HARSCO QUESTIONNAIRE - SLAG MANAGEMENT & METAL RECOVERY SERVI

Sl # MATERIAL UNIT Year - 1 Year - 2

1 Liquid steel tonnage TPA 1,450,000 2,000,000


Capacity Utilisation % 95% 95%

2 Actual Steel Tonnage TPA 1,377,500 1,900,000

3 EAF Slag Generation TPA 17.00% 234,175 323,000

4 L F Slag Generation TPA 2.00% 27,550 38,000

5 De Sulph Slag Generation TPA 1.50% 20,663 28,500

6 Skull from EAF Slag & Slag pots TPA 1.00% 13,775 19,000

7 Tundish Skull TPA 0.37% 5,097 7,030

8 Ladle & Caster Skull TPA 0.50% 6,888 9,500

DISTANCE FOR DIFFERENT LOCATIONS

ONE SIDE
SL # ACTIVITY DIST - KM
1 SMS to SLAG YARD 100 mtr
2 SLAG YARD to CONTRACTORS YARD 50 mtr
3 SMS to CONTRACTORS YARD 150 mtr
CONTRACTORS YARD TO PROCESSED SLAG
4 DUMP YARD 50 mtr
5 CONTRACTORS YARD TO SINTER PLANT NA
CONTRACTORS YARD TO MAX DISTANCE POINT
6 IN THE PLANT 150 mtr

SLAG HANDLING PRACTICE

1 Slag collection in Slag Pots Y

Slag from under furnace to slag pits through


Transfer Car / Loader / Truck / Slag pot carrier Slag pot
2 (Tire Mounted) carrier
3 Slag poured into deep pit / shallow pit 2.5 mtr DIP
4 Brief Description :
L RECOVERY SERVICE

Year - 3 Year - 4 Year - 5

2,000,000 2,000,000 2,000,000


95% 95% 95%

1,900,000 1,900,000 1,900,000


389,500 400 155,800,000
323,000 323,000 323,000
35,530 900 31,977,000
38,000 38,000 38,000 187,777,000

28,500 28,500 28,500 2,761,426.47

19,000 19,000 19,000

7,030 7,030 7,030

9,500 9,500 9,500