Beruflich Dokumente
Kultur Dokumente
Presented by
Hossam Ghanem,PMP,ITIL,MCSE
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Presentation Agenda:
• Define Activities
• Sequence Activities
• Developed Schedule
• Estimate cost
• Determine budget
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
What we will Study
• The Planning processes group consists of the following processes (Part 2): as follows
.
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan schedule Mgmt.
Plan Schedule Management is the process of establishing the policies, procedures, and documentation for
planning, developing, managing, executing, and controlling the project schedule. The key benefit of this
process is that it provides guidance and direction on how the project schedule will be managed throughout the
project.
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, Figure 6-3, Page 145”
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan schedule Mgmt./ Inputs
• Scope baseline. The scope baseline includes the project scope statement and the
work breakdown structure (WBS) details used for defining activities, duration
• Other information. Other scheduling related cost, risk, and communications decisions
from the project management plan are used to develop the schedule
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan schedule Mgmt./ Tools
Analytical Techniques
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan schedule Mgmt./ Tools
Meetings
Project teams may hold planning meetings to develop the schedule management plan.
Participants at these meetings may include the project manager, the project sponsor,
selected project team members, selected stakeholders, anyone with responsibility for
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan schedule Mgmt.
Note :
Schedule Mgmt. Plan can establish the following :
• Level of accuracy . The acceptable range and the amount for contingencies are specified.
• Units of measures. Each unit used in measurements such as ( staff hours , weeks for time ).
• Project schedule model maintenance . The process used to update the status and record
progress of the project.
• Organizational procedures links. The WBS provides the framework for the schedule
management plan, allowing for consistency with the estimates and resulting schedules
• Reporting format . The format and frequency for the various schedule reports are defined.
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan schedule Mgmt./ outputs
A component of the project management plan that establishes the criteria and the
activities for developing, monitoring, and controlling the schedule. The schedule
management plan may be formal or informal, highly detailed or broadly framed, based
upon the needs of the project, and includes appropriate control thresholds.
this definition is taken from the Glossary of the Project Management Institute, a Guide to the Project Management Body of
Knowledge, (PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013'
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, Figure 6-5, Page 149”
10
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / Description
11
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / Input
Scope Baseline The project deliverables, constraints, & assumptions documented in the
project scope baseline are considered explicitly when defining activities.
A key input from the schedule management plan is define the level of detail necessary to
manage the work
12
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / tools
Decomposition
Subdividing the work packages into smaller, more manageable components called activities,
Activities represents the effort needed to complete a work package with team members
involvement in the decomposition can lead to better and more accurate results.
Expert Judgment
these definitions are taken from the Glossary of the Project Management Institute, a Guide to the Project Management Body of
Knowledge, (PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013'
13
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / output
Activity List
• The activity list is a comprehensive list including all schedule activities that are
planned to be performed on the project.
this definition is taken from the Glossary of the Project Management Institute, a Guide to the Project Management Body of
Knowledge, (PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013'
• The activity list includes the activity identifier and a scope of work description for
each schedule activity in sufficient detail to ensure that project team members
understand what work is required to be completed.
• The activity list is used in the schedule model and is a component of the project
management plan.
• The schedule activities are discrete components of the project schedule, but are not
components of the WBS.
14
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / output
15
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / output
extension of the activity list. Activity attributes will change over the life of the project as
more information is known. In the early stages of the project, activity attributes might
include the activity ID, the WBS identification code it's associated with, and the activity
name. As you progress through the project and complete other Planning processes, you
might add predecessor and successor activities, logical relationships, leads and lags,
resource requirements, and constraints and assumptions associated with the activity.
this definition is taken from the Glossary of the Project Management Institute, a Guide to the Project Management Body of
Knowledge, (PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013'
16
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / output
Activity attributes
Activity attributes for each schedule activity may include :
-activity identifier
-activity codes
-activity description
-predecessor activities
-successor activities
-logical relationships
-leads and lags
-resource requirements
-imposed dates
-constraints, and assumptions.
-the person responsible for executing the work
17
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / output
Milestone List
• The list of schedule milestones identifies all milestones and indicates whether the
milestone is mandatory (required by the contract) or
• optional (based upon project requirements or historical information).
