regulator, in order to control the relative detected if significant changes occur in the kilowatt-
longer arc, of necessity must be much more responsive. hour consumption per ton or heat. An analysis review
So much for the theoretical side. Now let us consider of the scrap in such a situation may reveal that unusual
the practical aspect of the electric arc furnace. I believe levels of low melting point residuals are the problem.
that the most important concern of a furnace user is to Scrap quality is fundamental in developing good elec-
have a good understanding of how and why the arc tric furnace performance. Ionization excess causes un-
performs. We have all looked in the furnace and we usual happenings in the electric furnace where low
have all seen the arc in operation at the tip of the elec- melting point residuals can really be a liability. Scrap
trodes. In order to comprehend exactly how the energy dealers are cognizant of the various qualities of scrap.
is transmitted from the electrode, let us again review Generally, the more costly scrap does produce fewer
some of the discussion items. First of all, arc tempera- difficulties and will provide the best operating econom-
ture. The arc temperature in an electric arc furnace ics.
never changes. The average arc temperature is a func- If, in the electric furnace, we were arcing from a
tion of the materials producing the arc. Reducing or graphite electrode to a graphite pad, the arc length
increasing the kilowatt input of the furnace does not in would be an absolute dimension. This arc gap at a spe-
any way affect the actual temperature of this arc. Short- cified power input would be maintained all the time.
ening the arc or lengthening the arc in no way affects However, since various types of scrap are used in the
this temperature. The transfer of energy at the foot of furnace, the arc length varies depending on that type
the electrodes is affected by making adjustments both of scrap and hence the thermal transfer varies accord-
to raise or lengthen, lower, or shorten the arc, which ingly. We have no control over the type of scrap that
will increase or decrease the actual kilowatt input to customers use and it is up to the customer then to do
the furnace. his homework in data collecting on the various types
Ignition intervals, during both the times of the elec- of scrap that he purchases for a given furnace opera-
trode acting as the cathode and the metal response, af- tion. It is often the case that saving a dollar or two per
fect the shape of the sine wave input and produce addi- ton on certain types of scrap develops costs of $10 to
tional variations on its shape which are called harmon- $15 per ton in the melt shop. Such an economic ap-
ics. Depending on the nature of operation, long arc or praisal can very easily point up the need to purchase
short arc, high or low power input, this characteristic better quality. This means a good communication liaison
could be modified to the point where the actual fre- between the purchasing agent and the melt shop and
quency produced in harmonics from-the arc could be the importance of not using arbitrary judgment in pur-
in the high kilocycle range. chasing raw material.
Ionization or conductive vapors which occur in the Visual as well as audible indications of refractories
electric arc zone, both during the positive and negative damaging arc lengths are part of the arc furnace scene.
period, produce a resistance path from th? electrode to A good melter can easily detect the cutting sound of
the metal. The gases in this zone are highly conductive arc flare. This can also be detected during the refining
and provide the ignition and re-ignition paths from the period by simply opening the door of the furnace. If
electrode to the metal. The result of looking at the arc sparks issue from the furnace, this means that the va-
gives the appearance of one continuous arc stream, elec- pors and gases from the tip of the electrode to the metal
trode to metal. This gaseous and plastic resistor can be are actuaIly impinging on the refractories surface and
influenced by a number of factors. There is a weather are causing refractories erosion. During the finishing
influence, for example. Many of you will find that your period, with the door opened, and assuming there are no
furnace will perform better in the summer than it does small chunks of graphite floating around to intercept an
in the winter. As humidity is generally higher in the electrode and produce a burst of flare energy, the fur-
summer months, this high humidity tends to cause the nace should be very quiet and have a smooth 60 cycle
electrode to operate slightly closer to the metal. The hum.
result is a better thermal distribution of energy from As the electric arc furnace, during meltdown, drills
the tip of the electrode to the metal. three holes through the scrap, the actual amount of
The actual arc length is a function of secondary vol- metal delivered to the hearth is a function of a number
tage, impedence, circuit design, and ionization density. of factors and the character of the scrap. Most signifi-
An example of extreme ionization density and perhaps cant is secondary voltage and residual scrap carbon
the best one that comes to mind, is a small electric fur- Properly designed, the voItage should be correct for the
nace operation in Northeastern Ohio. This customer furnace size and power rating. Carbon is a vehicle for
charged some zinc-coated scrap into their furnace. When thermal conductivity. As the carbon levels increase, the
they began to meltdown, the electrodes retracted to the throat size will increase. As the carbon levels decrease,
roof of furnace. The instrumentation on the operator's the throat size will cause a very narrow socket to be
panel indicated that everything was normal in the fur- drilled through the scrap and result in cave-ins high u p
nace. The fact is that it was normal as far as power in- on the electrode column with resulting breakage. This
226 Electric Furnace Proceedings, 1971

