Beruflich Dokumente
Kultur Dokumente
Lecture 13th
Interruption Causes
Interruption Causes
✓Customer interruptions are caused by a wide range of phenomena including
• equipment failure,
• animals,
• trees,
• severe weather,
• and human error.
✓These causes are at the root of distribution reliability.
✓In addition, identifying and addressing physical root causes is often the
most cost effective way to address reliability problems.
Component Modeling
Component Modeling
✓A distribution system consists of thousands of components such as
transformers, circuit breakers, overhead lines, underground cable, fuse cutouts,
and sectionalizing switches. These components are building blocks that can be
assembled in a myriad of ways to create a wide variety of distribution system
designs, each with its own unique characteristics.
Component Modeling
✓From a reliability perspective, nearly all of the information needed to create
a distribution system model is contained in distribution component
information— a highly desirable feature. Given a palette of components,
systems can be constructed from scratch by choosing components and
connecting them together.
✓Once a system model has been created, modifications can be easily made by
adding components, removing components, and modifying component
characteristics.
Component Modeling
✓Needless to say, component models are critical to distribution system
reliability. A component model should be as simple as possible, but needs to
capture all of the features critical to system reliability. This chapter presents
the reliability parameters typically assigned to components, discusses how
these parameters can be modeled, and provides some guidelines for assigning
default component reliability data.
Reliability Terminologies
10
Reliability Terminologies
✓Reliability is a measure of continuous service accomplishment (or time to
failure).
✓Availability: the fraction of the time that service is available. The (steady-
state) probability that power will be available.
✓Clear: to remove a fault or other disturbance-causing condition from the
power supply source or from the electrical route between it and the customer.
✓Cut set: in reliability analysis, a set of components which when removed
from service causes a cessation of power flow.
✓Dependability: used here, it means reliability of performance over the
short-term, or with respect to only a certain schedule: "Although available only
during the day, the solar-power generator proved a dependable source of
power from 9 to 5 every day”.
11
Reliability Terminologies
✓Durability: the ability to maintain high levels of reliability or dependability
while in service over long periods of time. Two units of equipment can be
equally reliable, or dependable, when initially installed, but the more durable
will be in much better shape after ten years, etc.
✓Duration: the total elapsed time of an interruption or outage, as the case
may be.
✓Failure: a change in status of equipment or a system from performing its
function as expected to no longer performing its function completely.
✓Failure rate: the average number of failures of a component or unit of the
system in a given time (usually a year).
12
Reliability Terminologies
✓Frequency: how often interruptions or outages, as the case may be, occur.
✓Interruption: a cessation of service to one or more customers, whether
power was being used at that moment or not.
▪ Instantaneous interruption: an interruption lasting only as long as it
takes for completely automatic equipment to clear the disturbance or
outage. Often less than one second.
▪ Momentary interruption: an interruption lasting only as long as it takes
automatic but manually supervised equipment to be activated to restore
service, usually only a few minutes, sometimes less than fifteen seconds.
▪ Planned interruption: an interruption of power due to a planned outage,
of which customers were informed reasonably far in advance.
▪ Temporary interruption: an interruption manually restored, lasting as
long as it takes. 13
Reliability Terminologies
✓Outage: the failure of part of the power supply system - a line down,
transformer out of service, or whatever else is intended to be in operation but
is not - whether due to unexpected or planned circumstances.
▪ Expected Outage - an equipment outage that was anticipated in some
sense. Application of this differs from utility to utility, but generally this
means something more definite than “Well, we knew it would fail
eventually”. Often, this is applied to equipment failures that were
anticipated and for which preparations had been made: "Diagnostics
indicated that cable failure was imminent but not which section would
fail. We had switched in a backup cable to continue service when failure
occurred, and went ahead and let the failure happen so as to identify the
bad section of cable”.
14
Reliability Terminologies
✓Forced Outage - an equipment outage that was not scheduled in advance,
even if initiated by the utility. The equipment may not be damaged but usually
something went wrong: "The unit was observed to be smoking slightly so it
was withdrawn from service. It turned out just to be a slight oil leak and the
unit was repaired and returned to service the next day."
✓Scheduled Outage - an equipment outage that was scheduled in advance
and initiated by the utility's actions, as for example when work crews remove
equipment from service for maintenance, etc.
✓Unexpected Outage - an equipment outage that was not anticipated.
Usually, an unexpected outage is due to equipment failure, an accident, or
damage of some type.
15
Reliability Terminologies
✓Trouble: anything that causes an unexpected outage or interruption
including equipment failures, storms, earthquakes, automobile wrecks,
vandalism, operator error, or "unknown causes." consumers see good
reliability from their point of view when looking back into the system,
regardless of equipment issues.
✓Continuous availability: Perhaps the most important aspect of reliability is
that power most be continuously available. Basically, the utility must maintain
an always unbroken chain of power flow from a source of power to each
consumer.
✓Sufficient power: This chain of power flow must be able to deliver enough
power that it does not constrain the consumer's ability to have as much as he
needs whenever he needs it.
16
Reliability Terminologies
✓Satisfactory quality: Voltage, frequency, and other aspects of the power
made available must be suitable to meet the consumer's needs. This is what it
really means to design and operate a "reliable" power delivery system.
✓Figure 4.1 illustrates this, based on a diagram (Figure 2.1) from Brown
(2002). Reliability - whatever guise it takes - is a part of "Power Quality" in
the larger sense. Power quality in turn is part of customer satisfaction, the real
measure of a utility's good customer focus. However, many of the other factors
contributing to customer satisfaction, such as the quality of billing and
response to customer inquiries, are generally beyond the venue of the planner.
17
Reliability Terminologies
✓a
18
Types of Failure
✓Transient failures (or soft errors):
▪ Charge q = c*v if c and v decrease then it is easier to flip a bit
▪ Sources are cosmic rays and alpha particles and electrical noise
▪ Device is still operational but value has been corrupted
✓Intermittent/temporary failures
▪ Last longer due to Temporary: environmental variations (eg, temperature)
▪ Last longer due to Intermittent: aging
✓Permanent failures
▪ Means that the device will never function again
▪ Must be isolated and replaced by spare
▪ Process variations increase the probability of failures
19
20
21
22
23
25
26
29
30
✓This is because failure rates have unique characteristics and are essential for
all types of reliability analyses. The next section looks at failure rates in more
detail and explains how electrical component failure rates tend to vary with
time.
31
32
33
34
35
36
✓a
37
1
defects or defects resulting from manufacturing
process.
Early Life
Region
0 Time t
38
0 Time t
39
Wear-Out
Region
0 Time t
40
Derivation of R(t)
• Probability[no failure @ time t] = R(t)
• Assuming a constant failure rate λ, N is the number of units
dN N (t )dt
dN (t )
dR(t )
dN (0)
41
42
✓Instead of using a constant failure rate in the useful life period, this curve
uses an increasing failure rate. The increase is attributed to normal wear, and
can be mitigated by periodic maintenance.
43
44
45
46