18
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / output
19
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Define Activities / output
Sponsor
Purpose of milestone is
who , and what
information need to be
transferred
20
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, Figure 6-7, Page 153”
21
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ description
Summary
• Sequence Activities involves identifying and documenting the logical
relationships among schedule activities.
22
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ inputs
• Activity List
• Activity Attributes
• Milestone List
23
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ Tools
Precedence Diagram Method (PDM) is a visual representation technique that depicts the
activities involved in a project. It is a method of constructing a project schedule network
diagram that uses boxes/nodes to represent activities and connects them with arrows that
show the dependencies
24
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ Tools
25
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ Tools
26
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ Tools
27
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ Tools
28
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ Tools
29
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ Tools
Dependency Determination
Four types of dependencies are used to define the sequence among the activities.
30
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ inputs
Definition
31
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ inputs
32
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/
33
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Sequence Activities/ outputs
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Resources
Summary
• Analyzing project activity to determine the type and quantities of material,
people, equipment, or supplies required to perform each activity,
• Understanding the number of resources required to complete the activity and
determining how long they will be used for that activity,
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, Figure 6-12, Page 161.
35
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Resource / inputs
Activity Attributes
Resource Calendars
Information on which resources (such as people, equipment, and materiel) are potentially
available is used for estimating the resource types.
36
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Resource / tools and techniques
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Resource / Outputs
OUTPUTS
1. Activity Resource Identifies the type and quantity of resources
Requirements needed for each activity in a work package.
2. Resource Breakdown Hierarchical representation of resources by
Structure category and type, typical categories
being: labor, material, equipment, supplies.
3. Project Documents •Activity list
Updates •Activity attributes
•Resource calendars
38
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Duration
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, F 6-14, Page 166
39
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Duration
40
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Duration / Inputs
For example: if a senior and junior staff member are assigned full time, a senior staff member can
generally be expected to complete a given schedule activity in less time than a junior staff
member..
41
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Duration / Inputs
42
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Duration / tools
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Duration / outputs
OUTPUTS
Activity Duration The duration estimates may include a range of possible
1.
Estimates results.
•Activity attributes
Project Document
2.
Updates •Assumptions made during the activity duration
estimate
44
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Duration / Exercise
45
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate Activities Duration / Exercise
46
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, Figure 6-16, Page 173
47
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule
• The purpose of this process is to put everything together from the first
five time management processes and create a schedule model
• Project schedule development, an iterative process, determines
planned start and finish dates for project activities.
• Schedule development can require that duration estimates and
resource estimates are reviewed and revised to create an approved
project schedule that can serve as a baseline against which progress
can be tracked.
48
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ Inputs
INPUTS
1. Schedule Management Plan Identifies the scheduling method and tools to be used,
and how the schedule is to be calculated. It is an output
of process 6.1 Plan Schedule Management.
2. Activity List Identifies activities that will be included in the schedule
model. This is an output of process 6.2 Define Activities.
3. Activity Attributes Provides details to be used to build the schedule
model. This is an output of process 6.2 Define Activities.
4. Project Network Schedule Contains the logical relationships between predecessor
Diagrams and successor activities used to calculate the
schedule. This is an output of process 6.3 Sequence
Activities.
5. Activity Resource Identifies types and quantities of resources required for
Requirements each activity used to create the schedule model. This is
an output of process 6.4 Estimate Activity Resources.
49
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ Inputs
7. Activity Duration Estimates Contains quantitative assessments of the likely number of work periods
required to complete an activity. This is an output of process 6.5
Estimate Activity Durations.
8. Project Scope Statement Contains assumptions and constraints that can impact development of
the project schedule model. This is an output of process 5.6 Define
Scope.
9.. Risk Register Identified risks and their characteristics affect the schedule
model. This is an output of Risk Management.
10. Project Staff Assignments Specifies which resources are assigned to each activity. This is an
output of Human Resources Management.
11. Resource Breakdown Structure Provides details by which resource analysis can be done. This is an
output of process 6.4 Estimate Activity Resources.
50
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/Tools
51
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/Tools
6. Leads and lags Develops viable schedule by adjusting the start time of successor activities.
7. Schedule Shortens project duration without reducing the project scope in order to
compression meet schedule constraints.