would imply that if the charge carbon is quite low, electric arc furnaces were in the 80 to 100 kva per square
higher voltage and longer arc would be necessary to foot of hearth cross section. These have been superceded
produce the desired result of delivering about 15% of and we are now using hearth loadings in the 200 kva per
charge into fluid metal to the hearth. With low carbon square foot range. Again, these higher powered fur-
and a small throat through the scrap, the insufficient naces require careful electrical design, and demand the
metal in the basin will be super-heated and cause use of the smallest possible electrode size with mini-
hearth refractories eruption. The hearth will spa11 or mum pitch diameter circles to contain the effect of arc
become quite soft. This may also cause scrap bridging flare. Consistent with arc control, is the low impedance
and adhesions. The charge carbon should be somewhere furnace circuit design which in effect offers operation of
around 0.3 to 0.8%. the furnace at lower voltages with corresponding higher
Chemical and metallurgical adjustment should be currents. Again higher currents call for larger diameter
made after the metal is fluid. If the aim is for unusually electrodes or electrodes that have lower resistivity fac-
low carbon such as the stainless steel heat, you simply tors. It almost goes without saying that as we progress
could not do a good job in melting down all stainless in the direction of increasing the power input to arc
since the lack of carbon would cause an unusually furnaces, more and more demands will be put on the
small meltdown throat and precipitate the problems electrode suppliers to develop electrodes that are of
outlined. extremely high purity so that smaller diameters can b%
In order to develop an electric arc and do a reasonably used with a given size furnace and power supply. Cor-
good job with scrap steel, the phase-to-phase voltage responding improvements in refractories will be neces-
should not be below 150 volts. As a result, on electric sary to provide longer useful operating campaigns to
arc furnace transformers below 7,500 kva, iron core re- dilute the furnace downtime.
actors are used and mounted inside the furnace trans- We often have inquiries relating to incipient sparking
former case. This means that varying amounts of re- or arcing around the furnace, furnace shell, or tap spout.
actance will be used in furnace transformers from say Obviously safety is no small factor in the melt shop and
1,000 kva having a 35% or a 350 kva reactor to 7,500 kva we recognize our responsibility relative to the safe op-
at 10% or a 750 kva reactor. The reactor does not cause eration of all electrical equipment, be it in the trans-
a voltage drop at no load and will give a full voltage former vault or around the furnace. Unfortunately the
impulse to pierce or puncture through rusted or coated electric arc furnace can tolerate only one ground with-
scrap at initial contact. As the load increases with cur- out substantially impeding its satisfactory operation as
rent flow the reactor produces a voltage reduction to a regards regulation. This ground should be located at
level consistent with the furnace transformer rating. the bottom center of the shell. No other grounds should
The total circuit reactance in a typical electric arc fur- be attached to the furnace. We have heard of cases
nace involves between 52 and 65% total. In furnaces where customers have experienced sparking and arcing
less than 10,000 kva, a great portion of this is made up around the roof ring, the tap spout, and charging door
in the iron core reactor. As a result, this component, and have grounded these areas. The grounds then
which is symmetric by winding design and flux linkage quickly melt off and the customer becomes more
within the transformer tank, does not contribute to an alarmed. The voltages that are apparent as a result of
unbalance operation. this sparking are generally below 20 volts. The threshold
On a typical 3,000 kva electric arc furnace trans- of sensitivity for personnel safety is approximately 40
former, the supplemental reactance or iron core reactor volts. Obviously, a man should not be on top of the fur-
in the transformer is 25%. This is 750 kva of reactance nace, in the proximity of the electrodes, the secondary
in series with the primary windings, and will provide a flexible conductors, the furnace transformer primary
25% voltage drop under full load conditions. conductors, or any other area where power voltages are
Above 10 mva, no supplemental reactor is used, and in involved during operation. However, it is not uncom-
fact efforts are made to reduce the reactance, especially mon to obtain spoon specimens from the furnace while
intraphase reactance. This is the reason for triangulation the electrodes are arcing. Nor is it uncommon to make a
of the secondary conductors. At these power levels the temperature test while the electrodes are in operation
secondary flexible conductors represent about 40% of in the furnace. Certainly, the furnace operator should
the total circuit reactance with the bus tubes involving avoid bringing his sampling spoon or his temperature
perhaps 30%, the electrodes 20%, and the remainder in measuring probe into contact with an electrode during
the delta enclosure and primary supply. On these larger this time. The biggest hazard in an arc furnace as re-
furnaces, flux linkage is an extremely important factor lated to the secondary voltage side is burns. Since an
in obtaining good furnace balance. The conductor spac- arc furnace is like a welding operation, severe burns
ing should form an equilateral triangle. The triangle can occur if metallic objects are brought in contact with
ideally should be sustained a t all times during operation. an electrode, with a secondary bus tube, terminal head,
Obviously, its not possible to have the arms of the fur- or a connection to an air-cooled secondary flexible con-
nace level throughout meltdown since the scrap is ran- ductor during the time the circuit breaker is closed. Not
domly distributed in the furnace, and one electrode con- only surface burns, but also severe eye arc burns have
ceivably could be melting through a light scrap section occurred from watching the electric arc.
while another electrode is working on very heavy dense In an effort to minimize the amount of secondary bus
scrap. This will always shake out to be offsetting with copper used in the furnace transformer through the wall
uniform scrap distribution and will result in uniform re- to the terminal connection flexible conductors, low vol-
fractories wear in the three sectors in the furnace. tage current transformers are installed within the fur-
r h e electrodes in an electric arc furnace should al- nace transformer proper. These current transformers
ways be truly vertical and the face to face spacing of are located on one of a number of parallel low voltage
the electrodes should be such as to provide an equilat- bus sections. As a result of their electrical location in
eral triangle, or 120" displacement between the elec- the parallel secondary groupings, some inaccuracy may
trodes. The objective in good electric arc furnace design occur on these low voltage CT's. This inaccuracy', of
is to use the smallest possible electrode size with a mini- course, is reflected in the secondary current measure-
mum electrode pitch diameter. This means the electrodes ment. This error, due to impedance coupling at the vari-
should be held as close together as possible within the ous transformer tappings is generally found to be uni-
mechanical clearance tolerances, such that the distance form between the phases and does provide reliable elec-
between the face of the electrode and the inside hot face trode regulation. Power measurements, kilowatts, kilo-
refractories is maximized. watthours and kilovars should be made in the primary
Furnace powering has steadily increased over the circuit as electrical noise as well as varying voltage in
years with better refractories and improved electrodes. the secondary precludes accuracy across the complete
Both of these expendables will obviously continue to tap range.
improve as time goes on and furnace powerings will Electric arc furnaces sometimes have inherent hot
continue to increase. Ten years ago the standards for spots akin to the electrical conductor arrangement. A
Arc Furnace Electrical Workshop 227