•Crashing: adds resources
•Fast-tracking: activities normally done in sequence are now performed in
parallel for part of their duration
8. Scheduling tool Automated scheduling tools contain the schedule model and expedite the
scheduling process.
52
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
53
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
Critical chain scheduling assumes resources do not multitask because it often delays
task completions and increases total durations
54
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
Can there be more one critical path ? Yes , you can have two , three , or many critical paths
How much float does the critical path have ? Zero total float
55
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
56
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
Recourse smoothing–
57
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
Schedule Compression
Schedule compression techniques are used to shorten the schedule duration without reducing the project scope,
in order to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression
techniques include, but are not limited to:
• Crashing. A technique used to shorten the schedule duration for the least incremental cost by adding
resources. Examples of crashing include approving overtime, bringing in additional resources, or paying to
expedite delivery to activities on the critical path. Crashing works only for activities on the critical path where
additional resources will shorten the activity’s duration. Crashing does not always produce a viable alternative
and may result in increased risk and/or cost.
• Fast tracking. A schedule compression technique in which activities or phases normally done in sequence
are performed in parallel for at least a portion of their duration. An example is constructing the foundation for a
building before completing all of the architectural drawings. Fast tracking may result in rework and increased
risk. Fast tracking only works if activities can be overlapped to shorten the project duration.
58
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
59
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
Scheduling Tool
Automated scheduling tools contain the schedule model and expedite the scheduling process
by generating start and finish dates based on the inputs of activities, network diagrams,
resources and activity durations using schedule network analysis. A scheduling tool can be
manual methods.
60
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
61
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/ITools
Modeling Techniques
Modeling techniques typically include the use of what-if scenario analysis and simulation.
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Developed Schedule/outputs
OUTPUTS
1. Schedule Baseline The approved version of the schedule model by which performance of the project
will be measured. Can only be changed through formal change control
procedures.
2. Project Schedule The schedule baseline refers to the schedule model, whereas the project schedule
refers output of the schedule model. It can be represented in the following ways:
•Bar charts
•Milestone charts
•Project schedule network diagrams
3. Schedule Data Information used to describe and control the schedule:
•Resource requirements
•Alternative schedules (best case vs. worst case, resource-leveled vs. non-
resource-leveled, etc.)
•Scheduling of contingency reserve
4. Project Calendars Identifies working days and shifts available for scheduled activities of the project.
63
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Break
64
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
What we will Study
• The Planning processes group consists of the following processes (Part 3): as follows
.
65
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan cost Mgmt.
Summary
Project cost Mgmt. includes the process involved in planning , estimating , budgeting and
controlling cost so that the project can be completed within the approved budget.
this definition is taken from the Glossary of the Project Management Institute, a Guide to the Project Management Body of
Knowledge, (PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013'
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, Figure 7-2, Page 195
66
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan cost Mgmt. / Tools
Expert Judgment
Expert judgment, guided by historical information, provides valuable insight about the environment
and information from prior similar projects. Expert judgment can also suggest whether to combine
methods and how to reconcile differences between them.
Judgment based upon expertise in an application area, Knowledge Area, discipline, industry, etc., as
appropriate for the activity being performed should be used in developing the cost management plan.
Analytical Techniques
Developing the cost management plan may involve choosing strategic options to fund the project such
as: self-funding, funding with equity, or funding with debt. The cost management plan may also detail
ways to finance project resources such as making, purchasing, renting, or leasing. These decisions,
like other financial decisions affecting the project, may affect project schedule and/or risks.
Organizational policies and procedures may influence which financial techniques are employed in
these decisions. Techniques may include (but are not limited to): payback period, return on
investment, internal rate of return, discounted cash flow, and net present value.
Meetings
Project teams may hold planning meetings to develop the cost management plan. Attendees at these
meetings may include the project manager, the project sponsor, selected project team members,
selected stakeholders, anyone with responsibility for project costs, and others as needed.
67
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Plan cost Mgmt. outputs
For example, the cost management plan can establish the following:
• U nits of measure. Each unit used in measurements (such as staff hours, staff days,
weeks for time measures; or meters, liters, tons, kilometers, or cubic yards for quantity
measures; or lump sum in currency form) is defined for each of the resources
• Reporting formats. The formats and frequency for the various cost reports are defined.