good method of determining the hot zone is to perform


a so-calIed short circuit or impedance test. This is done
by selecting a transformer tap which will cause full load
current to flow in the secondary circuit with this tap
position, usually the lowest delta-delta connection, and
a flat bath in the furnace, run the electrodes into the
liquid metal. The metal penetration should be perhaps
18 to 24 inches for good electrical contact of liquid metal
and electrodes. The electrode arms should be level. Dur-
ing the time the electrodes are in the metal, measure
the primary kilowatts, primary kilovars or phase angle
on each of the three phases in the primary, and also
primary and secondary currents and primary and sec-
ondary voltages both phase-to-phase and phase-to-neu-
tral. This test procedure will provide a complete evalua-
tion of the system under sine wave conditions.
A simpler method is to proceed as above, immersing
the electrodes into the liquid metal and simply record
the three phase primary watts on the wattmeter. Raise
"A" phase out of the metal while leaving "B" and "C"
phase in, again record watts. Run "A" phase back in
and raise "B" phase; record watts and do the same for
"C" phase. The variation between these single-phase
(two electrode penetration) tests is the furnace unbal- Fig. 19-Arc furnace operator's control panel.
ance.
With triangulation of the secondary conductors, the sufficient energy to hold metal temperature awaiting a
quantity of imbalance is reduced and reasonably uni- ladle or for some arc length control in cases where the
form power input distribution is available to each of scrap density is either unusually heavy or unusually
the three phases. If an unbalance of power input exists, light. This means that minimum rheostat control should
the refractories damaging effects of the hot phase can be used. If a furnace operator chooses to increase or de-
best be controlled by increasing the current to this crease the energy level in the operation of a furnace to
phase. This may seem contrary to solving the problem, get a corresponding increase or decrease in power input,
but in fact works best since this adjustment will create a he should relate only to the furnace transformer tap
shorter arc on the hot phase thereby reducing the arc changer by increasing or decreasing its relative tap
flare impingement. position. The load fixing rheostats should not be used
There has been much discussion on just how you go as a method of governing power input on a given tap
about starting a cold furnace. In starting a cold furnace, through a complete heat. A good example of this would
the best measure of electrode control with power cir- be a situation where you would be operating on trans-
cuit stability is for the furnace operator to observe the former tap position one for meltdown and using this
secondary flexible conductors and/or phase ammeters. same tap position for refining and finishing the heat.
On Monday morning after the furnace has been down Assume this to be a 10,000 kva transformer operating at
over a weekend, for example, with cold electrodes and 75% power factor at meltdown. This means that you
cold scrap charge in the furnace, arc ionization vaporiza- would be applying 7,500 kilowatts into the furnace dur-
tion or the gaseous resistance path between the elec- ing the meltdown period. During the finishing period we
trodes to the metal is at minimum. The graphite elec- say that the power input should be % the transformer
trodes, having a high affinity to produce ionization or a nameplate kva rating expressed in kilowatts or in this
conductor path, will cause conduction to occur during particular case 5,000 kw at a power factor about 5% less
interval whenever the electrode acts as the emitter. If than the meltdown or 70%. At this level, 5,000 kilowatts
the high transformer tap is used, extreme bursts of en- would be used to finish the heat. If by rheostat control
ergy will occur from the electrodes to the metal (diod- you could reduce the power input on tap one from 7,500
ing) without re-ignition from the metal back to the kilowatts to 5,000 kilowatts, an unusually long arc would
electrode. This results in unusual violence with the be created as a result of the current or ampere reduction
electrodes dancing and the cables whipping. Under which would be very detrimental to the refractories.
these conditions the power input should be reduced to Therefore, the furnace operator should reduce the power
approximately 50% of the original meltdown power. input by corresponding tap change adjustment which
Whenever the cables begin to quiet down, the tap changer reduces the voltage and provides a shorter arc which
can be increased to a position at a time to full power, will be both captive, generally in the slag layer, and not
again observing the cables as you go along. The time in- precipitate flare to the sidewalls. The shorter, stouter arc
terval, depending on furnace size and power input, is with the electrodes actually physically closer to the
generally from three to eight minutes. After the furnace liquid metal produces a vertical deflection in the liquid
refractories are hot, and if they remain hot during con- metal surface. The cavity that is established then con-
secutive charges, recharges, or start-ups after the fur- fines the arc flare to the under side of the electrode and
nace has been tapped empty, the furnace can be started drives the heat deep into the metal. Rheostat reduction
after charging on the highest energy level. There has on tap position No. 1, for instance, in order to obtain
been much discussion about roof wear as a result of 5,000 kw in our hypothetical case would result in ther-
starting on the high tap with the electrode being close to mal input in the metal of perhaps 60% or 3,000 kilowatts
the roof and the cap scrap being closer to this area. We . as compared to a thermal input of 5,000 kilowatts with a
have not found this to be valid in most cases, since again shorter arc. Explaining this a little further, the arc as
during the meltdown period the scrap has an unusual related to 5,000 kilowatts under rheostat adjustment us-
high infinity to absorb all of the thermal energy from the ing the high tap would be approximately six inches long.
electrodes, and little if any refractories damage will This six-inch arc would both flare to the sidewall and
occur in the roof or throat areas around the electrodes have little impact on driving the heat deep into the
using this procedure. metal. On the other hand, by reducing the transformer
The furnace operator's control panel contains instru- tap and not adjusting the rheostats in this properly
mentation and controls to properly operate the furnace adjusted furnace, nearly all of this thermal energy
(Figure 19). would be driven into the metal to cause a rapid increase
The load adjusting rheostats located on the front of in temperature consistent with good operation obtain-
the operator's control panel, if the furnace is properly ing a fast temperature rise and a reasonably short heat
adjusted, should only be used on the low tap to obtain time.
I 228 Electric Furnace Proceedings, 1971

Instrumentation is available on the operator's control


panel to make a determination of power factor. This is
switch is equipped with mechanical key interlocks to
prevent operation of this mechanism while the furnace
indicated by a wattmeter and varmeter connected switch is closed. It may also have mechanical key inter-
through instrument transformers in the primary circuit locks to a capacitor bank which could be included in the
of the power system ahead of the furnace transformer. circuit line-up.
When the wattmeter and varmeter read the same value,
a phase angle of 45" exists and the power factor is Capacitor Bank
70.7%. This would be consistent with meltdown opera- Capacitor banks may be used for power factor correc-
tion with furnaces sized 25,000 kva and above. For tion on electric arc furnaces where power factor penal-
smaller furnaces, high power factors have proven effec- ties are part of the utilities billing and demand con-
tive in obtaining good production with the best eco- tract. These capacitors generate what is termed leading
nomics. The ranges are as follows: Furnace transformers vars which can compensate the lagging vars or lagging
up to 7,500 kva, meltdown 80% power factor and refining power factor involved in electric arc furnace operation.
at 75% power factor; 7,500 to 15,000 kva, meltdown Perhaps the most important consideration in the ca-
78% power factor and refining 73%. From 15,000 to pacitor bank is to size them properly so that there is
25,000 kva, meltdown 75% power factor and refining at sufficient over voltage range to protect the capacitors
70%. At 25,000 kva and above, meltdown is 70% power from premature failure. We found it desirable also that
factor and refining 65%. These power factors are mea- the capacitor bank be located at a point in the system
sured at the primary terminals of the furnace trans- where it will not be necessary to frequently switch the
former using properly mated furnace transformer and capacitors. Switching capacitors as well as over voltage
furnace sizes. These are not necessarily the power fac- can lead to capacitor failures.
tors that will achieve the best economics in all opera-
tions. Unfortunately, there is no way to absolutely pre- Furnace Switch
dict a power factor level for every size and every scrap The furnace switch which has proven to be most re-
condition which will prove to be year in and year out liable is a vacuum interruptor. This device is the prod-
the very best for any class of scrap. The scrap material uct of a great deal of research and with low inertia
pretty much dictates the variation to be used in power makes it very suitable for repetitive switching the type
factors and the values above should be starting points required for electric arc furnaces.
only. It certainly would behoove a furnace user to collect Furnace Transformer
data information on all the types of scrap that are being
used in his plant and relate these to energy consumption, Gince most all furnace transformers are water cooled,
power factor and corresponding arc length. We recom- the ambient temperature is said to be that of the inlet
mend that the furnace be operated through a refrac- cooling water. Routine maintenance of a furnace trans-
tories campaign at a specific power factor setting. After former consists of internal inspection by oil test. The oil
this refractories campaign, if the customer feels they should be semiannually tested for dielectric strength,
can obtain better economics at higher or lower current acid, color, and interfacial surface tension. This test data
flows, longer or shorter arcs, then make the adjustment. should be carefully logged and a comparison made
There simply are not enough data available from one or against previous tests to determine the condition of the
two heats to make an economic assessment of a furnace transformer.
operation (Figure 20). Perhaps the most severe loading on an arc furnace
transformer occurs during the refining or finishing time,
Back-up Breaker where the furnace operator may, in an effort to get an
The back-up breaker suitable to handle the total sys- unusually short arc to prevent refractory erosion, cause
tem short circuit capability, generally an oil type, can be unusually high currents to circulate in the windings.
located either in the transformer room or out in the sub- This ampere overloading may be well beyond the capa-
station. It is preferable to locate this switch in the sub- bility of the transformer and cause unusual hot spots
station since it can then act as the total system protec- which will result in oil sludging and reduce the effective
tion device. With current transformers and time-over- cooling of the windings.
current relays on the incoming bushings of this back-up Furnace Electrical Protection
breaker, the total current flow to the furnace circuit is
monitored and protected. Such an arrangement provides Due to switching effects, lightning arrestors, and surge
back-up protection for major faults, both at the furnace capacitors should be located as close as possible to the
transformer as well as in the conductor system from the high voltage terminals of the furnace transformer. We
substation to the furnace transformer. recommend they be pedestal mounted adjacent to the
high voltage bushings on the transformer tank.
Disconnect Switch
Power Input Control
A no load manual or motor-operated disconnect
switch is located in the transformer room to provide The adjustments of the voltages for good furnace
visual isolation of the supply system to the furnace operation should be based on equal energy levels across
vacuum interruptor and furnace transformer. This the tap range. For example, on a four position trans-
former changer, tap No. 1 or the high tap, should be
selected based on the full load capability of the furnace
transformer. This, then would be the meltdown tap. Tap
No. 3 should be one half the nameplate kva rating ex-
pressed in kilowatts. Tap No. 2 then should be a kilowatt
or energy level between these two values, and tap No. 4
should be one half of the available kw or energy input of
tap No. 2.
Secondary Circuit
The furnace secondary circuit or that portion of the
current carrying conductors between the furnace trans-
former and the electrode holders should be arranged to
minimize electrical imbalance. This is particularly true
of furnace installations where the secondary currents
exceed 15,000 amperes. The conductors should have a
profile which will provide equal distances between the
centers of the phase conductors. This can most effec-
tively be done by using water-cooled secondary flexible
Fig. 20--Characteristic power input diagram. cables since bundling of air-cooled cables results in an
Arc Furnace Electrical Workshop 229