• Process descriptions. Descriptions of each of the other cost management processes are
documented.
68
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate cost
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, Figure 7-4, Page 200
69
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate cost / input
Cost management plan the output of plan cost management process. The cost management plan
defines how project costs will be managed and controlled. It includes the method used and the level of
accuracy required to estimate activity cost
Scope baseline.
This uses the project scope statement with important references relating back to the underlying needs that
led to its creation. Also important here is that the scope statement contains assumptions and constraints
that relates to the scope, and each of these will affect the cost estimates.
Project schedule.
Projects consume large amounts of cost and knowing when such costs are needed, is important
particularly when considering cash-flow. For this reason, and cost performance baseline will be created as
part of the next process, ‘determine budget’.
.
70
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate cost / input
71
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate cost / Tools and Techniques
72
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Duration estimates can use “contingency reserves” for risks in
6. Reserve Analysis
the risk register that the “known-unknowns” of the project.
Assumptions about the cost of quality may effect the cost
7. Cost of Quality (COQ)
estimates.
Project Management
8. Automated tools used to create cost estimates.
Software
Responsive bids from qualified vendors should be analyzed to
9. Vendor Bid Analysis
create cost estimates.
Group Decision-Making Team-based approaches can be useful for improving duration
10.
Techniques estimates.
73
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate cost / Tools
Notes
Parametric Modeling Estimation: there are two type of this techniques
• Learning Curve model is based upon the principal that the cost per unit decreases
as more work gets completed.
Many of these techniques used in the Cost Management knowledge area are
similar to those used in creating the duration estimates in the Time Management
knowledge areas. Some additional techniques not used in Time Management are
the Cost of Quality and Vendor Bid Analysis, from the Quality and Procurements
knowledge areas, respectively.
74
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Estimate cost / outputs
OUTPUTS
2. Basis of Estimates Details supporting the activity cost estimates (output #1).
75
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Determine Budget : Input
Source: Project Management Institute, a Guide to the Project Management Body of Knowledge, (PMBOK® Guide) - Fifth Edition,
Project Management Institute, Inc., 2013, Figure 7-6, page 208”
76
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Determine Budget :
Determine Budget
What is Determine Budget?:-Allocating the overall cost estimate to individual activities
or work packages, in order to establish a cost baseline for measuring project
performance.
this definition is taken from the Glossary of the Project Management Institute, a Guide to the Project Management Body of
Knowledge, (PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc., 2013'
It distribute cost on time phases so that the performing org will know how to plan for
cash flow and likely expenditures.
77
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Determine Budget : Input
INPUTS
1. Cost Management Plan This is an output of process 7.1 Plan Cost Management.
The scope management plan has three components of the scope
baseline:
78
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Determine Budget : Input
Details supporting the activity cost estimates (input #3). This is another output
4. Basis of Estimates
of process 7.3 Estimate Costs.
This is used to assign costs to the calendar period in which they are scheduled
5. Project Schedule
to occur. This is an output of process 6.6 Determine Schedule.
This is used to indicate resource costs over the duration of the project.
6. Resource Calendars
This is an output of the Human Resources Management process 9.2 Acquire
Project Team.
Used to aggregate costs for risk responses to obtain the contingency reserves
7. Risk Register
for the project. This is an output of process 11.2 Identify Risks.
This is used for products, services or results that are purchased from suppliers
8. Procurement Agreements or vendors in order to complete the project. This is an output of Procurements
Management process 12.
•Cost budgeting policies, templates, guidelines
79
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Determine Budget : tools
80
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Determine Budget : outputs
OUTPUTS
The approved version of the time-phased project budget.
Management reserves are not included in this cost baseline.
1. Cost Baseline
The management reserves plus the cost baseline give the
project budget.
The funding for the project may occur in periodic
2. Project Funding Requirements increments, which may place time constraints on work to be
done in the project schedule.
•Risk register
•Project schedule
81
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
Determine Budget : outputs
82
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.
End
83
PMP® , "PMBOK "PMI R.E.P logo are registered marks of the Project Management Institute, Inc.