unwieldy secondary flexible circuit. In addition, air


cooled secondary flexibles should be arranged such that
they effectively become a cylinder of conductors. If one
of these conductors in the air-cooled secondary flexible
phase group should get inside the group of cables, elec-
trical erosion will occur and lead to cable failure. This is
due to current flow as regards skin effect. The current at
60 cycles tends to flow on the outer surface of the con-
ductors. The resulting voltage drop then is a product of
the conductor group resistance and current flow, and is
summarized in the equation Ed = IR, or the voltage drop
is a product of the current times the resistance. Since the
outside conductors carry the bulk of the current, their
singular voltage drop will be significantly higher than a
conductor which may exist in the core of the group. The
result is a voltage difference between the outside and
inside conductors which will cause sparking or arcing
when the conductors touch leading to rapid cable ero-
sion. Fig. 22-Furnace equipped with direct evacuation system.
Arc Voltage Indicating Lamps
The arc voltage indicating lamps on the front of the per kilowatt-hour, this is a 50 cent per ton reduction in
operator's control panel are good indications of balanced power input. I t is certainly not the whole story in op-
furnace operation during the period when the metal is erating costs, but again reveals the sensitivity of the arc
fluid in the furnace. The intensity of these lamps should to environmental change.
be essentially the same during operation.
Time Utilization
Electrode Regulation In the operation of the furnace, time utilization is
The regulation of an electric arc furnace requires good perhaps the most important criteria. Since all electric
control, sensitivity, and gain during the meltdown pe- arc furnace melt shops develop their costs as a function
riod. During this time the electrodes are positioned of the number of tons produced, it is obvious that the
rapidly to compensate for the scrap movement under the furnace operator's first concern is to tip the furnace
electrodes. Regulation then requires extreme accuracy empty as many times as possible to produce as much
from the standpoint of maintaining and supporting an fluid metal as he possibly can. It is a rarity to find
arc at a specific power factor. This is particularly true of a melt shop where the people record the time the fur-
smaller furnaces where a relatively longer arc is neces- nace was at 2,900°F. For example, how many hours
sary in order to do a good melting job. During the refin- a day were the furnace hot face refractories a t 2,900°?
ing o r finishing period, regulation should be suppressed How many hours of that 24 hour period were the elec-
to reasonably stabilize movement of the electrodes to trodes subjected to an environment where the tempera-
drive the energy deep into the bath. ture was 2,900°? If these were developed, you prob-
ably would find that the kilowatt-hours, refractory con-
Smoke and Fume Collection sumption, and electrode usage from shop to shop would
Smoke and fume collection is now pretty much the be nearly the same in spite of the number of tons pro-
concern of our city fathers, and all new electric arc duced.
furnaces are equipped with effluent or emission contain-
ing devices. They are also rapidly being applied to exist- Productivity
ing furnaces (Figures 21 and 22). Smoke and fume It has generally been considered a rule of thumb that
collection somewhat enhances the electrical performance you should be able to produce one ton per hour per
of the arc furnace. In fact, this is the only melting tool thousand kva tap to tap. This means that if you have a
whose performance is influenced and influenced in a 10,000 kva furnace transformer, your shop should pro-
positive way for melting or producing liquid metal. The duce approximately 10 tons per hour tap to tap. To de-
slight negative pressure in the furnace does tend to termine the amount of time to produce a typical heat,
ventilate the arc zone and does tend to get better ther- you can use the following equation:
mal transfer in this area. A major steel producer in
Atlanta, Georgia, found that with the use of direct A. Meltdown: multiply the number of tons charged
evacuation on their furnaces the kilowatt-hour per ton times 1.08 x 1.1 x 375 x 60 divided by the kva and
consumption was reduced about 50. Assuming a penny power factor. This will give the time in minutes to get
the charge up to an average 2,600°F.
B. Refining-finishing from 2,600°F to tapping tem-
perature: multiply the number of liquid tons times a
factor of 30 kilowatt-hours per ton per hundred degrees
of temperature boost x 60, divided by one half the
nameplate kva (refining kilowatts). This will give the
time in minutes to reach tapping temperature.
We generally figure charging to be 5 minutes per
bucket. Tap out should involve 5 to 9 minutes. Slag off
and chemistry perhaps 5 to 15 minutes, patching the bot-
tom, slipping and adding electrodes, etc., perhaps an-
other 5 to 20 minutes depending on the furnace size. This
then will yield a complete heat profile for a typical car-
bon steel charge in a basic operation.
Burning in Procedure
When complete new refractories are installed in the
furnace, it is necessary to heat sinter both the hearth
and lining. This should be done by using 8 kilowatts per
square foot of cross section across the hot face. This is
the number you should read on the wattmeter during
Fig. 21-Furnace equipped with side drnft hood. the burn in cycling period. We recommend a graphite
230 Electric Furnace Proceedings, 1971

"T" as the contact device to provide good uniform heat tice is a service that the electrode manufacturers spon-
absorption and glazing not only in the hearth, but to the sor, and we strongly advocate customers taking advan-
sidewalls and the roof. tage of these programs which can significantly reduce
loss in electrode usage from breakage and also reduce
Computer Programming consumption.
A lot has been done relating to computer program-
ming of the electric arc furnace. A comwuter is nothine Refractory Repairs
more than a super clerk in this connection, save its us: This is another area where the suppliers can be of
as a demand limiting tool. Perhaps the most vital con- great service. In replacing furnace linings, a water-
cern in obtaining benefit from a computer would be to cooled dish or pan is generally located in the hearth of
categorize scrap. That is, develop a good analysis in- the furnace and the wall refractories torn down into this
ventory of the type scrap that is purchased and its op- dish and lifted out with the overhead crane. Roof repairs
erating characteristics in a furnace. From such data you can be expedited with a roof break out station where the
can easily determine, when cheaper scrap is purchased, brick arch can be broken, dropped through a floor open-
what it really means to the furnace operator. For ex- ing into a dump box below.
ample, nominal savings may occur in purchasing a On larger electric furnaces there are a number of
cheaper grade of scrap, but many hours will be spent in clever devices used for both patching and relining. I
the melt shop in order to meet specific chemistry as have seen a small track vehicle with attached boom hook
required in the final product. If total in-plant control which is crane lowered into the furnace and the hook
can also be used, heat time can be improved by divert- used to pull in all of the wall refractories onto the
ing certain heats to meet the order book requirements. water-cooled dish. This provides a very quick removal
For example, assuming both high carbon and low carbon of the sidewall refractories and the reline time is sig-
heats are required, the meltdown sample tests with high nificantly reduced. There are a number of refractory
carbon may indicate this heat be completed in a short service organizations which have such equipment for
time and meet the specifications of a current order re- furnace linings.
quiring high carbon. It could then quickly be diverted
precluding a lengthy oxygen blow to achieve a low Scrap Preheating
carbon chemistry which may meet the requirements of This is a subject of much discussion and controversy.
another customers' specifications. If a computer is con- We believe that the electric arc furnace efficiencies are
sidered, it should be used not as a rival to but an as- such that scrap preheating may prove to be a liability
sistant for the melter. If this conditioning of personnel when compared with the melting performance of a fur-
to the use of a super clerk is done beforehand, little if nace. In a small furnace shop a customer may advan-
any difficulty will occur during operation and the com- tageously overcome a temporary peak production period
puter can be made to be useful. We know cases where reauirine additional BTU into the scraw bv the use of
very expensive computers have been purchased and in- naiural gas or oil fired devices. ~ o w e v e i thk
, great bulk
stalled and have later been abandoned because the of energy during meltdown goes directly into the metal
equipment did not satisfy the melting personnel. with the arc furnace efficiency unusually high during
this time. During this same period if you consider scrap
Power Demand Control preheating, there would be the additional involvements
Power demand control is often used in electric furnace of effluent control, refractories lined charge vessels, as
shops with the electric arc furnace the target for demand well as the straight forward problems involved in han-
cut backs. Power shedding can easily be done during dling hot material from a preheat station to the furnace
meltdown on a furnace or furnaces, but it should be in a proper. If supplemental heating is used in an operating
fashion where the electrodes are simply raised to arc furnace, it should never be directed toward the arc zone
extinction. This can very easily be accomplished by thereby upsetting the arc environment.
interrupting the potential reference circuit so that fur-
nace switching is not necessary. The electrodes during a Charging
demand situation are then raised to arc extension and In charging the electric furnace, the charge bucket
remain there until the demand interval is cleared. At base should be at vessel bezel height. We have seen
this time the electrodes go back into operation provid- some very interesting methods of charging with clam
ing automatic control not necessitating the furnace op- shell buckets where the auxiliary hook or the hook con-
erator's supervision. Demand control implies holding a trolling bucket opening is held stationary while the main
uniform level of kilowatts based on production require- hook and bucket is lowered. Doing it this way, the
ments in a specific operation. Obviously, if frequent de- bucket tends to remain located more precisely centered
mand cut backs occur, they should be carefully weighed across the two axes of the furnace and provides a good
against the consequence of increasing the demand level bottom discharge of the scrap.
and the corresponding improvement in production. The Since most electric arc furnaces involve more than one
power cost, although the most significant, save scrap charge, the first charge should be melted only so far as
cost, in the total operation, can often be easily offset by required for accommodation of the second or consecu-
the added production as a result of increasing the de- tive charge. A good way of determining this time factor
mand just slightly. is to observe the roof when it is being swung between
In comparing off-peak power versus on-peak opera- bucket charges. The roof should be orange to yellow
tion in a number of economic evaluations covering this during this time. This means there is very little heat
subject, we found that it sometimes is a standoff and impinging on the roof and all of the energy has gone
generally favors on-peak operation. We are not advocat- into the scrap.
ing that everyone just simply ignore off-peak power
savings, but you should review on-peak versus off-peak Tapout
in light of available personnel, handling facilities, the The taphole of the arc furnace should be quite large
actual energy cost, and the equipment involvements in to accommodate a good fast metal drain flow from the
the final analysis. furnace and also to prevent temperature loss from cas-
cading metal. We have seen cases where the complete
Electrode Handling tapout involves two or three minutes.
Electrode handling should be carefully considered in
the operation. The threaded socket and nipple of the Furnace Performance
electrode section should be cleaned and the electrodes Each electric arc furnace is a bit different from the
carefully attached to prevent thread, socket and nipple other, and particularly when there is a broad range of
damage. The electrodes should be properly torque scrap material available. A furnace operator should be-
tightened to prevent separation and spalling whenever come familiar with the audible and visible indications of
the joint arrives at the arcing tip. Good electrode prac- good furnace performance. He should have a smattering
Arc Furnace Electrical Workshop 231

of how and why the arc works and what the indications significant and yields perhaps the best measure of just
on the operator's control panel a r e as regards instru- how the furnace is functioning.
mentation. Certainly kilowatt-kilovar input is the most

DISCUSSION
by Robert C. Maxton

Would you care to comment on the degree of electrode larly when melting in an acid operation. These higher
"penciling" that occurs in an acid-lined furnace, versus voltages would imply a longer arc dimensionally, at the
the basic-lined furnace? foot of each of the three electrodes. The longer arc at a
higher voltage means somewhat lower current for a
Author's R e p l y given furnace transformer size. It would follow then that
It has generally been the practice in electric arc fur- somewhat greater pencilling or tapering would occur
nace operation to use somewhat higher voltages particu- near the tip of the electrode than would be exhibited at
higher currents, ie., lower voltages, in a basic operation.
In steel production using either basic or acid practice,
about 50% of electrode wear is oxidation. The remain-
ROBERT C . M A X T O N is Technical Director, Minneapolis Electric ing 50% could be roughly considered sublimation and is
Steel Co., Minneapolis, Minn. more definitively analyzed in a paper given by Union
Carbide during these technical sessions.

DISCUSSION
by Paul E. Lacke

Question: You mentioned that the electrode position- resource is not available in an acid bottom furnace since
ing unit should be big enough to push the electrode to its this material tends to surface sinter developing a ce-
natural frequency of vibration. In practice, how do you ramic glaze which penetrates perhaps an inch or two
test for the natural frequency of vibration? from the hot face. The remaining refractory is highly
Author's Reply: Put a stylus on the electrode clamp. insulating and the ground straps are necessary. The
Let this stylus operate a potentiometer with the output placement, size and location of these straps is covered in
going to the brush recorder. the text.
Question: Do you know of anyone having trouble with The ground straps melt to the normal hearth grade
the hot metal burning through the bottom where the since the surrounding refractories wiil insulate them
ground rods come up through the refractory? We 'don't from liquid metal penetration. It was common practice
have ground straps in our furnaces and the operation is some years back to install ground straps at the tangent
satisfactory. junction of the shell basin to the vertical shell side plate.
Some 12 to 15 spires were used projecting toward the
Author's R e p l y hearth center. This was a carryover from earliest elec-
As I pointed out earlier, neutral or basic refractories tric furnace operation where acid refractory material
do, after initial preheating, effectively conduct to the was universally used. The present practice is to obtain
hearth basin and ground straps are not required. This from the ultimate customer, information regarding the
type of refractories to be installed and be guided ac-
cordingly. That is, in case of neutral or basic materials,
PAUL E. LACKE is affiliated with Laclede Steel Co., Alton, Ill. no ground rods are used and with acid-lined hearths,
-- ground rods are installed at the factory.

DISCUSSION
by R. S. Harrison

-
You state that arc temperature is constant and not a
R. 5. HARRISON is affiliated with Beaver Electrical Machinery Ltd.,
Burnaby, B.C., Canada.
function of current other things being equal. I find this
difficult to reconcile with my understanding of what
232 Electric Furnace Proceedings, 1971

happens. It would appear if this were true that arc to make clearly apparent that the electric arc, the melt-
diameter would be a function of arc power because arc ing vehicle in an electric arc furnace, creates a tempera-
energy must radiate from a proportional surface area. ture during both phases of ignition which is significantly
If the statement were true it would seem that much higher than the thermal resistance of a furnace refrac-
about arc behavior has been simplified. tories lining. It is not so imperative as to the precise
I would be interested in the theory or measurements temperature, save that the furnace operator and main-
made to arrive a t this conclusion. tenance technician recognizes the inherent effects of the
arc gasses and vapors sweeping across the surface of the
metal and bursting against the side walls and roof arch.
The thermal emission, a function of kilowatt input must
Author's Reply
be controlled or directed to accommodate the meltdown
The phenomenon surrounding the electric arc still and refining entity. The greatest danger is the transition
leaves a great deal to fundamental research. At present, period between these energy levels and remains con-
we could say that rudimentary information is available stant during the complete refining cycle, particularly
and largely the investigations have been devoted graph- with high energy input and a minimum slag cover on the
ite to graphite exploration in the main with direct cur- metal surface. From the standpoint of people concerned
rent. The purpose of my paper was not to delve heavily both with the production and economics of the furnace
into the sophisticated technical aspects surrounding the operation, recognizing arc flare and its damaging effects
nature of an alternating current arc with ignition inter- is consistent with the criteria used in the paper relating
vals from graphite and metal and metal to graphite, but to arc temperature.

Das könnte Ihnen auch gefallen